Bid Guarantees, Performance, and Payments Bonds, and Alternative Payment Protection - FAR Sections Affected: Subparts 28.1 and 28.2; 52.228-1; 52-228-2; 52-228-13; 52.228-15; 52-228-16

ICR 201606-9000-004

OMB: 9000-0045

Federal Form Document

Forms and Documents
Document
Name
Status
Supplementary Document
2016-06-22
Supporting Statement A
2016-06-22
ICR Details
9000-0045 201606-9000-004
Historical Active 201303-9000-001
FAR
Bid Guarantees, Performance, and Payments Bonds, and Alternative Payment Protection - FAR Sections Affected: Subparts 28.1 and 28.2; 52.228-1; 52-228-2; 52-228-13; 52.228-15; 52-228-16
Revision of a currently approved collection   No
Regular
Approved without change 07/25/2016
Retrieve Notice of Action (NOA) 06/22/2016
  Inventory as of this Action Requested Previously Approved
07/31/2019 36 Months From Approved 07/31/2016
974 0 56,013
974 0 41,845
44,668 0 0

These regulations implement the statutory requirements of the Miller Act (40 U.S.C. §§ 3131 to 3134), which requires performance and payment bonds for any construction contract exceeding $150,000 unless it is impracticable to require bonds for work performed in a foreign country, or it is otherwise authorized by law. In addition, the regulations implement the notice to 40 U.S.C. § 3132, entitled "Alternatives to Payment Bonds Provided by the Federal Acquisition Regulation," which requires alternative payment protection for construction contracts that exceed $30,000 but do not exceed $150,000. Although not required by statute, under certain circumstances the FAR permits the Government to require bonds on other than construction contracts.

None
None

Not associated with rulemaking

  81 FR 15304 05/22/2016
81 FR 38180 06/14/2016
No

  Total Approved Previously Approved Change Due to New Statute Change Due to Agency Discretion Change Due to Adjustment in Estimate Change Due to Potential Violation of the PRA
Annual Number of Responses 974 56,013 0 -35,435 -19,604 0
Annual Time Burden (Hours) 974 41,845 0 -32,637 -8,234 0
Annual Cost Burden (Dollars) 44,668 0 0 44,668 0 0
No
Yes
Miscellaneous Actions
The Federal Procurement Data System showed significantly fewer construction contracts at the given ranges of dollar values than were shown in FY2011; this is possibly due to a large number of Recovery Act projects in the earlier part of this decade. Additionally, the assumption of 10 minutes per review (on the Government side) was increased to 15 minutes per review.

$11,161
No
No
No
No
No
Uncollected
Kathy Hopkins 202 969-7226 [email protected]

  No

On behalf of this Federal agency, I certify that the collection of information encompassed by this request complies with 5 CFR 1320.9 and the related provisions of 5 CFR 1320.8(b)(3).
The following is a summary of the topics, regarding the proposed collection of information, that the certification covers:
 
 
 
 
 
 
 
    (i) Why the information is being collected;
    (ii) Use of information;
    (iii) Burden estimate;
    (iv) Nature of response (voluntary, required for a benefit, or mandatory);
    (v) Nature and extent of confidentiality; and
    (vi) Need to display currently valid OMB control number;
 
 
 
If you are unable to certify compliance with any of these provisions, identify the item by leaving the box unchecked and explain the reason in the Supporting Statement.
06/22/2016


© 2024 OMB.report | Privacy Policy