General
	Conditions for Construction Public Housing Programs 
	U.S.
	Department of Housing and Urban 
	Contracts 
	Development 
	- 
	Office
	of Public and Indian Housing OMB
	Approval No. 2577-0157 (exp. 1/31/2017) 
	Applicability.
	This form is applicable to any 
	construction/development
	contract greater than $100,000. 
	This
	form includes those clauses required by OMB's common rule on grantee
	procurement, implemented at HUD in 24 CFR 85.36, and those
	requirements set forth in Section 3 of the Housing and Urban
	Development Act of 1968 and its amendment by the Housing and
	Community Development Act of
	1992,
	implemented by HUD at 24 CFR Part 135. The form is required for
	construction contracts 
	awarded
	by Public Housing Agencies (PHAs). 
	The
	form is used by Housing Authorities in solicitations to provide
	necessary contract clauses. If the form were not used, HAs would be 
	unable
	to enforce their contracts. 
	Public
	reporting burden for this collection of information is estimated to
	average 1.0 hours per response, including the time for reviewing
	instructions, searching existing data sources, gathering and
	maintaining the data needed, and completing and reviewing the
	collection of information. Responses to the collection of
	information are required to obtain a benefit or to retain a benefit. 
	The
	information requested does not lend itself to confidentiality. 
	HUD
	may not conduct or sponsor, and a person is not required to respond
	to a collection of information unless it displays a currently valid
	OMB number. 
	Table
	of Contents 
	Clause 
	Page 
	Clause 
	Page 
	1. 
	Definitions 
	2 
	Administrative
	Requirements 
	Construction
	Requirements 
	28. 
	Contract
	Modifications 
	10 
	Previous
	editions are obsolete Replaces form HUD-5370-A 
	Page
	1 of 19 
	form
	HUD-5370 (1/2014) 
	 
	14. 
	Temporary
	Buildings and Transportation Materials 
	6 
	38. 
	13 
	16. 
	40. 
	14 
	18. 
	Clean
	Air and Water 
	7 
	42. 
	15 
				2. 
				Contractor’s
				Responsibility for Work 
					 
				2 
				25. 
				Contract
				Period 
					 
				9 
				3. 
				Architect’s
				Duties, Responsibilities and Authority 
					 
				2 
				26. 
				Order
				of Precedence 
					 
				9 
				4. 
				Other
				Contracts 
					 
				3 
				27. 
				Payments 
					 
				9 
				5. 
				Preconstruction
				Conference and Notice to Proceed 
					 
				3 
				29. 
				Changes 
					 
				10 
				6. 
				Construction
				Progress Schedule 
					 
				3 
				30. 
				Suspension
				of Work 
					 
				11 
				7. 
				Site
				Investigation and Conditions Affecting the Work 
					 
				3 
				31. 
				Disputes 
					 
				11 
				8. 
				Differing
				Site Conditions 
					 
				4 
				32. 
				Default 
					 
				11 
				9. 
				Specifications
				and Drawings for Construction 
					 
				4 
				33. 
				Liquidated
				Damages 
					 
				12 
				10. 
				As-Built
				Drawings 
					 
				5 
				34. 
				Termination
				of Convenience 
					 
				12 
				11. 
				Material
				and Workmanship 
					 
				5 
				35. 
				Assignment
				of Contract 
					 
				12 
				12. 
				Permits
				and Codes 
					 
				5 
				36. 
				Insurance 
					 
				12 
				13. 
				Health,
				Safety, and Accident Prevention 
					 
				6 
				37. 
				Subcontracts 
					 
				13 
				 
				 
				 
				 
				Subcontracting
				with Small and Minority Firms, Women’s Business Enterprise,
				and Labor Surplus Area Firms 
				 
				15. 
				Availability
				and Use of Utility Services 
					 
				6 
				39. 
				Equal
				Employment Opportunity 
					 
				13 
				 
				Protection
				of Existing Vegetation, Structures, Equipment, Utilities, and
				Improvements 
				6 
				 
				Employment,
				Training, and Contracting Opportunities for Low-Income Persons,
				Section 3 of the Housing and Urban Development Act of 1968 
				 
				17. 
				Temporary
				Buildings and Transportation Materials 
					 
				7 
				41. 
				Interest
				of Members of Congress 
					 
				15 
				 
				 
				 
				 
				Interest
				of Members, Officers, or Employees and Former Members, Officers,
				or Employees 
				 
				19. 
				Energy
				Efficiency 
					 
				7 
				43. 
				Limitations
				on Payments Made to Influence 
					 
				15 
				20. 
				Inspection
				and Acceptance of Construction 
					 
				7 
				44. 
				Royalties
				and Patents 
					 
				15 
				21. 
				Use
				and Possession Prior to Completion 
					 
				8 
				45. 
				Examination
				and Retention of Contractor’s Records 
					 
				15 
				22. 
				Warranty
				of Title 
					 
				8 
				46. 
				Labor
				Standards-Davis-Bacon and Related Acts 
					 
				15 
				23. 
				Warranty
				of Construction 
					 
				8 
				47. 
				Non-Federal
				Prevailing Wage Rates 
					 
				19 
				24. 
				Prohibition
				Against Liens 
					 
				9 
				48. 
				Procurement
				of Recovered Materials 
					 
				19
	
	
	
	
	
	
	
	
	 
	
 
										
	
		
	
			 
		
			 
		
			 
	
	
		
	
			 
		
			 
		
			 
		
			 
		
			 
		
			 
		
			 
		
			 
		
			 
		
			 
		
				
				
				
				
				
			 
		
			 
		
				
				
				
			 
		
			 
		
				
				
				
				
				
			 
		
			 
		
			 
		
			 
		
			 
		
			 
	
	 
	
 
	
 
												
 
 
 
	1.
	Definitions 
	(a)
	The Contractor shall furnish all necessary labor, 
	(a)
	“Architect” means the person or other entity engaged by
	the PHA to perform architectural, engineering, design, and other
	services related to the work as provided for in the contract. When a
	PHA uses an engineer to act in this capacity, the terms “architect”
	and “engineer” shall be synonymous. The Architect shall
	serve as a technical representative of the Contracting Officer. The
	Architect’s 
	materials,
	tools, equipment, and transportation necessary for performance of
	the work. The Contractor shall also furnish all necessary water,
	heat, light, and power not made available to the Contractor by the
	PHA pursuant to the clause entitled Availability and Use of Utility
	Services 
	herein. 
	(b)
	The Contractor shall perform on the site, and with its own 
	authority
	is as set forth elsewhere in this contract. 
	organization,
	work equivalent to at least [	] (12 percent unless
	otherwise indicated) of the total amount of work to be performed
	under the order. This percentage may be reduced by a supplemental
	agreement to this order if, during performing the work, the
	Contractor requests a reduction and the Contracting Officer
	determines that the 
	(b)
	“Contract” means the contract entered into between the 
	PHA
	and the Contractor. It includes the forms of Bid, the Bid Bond, the
	Performance and Payment Bond or Bonds or other assurance of
	completion, the Certifications, Representations, and Other
	Statements of Bidders (form HUD-5370), these General Conditions of
	the Contract for Construction (form HUD-5370), the applicable wage
	rate determinations from the U.S. Department of Labor, any special
	conditions included elsewhere in the contract, the specifications,
	and drawings. It includes all formal changes to any of those
	documents by addendum, 
	reduction
	would be to the advantage of the PHA. 
	(c)
	At all times during performance of this contract and until 
	the
	work is completed and accepted, the Contractor shall directly
	superintend the work or assign and have on the work site a competent
	superintendent who is satisfactory to the Contracting Officer and
	has authority to act for the 
	Contractor. 
	change
	order, or other modification. 
	(d)
	The Contractor shall be responsible for all damages to 
	(c)
	“Contracting Officer” means the person delegated the au- 
	persons
	or property that occur as a result of the Contractor’s fault
	or negligence, and shall take proper 
	thority
	by the PHA to enter into, administer, and/or terminate this contract
	and designated as such in writing to the Contractor. The term
	includes any successor 
	safety
	and health precautions to protect the work, the workers, the public,
	and the property of others. The Contractor shall hold and save the
	PHA, its officers and agents, free and harmless from liability of
	any nature occasioned by the Contractor’s performance. The
	Contractor shall also be responsible for all materials delivered and
	work performed until completion and acceptance of the entire work,
	except for any completed unit of work which may have been accepted
	under the 
	Contracting
	Officer and any duly authorized 
	representative
	of the Contracting Officer also designated in writing. The
	Contracting Officer shall be deemed the authorized agent of the PHA
	in all dealings with the 
	Contractor. 
	(d)
	“Contractor” means the person or other entity entering 
	into
	the contract with the PHA to perform all of the work 
	required
	under the contract. 
	contract. 
	(e)
	“Drawings” means the drawings enumerated in the 
	(e)
	The Contractor shall lay out the work from base lines and 
	schedule
	of drawings contained in the Specifications and as described in the
	contract clause entitled Specifications 
	bench
	marks indicated on the drawings and be responsible for all lines,
	levels, and measurements of all work executed under the contract.
	The Contractor shall verify the figures before laying out the work
	and will be held responsible for any error resulting from its
	failure to 
	and
	Drawings for Construction herein. 
	(f)
	“HUD” means the United States of America acting through
	the Department of Housing and Urban Development including the
	Secretary, or any other person designated to act on its behalf. HUD
	has agreed, subject to the provisions of an Annual Contributions
	Contract (ACC), to provide financial assistance to the PHA, which
	includes assistance in financing the work to be performed under this
	contract. As defined elsewhere in these General Conditions or the
	contract documents, the determination of HUD may be required to
	authorize changes in the work or for release of funds to the PHA for
	payment to the Contractor. Notwithstanding HUD’s role, nothing
	in this contract shall be construed to create any contractual 
	do
	so. 
	(f)
	The Contractor shall confine all operations (including storage of
	materials) on PHA premises to areas authorized or approved by the
	Contracting Officer. 
	(g)
	The Contractor shall at all times keep the work area, 
	relationship
	between the Contractor and HUD. 
	including
	storage areas, free from accumulations of waste materials. After
	completing the work and before final inspection, the Contractor
	shall (1) remove from the premises all scaffolding, equipment,
	tools, and materials (including rejected materials) that are not the
	property of the PHA and all rubbish caused by its work; (2) leave
	the work area in a clean, neat, and orderly condition satisfactory
	to the Contracting Officer; (3) perform all specified tests; and,
	(4) deliver the installation in 
	(g)
	“Project” means the entire project, whether construction
	or rehabilitation, the work for which is provided for in 
	whole
	or in part under this contract. 
	complete
	and operating condition. 
	(h)
	“PHA” means the Public Housing Agency organized under
	applicable state laws which is a party to this 
	(h)
	The Contractor’s responsibility will terminate when all 
	contract. 
	work
	has been completed, the final inspection made, and the work accepted
	by the Contracting Officer. The Contractor will then be released
	from further obligation except as required by the warranties
	specified elsewhere in the contract. 
	(j)
	“Specifications” means the written description of the 
	technical
	requirements for construction and includes the criteria and tests
	for determining whether the 
	requirements
	are met. 
	(l)
	“Work” means materials, workmanship, and manufacture and
	fabrication of components. 
	3.
	Architect’s Duties, Responsibilities, and Authority 
	2.
	Contractor’s Responsibility for Work 
	(a)
	The Architect for this contract, and any successor, shall be
	designated in writing by the Contracting Officer. 
	Previous
	editions are obsolete Replaces form HUD-5370-A 
	Page
	2 of 19 
	form
	HUD-5370 (1/2014) 
	 
	
 
 
 
 
	 
	(b)
	The Architect shall serve as the Contracting Officer’s 
	technical
	representative with respect to architectural, engineering, and
	design matters related to the work performed under the contract. The
	Architect may provide direction on contract performance. Such
	direction shall be within the scope of the contract and may not be
	of a nature which: (1) institutes additional work outside the scope
	of the contract; (2) constitutes a change as defined in the Changes
	clause herein; (3) causes an increase or decrease in the cost of the
	contract; (4) alters the Construction Progress Schedule; or (5)
	changes any of the other express terms or conditions of the
	contract. 
	6.
	Construction Progress Schedule 
	(a)
	The Contractor shall, within five days after the work 
	(c)
	The Architect’s duties and responsibilities may include but 
	commences
	on the contract or another period of time determined by the
	Contracting Officer, prepare and submit to the Contracting Officer
	for approval three copies of a practicable schedule showing the
	order in which the Contractor proposes to perform the work, and the
	dates on which the Contractor contemplates starting and completing
	the several salient features of the work (including acquiring labor,
	materials, and equipment). The schedule shall be in the form of a
	progress chart of suitable scale to indicate appropriately the
	percentage of work scheduled for completion by any given date during
	the period. If the Contractor fails to submit a schedule within the
	time prescribed, the Contracting Officer may withhold approval of
	progress payments or take other remedies under the contract until
	the Contractor submits 
	shall
	not be limited to: 
	(1)
	Making periodic visits to the work site, and on the 
	basis
	of his/her on-site inspections, issuing written reports to the PHA
	which shall include all observed deficiencies. The Architect shall
	file a copy of the report with the Contractor’s designated
	representative 
	at
	the site; 
	the
	required schedule. 
	(2)
	Making modifications in drawings and technical 
	(b)
	The Contractor shall enter the actual progress on the chart as
	required by the Contracting Officer, and immediately deliver three
	copies of the annotated schedule to the Contracting Officer. If the
	Contracting Officer determines, upon the basis of inspection
	conducted pursuant to the clause entitled Inspection and Acceptance
	of Construction, herein that the Contractor is not meeting the
	approved schedule, the Contractor shall take steps necessary to
	improve its progress, including those that may be required by the
	Contracting Officer, without additional cost to the PHA. In this
	circumstance, the Contracting Officer may require the Contractor to
	increase the number of shifts, overtime operations, days of work,
	and/or the amount of construction plant, and to submit for approval
	any supplementary schedule or schedules in chart form as the
	Contracting Officer deems necessary to demonstrate how the approved
	rate of 
	specifications
	and assisting the Contracting Officer in the preparation of change
	orders and other contract 
	modifications
	for issuance by the Contracting Officer; 
	(3)
	Reviewing and making recommendations with respect 
	to
	- (i) the Contractor’s construction progress schedules; (ii)
	the Contractor’s shop and detailed drawings; (iii) the
	machinery, mechanical and other equipment and materials or other
	articles proposed for use by the Contractor; and, (iv) the
	Contractor’s 
	price
	breakdown and progress payment estimates; 
	and, 
	(4)
	Assisting in inspections, signing Certificates of 
	Completion,
	and making recommendations with respect to acceptance of work
	completed under the contract. 
	4.
	Other Contracts 
	progress
	will be regained. 
	The
	PHA may undertake or award other contracts for additional work at or
	near the site of the work under this contract. The Contractor shall
	fully cooperate with the other contractors and with PHA employees
	and shall carefully adapt scheduling and performing the work under
	this contract to accommodate the additional work, heeding any
	direction that may be provided by the Contracting Officer. The
	Contractor shall not commit or permit any act that will interfere
	with the performance of work by any other contractor or by PHA
	employees 
	(c)
	Failure of the Contractor to comply with the requirements of the
	Contracting Officer under this clause shall be grounds for a
	determination by the Contracting Officer that the Contractor is not
	prosecuting the work with sufficient diligence to ensure completion
	within the time 
	specified
	in the Contract. Upon making this 
	determination,
	the Contracting Officer may terminate the Contractor’s right
	to proceed with the work, or any separable part of it, in accordance
	with the Default clause of this contract. 
	7.
	Site Investigation and Conditions Affecting the Work 
	Construction
	Requirements 
	5.
	Pre-construction Conference and Notice to Proceed 
	(a)
	The Contractor acknowledges that it has taken steps reasonably
	necessary to ascertain the nature and location of the work, and that
	it has investigated and satisfied itself as to the general and local
	conditions which can affect the work or its cost, including but not
	limited to, (1) conditions bearing upon transportation, disposal,
	handling, and storage of materials; (2) the availability of labor,
	water, electric power, and roads;(3) uncertainties of weather, river
	stages, tides, or similar physical conditions at the site; (4) the
	conformation and conditions of the ground; and (5) the character of
	equipment and facilities needed preliminary to and during work
	performance. The Contractor also acknowledges that it has satisfied
	itself as to the character, quality, and quantity of surface and
	subsurface materials or obstacles to be encountered insofar as this
	information is 
	(a)
	Within ten calendar days of contract execution, and prior to the
	commencement of work, the Contractor shall attend a preconstruction
	conference with representatives of the PHA, its Architect, and other
	interested parties convened by the PHA. The conference will serve to
	acquaint the participants with the general plan of the construction
	operation and all other requirements of the contract. The PHA will
	provide the Contractor with the 
	date,
	time, and place of the conference. 
	(b)
	The contractor shall begin work upon receipt of a written 
	Notice
	to Proceed from the Contracting Officer or designee. The Contractor
	shall not begin work prior to receiving such notice. 
	Previous
	editions are obsolete Replaces form HUD-5370-A 
	Page
	3 of 19 
	form
	HUD-5370 (1/2014) 
	 
	
	
	 
	
 
 
 
 
	reasonably
	ascertainable from an inspection of the site, including all
	exploratory work done by the PHA, as well as from the drawings and
	specifications made a part of this contract. Any failure of the
	Contractor to take the actions described and acknowledged in this
	paragraph will not relieve the Contractor from responsibility for
	estimating properly the difficulty and cost of successfully
	performing the work, or for proceeding to successfully 
	promptly
	submitted to the Contracting Officer, who shall promptly make a
	determination in writing. Any adjustment by the Contractor without
	such a determination shall be at its own risk and expense. The
	Contracting Officer shall furnish from time to time such detailed
	drawings and other information as considered necessary, unless 
	otherwise
	provided. 
	perform
	the work without additional expense to the PHA. 
	(b)
	Wherever in the specifications or upon the drawings the words
	“directed”, “required”, “ordered”,
	“designated”, “prescribed”, or words of like
	import are used, it shall be 
	(b)
	The PHA assumes no responsibility for any conclusions 
	or
	interpretations made by the Contractor based on the information made
	available by the PHA. Nor does the PHA assume responsibility for any
	understanding reached or representation made concerning conditions
	which can affect the work by any of its officers or agents before
	the execution of this contract, unless that understanding or
	representation is expressly stated in this contract. 
	understood
	that the “direction”, “requirement”,
	“order”, “designation”, or “prescription”,
	of the Contracting Officer 
	is
	intended and similarly the words “approved”,
	“acceptable”, “satisfactory”, or words of
	like import shall 
	mean 
	“approved
	by”, or 
	“acceptable
	to”, or “satisfactory 
	 
	to”
	the Contracting Officer, unless otherwise expressly 
	stated. 
	(c)
	Where “ shown” “ indicated”, “
	detailed”, or words 
	as 
	,as 
	as 
	8.
	Differing Site Conditions 
	of
	similar import are used, it shall be understood that the reference
	is made to the drawings accompanying this contract unless stated
	otherwise. The word “provided” as used herein shall be
	understood to mean “provide complete in place” that is
	“furnished and installed”. 
	(a)
	The Contractor shall promptly, and before the conditions are
	disturbed, give a written notice to the Contracting Officer of (1)
	subsurface or latent physical conditions at the site which differ
	materially from those indicated in this contract, or (2) unknown
	physical conditions at the site(s), of an unusual nature, which
	differ materially from those ordinarily encountered and generally
	recognized as inhering in work of the character provided for in the 
	(d)
	“Shop drawings” means drawings, submitted to the PHA 
	contract. 
	by
	the Contractor, subcontractor, or any lower tier subcontractor,
	showing in detail (1) the proposed fabrication and assembly of
	structural elements and (2) the installation (i.e., form, fit, and
	attachment details) of materials of equipment. It includes drawings,
	diagrams, layouts, schematics, descriptive literature,
	illustrations, schedules, performance and test data, and similar
	materials furnished by the Contractor to explain in detail specific
	portions of the work required by the contract. The PHA may
	duplicate, use, and disclose in any manner and for any purpose shop
	drawings delivered under this 
	(b)
	The Contracting Officer shall investigate the site 
	conditions
	promptly after receiving the notice. Work shall not proceed at the
	affected site, except at the Contractor’s risk, until the
	Contracting Officer has provided written instructions to the
	Contractor. If the conditions do materially so differ and cause an
	increase or decrease in the Contractor’s cost of, or the time
	required for, performing any part of the work under this contract,
	whether or not changed as a result of the conditions, the Contractor
	shall file a claim in writing to the PHA within ten days after
	receipt of such instructions and, in any event, before proceeding
	with the work. An equitable adjustment in the contract price, the
	delivery schedule, or both shall be made under this clause and 
	contract. 
	(e)
	If this contract requires shop drawings, the Contractor 
	the
	contract modified in writing accordingly. 
	shall
	coordinate all such drawings, and review them for accuracy,
	completeness, and compliance with other contract requirements and
	shall indicate its approval thereon as evidence of such coordination
	and review. Shop drawings submitted to the Contracting Officer
	without evidence of the Contractor’s approval may be returned
	for resubmission. The Contracting Officer will indicate an approval
	or disapproval of the shop drawings and if not approved as submitted
	shall indicate the PHA’s reasons therefore. Any work done
	before such approval shall be at the Contractor’s risk.
	Approval by the Contracting Officer shall not relieve the Contractor
	from responsibility for any errors or omissions in such drawings,
	nor from responsibility for complying with the requirements of this
	contract, except with respect to variations described and approved
	in accordance with (f) 
	(c)
	No request by the Contractor for an equitable adjustment 
	to
	the contract under this clause shall be allowed, unless the
	Contractor has given the written notice required; provided, that the
	time prescribed in (a) above for giving written notice may be
	extended by the Contracting 
	Officer. 
	(d)
	No request by the Contractor for an equitable adjustment 
	to
	the contract for differing site conditions shall be allowed if made
	after final payment under this contract. 
	below. 
	9.
	Specifications and Drawings for Construction 
	(f)
	If shop drawings show variations from the contract requirements, the
	Contractor shall describe such variations in writing, separate from
	the drawings, at the time of submission. If the Architect approves
	any such variation and the Contracting Officer concurs, the 
	(a)
	The Contractor shall keep on the work site a copy of the 
	drawings
	and specifications and shall at all times give the Contracting
	Officer access thereto. Anything mentioned in the specifications and
	not shown on the drawings, or shown on the drawings and not
	mentioned in the specifications, shall be of like effect as if shown
	or mentioned in both. In case of difference between drawings and
	specifications, the specifications shall govern. In case of
	discrepancy in the figures, in the drawings, or in the
	specifications, the matter shall be 
	Contracting
	Officer shall issue an appropriate 
	modification
	to the contract, except that, if the variation is minor or does not
	involve a change in price or in time of performance, a modification
	need not be issued. 
	(g)
	It shall be the responsibility of the Contractor to make 
	timely
	requests of the PHA for such large scale and full size drawings,
	color schemes, and other additional information, not already in his
	possession, which shall be 
	Previous
	editions are obsolete Replaces form HUD-5370-A 
	Page
	4 of 19 
	form
	HUD-5370 (1/2014) 
	 
 
	
 
 
 
 
	required
	in the planning and production of the work. Such requests may be
	submitted as the need arises, but each such request shall be filed
	in ample time to permit appropriate action to be taken by all
	parties involved so 
	machinery
	and mechanical and other equipment. When required by this contract
	or by the Contracting Officer, the Contractor shall also obtain the
	Contracting Officer’s approval of the material or articles
	which the Contractor contemplates incorporating into the work. When
	requesting approval, the Contractor shall provide full information
	concerning the material or articles. Machinery, equipment, material,
	and articles that do not have the required approval shall be
	installed or used at the risk 
	as
	to avoid delay. 
	(h)
	The Contractor shall submit to the Contracting Officer for approval
	four copies (unless otherwise indicated) of all shop drawings as
	called for under the various headings of these specifications. Three
	sets (unless otherwise indicated) of all shop drawings, will be
	retained by the PHA and one set will be returned to the Contractor.
	As required by the Contracting Officer, the Contractor, upon
	completing the work under this contract, shall furnish a complete
	set of all shop drawings as finally approved. These drawings shall
	show all changes and revisions 
	of
	subsequent rejection. 
	(2)
	When required by the specifications or the 
	Contracting
	Officer, the Contractor shall submit appropriately marked samples
	(and certificates related to them) for approval at the Contractor’s 
	made
	up to the time the work is completed and accepted. 
	expense,
	with all shipping charges prepaid. The Contractor shall label, or
	otherwise properly mark on the container, the material or product
	represented, its place of origin, the name of the producer, the
	Contractor’s name, and the identification of the construction
	project for which the material or product 
	(i)
	This clause shall be included in all subcontracts at any tier. It
	shall be the responsibility of the Contractor to ensure that all
	shop drawings prepared by subcontractors are submitted to the
	Contracting Officer. 
	10.
	As-Built Drawings 
	is
	intended to be used. 
	(a)
	“As-built drawings,” as used in this clause, means 
	(3)
	Certificates shall be submitted in triplicate, describing each
	sample submitted for approval and certifying that the material,
	equipment or accessory complies with contract requirements. The
	certificates shall include the name and brand of the product, name
	of manufacturer, and the location where produced. 
	drawings
	submitted by the Contractor or subcontractor at any tier to show the
	construction of a particular structure or work as actually completed
	under the contract. “As-built drawings” shall be
	synonymous with “Record 
	drawings.” 
	(4)
	Approval of a sample shall not constitute a waiver of 
	(b)
	As required by the Contracting Officer, the Contractor 
	the
	PHA right to demand full compliance with contract  
	shall
	provide the Contracting Officer accurate information to be used in
	the preparation of permanent as-built drawings. For this purpose,
	the Contractor shall record on one set of contract drawings all
	changes from the installations originally indicated, and record
	final locations of underground lines by depth from finish grade and
	by accurate horizontal offset distances to permanent surface
	improvements such as buildings, curbs, or edges of 
	been
	approved. 
	walks. 
	(5)
	Wherever materials are required to comply with recognized standards
	or specifications, such specifications shall be accepted as
	establishing the technical qualities and testing methods, but shall
	not govern the number of tests required to be made nor modify other
	contract requirements. The Contracting Officer may require
	laboratory test reports on items submitted for approval or may
	approve materials on the basis of data submitted in certificates
	with samples. Check tests will be made on materials delivered for
	use only as frequently as the Contracting Officer determines
	necessary to insure compliance of materials with the specifications.
	The Contractor will assume all costs of retesting materials which
	fail to meet contract requirements and/or testing materials offered
	in substitution for those found deficient. 
	(c)
	This clause shall be included in all subcontracts at any tier. It
	shall be the responsibility of the Contractor to 
	ensure
	that all as-built drawings prepared by 
	subcontractors
	are submitted to the Contracting Officer. 
	11.
	Material and Workmanship 
	(a)
	All equipment, material, and articles furnished under this 
	contract
	shall be new and of the most suitable grade for the purpose
	intended, unless otherwise specifically provided in this contract.
	References in the contract to equipment, material, articles, or
	patented processes by trade name, make, or catalog number, shall be
	regarded as establishing a standard of quality and shall not be
	construed as limiting competition. The Contractor may, at its
	option, use any equipment, material, article, or process that, in
	the judgment of, and as approved by the Contracting Officer, is
	equal to that named in the specifications, unless otherwise
	specifically provided in 
	(6)
	After approval, samples will be kept in the Project 
	office
	until completion of work. They may be built into the work after a
	substantial quantity of the materials 
	they
	represent has been built in and accepted. 
	(c)
	Requirements concerning lead-based paint. The 
	Contractor
	shall comply with the requirements concerning lead-based paint
	contained in the Lead-Based Paint Poisoning Prevention Act (42
	U.S.C. 4821-4846) as implemented by 24 CFR Part 35. 
	this
	contract. 
	(b)
	Approval of equipment and materials. 
	12.
	Permits and Codes 
	(1)
	The Contractor shall obtain the Contracting Officer’s 
	approval
	of the machinery and mechanical and other equipment to be
	incorporated into the work. When requesting approval, the Contractor
	shall furnish to the Contracting Officer the name of the
	manufacturer, the model number, and other information concerning the
	performance, capacity, nature, and rating of the 
	(a)
	The Contractor shall give all notices and comply with all 
	applicable
	laws, ordinances, codes, rules and regulations. Notwithstanding the
	requirement of the Contractor to comply with the drawings and
	specifications in the contract, all work installed shall comply with
	all applicable codes and regulations as amended by any 
	Previous
	editions are obsolete Replaces form HUD-5370-A 
	Page
	5 of 19 
	form
	HUD-5370 (1/2014) 
	 
	
requirements.
	Materials, equipment and accessories 
may be rejected for cause
	even though samples have
	 
	
 
 
 
 
	waivers.
	Before installing the work, the Contractor shall examine the
	drawings and the specifications for compliance with applicable codes
	and regulations bearing on the work and shall immediately report any
	discrepancy it may discover to the Contracting Officer. 
	14.
	Temporary Heating 
	Where
	the requirements of the drawings and 
	The
	Contractor shall provide and pay for temporary heating, covering,
	and enclosures necessary to properly protect all work and materials
	against damage by dampness and cold, to dry out the work, and to
	facilitate the completion of the work. Any permanent heating
	equipment used shall be turned over to the PHA in the condition and
	at the time required by the specifications. 
	specifications
	fail to comply with the applicable code or regulation, the
	Contracting Officer shall modify the contract by change order
	pursuant to the clause entitled Changes herein to conform to the
	code or regulation. 
	(b)
	The Contractor shall secure and pay for all permits, fees, and
	licenses necessary for the proper execution and completion of the
	work. Where the PHA can arrange for the issuance of all or part of
	these permits, fees and licenses, without cost to the Contractor,
	the contract amount shall be reduced accordingly. 
	15.
	Availability and Use of Utility Services 
	(a)
	The PHA shall make all reasonably required amounts of 
	13.
	Health, Safety, and Accident Prevention 
	utilities
	available to the Contractor from existing outlets and supplies, as
	specified in the contract. Unless otherwise provided in the
	contract, the amount of each utility service consumed shall be
	charged to or paid for by the Contractor at prevailing rates charged
	to the PHA or, where the utility is produced by the PHA, at
	reasonable rates determined by the Contracting Officer. The
	Contractor shall carefully conserve any utilities furnished 
	(a)
	In performing this contract, the Contractor shall: 
	(1)
	Ensure that no laborer or mechanic shall be required 
	to
	work in surroundings or under working conditions which are
	unsanitary, hazardous, or dangerous to his/her health and/or safety
	as determined under construction safety and health standards
	promulgated 
	without
	charge. 
	(b)
	The Contractor, at its expense and in a manner 
	by
	the Secretary of Labor by regulation; 
	satisfactory
	to the Contracting Officer, shall install and maintain all necessary
	temporary connections and distribution lines, and all meters
	required to measure the amount of each utility used for the purpose
	of determining charges. Before final acceptance of the work by the
	PHA, the Contractor shall remove all the temporary connections,
	distribution lines, meters, and associated paraphernalia. 
	(2)
	Protect the lives, health, and safety of other persons; 
	(3)
	Prevent damage to property, materials, supplies, and 
	equipment;
	and, 
	(4)
	Avoid work interruptions. 
	(b)
	For these purposes, the Contractor shall: 
	(1)
	Comply with regulations and standards issued by the Secretary of
	Labor at 29 CFR Part 1926. Failure to comply may result in
	imposition of sanctions pursuant to the Contract Work Hours and
	Safety Standards Act (Public Law 91-54, 83 Stat. 96), 40 U.S.C. 3701
	et 
	16.
	Protection of Existing Vegetation, Structures, Equipment, Utilities,
	and Improvements 
	seq.;
	and 
	(a)
	The Contractor shall preserve and protect all structures, 
	(2)
	Include the terms of this clause in every subcontract 
	equipment,
	and vegetation (such as trees, shrubs, and grass) on or adjacent to
	the work site, which are not to be removed under this contract, and
	which do not unreasonably interfere with the work required under
	this 
	so
	that such terms will be binding on each 
	subcontractor. 
	(c)
	The Contractor shall maintain an accurate record of exposure data on
	all accidents incident to work performed under this contract
	resulting in death, traumatic injury, occupational disease, or
	damage to property, materials, supplies, or equipment, and shall
	report this data in the manner prescribed by 29 CFR Part 
	contract. 
	(b)
	The Contractor shall only remove trees when specifically 
	1904. 
	authorized
	to do so, and shall avoid damaging vegetation that will remain in
	place. If any limbs or branches of trees are broken during
	performance of this contract, or by the careless operation of
	equipment, or by workmen, the Contractor shall trim those limbs or
	branches with a clean cut and paint the cut with a tree-pruning
	compound as 
	(d)
	The Contracting Officer shall notify the Contractor of any
	noncompliance with these requirements and of the corrective action
	required. This notice, when delivered to the Contractor or the
	Contractor’s representative at the site of the work, shall be
	deemed sufficient notice of the noncompliance and corrective action
	required. After receiving the notice, the Contractor shall
	immediately take corrective action. If the Contractor fails or
	refuses to take corrective action promptly, the Contracting Officer
	may issue an order stopping all or part of the work until
	satisfactory corrective action has been taken. The Contractor shall
	not base any claim or request for equitable adjustment for
	additional time or money on any 
	directed
	by the Contracting Officer. 
	(c)
	The Contractor shall protect from damage all existing 
	improvements
	and utilities (1) at or near the work site and (2) on adjacent
	property of a third party, the locations of which are made known to
	or should be known by the Contractor. Prior to disturbing the ground
	at the construction site, the Contractor shall ensure that all 
	underground
	utility lines are clearly marked. 
	(d)
	The Contractor shall shore up, brace, underpin, secure, 
	stop
	order issued under these circumstances. 
	and
	protect as necessary all foundations and other parts of existing
	structures adjacent to, adjoining, and in the vicinity of the site,
	which may be affected by the excavations or other operations
	connected with the 
	(e)
	The Contractor shall be responsible for its subcontractors’ 
	compliance
	with the provisions of this clause. The Contractor shall take such
	action with respect to any subcontract as the PHA, the Secretary of
	Housing and Urban Development, or the Secretary of Labor shall
	direct as a means of enforcing such provisions. 
	construction
	of the project. 
	(e)
	Any equipment temporarily removed as a result of work under this
	contract shall be protected, cleaned, and replaced in the same
	condition as at the time of award of this contract. 
	Previous
	editions are obsolete Replaces form HUD-5370-A 
	Page
	6 of 19 
	form
	HUD-5370 (1/2014) 
	 
	
	 
	
 
 
 
 
	(f)
	New work which connects to existing work shall 
	The
	contactor shall comply with the Clean Air Act, as amended, 42 USC
	7401 et seq., the Federal Water Pollution Control Water Act, as
	amended, 33 U.S.C. 1251 et seq., and standards issued pursuant
	thereto in the facilities in which this contract is to be performed. 
	correspond
	in all respects with that to which it connects and/or be similar to
	existing work unless otherwise 
	required
	by the specifications. 
	(g)
	No structural members shall be altered or in any way weakened
	without the written authorization of the Contracting Officer, unless
	such work is clearly specified 
	19.
	Energy Efficiency 
	in
	the plans or specifications. 
	(h)
	If the removal of the existing work exposes discolored or unfinished
	surfaces, or work out of alignment, such surfaces shall be
	refinished, or the material replaced as necessary to make the
	continuous work uniform and harmonious. This, however, shall not be
	construed to require the refinishing or reconstruction of dissimilar
	finishes previously exposed, or finished surfaces in good condition,
	but in different planes or on different levels when brought together
	by the removal of intervening work, unless such refinishing or
	reconstruction is 
	The
	Contractor shall comply with mandatory standards and policies
	relating to energy efficiency which are contained in the energy
	conservation plan issued in compliance with the Energy Policy and
	Conservation Act (Pub.L. 94-163) for the State in which the work
	under the contract is performed. 
	20.
	Inspection and Acceptance of Construction 
	(a)
	Definitions. As used in this clause - 
	specified
	in the plans or specifications. 
		“Acceptance”
		means the act of an authorized representative of the PHA by which
		the PHA approves and assumes ownership of the work performed under
		this contract. Acceptance may be partial or complete. 
		“Inspection”
		means examining and testing the work 
	(i)
	The Contractor shall give all required notices to any 
	adjoining
	or adjacent property owner or other party before 
	the
	commencement of any work. 
	(j)
	The Contractor shall indemnify and save harmless the 
	PHA
	from any damages on account of settlement or the loss of lateral
	support of adjoining property, any damages from changes in
	topography affecting drainage, and from all loss or expense and all
	damages for which the PHA may become liable in consequence of such
	injury or damage to adjoining and adjacent structures and their 
	performed
	under the contract (including, when 
	appropriate,
	raw materials, equipment, components, and intermediate assemblies)
	to determine whether it 
	conforms
	to contract requirements. 
	premises. 
	(3)
	“Testing” means that element of inspection that
	determines the properties or elements, including functional
	operation of materials, equipment, or their components, by the
	application of established scientific 
	(k)
	The Contractor shall repair any damage to vegetation, structures,
	equipment, utilities, or improvements, including those that are the
	property of a third party, resulting from failure to comply with the
	requirements of this contract or failure to exercise reasonable care
	in performing the work. If the Contractor fails or refuses to repair
	the damage promptly, the Contracting Officer may have the necessary
	work performed and charge the cost to the Contractor. 
	principles
	and procedures. 
	(b)
	The Contractor shall maintain an adequate inspection 
	system
	and perform such inspections as will ensure that the work performed
	under the contract conforms to contract requirements. All work is
	subject to PHA inspection and test at all places and at all
	reasonable times before acceptance to ensure strict compliance with 
	the
	terms of the contract. 
	(c)
	PHA inspections and tests are for the sole benefit of the 
	17.
	Temporary Buildings and Transportation of Materials 
	PHA
	and do not: (1) relieve the Contractor of responsibility for
	providing adequate quality control measures; (2) relieve the
	Contractor of responsibility for loss or damage of the material
	before acceptance; (3) constitute or imply acceptance; or, (4)
	affect the continuing rights of the PHA after acceptance of the 
	(a)
	Temporary buildings (e.g., storage sheds, shops, offices, sanitary
	facilities) and utilities may be erected by the Contractor only with
	the approval of the Contracting Officer and shall be built with
	labor and materials furnished by the Contractor without expense to
	the PHA. The temporary buildings and utilities shall remain the
	property of the Contractor and shall be removed by the Contractor at
	its expense upon completion of the work. With the written consent of
	the Contracting Officer, the buildings and utilities may be
	abandoned and need not 
	completed
	work under paragraph (j) below. 
	(d)
	The presence or absence of the PHA inspector does not 
	relieve
	the Contractor from any contract requirement, nor is the inspector
	authorized to change any term or condition of the specifications
	without the Contracting Officer’s written authorization. All
	instructions and 
	be
	removed. 
	approvals
	with respect to the work shall be given to the 
	(b)
	The Contractor shall, as directed by the Contracting 
	Contractor
	by the Contracting Officer. 
	Officer,
	use only established roadways, or use temporary roadways constructed
	by the Contractor when and as authorized by the Contracting Officer.
	When materials are transported in prosecuting the work, vehicles
	shall not be loaded beyond the loading capacity recommended by the
	manufacturer of the vehicle or prescribed by any federal, state, or
	local law or regulation. When it is necessary to cross curbs or
	sidewalks, the Contractor shall protect them from damage. The
	Contractor shall repair or pay for the repair of any damaged curbs,
	sidewalks, or roads. 
	(e)
	The Contractor shall promptly furnish, without additional charge,
	all facilities, labor, and material reasonably needed for performing
	such safe and convenient inspections and tests as may be required by
	the Contracting Officer. The PHA may charge to the Contractor any
	additional cost of inspection or test when work is not ready at the
	time specified by the Contractor for inspection or test, or when
	prior rejection makes reinspection or retest necessary. The PHA
	shall perform all inspections and tests in a manner that will not
	unnecessarily delay the work. Special, full size, and performance
	tests shall be performed as described in the contract. 
	18.
	Clean Air and Water 
	Previous
	editions are obsolete Replaces form HUD-5370-A 
	Page
	7 of 19 
	form
	HUD-5370 (1/2014) 
	 
	
	 
	
 
 
 
 
	(f)
	The PHA may conduct routine inspections of the 
	occupied
	without proper remuneration therefore. If prior possession or use by
	the PHA delays the progress of the work or causes additional expense
	to the Contractor, an equitable adjustment shall be made in the
	contract price or the time of completion, and the contract shall be
	modified in writing accordingly. 
	construction
	site on a daily basis. 
	(g)
	The Contractor shall, without charge, replace or correct work found
	by the PHA not to conform to contract requirements, unless the PHA
	decides that it is in its interest to accept the work with an
	appropriate adjustment in contract price. The Contractor shall
	promptly segregate and remove rejected material from 
	22.
	Warranty of Title 
	the
	premises. 
	(h)
	If the Contractor does not promptly replace or correct 
	The
	Contractor warrants good title to all materials, supplies, and
	equipment incorporated in the work and agrees to deliver the
	premises together with all improvements thereon free from any
	claims, liens or charges, and agrees further that neither it nor any
	other person, firm or corporation shall have any right to a lien
	upon the premises or anything appurtenant thereto. 
	rejected
	work, the PHA may (1) by contract or otherwise, replace or correct
	the work and charge the cost to the Contractor, or (2) terminate for
	default the Contractor’s 
	right
	to proceed. 
	(i)
	If any work requiring inspection is covered up without ap- 
	proval
	of the PHA, it must, if requested by the Contracting Officer, be
	uncovered at the expense of the Contractor. If at any time before
	final acceptance of the entire work, the PHA considers it necessary
	or advisable, to examine work already completed by removing or
	tearing it out, the Contractor, shall on request, promptly furnish
	all necessary facilities, labor, and material. If such work is found
	to be defective or nonconforming in any material respect due to the
	fault of the Contractor or its subcontractors, the Contractor shall
	defray all the expenses of the examination and of satisfactory
	reconstruction. If, however, such work is found to meet the
	requirements of the contract, the Contracting Officer shall make an
	equitable adjustment to cover the cost of the examination and
	reconstruction, including, if completion of the work was thereby
	delayed, an 
	23.
	Warranty of Construction 
	(a)
	In addition to any other warranties in this contract, the 
	Contractor
	warrants, except as provided in paragraph (j) of this clause, that
	work performed under this contract conforms to the contract
	requirements and is free of any defect in equipment, material, or
	workmanship performed 
	by
	the Contractor or any subcontractor or supplier at any 
	tier.
	This warranty shall continue for a period of 
	(one
	year unless otherwise indicated) from the date of final acceptance
	of the work. If the PHA takes possession of any part of the work
	before final acceptance, this warranty shall continue for a period
	of (one year unless otherwise indicated) from the date that the PHA
	takes 
	extension
	of time. 
	possession. 
	(j)
	The Contractor shall notify the Contracting Officer, in 
	(b)
	The Contractor shall remedy, at the Contractor’s 
	writing,
	as to the date when in its opinion all or a designated portion of
	the work will be substantially completed and ready for inspection.
	If the Architect determines that the state of preparedness is as
	represented, the PHA will promptly arrange for the inspection.
	Unless otherwise specified in the contract, the PHA shall accept, as
	soon as practicable after completion and inspection, all work
	required by the contract or that portion of the work the Contracting
	Officer determines and designates can be accepted separately.
	Acceptance shall be final and conclusive except for latent defects,
	fraud, gross mistakes amounting to fraud, or the PHA’s right
	under any warranty or guarantee. 
	expense,
	any failure to conform, or any defect. In addition, the Contractor
	shall remedy, at the Contractor’s expense, any damage to
	PHA-owned or controlled real or personal property when the damage is
	the result of— 
	(1)
	The Contractor’s failure to conform to contract require- 
	ments;
	or 
	(2)
	Any defects of equipment, material, workmanship or 
	design
	furnished by the Contractor. 
	(c)
	The Contractor shall restore any work damaged in 
	fulfilling
	the terms and conditions of this clause. The Contractor’s
	warranty with respect to work repaired or 
	replaced
	will run for (one year unless otherwise indicated) 
	from
	the date of repair or replacement. 
	(d)
	The Contracting Officer shall notify the Contractor, in 
	21.
	Use and Possession Prior to Completion 
	writing,
	within a reasonable time after the discovery of 
	any
	failure, defect or damage. 
	(a)
	The PHA shall have the right to take possession of or use any
	completed or partially completed part of the work. Before taking
	possession of or using any work, the Contracting Officer shall
	furnish the Contractor a list of items of work remaining to be
	performed or corrected on those portions of the work that the PHA
	intends to take possession of or use. However, failure of the
	Contracting Officer to list any item of work shall not relieve the
	Contractor of responsibility for complying with the terms of the
	contract. The PHA’s possession or use shall not be 
	(e)
	If the Contractor fails to remedy any failure, defect, or 
	damage
	within a reasonable time after receipt of notice, the PHA shall have
	the right to replace, repair or otherwise remedy the failure,
	defect, or damage at the 
	Contractor’s
	expense. 
	(f)
	With respect to all warranties, express or implied, from
	subcontractors, manufacturers, or suppliers for work performed and
	materials furnished under this contract, 
	the
	Contractor shall: 
	(1)
	Obtain all warranties that would be given in normal 
	deemed
	an acceptance of any work under the contract. 
	commercial
	practice; 
	(b)
	While the PHA has such possession or use, the 
	(2)
	Require all warranties to be executed in writing, for the 
	Contractor
	shall be relieved of the responsibility for (1) the loss of or
	damage to the work resulting from the PHA’s possession or use,
	notwithstanding the terms of the clause entitled Permits and Codes
	herein; (2) all maintenance costs on the areas occupied; and, (3)
	furnishing heat, light, power, and water used in the areas 
	benefit
	of the PHA; and, 
	(3)
	Enforce all warranties for the benefit of the PHA. 
	(g)
	In the event the Contractor’s warranty under paragraph 
	(a)
	of this clause has expired, the PHA may bring suit at its own
	expense to enforce a subcontractor’s, manufacturer’s or
	supplier’s warranty. 
	Previous
	editions are obsolete Replaces form HUD-5370-A 
	Page
	8 of 19 
	form
	HUD-5370 (1/2014) 
	 
	
	 
	
 
 
 
 
	 
	(h)
	Unless a defect is caused by the negligence of the 
	basis
	for determining progress payments. The breakdown shall be approved
	by the Contracting Officer and must be acceptable to HUD. If the
	contract covers more than one 
	Contractor
	or subcontractor or supplier at any tier, the Contractor shall not
	be liable for the repair of any defect of material or design
	furnished by the PHA nor for the repair of any damage that results
	from any defect in PHA 
	project,
	the Contractor shall furnish a separate 
	furnished
	material or design. 
	breakdown
	for each. The values and quantities employed in making up this
	breakdown are for determining the amount of progress payments and
	shall not be construed as a basis for additions to or deductions
	from the contract price. The Contractor shall prorate its overhead
	and profit 
	(i)
	Notwithstanding any provisions herein to the contrary, the
	establishment of the time periods in paragraphs (a) and (c) above
	relate only to the specific obligation of the Contractor to correct
	the work, and have no relationship to the time within which its
	obligation to comply with the contract may be sought to be enforced,
	nor to the time within which proceedings may be commenced to
	establish the Contractor’s liability with respect to its
	obligation other than specifically to correct the work. 
	over
	the construction period of the contract. 
	(d)
	The Contractor shall submit, on forms provided by the 
	PHA,
	periodic estimates showing the value of the work performed during
	each period based upon the approved 
	 
	submitted
	not later than 
	days
	in advance of 
	(j)
	This warranty shall not limit the PHA’s rights under the 
	the
	date set for payment and are subject to correction and revision as
	required. The estimates must be approved by the Contracting Officer
	with the concurrence of the Architect prior to payment. If the
	contract covers more than one project, the Contractor shall furnish
	a 
	Inspection
	and Acceptance of Construction clause of this contract with respect
	to latent defects, gross mistakes or fraud. 
	24.
	Prohibition Against Liens 
	separate
	progress payment estimate for each. 
	The
	Contractor is prohibited from placing a lien on the PHA’s
	property. This prohibition shall apply to all subcontractors at any
	tier and all materials suppliers. 
	(e)
	Along with each request for progress payments and the required
	estimates, the Contractor shall furnish the following certification,
	or payment shall not be made: I hereby certify, to the best of my
	knowledge and belief, 
	that: 
	Administrative
	Requirements 
	(1)
	The amounts requested are only for performance in accordance with
	the specifications, terms, and 
	25.
	Contract Period 
	conditions
	of the contract; 
	 
	(2)
	Payments to subcontractors and suppliers have been made from
	previous payments received under the contract, and timely payments
	will be made from the proceeds of the payment covered by this
	certification, in accordance with subcontract agreements; and, 
	this
	contract within 
	calendar
	days of the 
	effective
	date of the contract, or within the time schedule established in the
	notice to proceed issued by the Contracting Officer. 
	(3)
	This request for progress payments does not include 
	26.
	Order of Provisions 
	any
	amounts which the prime contractor intends to withhold or retain
	from a subcontractor or supplier in accordance with the terms and
	conditions of the subcontract. 
	In
	the event of a conflict between these General 
	Conditions
	and the Specifications, the General 
	Conditions
	shall prevail. In the event of a conflict between the contract and
	any applicable state or local law or regulation, the state or local
	law or regulation shall prevail; provided that such state or local
	law or regulation does not conflict with, or is less restrictive
	than applicable federal law, regulation, or Executive Order. In the
	event of such a conflict, applicable federal law, regulation, and
	Executive Order shall prevail. 
	Name: 
	Title: 
	Date: 
	27.
	Payments 
	(f)
	Except as otherwise provided in State law, the PHA shall 
	(a)
	The PHA shall pay the Contractor the price as provided in 
	retain
	ten (10) percent of the amount of progress payments until completion
	and acceptance of all work under the contract; except, that if upon
	completion of 50 percent of the work, the Contracting Officer, after
	consulting with the Architect, determines that the Contractor’s
	performance and progress are satisfactory, 
	this
	contract. 
	(b)
	The PHA shall make progress payments approximately every 30 days as
	the work proceeds, on estimates of work accomplished which meets the
	standards of quality established under the contract, as approved by
	the Contracting Officer. The PHA may, subject to written
	determination and approval of the Contracting Officer, make more
	frequent payments to contractors which are 
	the
	PHA may make the remaining payments in full for the work
	subsequently completed. If the Contracting Officer subsequently
	determines that the Contractor’s performance and progress are
	unsatisfactory, the PHA shall reinstate the ten (10) percent (or
	other percentage as provided in State law) retainage until such time
	as the Contracting Officer determines that performance and 
	qualified
	small businesses. 
	(c)
	Before the first progress payment under this contract, the
	Contractor shall furnish, in such detail as requested by the
	Contracting Officer, a breakdown of the total contract price showing
	the amount included therein for each principal category of the work,
	which shall substantiate the payment amount requested in order to
	provide a 
	progress
	are satisfactory. 
	(g)
	The Contracting Officer may authorize material delivered on the site
	and preparatory work done to be taken into consideration when
	computing progress payments. 
	Previous
	editions are obsolete Replaces form HUD-5370-A 
	Page
	9 of 19 
	form
	HUD-5370 (1/2014) 
	 
	 
		
	
	
	
	 
	
 
 
 
 
	Material
	delivered to the Contractor at locations other than the site may
	also be taken into consideration if the Contractor furnishes
	satisfactory evidence that (1) it has acquired title to such
	material; (2) the material is properly stored in a bonded warehouse,
	storage yard, or similar suitable place as may be approved by the
	Contracting Officer; (3) the material is insured to cover its full
	value; and (4) the material will be used to perform this contract.
	Before any progress payment which includes delivered material is
	made, the Contractor shall furnish such documentation as the
	Contracting Officer may require to assure the protection of the
	PHA’s interest in such materials. The Contractor shall remain
	responsible for such stored material notwithstanding the transfer of
	title 
	responsibilities
	of the parties (e.g., change in the PHA address). All other contract
	modifications shall be in the form of supplemental agreements signed
	by the 
	Contractor
	and the Contracting Officer. 
	(c)
	When a proposed modification requires the approval of HUD prior to
	its issuance (e.g., a change order that exceeds the PHA’s
	approved threshold), such modification shall not be effective until
	the required approval is received by the PHA. 
	29.
	Changes 
	(a)
	The Contracting Officer may, at any time, without notice 
	to
	the PHA. 
	to
	the sureties, by written order designated or indicated to be a
	change order, make changes in the work within the general scope of
	the contract including changes: 
		In
		the specifications (including drawings and designs); In
		the method or manner of performance of the work; 
	(h)
	All material and work covered by progress payments 
	made
	shall, at the time of payment become the sole property of the PHA,
	but this shall not be construed as (1) relieving the Contractor from
	the sole responsibility for all material and work upon which
	payments have been made or the restoration of any damaged work; or,
	(2) waiving the right of the PHA to require the fulfillment of all
	of the terms of the contract. In the event the work of the
	Contractor has been damaged by other contractors or persons other
	than employees of the PHA in the course of their employment, the
	Contractor shall restore such damaged work without cost to the PHA
	and to seek redress for its damage only from those who directly 
	(3)
	PHA-furnished facilities, equipment, materials, 
	services,
	or site; or, 
	(4)
	Directing the acceleration in the performance of the 
	caused
	it. 
	work. 
	(b)
	Any other written order or oral order (which, as used in this
	paragraph (b), includes direction, instruction, interpretation, or
	determination) from the Contracting Officer that causes a change
	shall be treated as a change order under this clause; provided, that
	the Contractor gives the Contracting Officer written notice stating
	(1) the date, circumstances and source of the order and (2) that the
	Contractor regards the order as a 
	(i)
	The PHA shall make the final payment due the Contractor 
	under
	this contract after (1) completion and final acceptance of all work;
	and (2) presentation of release of all claims against the PHA
	arising by virtue of this contract, other than claims, in stated
	amounts, that the Contractor has specifically excepted from the
	operation of the release. Each such exception shall embrace no more
	than one claim, the basis and scope of which shall be clearly
	defined. The amounts for such excepted claims shall not be included
	in the request for final payment. A release may also be required of
	the assignee if the Contractor’s claim to amounts payable
	under this contract 
	change
	order. 
	(c)
	Except as provided in this clause, no order, statement or conduct of
	the Contracting Officer shall be treated as a change under this
	clause or entitle the Contractor to an 
	equitable
	adjustment. 
	(d)
	If any change under this clause causes an increase or 
	has
	been assigned. 
	decrease
	in the Contractor’s cost of, or the time required for the
	performance of any part of the work under this contract, whether or
	not changed by any such order, the Contracting Officer shall make an
	equitable adjustment and modify the contract in writing. However,
	except for a adjustment based on defective specifications, no
	proposal for any change under paragraph (b) above shall be allowed
	for any costs incurred more than 20 days (5 days for oral orders)
	before the Contractor gives written notice as required. In the case
	of defective specifications for which the PHA is responsible, the
	equitable adjustment shall include any increased cost reasonably
	incurred by the Contractor in attempting to comply with 
	(j)
	Prior to making any payment, the Contracting Officer may 
	require
	the Contractor to furnish receipts or other evidence of payment from
	all persons performing work and supplying material to the
	Contractor, if the Contracting Officer determines such evidence is 
	necessary
	to substantiate claimed costs. 
	(k)
	The PHA shall not; (1) determine or adjust any claims for payment or
	disputes arising there under between the Contractor and its
	subcontractors or material suppliers; or, (2) withhold any moneys
	for the protection of the subcontractors or material suppliers. The
	failure or refusal of the PHA to withhold moneys from the Contractor
	shall in nowise impair the obligations of any surety or sureties
	under any bonds furnished under this contract. 
	the
	defective specifications. 
	(e)
	The Contractor must assert its right to an adjustment 
	28.
	Contract Modifications 
	under
	this clause within 30 days after (1) receipt of a written change
	order under paragraph (a) of this clause, or (2) the furnishing of a
	written notice under paragraph (b) of this clause, by submitting a
	written statement describing the general nature and the amount of
	the proposal. If the facts justify it, the Contracting Officer may
	extend the period for submission. The proposal may be included in
	the notice required under paragraph (b) above. No proposal by the
	Contractor for an equitable adjustment shall be allowed if asserted
	after final 
	(a)
	Only the Contracting Officer has authority to modify any 
	term
	or condition of this contract. Any contract 
	payment
	under this contract. 
	modification
	shall be authorized in writing. 
	(f)
	The Contractor’s written proposal for equitable adjustment
	shall be submitted in the form of a lump sum proposal supported with
	an itemized breakdown of all increases and decreases in the contract
	in at least the following details: 
	(b)
	The Contracting Officer may modify the contract 
	unilaterally
	(1) pursuant to a specific authorization stated 
	in
	a contract clause (e.g., Changes); or (2) for 
	administrative
	matters which do not change the rights or 
	Previous
	editions are obsolete Replaces form HUD-5370-A 
	Page
	10 of 19 
	form
	HUD-5370 (1/2014) 
	 
	
		
	 
	
 
 
 
 
	(1)
	Direct Costs. Materials (list individual items, the 
	been
	so suspended, delayed, or interrupted by any other cause, including
	the fault or negligence of the Contractor or for which any equitable
	adjustment is provided for or excluded under any other provision of
	this contract. 
	quantity
	and unit cost of each, and the aggregate cost); Transportation and
	delivery costs associated with materials; Labor breakdowns by hours
	or unit costs (identified with specific work to be performed);
	Construction equipment exclusively necessary for the change; Costs
	of preparation and/ or revision to shop drawings resulting from the
	change; Worker’s Compensation and Public Liability Insurance;
	Employment taxes under FICA and FUTA; and, Bond Costs when size of
	change warrants revision. 
		Indirect
		Costs. Indirect costs may include overhead, general and
		administrative expenses, and fringe benefits not normally treated
		as direct costs. 
		Profit.
		The amount of profit shall be negotiated and 
	may
	vary according to the nature, extent, and 
	complexity
	of the work required by the change. The allowability of the direct
	and indirect costs shall be determined in accordance with the
	Contract Cost Principles and Procedures for Commercial Firms in Part
	31 of the Federal Acquisition Regulation (48 CFR 1-31), as
	implemented by HUD Handbook 2210.18, in effect on the date of this
	contract. The Contractor shall not be 
	(c)
	A claim under this clause shall not be allowed (1) for any 
	costs
	incurred more than 20 days before the Contractor shall have notified
	the Contracting Officer in writing of the act or failure to act
	involved (but this requirement shall not apply as to a claim
	resulting from a suspension order); and, (2) unless the claim, in an
	amount stated, is asserted in writing as soon as practicable after
	the termination of the suspension, delay, or interruption, but not
	later than the date of final payment under the contract. 
	31.
	Disputes 
	allowed
	a profit on the profit received by any 
	(a)
	“Claim,” as used in this clause, means a written demand
	or written assertion by one of the contracting parties seeking, as a
	matter of right, the payment of money in a sum certain, the
	adjustment or interpretation of contract terms, or other relief
	arising under or relating to the contract. A claim arising under the
	contract, unlike a claim relating to the contract, is a claim that
	can be resolved under a contract clause that provides for the relief
	sought by the claimant. A voucher, invoice, or other routine request
	for payment that is not in dispute when submitted is not a claim.
	The submission may be converted to a claim by complying with the
	requirements of this clause, if it is disputed either as to
	liability or amount or is not acted upon in a reasonable time. 
	subcontractor.
	Equitable adjustments for deleted work shall include a credit for
	profit and may include a credit for indirect costs. On proposals
	covering both increases and decreases in the amount of the contract,
	the application of indirect costs and profit shall be on the
	net-change in direct costs for the Contractor or subcontractor 
	performing
	the work. 
	(g)
	The Contractor shall include in the proposal its request for time
	extension (if any), and shall include sufficient information and
	dates to demonstrate whether and to what extent the change will
	delay the completion of the 
	(b)
	Except for disputes arising under the clauses entitled 
	contract
	in its entirety. 
	Labor
	Standards - Davis Bacon and Related Acts, herein, all disputes
	arising under or relating to this contract, including any claims for
	damages for the alleged breach thereof which are not disposed of by
	agreement, shall be 
	(h)
	The Contracting Officer shall act on proposals within 30 days after
	their receipt, or notify the Contractor of the 
	resolved
	under this clause. 
	(c)
	All claims by the Contractor shall be made in writing and 
	date
	when such action will be taken. 
	submitted
	to the Contracting Officer for a written decision. A claim by the
	PHA against the Contractor shall be subject to a written decision by
	the Contracting Officer. 
	(d)
	The Contracting Officer shall, within 60 (unless otherwise
	indicated) days after receipt of the request, decide the claim or
	notify the Contractor of the date by which the 
	(i)
	Failure to reach an agreement on any proposal shall be a 
	dispute
	under the clause entitled Disputes herein. Nothing in this clause,
	however, shall excuse the 
	Contractor
	from proceeding with the contract as changed. 
	(j)
	Except in an emergency endangering life or property, no 
	change
	shall be made by the Contractor without a prior order from the
	Contracting Officer. 
	decision
	will be made. 
	(e)
	The Contracting Officer’s decision shall be final unless 
	30.
	Suspension of Work 
	the
	Contractor (1) appeals in writing to a higher level in the PHA in
	accordance with the PHA’s policy and procedures, (2) refers
	the appeal to an independent mediator or arbitrator, or (3) files
	suit in a court of competent jurisdiction. Such appeal must be made
	within (30 unless otherwise indicated) days after receipt of the 
	(a)
	The Contracting Officer may order the Contractor in 
	writing
	to suspend, delay, or interrupt all or any part of the work of this
	contract for the period of time that the Contracting Officer
	determines appropriate for the 
	Contracting
	Officer’s decision. 
	convenience
	of the PHA. 
	(f)
	The Contractor shall proceed diligently with performance 
	(b)
	If the performance of all or any part of the work is, for an
	unreasonable period of time, suspended, delayed, or interrupted (1)
	by an act of the Contracting Officer in the administration of this
	contract, or (2) by the Contracting Officer’s failure to act
	within the time specified (or within a reasonable time if not
	specified) in this contract an adjustment shall be made for any
	increase in the cost of performance of the contract (excluding
	profit) necessarily caused by such unreasonable suspension, delay,
	or interruption and the contract modified in writing accordingly.
	However, no adjustment shall be made under this clause for any
	suspension, delay, or interruption to the extent that performance
	would have 
	of
	this contract, pending final resolution of any request for relief,
	claim, appeal, or action arising under or relating to the contract,
	and comply with any decision of the Contracting Officer. 
	32.
	Default 
	(a)
	If the Contractor refuses or fails to prosecute the work, or any
	separable part thereof, with the diligence that will insure its
	completion within the time specified in this contract, or any
	extension thereof, or fails to complete said work within this time,
	the Contracting Officer may, by written notice to the Contractor,
	terminate the right to 
	Previous
	editions are obsolete Replaces form HUD-5370-A 
	Page
	11 of 19 
	form
	HUD-5370 (1/2014) 
	 
	
		
	 
	
 
 
 
 
	proceed
	with the work (or separable part of the work) that has been delayed.
	In this event, the PHA may take over the work and complete it, by
	contract or otherwise, and may take possession of and use any
	materials, equipment, and plant on the work site necessary for
	completing the work. The Contractor and its sureties shall be liable
	for any damage to the PHA resulting from the Contractor’s
	refusal or failure to complete the work within 
	completion
	of the work together with any increased costs 
	occasioned
	the PHA in completing the work. 
	(c)
	If the PHA does not terminate the Contractor’s right to 
	proceed,
	the resulting damage will consist of liquidated damages until the
	work is completed or accepted. 
	34.
	Termination for Convenience 
	the
	specified time, whether or not the Contractor’s right to
	proceed with the work is terminated. This liability includes any
	increased costs incurred by the PHA in completing 
	(a)
	The Contracting Officer may terminate this contract in whole, or in
	part, whenever the Contracting Officer determines that such
	termination is in the best interest of the PHA. Any such termination
	shall be effected by delivery to the Contractor of a Notice of
	Termination specifying the extent to which the performance of the
	work under the contract is terminated, and the date upon 
	the
	work. 
	(b)
	The Contractor’s right to proceed shall not be terminated or
	the Contractor charged with damages under this 
	clause
	if— 
	(1)
	The delay in completing the work arises from 
	which
	such termination becomes effective. 
	unforeseeable
	causes beyond the control and without the fault or negligence of the
	Contractor. Examples of such causes include (i) acts of God, or of
	the public enemy, (ii) acts of the PHA or other governmental entity
	in either its sovereign or contractual capacity, (iii) acts of
	another contractor in the performance of a contract with the PHA,
	(iv) fires, (v) floods, (vi) epidemics, (vii) quarantine
	restrictions, (viii) strikes, (ix) freight embargoes, (x) unusually
	severe weather, or (xi) delays of subcontractors or suppliers at any
	tier arising from unforeseeable causes beyond the control and
	without the fault or negligence of both the Contractor and the
	subcontractors or suppliers; and 
	(2)
	The Contractor, within days (10 days unless otherwise indicated)
	from the beginning of such delay (unless extended by the Contracting
	Officer) notifies the Contracting Officer in writing of the causes
	of delay. The Contracting Officer shall ascertain the facts and the
	extent of the delay. If, in the judgment of the Contracting Officer,
	the findings of fact warrant such action, time for completing the
	work shall be extended by written modification to the contract. The
	findings of the Contracting Officer shall be reduced to a written
	decision which shall be subject to the provisions of 
	(b)
	If the performance of the work is terminated, either in 
	whole
	or in part, the PHA shall be liable to the Contractor for reasonable
	and proper costs resulting from such termination upon the receipt by
	the PHA of a properly presented claim setting out in detail: (1) the
	total cost of the work performed to date of termination less the
	total amount of contract payments made to the Contractor; (2) the
	cost (including reasonable profit) of settling and paying claims
	under subcontracts and material orders for work performed and
	materials and supplies delivered to the site, payment for which has
	not been made by the PHA to the Contractor or by the Contractor to
	the subcontractor or supplier; (3) the cost of preserving and
	protecting the work already performed until the PHA or 
	assignee
	takes possession thereof or assumes 
	responsibility
	therefore; (4) the actual or estimated cost of legal and accounting
	services reasonably necessary to prepare and present the termination
	claim to the PHA; and (5) an amount constituting a reasonable profit
	on the 
	value
	of the work performed by the Contractor. 
	(c)
	The Contracting Officer will act on the Contractor’s claim
	within days (60 days unless otherwise indicated) of 
	receipt
	of the Contractor’s claim. 
	(d)
	Any disputes with regard to this clause are expressly 
	the
	Disputes clause of this contract. 
	made
	subject to the provisions of the Disputes clause of this contract. 
	(c)
	If, after termination of the Contractor’s right to proceed, it
	is determined that the Contractor was not in default, or that the
	delay was excusable, the rights and obligations of the parties will
	be the same as if the termination had been for convenience of the
	PHA. 
	35.
	Assignment of Contract 
	33.
	Liquidated Damages 
	The
	Contractor shall not assign or transfer any interest in this
	contract; except that claims for monies due or to become due from
	the PHA under the contract may be assigned to a bank, trust company,
	or other financial institution. Such assignments of claims shall
	only be made with the written concurrence of the Contracting
	Officer. If the Contractor is a partnership, this contract shall
	inure to the benefit of the surviving or remaining member(s) of such
	partnership as approved by the Contracting Officer. 
	(a)
	If the Contractor fails to complete the work within the time 
	specified
	in the contract, or any extension, as specified in the clause
	entitled Default of this contract, the Contractor 
	shall
	pay to the PHA as liquidated damages, the sum of Contracting Officer
	insert amount] for 
	$ 
	each
	day of delay. If different completion dates are specified in the
	contract for separate parts or stages of the work, the amount of
	liquidated damages shall be assessed on those parts or stages which
	are delayed. To the extent that the Contractor’s delay or
	nonperformance is excused under another clause in this contract,
	liquidated damages shall not be due the PHA. The Contractor remains
	liable for damages caused other than 
	36.
	Insurance 
	(a)
	Before commencing work, the Contractor and each 
	subcontractor
	shall furnish the PHA with certificates of insurance showing the
	following insurance is in force and 
	will
	insure all operations under the Contract: 
	by
	delay. 
	(1)
	Workers’ Compensation, in accordance with state or 
	(b)
	If the PHA terminates the Contractor’s right to proceed, 
	Territorial
	Workers’ Compensation laws. 
	the
	resulting damage will consist of liquidated damages until such
	reasonable time as may be required for final 
	(2)
	Commercial General Liability with a combined single 
	than
	$ 
	limit
	for bodily injury and property damage of not less [Contracting
	Officer insert amount] 
	Previous
	editions are obsolete Replaces form HUD-5370-A 
	Page
	12 of 19 
	form
	HUD-5370 (1/2014) 
	 
	
	 
	
 
 
 
 
	per
	occurrence to protect the Contractor and each subcontractor against
	claims for bodily injury or death and damage to the property of
	others. This shall cover the use of all equipment, hoists, and
	vehicles 
	(2)
	“Subcontractor” means any supplier, vendor, or firm that
	furnishes supplies, materials, equipment, or services to or for the
	Contractor or another 
	subcontractor. 
	on
	the site(s) not covered by Automobile Liability 
	(b)
	The Contractor shall not enter into any subcontract with any
	subcontractor who has been temporarily denied participation in a HUD
	program or who has been suspended or debarred from participating in
	contracting 
	under
	(3) below. If the Contractor has a made” policy, then the
	following additional requirements apply: the policy must provide a
	“retroactive date” which must be on or before the 
	“claims- 
	programs
	by any agency of the United States 
	execution
	date of the Contract; and the extended reporting period may not be
	less than five years 
	Government
	or of the state in which the work under this 
	contract
	is to be performed. 
	following
	the completion date of the Contract. 
	(c)
	The Contractor shall be as fully responsible for the acts or
	omissions of its subcontractors, and of persons either directly or
	indirectly employed by them as for the acts or omissions of persons
	directly employed by the 
	(3)
	Automobile Liability on owned and non -owned motor vehicles used on
	the site(s) or in connection therewith 
	for
	a combined single limit for bodily injury and 
	property
	damage of not less than $ 
	Contractor. 
	[Contracting
	Officer insert amount] per occurrence. 
	(d)
	The Contractor shall insert appropriate clauses in all 
	(b)
	Before commencing work, the Contractor shall furnish the 
	subcontracts
	to bind subcontractors to the terms and conditions of this contract
	insofar as they are applicable 
	PHA
	with a certificate of insurance evidencing that Builder’s Risk
	(fire and extended coverage) Insurance on all work in place and/or
	materials stored at the building site(s), including foundations and
	building equipment, is in force. The Builder’s Risk Insurance
	shall be for the benefit of the Contractor and the PHA as their
	interests may appear and each shall be named in the policy or
	policies as an insured. The Contractor in installing equipment
	supplied by the PHA shall carry insurance on such equipment from the
	time the Contractor takes possession thereof until the Contract work
	is accepted by the PHA. The Builder’s Risk Insurance need not
	be carried on excavations, piers, footings, or foundations until
	such time as work on the superstructure is started. It need not be
	carried on landscape work. Policies shall furnish coverage at all
	times for the full cash value of all completed construction, as well
	as materials in place and/or stored at the site(s), whether or not
	partial payment has been made by the PHA. The Contractor may
	terminate this insurance on buildings as of the date taken over for
	occupancy by the PHA. The Contractor is not required to carry
	Builder’s Risk Insurance for modernization work which does not
	involve structural alterations or additions and where the PHA’s
	existing fire and extended coverage policy can be endorsed to 
	to
	the work of subcontractors. 
	(e)
	Nothing contained in this contract shall create any 
	contractual
	relationship between any subcontractor and the PHA or between the
	subcontractor and HUD. 
	38.
	Subcontracting with Small and Minority Firms, 
	Women’s
	Business Enterprise, and Labor Surplus Area Firms 
	The
	Contractor shall take the following steps to ensure  
	enterprises,
	and labor surplus area firms: 
	(a)
	Placing qualified small and minority businesses and 
	women’s
	business enterprises on solicitation lists; 
	(b)
	Ensuring that small and minority businesses and women’s
	business enterprises are solicited whenever 
	they
	are potential sources; 
	(c)
	Dividing total requirements, when economically feasible, into
	smaller tasks or quantities to permit maximum participation by small
	and minority businesses and 
	women’s
	business enterprises; 
	(d)
	Establishing delivery schedules, where the requirements 
	include
	such work. 
	of
	the contract permit, which encourage participation by small and
	minority businesses and women’s business 
	(c)
	All insurance shall be carried with companies which are 
	enterprises;
	and 
	financially
	responsible and admitted to do business in the State in which the
	project is located. If any such insurance is due to expire during
	the construction period, the Contractor (including subcontractors,
	as applicable) shall not permit the coverage to lapse and shall
	furnish evidence of coverage to the Contracting Officer. All
	certificates of insurance, as evidence of coverage, shall provide
	that no coverage may be canceled or non-renewed by the insurance
	company until at least 30 days prior written notice has been given
	to the Contracting Officer. 
	(e)
	Using the services and assistance of the U.S. Small Business
	Administration, the Minority Business Development Agency of the U.S.
	Department of Commerce, and State and local governmental small
	business agencies. 
	39.
	Equal Employment Opportunity 
	During
	the performance of this contract, the Contractor 
	agrees
	as follows: 
	(a)
	The Contractor shall not discriminate against any 
	employee
	or applicant for employment because of race, 
	37.
	Subcontracts 
	color,
	religion, sex, national origin, or handicap. 
	(b)
	The Contractor shall take affirmative action to ensure that 
	(a)
	Definitions. As used in this contract - 
	applicants
	are employed, and that employees are treated during employment
	without regard to their race, color, religion, sex, national origin,
	or handicap. Such action shall include, but not be limited to, (1)
	employment, (2) upgrading, (3) demotion, (4) transfer, (5)
	recruitment or recruitment advertising, (6) layoff or termination,
	(7) rates of pay or other forms of compensation, and (8) selection
	for training, including apprenticeship. 
	(1)
	“Subcontract” means any contract, purchase order, or
	other purchase agreement, including modifications and change orders
	to the foregoing, entered into by a subcontractor to furnish
	supplies, materials, equipment, and services for the performance of
	the prime contract or a subcontract. 
	Previous
	editions are obsolete Replaces form HUD-5370-A 
	Page
	13 of 19 
	form
	HUD-5370 (1/2014) 
	 
	
that,
	whenever possible, subcontracts are awarded to 
small business
	firms, minority firms, women’s business
	 
	
 
 
 
 
	(c)
	The Contractor shall post in conspicuous places available 
	(a)
	The work to be performed under this contract is subject to the
	requirements of section 3 of the Housing and Urban Development Act
	of 1968, as amended, 12 U.S.C. 1701u (section 3). The purpose of
	section 3 is to ensure that employment and other economic
	opportunities generated by HUD assistance or HUD-assisted projects
	covered by section 3, shall, to the greatest extent feasible, be
	directed to low- and very low-income persons, particularly persons
	who are recipients of HUD assistance for 
	to
	employees and applicants for employment the notices to be provided
	by the Contracting Officer that explain this 
	clause. 
	(d)
	The Contractor shall, in all solicitations or advertisements for
	employees placed by or on behalf of the Contractor, state that all
	qualified applicants will receive consideration for employment
	without regard to race, color, religion, sex, national origin, or
	handicap. 
	(e)
	The Contractor shall send, to each labor union or 
	housing. 
	representative
	of workers with which it has a collective bargaining agreement or
	other contract or understanding, the notice to be provided by the
	Contracting Officer advising the labor union or workers’
	representative of the Contractor’s commitments under this
	clause, and post copies of the notice in conspicuous places
	available to 
	(b)
	The parties to this contract agree to comply with HUD's 
	regulations
	in 24 CFR Part 135, which implement section 3. As evidenced by their
	execution of this contract, the parties to this contract certify
	that they are under no contractual or other impediment that would
	prevent them 
	from
	complying with the Part 135 regulations. 
	employees
	and applicants for employment. 
	(c)
	The contractor agrees to send to each labor organization or
	representative of workers with which the contractor has a collective
	bargaining agreement or other understanding, if any, a notice
	advising the labor organization or workers' representative of the
	contractor's commitments under this section 3 clause, and will post
	copies of the notice in conspicuous places at the work site where
	both employees and applicants for training and employment positions
	can see the notice. The notice shall describe the section 3
	preference, shall set forth minimum number and job titles subject to
	hire, availability of apprenticeship and training positions, the
	qualifications for each; and the name and location of the person(s)
	taking applications for each of the positions; and the 
	(f)
	The Contractor shall comply with Executive Order 11246, 
	as
	amended, and the rules, regulations, and orders of the 
	Secretary
	of Labor. 
	(g)
	The Contractor shall furnish all information and reports 
	required
	by Executive Order 11246, as amended, Section 503 of the
	Rehabilitation Act of 1973, as amended, and by rules, regulations,
	and orders of the Secretary of Labor, or pursuant thereto. The
	Contractor shall permit access to its books, records, and accounts
	by the Secretary of Labor for purposes of investigation to ascertain
	compliance with such rules, regulations, and 
	orders. 
	(h)
	In the event of a determination that the Contractor is not 
	in
	compliance with this clause or any rule, regulation, or order of the
	Secretary of Labor, this contract may be canceled, terminated, or
	suspended in whole or in part, and the Contractor may be declared
	ineligible for further Government contracts, or Federally assisted
	construction contracts under the procedures authorized in Executive
	Order 11246, as amended. In addition, sanctions may be imposed and
	remedies invoked against the Contractor as provided in Executive
	Order 11246, as amended, the rules, regulations, and orders of the
	Secretary of Labor, 
	anticipated
	date the work shall begin. 
	(d)
	The contractor agrees to include this section 3 clause in 
	every
	subcontract subject to compliance with regulations in 24 CFR Part
	135, and agrees to take appropriate action, as provided in an
	applicable provision of the subcontract or in this section 3 clause,
	upon a finding that the subcontractor is in violation of the
	regulations in 24 CFR Part 135. The contractor will not subcontract
	with any subcontractor where the contractor has notice or knowledge
	that the subcontractor has been found in 
	or
	as otherwise provided by law. 
	violation
	of the regulations in 24 CFR Part 135. 
	(i)
	The Contractor shall include the terms and conditions of 
	(e)
	The contractor will certify that any vacant employment 
	this
	clause in every subcontract or purchase order unless exempted by the
	rules, regulations, or orders of the Secretary of Labor issued under
	Executive Order 11246, as amended, so that these terms and
	conditions will be binding upon each subcontractor or vendor. The
	Contractor shall take such action with respect to any subcontract or
	purchase order as the Secretary of Housing and Urban Development or
	the Secretary of Labor may direct as a means of enforcing such
	provisions, including sanctions for noncompliance; provided that if
	the Contractor becomes involved in, or is threatened with,
	litigation with a subcontractor or vendor as a result of such
	direction, the Contractor may request the United States to enter
	into the litigation to protect the 
	positions,
	including training positions, that are filled (1) after the
	contractor is selected but before the contract is executed, and (2)
	with persons other than those to whom the regulations of 24 CFR Part
	135 require employment opportunities to be directed, were not filled
	to circumvent the contractor's obligations under 24 CFR Part 135. 
	(f)
	Noncompliance with HUD's regulations in 24 CFR Part 
	135
	may result in sanctions, termination of this contract for default,
	and debarment or suspension from future 
	HUD
	assisted contracts. 
	interests
	of the United States. 
	(g)
	With respect to work performed in connection with section 3 covered
	Indian housing assistance, section 7(b) of the Indian
	Self-Determination and Education Assistance Act (25 U.S.C. 450e)
	also applies to the work to be performed under this contract.
	Section 7(b) requires that to the greatest extent feasible (i)
	preference and opportunities for training and employment shall be
	given to Indians, and (ii) preference in the award of contracts and
	subcontracts shall be given to Indian organizations and Indian-owned
	Economic Enterprises. Parties to this contract that are subject to
	the provisions of section 3 and section 7(b)agree to comply with
	section 3 to the maximum extent feasible, but not in derogation of
	compliance with section 7(b). 
	(j)
	Compliance with the requirements of this clause shall be 
	to
	the maximum extent consistent with, but not in derogation of,
	compliance with section 7(b) of the Indian Self-Determination and
	Education Assistance Act and the Indian Preference clause of this
	contract. 
	40.
	Employment, Training, and Contracting 
	Opportunities
	for Low-Income Persons, Section 3 of the Housing and Urban
	Development Act of 1968. 
	Previous
	editions are obsolete Replaces form HUD-5370-A 
	Page
	14 of 19 
	form
	HUD-5370 (1/2014) 
	 
	
	 
	
 
 
 
 
	41.
	Interest of Members of Congress 
	(a)
	The PHA, HUD, or Comptroller General of the United 
	No
	member of or delegate to the Congress of the United States of
	America shall be admitted to any share or part of this contract or
	to any benefit that may arise therefrom. 
	States,
	or any of their duly authorized representatives shall, until 3 years
	after final payment under this contract, have access to and the
	right to examine any of the Contractor’s directly pertinent
	books, documents, papers, or other records involving transactions
	related to this contract for the purpose of making audit,
	examination, 
	42.
	Interest of Members, Officers, or Employees and Former Members,
	Officers, or Employees 
	excerpts,
	and transcriptions. 
	No
	member, officer, or employee of the PHA, no member of the governing
	body of the locality in which the project is situated, no member of
	the governing body of the locality in which the PHA was activated,
	and no other public official of such locality or localities who
	exercises any functions or responsibilities with respect to the
	project, shall, during his or her tenure, or for one year
	thereafter, have any interest, direct or indirect, in this contract
	or the proceeds thereof. 
	(b)
	The Contractor agrees to include in first-tier subcontracts under
	this contract a clause substantially the same as paragraph (a)
	above. “Subcontract,” as used in this clause, excludes
	purchase orders not exceeding 
	$10,000. 
	43.
	Limitations on Payments made to Influence Certain Federal Financial
	Transactions 
	(c)
	The periods of access and examination in paragraphs (a) and (b)
	above for records relating to (1) appeals under the Disputes clause
	of this contract, (2) litigation or settlement of claims arising
	from the performance of this contract, or (3) costs and expenses of
	this contract to which the PHA, HUD, or Comptroller General or any
	of their duly authorized representatives has taken exception shall
	continue until disposition of such appeals, litigation, claims, or
	exceptions. 
	(a)
	The Contractor agrees to comply with Section 1352 of 
	Title
	31, United States Code which prohibits the use of Federal
	appropriated funds to pay any person for influencing or attempting
	to influence an officer or employee of any agency, a Member of
	Congress, and officer or employee of Congress, or an employee of a
	Member of Congress in connection with any of the following covered
	Federal actions: the awarding of any Federal contract; the making of
	any Federal grant; the making of any Federal loan; the entering into
	of any cooperative agreement; or the modification of any 
	46.
	Labor Standards - Davis-Bacon and Related Acts 
	If
	the total amount of this contract exceeds $2,000, the Federal labor
	standards set forth in the clause below shall apply to the
	development or construction work to be 
	performed
	under the contract. 
	(a)
	Minimum Wages. 
	Federal
	contract, grant, loan, or cooperative agreement. 
	(1)
	All laborers and mechanics employed under this contract in the
	development or construction of the project(s) involved will be paid
	unconditionally and not less often than once a week, and without
	subsequent deduction or rebate on any account (except such payroll
	deductions as are permitted by regulations issued by the Secretary
	of Labor under the Copeland Act (29 CFR Part 3)), the full amount of
	wages and bona fide fringe benefits (or cash equivalents thereof)
	due at time of payment computed at rates not less than those
	contained in the wage determination of the Secretary of Labor which
	is attached hereto and made a part hereof, regardless of any
	contractual relationship which may be alleged to exist between the
	Contractor and such laborers and mechanics. Contributions made or
	costs reasonably anticipated for bona fide fringe benefits under
	Section 1(b)(2) of the Davis-Bacon Act on behalf of laborers or
	mechanics are considered wages paid to such laborers or mechanics,
	subject to the provisions of 29 CFR 5.5(a)(1)(iv); also, regular
	contributions made or costs incurred for more than a weekly period
	(but not less often than quarterly) under plans, funds, or programs
	which cover the regular weekly period, are deemed to be
	constructively made or incurred during such weekly period. Such
	laborers and mechanics shall be paid the appropriate wage rate and
	fringe benefits in the wage determination for the classification of
	work actually performed, without regard to skill, except as provided
	in 29 CFR 5.5(a)(4). Laborers or mechanics performing 
	(b)
	The Contractor further agrees to comply with the 
	requirement
	of the Act to furnish a disclosure (OMB Standard Form LLL,
	Disclosure of Lobbying Activities) if any funds other than Federal
	appropriated funds (including profit or fee received under a covered
	Federal transaction) have been paid, or will be paid, to any person
	for influencing or attempting to influence an officer or employee of
	any agency, a Member of Congress, an officer or employee of
	Congress, or an employee of a Member of Congress in connection with
	a Federal contract, grant, loan, or cooperative agreement. 
	44.
	Royalties and Patents 
	The
	Contractor shall pay all royalties and license fees. It shall defend
	all suits or claims for infringement of any patent rights and shall
	save the PHA harmless from loss on account thereof; except that the
	PHA shall be responsible for all such loss when a particular design,
	process or the product of a particular manufacturer or manufacturers
	is specified and the Contractor has no reason to believe that the
	specified design, process, or product is an infringement. If,
	however, the Contractor has reason to believe that any design,
	process or product specified is an infringement of a patent, the
	Contractor shall promptly notify the Contracting Officer. Failure to
	give such notice shall make the Contractor responsible for resultant
	loss. 
	work
	in more than one classification may be 
	45.
	Examination and Retention of Contractor’s Records 
	compensated
	at the rate specified for each classification for the time actually
	worked therein; provided, that the employer’s payroll records
	accurately set forth the time spent in each classification in which
	work is performed. The wage determination (including any additional
	classification and wage rates conformed under 29 CFR 5.5(a)(1)(ii)
	and the Davis-Bacon poster (WH-1321) shall 
	Previous
	editions are obsolete Replaces form HUD-5370-A 
	Page
	15 of 19 
	form
	HUD-5370 (1/2014) 
	 
	
	 
	
 
 
 
 
	be
	posted at all times by the Contractor and its subcontractors at the
	site of the work in a prominent and accessible place where it can be
	easily seen by the 
	amount
	of any costs reasonably anticipated in providing bona fide fringe
	benefits under a plan or program; provided, that the Secretary of
	Labor has found, upon the written request of the Contractor, that
	the applicable standards of the Davis-Bacon Act have been met. The
	Secretary of Labor may require the Contractor to set aside in a
	separate account assets for the meeting of obligations under the
	plan or 
	workers. 
	(2)
	(i) Any class of laborers or mechanics, including 
	helpers,
	which is not listed in the wage 
	determination
	and which is to be employed under the contract shall be classified
	in conformance with the wage determination. HUD shall approve an
	additional classification and wage rate and fringe benefits therefor
	only when all the following criteria have been met: (A) The work to
	be performed by the classification requested is not performed by a
	classification in the wage determination; and (B) The classification
	is utilized in the area by the construction industry; and (C) The
	proposed wage rate, including any bona fide fringe benefits, bears a
	reasonable relationship to the wage rates contained in the wage 
	program. 
	determination. 
	(b)
	Withholding of funds. HUD or its designee shall, upon its own action
	or upon written request of an authorized representative of the
	Department of Labor, withhold or cause to be withheld from the
	Contractor under this contract or any other Federal contract with
	the same prime Contractor, or any other Federally-assisted contract
	subject to Davis-Bacon prevailing wage requirements, which is held
	by the same prime Contractor, so much of the accrued payments or
	advances as may be considered necessary to pay laborers and
	mechanics, including apprentices, trainees, and helpers, employed by
	the Contractor or any subcontractor the full amount of wages
	required by the contract. In the event of failure to pay any laborer
	or mechanic, including any apprentice, trainee, or helper, employed
	or working in the construction or development of the project, all or
	part of the wages required by the contract, HUD or its designee may,
	after written notice to the Contractor, take such action as may be
	necessary to cause the suspension of any further payment, advance,
	or guarantee of funds until such violations have ceased. HUD or its
	designee may, after written notice to the Contractor, disburse such
	amounts withheld for and on account of the Contractor or
	subcontractor to the 
	(ii)
	If the Contractor and the laborers and mechanics 
	to
	be employed in the classification (if known), or their
	representatives, and HUD or its designee agree on the classification
	and wage rate (including the amount designated for fringe benefits
	where appropriate), a report of the action taken shall be sent by
	HUD or its designee to the Administrator of the Wage and Hour
	Division, Employee Standards Administration, U.S. Department of
	Labor, Washington, DC 20210. 
	The
	Administrator, or an authorized 
	representative,
	will approve, modify, or disapprove every additional classification
	action within 30 days of receipt and so advise HUD or its designee
	or will notify HUD or its designee within the 30-day period that
	additional time is necessary. 
	respective
	employees to whom they are due. 
	(c)
	Payrolls and basic records. 
	(1)
	Payrolls and basic records relating thereto shall be 
	(iii)
	In the event the Contractor, the laborers or 
	maintained
	by the Contractor during the course of the work and preserved for a
	period of three years thereafter for all laborers and mechanics
	working in the construction or development of the project. Such
	records shall contain the name, address, and social security number
	of each such worker, his or her correct classification, hourly rates
	of wages paid (including rates of contributions or costs anticipated
	for bona fide fringe benefits or cash equivalents thereof of the
	types described in section 1(b)(2)(B) of the Davis-Bacon Act), daily
	and weekly number of hours worked, deductions made, and actual wages
	paid. Whenever the Secretary of Labor has found, under 29 CFR
	5.5(a)(1)(iv), that the wages of any laborer or mechanic include the
	amount of costs reasonably anticipated in providing benefits under a
	plan or program described in section 1(b)(2)(B) of the Davis-Bacon
	Act, the Contractor shall maintain records which show that the
	commitment to provide such benefits is enforceable, that the plan or
	program is financially responsible, and that the plan or program has
	been communicated in writing to the laborers or mechanics affected,
	and records which show the costs anticipated or the actual cost
	incurred in providing such benefits. Contractors employing
	apprentices or trainees under approved programs shall maintain
	written evidence of the registration of apprenticeship programs and
	certification of trainee programs, the registration of the
	apprentices and trainees, and the ratios and wage rates prescribed
	in the applicable programs. 
	mechanics
	to be employed in the classification or their representatives, and
	HUD or its designee do not agree on the proposed classification and
	wage rate (including the amount designated for fringe benefits,
	where appropriate), HUD or its designee shall refer the questions,
	including the views of all interested parties and the recommendation
	of HUD or its designee, to the Administrator of the Wage and Hour
	Division for determination. The Administrator, or an authorized
	representative, will issue a determination within 30 days of receipt
	and so advise HUD or its designee or will notify HUD or its designee
	within the 30-day period that 
	additional
	time is necessary. 
	(iv)
	The wage rate (including fringe benefits where 
	appropriate)
	determined pursuant to 
	subparagraphs
	(a)(2)(ii) or (iii) of this clause shall be paid to all workers
	performing work in the classification under this contract from the
	first day 
	on
	which work is performed in classification. 
	(3)
	Whenever the minimum wage rate prescribed in the 
	contract
	for a class of laborers or mechanics includes a fringe benefit which
	is not expressed as an hourly rate, the Contractor shall either pay
	the benefit as stated in the wage determination or shall pay another
	bona fide fringe benefit or an hourly cash equivalent 
	thereof. 
	(4)
	If the Contractor does not make payments to a trustee 
	or
	other third person, the Contractor may consider as part of the wages
	of any laborer or mechanic the 
	Previous
	editions are obsolete Replaces form HUD-5370-A 
	Page
	16 of 19 
	form
	HUD-5370 (1/2014) 
	 
	
	 
	
 
 
 
 
	(2)
	(i) The Contractor shall submit weekly for each week 
	make
	such records available may be grounds for debarment action pursuant
	to 29 CFR 5.12. 
	in
	which any contract work is performed a copy of 
	all
	payrolls to the Contracting Officer for 
	(d)
	(1) Apprentices. Apprentices will be permitted to work at 
	transmission
	to HUD or its designee. The payrolls submitted shall set out
	accurately and completely all of the information required to be
	maintained under subparagraph (c)(1) of this clause. This
	information may be submitted in any form desired. Optional Form
	WH-347 (Federal Stock Number 029-005-00014-1) is available for this
	purpose and may be purchased from the Superintendent of Documents,
	U.S. Government Printing Office, Washington, D.C. 20402. The
	Contractor is responsible for the submission of copies of payrolls
	by all subcontractors. (Approved by the Office of Management and
	Budget under OMB 
	less
	than the predetermined rate for the work they performed when they
	are employed pursuant to and individually registered in a bona fide
	apprenticeship program registered with the U.S. Department of Labor,
	Employment and Training Administration, Office of Apprenticeship and
	Training, Employer and 
	Labor
	Services (OATELS), or with a State 
	Apprenticeship
	Agency recognized by OATELS, or if a person is employed in his or
	her first 90 days of probationary employment as an apprentice in
	such an apprenticeship program, who is not individually registered
	in the program, but who has been certified by OATELS or a State
	Apprenticeship Agency (where 
	Control
	Number 1214-0149.) 
	appropriate)
	to be eligible for probationary 
	(ii)
	Each payroll submitted shall be accompanied by a 
	employment
	as an apprentice. The allowable ratio of apprentices to journeymen
	on the job site in any craft classification shall not be greater
	than the ratio permitted to the Contractor as to the entire work
	force under the registered program. Any worker listed on a payroll
	at an apprentice wage rate, who is not registered or otherwise
	employed as stated in this paragraph, shall be paid not less than
	the applicable wage rate on the wage determination for the
	classification of work actually performed. In addition, any
	apprentice performing work on the job site in excess of the ratio
	permitted under the registered program shall be paid not less than
	the applicable wage rate on the wage determination for the work
	actually performed. Where a contractor is performing construction on
	a project in a locality other than that in which its program is
	registered, the ratios and wage rates (expressed in percentages of
	the journeyman’s 
	“Statement
	of Compliance,” signed by the Contractor or subcontractor or
	his or her agent who pays or supervises the payment of the persons
	employed under the contract and shall 
	certify
	the following: 
		That
		the payroll for the payroll period contains the information
		required to be maintained under paragraph (c) (1) of this clause
		and that such information is correct and complete; 
		That
		each laborer or mechanic (including each helper, apprentice, and
		trainee) employed on the contract during the payroll period has
		been paid the full weekly wages earned, without rebate, either
		directly or indirectly, and that no deductions have been made
		either directly or indirectly from the full wages earned, other
		than permissible deductions as set forth in 29 
	CFR
	Part 3; and 
	hourly
	rate) specified in the Contractor’s or 
	(C)
	That each laborer or mechanic has been paid not less than the
	applicable wage rates and fringe benefits or cash equivalents for
	the classification of work performed, as specified in the applicable
	wage determination 
	subcontractor’s
	registered program shall be observed. Every apprentice must be paid
	at not less than the rate specified in the registered program for
	the apprentice’s level of progress, expressed as a percentage
	of the journeyman hourly rate specified in the applicable wage
	determination. Apprentices shall be paid fringe benefits in
	accordance with the provisions of the apprenticeship program. If the
	apprenticeship program does not specify fringe benefits, apprentices
	must be paid the full amount of fringe benefits listed on the wage
	determination for the applicable classification. If the
	Administrator of the Wage and Hour Division determines that a
	different practice prevails for the applicable apprentice
	classification, fringes shall be paid in accordance with that
	determination. In the event OATELS, or a State Apprenticeship Agency
	recognized by OATELS, withdraws approval of an apprenticeship
	program, the Contractor will no longer be permitted to utilize
	apprentices at less than the applicable predetermined rate for the
	work performed until an acceptable 
	incorporated
	into the contract. 
	(iii)
	The weekly submission of a properly executed certification set forth
	on the reverse side of 
	Optional
	Form WH-347 shall satisfy the 
	requirements
	for submission of the “Statement of Compliance” required
	by subparagraph (c)(2)(ii) of 
	this
	clause. 
	(iv)
	The falsification of any of the above certifications 
	may
	subject the Contractor or subcontractor to civil or criminal
	prosecution under Section 1001 of Title 18 and Section 3729 of Title
	31 of the United 
	States
	Code. 
	(3)
	The Contractor or subcontractor shall make the 
	records
	required under subparagraph (c)(1) available for inspection,
	copying, or transcription by authorized representatives of HUD or
	its designee, the Contracting Officer, or the Department of Labor
	and shall permit such representatives to interview employees during
	working hours on the job. If the Contractor or subcontractor fails
	to submit the required records or to make them available, HUD or 
	program
	is approved. 
	(2)
	Trainees. Except as provided in 29 CFR 5.16, 
	its
	designee may, after written notice to the 
	trainees
	will not be permitted to work at less than the predetermined rate
	for the work performed unless they are employed pursuant to and
	individually registered in a program which has received prior
	approval, evidenced by formal certification by the U.S. Department
	of Labor, Employment and Training Administration. The ratio of
	trainees to journeymen on the job site shall not be greater than
	permitted under 
	Contractor,
	take such action as may be necessary to cause the suspension of any
	further payment, advance, or guarantee of funds. Furthermore,
	failure to submit the required records upon request or to 
	Previous
	editions are obsolete Replaces form HUD-5370-A 
	Page
	17 of 19 
	form
	HUD-5370 (1/2014) 
	 
	
	 
	
 
 
 
 
	the
	plan approved by the Employment and Training Administration. Every
	trainee must be paid at not less than the rate specified in the
	approved program for the trainee’s level of progress,
	expressed as a percentage of the journeyman hourly rate specified in
	the applicable wage determination. Trainees shall be paid fringe
	benefits in accordance with the provisions of the trainee program.
	If the trainee program does not mention fringe benefits, trainees
	shall be paid the full amount of fringe benefits listed in the wage
	determination unless the Administrator of the Wage and Hour Division
	determines that there is an apprenticeship program associated with
	the corresponding journeyman wage rate in the wage determination
	which provides for less than full fringe benefits for apprentices.
	Any employee listed on the payroll at a trainee rate who is not
	registered and participating in a training plan approved by the
	Employment and Training Administration shall be paid not less than
	the applicable wage rate in the wage determination for the
	classification of work actually performed. In addition, any trainee
	performing work on the job site in excess of the ratio permitted
	under the registered program shall be paid not less than the
	applicable wage rate in the wage determination for the work actually
	performed. In the event the Employment and Training Administration
	withdraws approval of a training program, the Contractor will no
	longer be permitted to utilize trainees at less than the applicable
	predetermined rate for the work performed 
	(2)
	No part of this contract shall be subcontracted to any 
	person
	or firm ineligible for award of a United States Government contract
	by virtue of section 3(a) of the Davis-Bacon Act or 29 CFR
	5.12(a)(1). 
	(3)
	The penalty for making false statements is prescribed 
	in
	the U. S. Criminal Code, 18 U.S.C. 1001. 
	(j)
	Contract Work Hours and Safety Standards Act. As used 
	in
	this paragraph, the terms “laborers” and “mechanics” 
	include
	watchmen and guards. 
	(1)
	Overtime requirements. No contractor or 
	subcontractor
	contracting for any part of the contract work which may require or
	involve the employment of laborers or mechanics, including watchmen
	and guards, shall require or permit any such laborer or mechanic in
	any workweek in which the individual is employed on such work to
	work in excess of 40 hours in such workweek unless such laborer or
	mechanic receives compensation at a rate not less than one and
	one-half times the basic rate of pay for all hours 
	worked
	in excess of 40 hours in such workweek. 
	(2)
	Violation; liability for unpaid wages; liquidated 
	damages.
	In the event of any violation of the provisions set forth in
	subparagraph (j)(1) of this clause, the Contractor and any
	subcontractor responsible therefor shall be liable for the unpaid 
	wages.
	In addition, such Contractor and 
	until
	an acceptable program is approved. 
	subcontractor
	shall be liable to the United States (in the case of work done under
	contract for the District of Columbia or a territory, to such
	District or to such territory), for liquidated damages. Such
	liquidated damages shall be computed with respect to each individual
	laborer or mechanic (including watchmen and guards) employed in
	violation of the provisions set forth in subparagraph (j)(1) of this
	clause, in the sum of $10 for each calendar day on which such
	individual was required or permitted to work in excess of the
	standard workweek of 40 hours without payment of the overtime wages
	required by provisions set forth in subparagraph (j)(1) of this 
	(3)
	Equal employment opportunity. The utilization of 
	apprentices,
	trainees, and journeymen under this clause shall be in conformity
	with the equal employment opportunity requirements of Executive 
	Order
	11246, as amended, and 29 CFR Part 30. 
	(e)
	Compliance with Copeland Act requirements. The 
	Contractor
	shall comply with the requirements of 29 CFR Part 3, which are
	hereby incorporated by reference in this 
	contract. 
	clause. 
	(f)
	Contract termination; debarment. A breach of this contract clause
	may be grounds for termination of the contract and for debarment as
	a Contractor and a subcontractor as provided in 29 CFR 5.12. 
	(3)
	Withholding for unpaid wages and liquidated 
	(g)
	Compliance with Davis-Bacon and related Act requirements. All
	rulings and interpretations of the Davis- 
	damages.
	HUD or its designee shall upon its own action or upon written
	request of an authorized representative of the Department of Labor
	withhold or cause to be withheld, from any moneys payable on account
	of work performed by the Contractor or subcontractor under any such
	contract or any Federal contract with the same prime Contractor, or
	any other Federally-assisted contract subject to the Contract Work
	Hours and Safety Standards Act, which is held by the same prime
	Contractor, such sums as may be determined to be necessary to
	satisfy any liabilities of such Contractor or subcontractor for
	unpaid wages and liquidated damages as provided in the provisions
	set forth in subparagraph (j)(2) of this clause. (k)
	Subcontracts. The Contractor or subcontractor shall insert 
	in
	any subcontracts all the provisions contained in this 
	clause,
	and such other clauses as HUD or its designee 
	may
	by appropriate instructions require, and also a 
	clause
	requiring the subcontractors to include these 
	provisions
	in any lower tier subcontracts. The prime 
	Contractor
	shall be responsible for the compliance by any 
	subcontractor
	or lower tier subcontractor with all these 
	provisions. 
	Bacon
	and related Acts contained in 29 CFR Parts 1, 3, and 5 are herein
	incorporated by reference in this 
	contract. 
	(h)
	Disputes concerning labor standards. Disputes arising out of the
	labor standards provisions of this clause shall not be subject to
	the general disputes clause of this contract. Such disputes shall be
	resolved in accordance with the procedures of the Department of
	Labor set forth in 29 CFR Parts 5, 6, and 7. Disputes within the
	meaning of this clause include disputes between the Contractor (or
	any of its subcontractors) and the PHA, HUD, the U.S. Department of
	Labor, or the employees or their 
	representatives. 
	(i)
	Certification of eligibility. 
	(1)
	By entering into this contract, the Contractor certifies that
	neither it (nor he or she) nor any person or firm who has an
	interest in the Contractor’s firm is a person or firm
	ineligible to be awarded contracts by the United States Government
	by virtue of section 3(a) of the Davis-Bacon Act or 29 CFR
	5.12(a)(1). 
	Previous
	editions are obsolete Replaces form HUD-5370-A 
	Page
	18 of 19 
	form
	HUD-5370 (1/2014) 
	 
	
	 
	
 
 
 
 
	47.
	Non-Federal Prevailing Wage Rates 
	(a)
	Any prevailing wage rate (including basic hourly rate and 
	any
	fringe benefits), determined under State or tribal law to be
	prevailing, with respect to any employee in any trade or position
	employed under the contract, is inapplicable to the contract and
	shall not be enforced against the Contractor or any subcontractor,
	with respect to employees engaged under the contract whenever 
	such
	non-Federal prevailing wage rate exceeds: 
	(1)
	The applicable wage rate determined by the Secretary of Labor
	pursuant to the Davis-Bacon Act (40 U.S.C. 3141 et seq.) to be
	prevailing in the locality with 
	respect
	to such trade; 
	(b)
	An applicable apprentice wage rate based thereon 
	specified
	in an apprenticeship program registered with the U.S. Department of
	Labor (DOL) or a DOL- 
	recognized
	State Apprenticeship Agency; or 
	(c)
	An applicable trainee wage rate based thereon specified in a
	DOL-certified trainee program. 
	48.
	Procurement of Recovered Materials. 
	(a)
	In accordance with Section 6002 of the Solid Waste 
	Disposal
	Act, as amended by the Resource Conservation and Recovery Act, the
	Contractor shall procure items designated in guidelines of the
	Environmental Protection Agency (EPA) at 40 CFR Part 247 that
	contain the highest percentage of recovered materials practicable,
	consistent with maintaining a satisfactory level of competition. The
	Contractor shall procure items designated in the EPA guidelines that
	contain the highest percentage of recovered materials practicable
	unless the Contractor determines that such items: (1) are not
	reasonably available in a reasonable period of time; (2) fail to
	meet reasonable performance standards, which shall be determined on
	the basis of the guidelines of the National Institute of Standards
	and Technology, if applicable to the item; or (3) are only available
	at an 
	unreasonable
	price. 
	(b)
	Paragraph (a) of this clause shall apply to items 
	purchased
	under this contract where: (1) the 
	Contractor
	purchases in excess of $10,000 of the item under this contract; or
	(2) during the preceding Federal fiscal year, the Contractor: (i)
	purchased any amount of the items for use under a contract that was
	funded with Federal appropriations and was with a Federal agency or
	a State agency or agency of a political subdivision of a State; and
	(ii) purchased a total of in excess of $10,000 of the item both
	under and outside that contract. 
	Previous
	editions are obsolete Replaces form HUD-5370-A 
	Page
	19 of 19 
	form
	HUD-5370 (1/2014) 
	 
	
	 
	
 
 
 
| File Type | application/vnd.openxmlformats-officedocument.wordprocessingml.document | 
| Author | Shelton, Thomas | 
| File Modified | 0000-00-00 | 
| File Created | 2021-01-23 |