Number of Respondents








Respondents That Submit Reports Respondents That Do Not Submit Any Reports

















(A) (B) (C) (D) (E)


Total Annual Responses



(A) (B) (C) (D) (E)
Year Number of New Respondents 1 Number of Existing Respondents Number of Existing Respondents that keep records but do not submit reports Number of Existing Respondents That Are Also New Respondents Number of Respondents
(E=A+B+C-D)



Information Collection Activity Number of Respondents Number of Responses Number of Existing Respondents That Keep Records But Do Not Submit Reports Total Annual Responses
E=(BxC)+D
1 0 149 0 0 149


Notification of construction/
reconstruction
0 1 N/A 0
2 0 149 0 0 149


Notification of modification 0 1 N/A 0
3 0 149 0 0 149


Notification of actual startup 0 1 N/A 0
Average 0 149 0 0 149


Initial certification of equipment and inspections 0 1 N/A 0
1 New respondent include sources with constructed, reconstructed and modified affected facilities.







Initial inspection report detailing emission problems 0 1 N/A 0









Notifications of various intent 0 1 N/A 0









Demonstration for alternative operational or process parameter 0 1 N/A 0









Notification of delay in compliance 0 1 N/A 0









Semiannual report 149 2 N/A 298









Notification of initial performance test 0 1 N/A 0












Total 298

Sheet 2: Industry






106.45 138.43 52.77









Burden item (A) Person- hours per occurrence (B) No. of occurrences per respondent per year (C) Person- hours per respondent per year (C=AxB) (D) Respondents
per year (a)
(E) Technical person- hours per year (E=CxD) (F) Management person-hours per year (Ex0.05) (G) Clerical person-hours per year (Ex0.1) (H) Cost (b)








1. Applications N/A














2. Survey and Studies N/A














3. Reporting requirements















A. Familiarize with regulatory requirements 2 1 2 149 298 14.9 29.8 $35,357.25








B. Required activities
















1. Inspect drain systems 2 12 24 149 3,576 178.8 357.6 $424,287.04








2. Inspect oil-water separators 8 2 16 149 2,384 119.2 238.4 $282,858.02








3. Performance test 330 1 330 0 0 0 0 $0








C. Create information See 3B















D. Gather existing information See 3E















E. Write report
















Notification of construction/reconstruction 2 1 2 0 0 0 0 $0








Notification of modification 2 1 2 0 0 0 0 $0








Notification of actual startup 2 1 2 0 0 0 0 $0








Initial certification of equipment and inspections 2 1 2 0 0 0 0 $0








Initial inspection report detailing emission problems 2 1 2 0 0 0 0 $0








Various notifications of intent 2 1 2 0 0 0 0 $0








Demonstration for alternative 2 1 2 0 0 0 0 $0








Operational or process parameter
















Notification of delay in compliance 2 1 2 0 0 0 0 $0








Semiannual report 8 2 16 149 2,384 119.2 238.4 $282,858.02








Notification of initial performance test 2 1 2 0 0 0 0 $0








Results of performance test See 3B















Subtotal for Reporting Requirements



9,938 $1,025,360








4. Recordkeeping requirements
















A. Familiarize with regulatory requirements See 3A















B. Plan activities N/A














C. Implement activities N/A














D. Develop record system N/A














E. Enter information 1.5 1 1.5 149 223.5 11.18 22.35 $26,517.94








F. Train personnel N/A















G. Audits N/A















Subtotal for Recordkeeping Requirements



257 $26,518








TOTAL ANNUAL BURDEN AND COST (rounded)



10,200 $1,050,000








Capital and O&M Costs (See Section 6(b)(iii))






$19,400








TOTAL COST



10,200 $1,070,000


























Assumptions:




34 hr/response



a. We have assumed that the average number of respondents that will be subject to the rule will be 135. There will be no additional new sources per year that will become subject to the rule over the three-year period of this ICR.









Capital/Startup vs. Operation and Maintenance (O&M) Costs
b This ICR uses the following labor rates: $138.43 per hour for Executive, Administrative, and Managerial labor; $106.45 per hour for Technical labor, and $52.77 per hour for Clerical labor. These rates are from the United States Department of Labor, Bureau of Labor Statistics, September 2015, “Table 2. Civilian Workers, by Occupational and Industry group.” The rates are from column 1, “Total Compensation.” The rates have been increased by 110 percent to account for the benefit packages available to those employed by private industry.









(A) (B) (C) (D) (E) (F) (G)
c. We have assumed that each respondent will read instructions one time per year.









Continuous Monitoring Device Capital/Startup Cost for One Respondent Number of New Respondents Total Capital/Startup Cost, (B X C) Annual O&M Costs for One Respondent Number of Respondents with O&M Total O&M,
(E X F)
d. We have assumed that each respondent will take two hours to inspect drain systems twelve times per year.









Portable VOC analyzer for non-regenerative carbon absorber $2,960 0 0 $130 149 $19,370
e. We have assumed that it will take eight hours for each respondent to inspect oil-water separators two times per year.
















f. We have assumed that each respondent will take eight hours to write the semiannual report two times per year.
















g Totals have been rounded to 3 significant figures. Figures may not add exactly due to rounding

















Sheet 3: Agency






47.62 64.16 25.76
Activity (A) EPA Person- hours per occurrence (B) No. of occurrences per plant per year (C) EPA person- hours per respondent per year (C=AxB) (D) Plants per year (a) (E) Technical person- hours per year (E=CxD) (F) Management person-hours per year (Ex0.05) (G) Clerical person-hours per year (Ex0.1) (H) Cost (b)
Report Review







Notification of construction/reconstruction 2 1 2 0 0 0 0 $0
Notification of modification 2 1 2 0 0 0 0 $0
Notification of actual startup 2 1 2 0 0 0 0 $0
Initial certification for equipment and inspections 2 1 2 0 0 0 0 $0
Initial inspection detailing emission problems 2 1 2 0 0 0 0 $0
Notification of various intent c 2 1 2 0 0 0 0 $0
Demonstration for alternative 2 1 2 0 0 0 0 $0
operational or process parameter







Notification of delay in compliance 2 1 2 0 0 0 0 $0
Notification of initial performance test 2 1 2 0 0 0 0 $0
Initial performance test report for flares 2 1 2 0 0 0 0 $0
Review of semiannual reports d 8 2 16 149 2,384 119.2 238.4 $127,315.14
TOTAL ANNUAL BURDEN AND COST (rounded)e



2,740 $127,000









Assumptions:







a. We have assumed that the average number of respondents that will be subject to the rule will be 135. There will be no additional new sources that will become subject to the rule over the three-year period of this ICR.







b. The cost is based on the following labor rate which incorporates a 1.6 benefits multiplication factor to account for government overhead expenses. Managerial rates of $64.16, Technical rate of $47.62, and Clerical rate of $25.76. These rates are from the Office of Personnel Management (OPM) “2016 General Schedule” which excludes locality rates of pay.







c. The following notification review is included: election to construct and operate a completely closed drain system; election to construct and operate a floating roof; intent to use an alternative means of emission limitation; and intent to use a VOC control device other than a carbon absorber to meet the requirements of 60.692-5(a).







d. We have assumed that it will take 8 hours two times per year to review each semiannual report.







e Totals have been rounded to 3 significant figures. Figures may not add exactly due to rounding







File Typeapplication/vnd.openxmlformats-officedocument.spreadsheetml.sheet
File Modified0000-00-00
File Created0000-00-00

© 2024 OMB.report | Privacy Policy