Defense Federal Acquisition Regulation Supplement
	
	
Part 242--Contract Administration and Audit Services
	
	
	
	
	
	
SUBPART 242.11--PRODUCTION SURVEILLANCE AND REPORTING
(Revised April 23, 2008)
242.1106 Reporting requirements.
(a) See DoDI 5000.2, Operation of the Defense Acquisition System, for reporting requirements for defense technology projects and acquisition programs.
(b)(i) Within four working days after receipt of the contractor's report, the CAO must provide the report and any required comments to the contracting officer and, unless otherwise specified in the contract, the inventory control manager.
(ii) If the contractor's report indicates that the contract is on schedule and the CAO agrees, the CAO does not need to add further comments. In all other cases, the CAO must add comments and recommend a course of action.
	
	
	
	
	1998
	EDITION		242.11-
| File Type | application/msword | 
| File Title | SUBPART 242.11—PRODUCTION SURVEILLANCE AND REPORTING | 
| Author | OUSD(A&T) | 
| Last Modified By | Mary Overstreet | 
| File Modified | 2016-04-07 | 
| File Created | 2016-04-07 |