PRC-012-2 Supplemental RAS

PRC-012-2-Supplemental Remedial Action Schemes.docx

FERC-725G, (Final Rule in RM16-20-000), Reliability Standards for the Bulk Power System: PRC Reliability Standards

PRC-012-2 Supplemental RAS

OMB: 1902-0252

Document [docx]
Download: docx | pdf

PRC0122 – Remedial Action Schemes


Standard Development Timeline

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.


Description of Current Draft

Draft 1 of PRC0122 corrects the applicability of the fillintheblank standards (PRC0121, PRC0131, and PRC0141) by assigning the requirement responsibilities to the specific users, owners, and operators of the BulkPower System, and incorporates the reliability objectives of all the RAS/SPSrelated standards. Draft 1 contains nine requirements and measures, the associated rationale boxes and corresponding technical guidelines. There are also three attachments within the draft standard that are incorporated via references in the requirements. Draft 1of PRC0122 is posted for a 45day initial formal comment period with a parallel initial ballot in the last ten days of the comment period.

Completed Actions Date

Standards Committee approved Standard Authorization Request

(SAR) for posting February 12, 2014, SAR posted for comment February 18, 2014

Standards Committee approved the SAR June 10, 2014


Draft 1 of PRC0122 posted for informal comment April 30 – May 20, 2015

45day formal comment period with initial ballot August 20 – October 5,

2015

Anticipated Actions Date

10day final ballot December 2015

NERC Board (Board) adoption February 2016


When this standard receives Board adoption, the rationale boxes will be moved to the

Supplemental Material Section of the standard.


A. Introduction

1. Title: Remedial Action Schemes

2. Number: PRC0122

3. Purpose: To ensure that Remedial Action Schemes (RAS) do not introduce

unintentional or unacceptable reliability risks to the Bulk Electric System (BES).

4. Applicability:

4.1. Functional Entities:

4.1.1. Reliability Coordinator

4.1.2. Transmission Planner

4.1.3. RASowner – the Transmission Owner, Generator Owner, or Distribution

Provider that owns all or part of a RAS

4.1.4. RASentity – the RASowner designated to represent all RASowner(s) for

Supplemental Material

Draft 1 of PRC0122

August 2015


coordinating the review and approval of a RAS

4.2. Facilities:

4.2.1. Remedial Action Schemes (RAS)

5. Effective Date: See the Implementation Plan for PRC0122.


B. Requirements and Measures


Rationale for Requirement R1: Each Remedial Action Scheme (RAS) is unique and its

action(s) can have a significant impact on the reliability and integrity of the Bulk Electric

System (BES). Therefore, a review of a proposed new RAS or an existing RAS proposed for functional modification or retirement (removal from service) must be completed prior to implementation or retirement. A functional modification is any modification to a RAS

beyond the replacement of components that preserves the original functionality.

To facilitate a review that promotes reliability, the RASentity must provide the reviewer

with sufficient details of the RAS design, function, and operation. This data and

supporting documentation are identified in Attachment 1 of this standard, and

Requirement R1 mandates that the RASentity provide them to the reviewing Reliability

Coordinator (RC). The RC (reviewing RC) that coordinates the area where the RAS is

located is responsible for the review. In cases where a RAS crosses one or more RC Area

boundaries, each affected RC is responsible for conducting either individual reviews or a

coordinated review.

R1. Prior to placing a new or functionally modified RAS in service or retiring an existing

RAS, each RASentity shall submit the information identified in Attachment 1 for

review to the Reliability Coordinator(s) that coordinates the area(s) where the RAS is

located. [Violation Risk Factor: Medium] [Time Horizon: Operations Planning]

M1. Acceptable evidence may include, but is not limited to, a copy of the Attachment 1

documentation and the dated communications with the reviewing Reliability

Coordinator(s) in accordance with Requirement R1.


Rationale for Requirement R2: The RC is the functional entity best suited to perform the RAS review because it has the widestarea reliability perspective of all functional entities and an awareness of reliability issues in any neighboring RC Area. This Wide Area purview provides continuity in the review process and facilitates the evaluation of interactions among separate RAS as well as interactions among RAS and other protection and control systems. Including the RC also minimizes the possibility of a conflict of interest that could exist because of business relationships among the RASentity, Planning Coordinator (PC), Transmission Planner (TP), or other entities that are likely to be involved in the planning or implementation of a RAS. The RC may request assistance


Supplemental Material

Draft 1 of PRC0122

August 2015


in RAS reviews from other parties such as the PC or regional technical groups; however, the RC will retain the responsibility for compliance with this requirement.

Attachment 2 of this standard is a checklist the RC can use to identify design and

implementation aspects of RAS and facilitate consistent reviews for each RAS submitted.

The time frame of fourfullcalendar months is consistent with current utility and regional

practice; however, flexibility is provided by allowing the parties to negotiate a mutually

agreed upon schedule for the review.


Note: An RC may need to include this task in its reliability plan(s) for the NERC Regions(s) in which it is located.

R2. Each Reliability Coordinator that receives Attachment 1 information pursuant to

Requirement R1, shall, within fourfullcalendar months of receipt, or on a mutually

agreed upon schedule, perform a review of the RAS in accordance with Attachment 2,

and provide written feedback to the RASentity. [Violation Risk Factor: Medium] [Time

Horizon: Operations Planning]

M2. Acceptable evidence may include, but is not limited to, dated reports, checklists, or

other documentation detailing the RAS review, and the dated communications with

the RASentity in accordance with Requirement R2.

Rationale for Requirement R3: The RC review is intended to identify reliability issues

that must be resolved before the RAS can be put in service. Examples of reliability issues

include a lack of dependability, security, or coordination.

A specific time period for the RASentity to respond to the RC review is not necessary

because it is in the RASentity’s interest to obtain an expeditious response from the

entity and thus ensure a timely implementation.

R3. Following the review performed pursuant to Requirement R2, the RASentity shall

address each identified issue and obtain approval from each reviewing Reliability

Coordinator prior to placing a new or functionally modified RAS in service or retiring

an existing RAS. [Violation Risk Factor: Medium] [Time Horizon: Operations Planning]

M3. Acceptable evidence may include, but is not limited to, dated documentation and

communications with the reviewing Reliability Coordinator in accordance with

Requirement R3.


Rationale for Requirement R4: Requirement R4 mandates that an evaluation of each RAS be performed at least once every sixtyfullcalendar months. The purpose of a periodic RAS evaluation is to verify the continued effectiveness and coordination of the RAS, as well as to verify that requirements for BES performance following an inadvertent RAS operation or a single component failure in the RAS continues to be satisfied. A periodic evaluation is needed because changes in system topology or operating conditions that have occurred since the previous RAS evaluation—or initial

Supplemental Material

Draft 1 of PRC0122

August 2015


review—was completed may change the effectiveness of a RAS or the way it impacts the BES.


Sixtyfullcalendar months, which begins on the effective date of the standard pursuant to

the implementation plan, was selected as the maximum time frame between evaluations

based on the time frames for similar requirements in Reliability Standards PRC006, PRC010, and PRC014. The RAS evaluation can be performed sooner if it is determined that material changes to system topology or system operating conditions have occurred that could potentially impact the effectiveness or coordination of the RAS. The periodic RAS evaluation will typically lead to one of the following outcomes: 1) affirmation that the existing RAS is effective; 2) identification of changes needed to the existing RAS; or, 3)justification for RAS retirement. The items required to be addressed in the evaluation are planning analyses that involve modeling of the interconnected transmission system to assess BES performance; consequently, the TP is the functional entity best suited to perform the analyses. To promote reliability, the TP is required to provide the RASowner(s) and each reviewing RC with the results of the evaluation.


The previous version of this standard (PRC0120 Requirement 1, R1.4) states “… the

inadvertent operation of a RAS shall meet the same performance requirement (TPL001

0, TPL0020, and TPL0030) as that required of the contingency for which it was

designed, and not exceed TPL0030.” Requirement R4 clarifies that the inadvertent

operation to be considered would only be that caused by the malfunction of a single RAS

component. This allows security features to be designed into the RAS such that

inadvertent operation due to a single component malfunction is prevented. Otherwise

and consistent with PRC0120 Requirement 1, R1.4, the RAS should be designed so that

its whole or partial inadvertent operation due to a single component malfunction satisfies

the system performance requirements for the same Contingency for which the RAS was

designed. If the RAS was installed for an extreme event in TPL0014 or for some other Contingency or System condition not defined in TPL0014 (therefore without performance requirements), its inadvertent operation still must meet some minimum System performance requirements. However, instead of referring to the TPL0014, Requirement R4 lists the System performance requirements that the inadvertent operation must satisfy. The performance requirements listed (Parts 4.3.1 – 4.3.5) are the ones that are common to all planning events P0P7 listed in TPL0014.


R4. Each Transmission Planner shall perform an evaluation of each RAS within its planning area at least once every 60fullcalendarmonths and provide the RASowner(s) and the reviewing Reliability Coordinator(s) the results including any identified

deficiencies. Each evaluation shall determine whether: [Violation Risk Factor:

Supplemental Material

Draft 1 of PRC0122

August 2015


Medium] [Time Horizon: Longterm Planning]

4.1. The RAS mitigates the System condition(s) or Contingency(ies) for which it was

designed.

4.2. The RAS avoids adverse interactions with other RAS, and protection and control

systems.

4.3. The possible inadvertent operation of the RAS resulting from any single RAS

component malfunction satisfies all of the following:

4.3.1. The BES shall remain stable.

4.3.2. Cascading shall not occur.

4.3.3. Applicable Facility Ratings shall not be exceeded.

4.3.4. BES voltages shall be within postContingency voltage limits and post

Contingency voltage deviation limits as established by the Transmission

Planner and the Planning Coordinator.

4.3.5. Transient voltage responses shall be within acceptable limits as

established by the Transmission Planner and the Planning Coordinator.

4.4. A single component failure in the RAS, when the RAS is intended to operate,

does not prevent the BES from meeting the same performance requirements

(defined in Reliability Standard TPL0014 or its successor) as those required for

the events and conditions for which the RAS is designed.

M4. Acceptable evidence may include, but is not limited to, dated reports or other

documentation of the analyses comprising the evaluation(s) of each RAS and dated

communications with the RASowner(s) and the reviewing Reliability Coordinator(s) in

accordance with Requirement R4.


Rationale for Requirement R5: The correct operation of a RAS is important for

maintaining the reliability and integrity of the BES. Any incorrect operation of a RAS

indicates that the RAS effectiveness and/or coordination has been compromised.

Therefore, all operations of a RAS and failures of a RAS to operate when expected must

be analyzed to verify that the RAS operation was consistent with its intended

functionality and design. A RAS operational performance analysis is intended to: 1) verify RAS operation is consistent with the implemented design; or 2) identify RAS performance deficiencies that manifested in the incorrect RAS operation or failure of RAS to operate when expected. The 120calendarday time frame for the completion of RAS operational performance analysis aligns with the time frame established in Requirement R1 from PRC0044 regarding the investigation of a Protection System Misoperation. To promote reliability, each RASowner is required to provide the results of RAS operational performance analyses to each reviewing RC. RASowners may need to collaborate with their associated TP to comprehensively analyze RAS operational performance. This is because a RAS operational performance analysis involves verifying

Supplemental Material

Draft 1 of PRC0122

August 2015


that the RAS operation triggers and responds (Parts 5.1, 5.2) and that the resulting BES response (Parts 5.3, 5.4) is consistent with the intended functionality and design of the RAS.


R5. Each RASowner shall, within 120calendar days of a RAS operation or failure of a RAS to operate when expected, analyze the RAS performance and provide the results of

the analysis, including any identified deficiencies, to its reviewing Reliability Coordinator(s). The RAS operational performance analysis shall determine whether:

[Violation Risk Factor: Medium] [Time Horizon: Operations Planning]

5.1. The System events and/or conditions appropriately triggered the RAS.

5.2. The RAS responded as designed.

5.3. The RAS was effective in mitigating BES performance issues it was designed to

address.

5.4. The RAS operation resulted in any unintended or adverse BES response.

M5. Acceptable evidence may include, but is not limited to, dated documentation detailing

the RAS operational performance analysis in accordance with Requirement R5.


Rationale for Requirement R6: Deficiencies, identified either in the periodic RAS

evaluation conducted by the TP in Requirement R4 or in the analysis conducted by the

RASowner pursuant to Requirement R5, are likely to pose a reliability risk to the BES. To mitigate potential reliability risks, Requirement R6 mandates that the RASowner develop a Corrective Action Plan (CAP) that establishes the mitigation actions and timetable to address the deficiency. If the CAP requires that a functional change be made to a RAS, the RASowner will need to submit information identified in Attachment 1 to the reviewing RC(s) prior to placing RAS modifications in service per Requirement R1.

Depending on the complexity of the issues, development of a CAP might require study,

engineering, or consulting work. A time frame of sixfullcalendar months is specified to

allow enough time for RASowner collaboration on the CAP development, while ensuring that deficiencies are addressed in a reasonable time.

R6. Within sixfullcalendar months of being notified of a deficiency in its RAS pursuant to Requirement R4 or Requirement R5, each RASowner shall participate in developing a

Corrective Action Plan (CAP) and submit the CAP to its reviewing Reliability

Coordinator(s). [Violation Risk Factor: Medium] [Time Horizon: Operations Planning,

Longterm Planning]

M6. Acceptable evidence may include, but is not limited to, a dated CAP and dated

communications with each reviewing Reliability Coordinator in accordance with

Requirement R6.


Supplemental Material

Draft 1 of PRC0122

August 2015


Rationale for Requirement R7: Requirement R7 mandates the RASowner(s) implement a CAP (developed in Requirement R6) that mitigates the deficiencies identified in Requirements R4 and R5. By definition, a CAP is: “A list of actions and an associated timetable for implementation to remedy a specific problem.” The implementation of a properly developed CAP ensures that RAS deficiencies are mitigated in a timely manner. Each reviewing Reliability Coordinator must be notified if CAP actions or timetables change.


R7. For each CAP submitted pursuant to Requirement R6, each RASowner shall:

[Violation Risk Factor: Medium] [Time Horizon: Operations Planning, Longterm

Planning]

7.1. Implement the CAP.

7.2. Update the CAP if actions or timetables change.

7.3. Notify each reviewing Reliability Coordinator if CAP actions or timetables change.

M7. Acceptable evidence may include, but is not limited to, dated documentation such as

CAPs, project or work management program records, settings sheets, work orders,

maintenance records, and communication with the appropriate Reliability

Coordinator(s) that documents the implementation or updating of a CAP in

accordance with Requirement R7.

Rationale for Requirement R8: Due to the wide variety of RAS designs and

implementations, and the potential for impacting BES reliability, it is important that

periodic functional testing of a RAS be performed. A functional test provides an overall

confirmation of the RAS to operate as designed and verifies the proper operation of the

nonProtection System (control) components of a RAS that are not addressed in PRC005.

Protection System components that are part of a RAS are maintained in accordance with

PRC005. The drafting team selected a sixcalendaryear testing interval to be consistent

with some of the maintenance intervals of various Protection System and Automatic

Reclosing components established in PRC005. This interval provides an entity the

opportunity to design its RAS functional testing program such that it coincides with the

testing of any associated PRC005 components. The sixcalendaryear interval, which begins on the effective date of the standard pursuant to the implementation plan, is a balance between the resources required to perform the testing and the potential reliability impacts to the BES created by undiscovered latent failures that could cause an incorrect operation of the RAS. Extending to longer intervals increases the reliability risk to the BES posed by a potentially undiscovered latent failure that could cause an incorrect operation of the RAS. The RAS owner is in the best position to determine the testing procedure and schedule due to its overall knowledge of the RAS design, installation, and functionality. Functional testing may be accomplished with endtoend testing or a

Supplemental Material

Draft 1 of PRC0122

August 2015


segmented approach. Each segment of a RAS should be tested but overlapping segments can be tested individually negating the need for complex maintenance schedules and outages. A correct operation of a RAS qualifies as a functional test as long as all segments operate. If an event causes a partial operation of a RAS, the segments without an operation will require a functional test within the six year interval to be compliant with Requirement R8.

R8. At least once every sixcalendar years, each RASowner shall perform a functional test of each RAS to verify the overall RAS performance and the proper operation of non

Protection System components. [Violation Risk Factor: High] [Time Horizon: Longterm

Planning]

M8. Acceptable evidence may include, but is not limited to, dated documentation of the

functional testing in accordance with Requirement R8.


Rationale for Requirement R9: The RAS database is a comprehensive record of all RAS existing in a Reliability Coordinator Area. The database enables the RC to provide other entities highlevel information on existing RAS that can potentially impact the entities’ operational and/or planning activities. Attachment 3 lists the minimum information required for the RAS database, which includes a summary of the RAS initiating conditions, corrective actions, and System issues being mitigated. This information allows an entity to evaluate the reliability need for requesting more detailed information from the RAS entity identified in the database contact information. The RC is the appropriate entity to maintain the database because the RC receives the required database information when a new or modified RAS is submitted for review.

R9. Each Reliability Coordinator shall update a RAS database containing, at a minimum,

the information in Attachment 3 at least once each calendar year. [Violation Risk

Factor: Lower] [Time Horizon: Operations Planning]

M9. Acceptable evidence may include, but is not limited to, dated spreadsheets, database

reports, or other documentation demonstrating a RAS database was maintained in

accordance with Requirement R9.


C. Compliance


1. Compliance Monitoring Process


1.1. Compliance Enforcement Authority:

As defined in the NERC Rules of Procedure, “Compliance Enforcement Authority”

means NERC or the Regional Entity in their respective roles of monitoring and

enforcing compliance with the NERC Reliability Standards.


Supplemental Material

Draft 1 of PRC0122

August 2015


1.2. Evidence Retention:


The following evidence retention period(s) identify the period of time an entity is

required to retain specific evidence to demonstrate compliance. For instances

where the evidence retention period specified below is shorter than the time

since the last audit, the Compliance Enforcement Authority may ask an entity to

provide other evidence to show that it was compliant for the fulltime period

since the last audit.

The applicable entity shall keep data or evidence to show compliance as identified

below unless directed by its Compliance Enforcement Authority to retain specific

evidence for a longer period of time as part of an investigation.


The Transmission Owner, Generator Owner, and Distribution Provider shall each

keep data or evidence to show compliance with Requirements R1 through R9, and

Measures M1 through M9 since the last audit, unless directed by its Compliance

Enforcement Authority to retain specific evidence for a longer period of time as

part of an investigation. If a Transmission Owner, Generator Owner or Distribution Provider is found noncompliant, it shall keep information related to the noncompliance until mitigation is completed and approved, or for the time specified above, whichever

is longer


The Compliance Enforcement Authority shall keep the last audit records and all

requested and submitted subsequent audit records.


1.3. Compliance Monitoring and Enforcement Program

As defined in the NERC Rules of Procedure, “Compliance Monitoring and

Enforcement Program” refers to the identification of the processes that will be

used to evaluate data or information for the purpose of assessing performance or

outcomes with the associated Reliability Standard.



Violation Severity Levels

R # Violation Severity Levels

Lower VSL Moderate VSL High VSL Severe VSL

R1. N/A N/A N/A The RASentity failed to submit the information identified in Attachment 1 to one or more of the Reliability Coordinator(s) in accordance with Requirement R1.


R2. The reviewing Reliability Coordinator performed the review and provided the

Supplemental Material

Draft 1 of PRC0122

August 2015


written feedback in accordance with Requirement R2, but was late by less than or equal to 30calendar days.


The reviewing Reliability Coordinator performed the review and provided the written feedback in accordance with Requirement R2, but was late by more than 30calendar days but less than or equal to 60calendar days.


The reviewing Reliability Coordinator performed the review and provided the written feedback in accordance with Requirement R2, but was late by more than 60calendar days but less than or equal to 90calendar days.


The reviewing Reliability Coordinator performed the review and provided the written feedback in accordance with Requirement R2, but was late by more than 90calendar days.


OR


The reviewing Reliability Coordinator failed to perform the review or provide feedback in accordance with Requirement R2.

VSL Moderate VSL High VSL Severe VSL

R3. The RASentity failed to obtain approval from each reviewing Reliability Coordinator prior to placing a new or functionally modified RAS in service or retiring an existing RAS in accordance with Requirement R3.


R4. The Transmission Planner performed the evaluation in accordance with Requirement R4, but in greater than 60fullcalendar months but less than 61full calendar months.


The Transmission Planner performed the evaluation in accordance with Requirement R4, but in greater than 61fullcalendar months but less than 62full calendar months.


The Transmission Planner performed the evaluation in accordance with Requirement R4, but in greater than 62fullcalendar months but less than 63full calendar

months.


OR

The Transmission Planner performed the evaluation in accordance with Requirement R4, but failed to evaluate one of the Parts 4.1 through 4.4.



Supplemental Material

Draft 1 of PRC0122

August 2015


The Transmission Planner performed the evaluation in accordance with Requirement R4, but in greater than 63fullcalendar months.


OR


The Transmission Planner failed to perform the evaluation in accordance with Requirement R4.


OR


The Transmission Planner performed the evaluation in accordance with Requirement R4, but failed to evaluate two or more of the Parts 4.1 through 4.4.


OR


The Transmission Planner performed the evaluation in accordance with Requirement R4, but failed to provide the results to one or more of the RASowner(s) and the reviewing Reliability Coordinator(s).


R5. The RASowner performed the analysis in greater than

120calendar days, but less than or equal to 130calendar days in accordance with Requirement R5.


The RASowner performed the analysis in greater than 130calendar days, but less

than or equal to 140calendar days in accordance with Requirement R5.


The RASowner performed the analysis in greater than 140calendar days, but less

than or equal to 150calendar days in accordance with Requirement R5.


OR


The RASowner performed the analysis in accordance with Requirement R5, but

failed to address one of the Parts 5.1 through 5.4.


The RASowner performed the analysis in greater than 150calendar days.


OR


The RASowner failed to perform the analysis in accordance with Requirement R5.


Supplemental Material

Draft 1 of PRC0122

August 2015


OR


The RASowner performed the analysis in accordance with Requirement R5, but

failed to address two or more of the Parts 5.1 through 5.4.


OR


The RASowner performed the analysis in accordance with Requirement R5, but

failed to provide the results to one or more of the reviewing Reliability Coordinator(s).


R6. The RASowner developed a Corrective Action Plan and submitted it to its reviewing

Reliability Coordinator(s) in accordance with Requirement R6, but was late by less than or equal to 10calendar days.


The RASowner developed a Corrective Action Plan and submitted it to its reviewing

Reliability Coordinator(s) in accordance with Requirement R6, but was late by more than 10calendar days but less than or equal to 20calendar days.


The RASowner developed a Corrective Action Plan and submitted it to its reviewing

Reliability Coordinator(s) in accordance with Requirement R6, but was late by more than 20calendar days but less than or equal to 30calendar days.


The RASowner developed a Corrective Action Plan and submitted it to its reviewing

Reliability Coordinator(s) in accordance with Requirement R6, but was late by more than 30calendar days.


OR


The RASowner developed a Corrective Action Plan and failed to submit it to one or

more of its reviewing Reliability Coordinator(s) in accordance with Requirement R6.


OR


The RASowner failed to develop a Corrective Action Plan in accordance with Requirement R6.


R7. The RASowner implemented a CAP (Part 7.1), but failed to update the


Supplemental Material

Draft 1 of PRC0122

August 2015


CAP (Part 7.2) if actions or timetables changed and failed to notify one or more of the reviewing Reliability Coordinator(s) (Part 7.3), in accordance with


Requirement R7.


N/A N/A The RASowner failed to implement a CAP (Part 7.1) in accordance with

Requirement R7.


R8. The RASowner performed the functional test for a RAS as specified in Requirement

R8, but was less than or equal to 30calendar days late.


The RASowner performed the functional test for a RAS as specified in Requirement R8, but was more than 30calendar days but less than or equal to 60calendar days late.


The RASowner performed the functional test for a RAS as specified in Requirement

R8, but was more than 60calendar days but less than or equal to 90calendar days

late.


The RASowner performed the functional test for a RAS as specified in Requirement R8, but was more than 90calendar days late.


OR


The RASowner failed to perform the functional test for a RAS as specified in Requirement R8.


R9. The Reliability Coordinator updated the RAS database in accordance with Requirement R9, but was late by less than or equal to 30calendar days.


The Reliability Coordinator updated the RAS database in accordance with Requirement R9, but was late by more than 30calendar days but less than or equal to 60calendar days.


The Reliability Coordinator updated the RAS database in accordance with Requirement R9, but was late by more than 60calendar days but less than or equal to 90calendar days.


The Reliability Coordinator updated the RAS database in accordance with Requirement R9 but was late by more than 90calendar days.


Supplemental Material

Draft 1 of PRC0122

August 2015


OR


The Reliability Coordinator failed to update the RAS database in accordance with Requirement R9.


D. Regional Variances

None.


E. Associated Documents

Version History

Version Date Action Change Tracking

1 Adopted by NERC Board of Trustees New


Supporting Documentation for RAS Review

The following checklist identifies important Remedial Action Scheme (RAS) information for each new or functionally modified1 RAS that the RASentity shall document and provide to the reviewing Reliability Coordinator(s) (RC) for review. If an item on this list does not apply to a specific RAS, a response of N/A or Not Applicable for that item is appropriate. When a RAS has been previously reviewed, only the proposed modifications to that RAS require review; however, the RASentity must provide a summary of the previously approved functionality. The RC may request additional information on any reliability issue related to the RAS. Additional entities (without decision authority) may be part of the RAS review process at the request of the RC.


I. General

1. Information such as maps, oneline drawings, substation and schematic drawings that

identify the physical and electrical location of the RAS and related facilities.

2. Functionality of new RAS or proposed functional modifications to existing RAS and

documentation of the pre and postmodified functionality of the RAS.

3. The Corrective Action Plan (CAP) if RAS modifications are proposed in a CAP.

[Reference NERC Reliability Standard PRC012, Requirements R5 and R7]

4. Data to populate the RAS database:

a. RAS name.

b. RASentity and contact information.

c. Expected or actual inservice date; most recent RCapproval date (Requirement R3);

most recent evaluation date (Requirement R4); and date of retirement, if applicable.

d. System performance issue or reason for installing the RAS (e.g., thermal overload,

angular instability, poor oscillation damping, voltage instability, under or overvoltage,

Supplemental Material

Draft 1 of PRC0122

August 2015


or slow voltage recovery).

e. Description of the contingencies or System conditions for which the RAS was

designed (i.e., initiating conditions).

f. Action(s) to be taken by the RAS.

g. Any additional explanation relevant to highlevel understanding of the RAS.

1 Functionally Modified: Any modification to a RAS beyond the replacement of components that preserve the original

functionality is a functional modification.


Attachments


II. Functional Description and Transmission Planning Information


1. Contingencies and System conditions that the RAS is intended to remedy.

[Reference NERC Reliability Standards PRC012, R1.2 and PRC013, R1.1]

2. The action(s) to be taken by the RAS in response to disturbance conditions.

[Reference NERC Reliability Standards PRC012, R1.2 and PRC013, R1.2]

3. A summary of technical studies, if applicable, demonstrating that the proposed RAS

actions satisfy System performance objectives for the scope of System events and

conditions that the RAS is intended to remedy. The technical studies summary shall also

include information such as the study year(s), System conditions, and Contingencies

analyzed on which the RAS design is based, and the date those technical studies were

performed. [Reference NERC Reliability Standard PRC014, R3.2]

4. Information regarding any future System plans that will impact the RAS.

[Reference NERC Reliability Standard PRC014, R3.2]

Documentation showing that the possible inadvertent operation of the RAS resulting

from any single RAS component malfunction satisfies all of the following:

[Reference NERC Reliability Standard PRC012, R1.4]

a. The BES shall remain stable.

b. Cascading shall not occur.

c. Applicable Facility Ratings shall not be exceeded.

d. BES voltages shall be within postContingency voltage limits and postContingency

voltage deviation limits as established by the Transmission Planner and the Planning

Coordinator.

e. Transient voltage responses shall be within acceptable limits as established by the

Transmission Planner and the Planning Coordinator.

5. An evaluation indicating that the RAS settings and operation avoid adverse interactions

with other RAS, and protection and control systems.

Supplemental Material

Draft 1 of PRC0122

August 2015


[Reference NERC Reliability Standards PRC012, R1.5 and PRC014, R3.4]

6. Identification of other affected RCs.


III. Implementation

1. Documentation describing the applicable equipment used for detection,

telecommunications, transfer trip, logic processing, and monitoring.

2. Information on detection logic and settings/parameters that control the operation of

the RAS. [Reference NERC Reliability Standards PRC012, R1.2 and PRC013, R1.3]

3. Documentation showing that any multifunction device used to perform RAS function(s),

in addition to other functions such as protective relaying or SCADA, does not

compromise the reliability of the RAS when the device is not in service or is being

maintained.

Attachments


4. Documentation showing that a single component failure in the RAS, when the RAS is

intended to operate, does not prevent the BES from meeting the same performance

requirements (defined in Reliability Standard TPL0014 or its successor) as those

required for the events and conditions for which the RAS is designed. The

documentation should describe or illustrate how the design achieves this objective.

[Reference NERC Reliability Standard PRC012, R1.3]

5. Documentation describing the functional testing process.


IV. RAS Retirement

The following checklist identifies RAS information that the RASentity shall document and

provide to each reviewing RC.

1. Information necessary to ensure that the RC is able to understand the physical and

electrical location of the RAS and related facilities.

2. A summary of applicable technical studies and technical justifications upon which the

decision to retire the RAS is based.

3. Anticipated date of RAS retirement.


Reliability Coordinator RAS Review Checklist


The following checklist identifies reliabilityrelated considerations for the Reliability Coordinator (RC) to review and verify for each new or functionally modified2 Remedial Action Scheme (RAS).


Supplemental Material

Draft 1 of PRC0122

August 2015


The RC review is not limited to the checklist items and the RC may request additional

information on any reliability issue related to the RAS.

I. Design

1. The RAS actions satisfy performance objectives for the scope of events and conditions

that the RAS is intended to mitigate.

2. The RAS arming conditions, if applicable, are appropriate to its System performance

objectives.

3. The RAS avoids adverse interactions with other RAS, and protection and control

systems.

4. The effects of RAS incorrect operation, including inadvertent operation and failure to

operate (if nonoperation for RAS single component failure is acceptable), have been

identified.

5. The possible inadvertent operation of the RAS resulting from any single RAS component malfunction satisfies all of the following:

a. The BES shall remain stable.

b. Cascading shall not occur.

c. Applicable Facility Ratings shall not be exceeded.

d. BES voltages shall be within postContingency voltage limits and postContingency

voltage deviation limits as established by the Transmission Planner and the Planning

Coordinator.

e. Transient voltage responses shall be within acceptable limits as established by the

Transmission Planner and the Planning Coordinator.

6. The effects of future BES modifications on the design and operation of the RAS have

been identified, where applicable.


II. Implementation

1. The implementation of RAS logic appropriately correlates desired actions (outputs) with

events and conditions (inputs).

2. The timing of RAS action(s) is appropriate to its BES performance objectives.

2 Functionally Modified:

Any modification to a RAS beyond the replacement of components that preserve the original functionality is a

functional modification.

3. A single component failure in a RAS does not prevent the BES from meeting the same

performance requirements as those required for the events and conditions for which

the RAS is designed.

4. The RAS design facilitates periodic testing and maintenance.

5. The mechanism or procedure by which the RAS is armed is clearly described, and is

Supplemental Material

Draft 1 of PRC0122

August 2015


appropriate for reliable arming and operation of the RAS for the conditions and events

for which it is designed to operate.


III. RAS Retirement

RAS retirement reviews should assure that there is adequate justification for why a RAS is no longer needed.


Database Information


1. RAS name.

2. RASentity and contact information.

3. Expected or actual inservice date; most recent RCapproval date (Requirement R3);

most recent evaluation date (Requirement R4); and date of retirement, if applicable.

4. System performance issue or reason for installing the RAS (e.g., thermal overload,

angular instability, poor oscillation damping, voltage instability, under or overvoltage,

or slow voltage recovery).

5. Description of the Contingencies or System conditions for which the RAS was designed

(i.e., initiating conditions).

6. Action(s) to be taken by the RAS.

7. Any additional explanation relevant to highlevel understanding of the RAS.


Supplemental Material


Technical Justifications for Requirements


Applicability


4.1.4 RASentity


The purpose of the RASentity is to be the single information conduit with each reviewing Reliability Coordinator (RC) for all RASowners for each RAS. The RASentity needs to coordinate all review materials and any presentations. If all of the RAS equipment has a single owner, then the RASentity is the same as the RASowner and that owner speaks for itself. If the RAS equipment has more than one owner, then each separate RAS equipment owner is a RASowner. The RASentity will always be one of these RASowners. A RASentity will be selected by all RASowners and, traditionally, has usually been the owner of the RAS controller and a Transmission Owner. If a specific


Supplemental Material

Draft 1 of PRC0122

August 2015


RASentity is not identified by the RASowners, the RC will assign that function to the RASowner who provides the review material to them.

The RASowner(s); i.e., Transmission Owner(s), Generator Owner(s), or Distribution Provider(s) who are not the RASentity still have responsibilities as assigned in other NERC Reliability Standards, such as equipment maintenance. In addition, when RAS modifications are needed, each RASowner of RAS equipment that must be modified must accept the specific responsibilities assigned to them as described in the necessary Corrective Action Plan (CAP), or otherwise as described in the revised Attachment 1.


Requirement R1

Each RAS is unique and its action(s) can have a significant impact on the reliability and integrity of the Bulk Electric System (BES); therefore, a review of a proposed new RAS or an existing RAS proposed for functional modification, or retirement (removal from service) must be completed prior to implementation.


Any modification to RAS hardware beyond the substitution of components that merely

preserve the original functionality is a functional modification. Any change in RAS logic such as new inputs or outputs, or any other modification that affects overall RAS functionality, or redundancy level as documented in the original submission for review are functional modifications. RAS modifications identified by a CAP pursuant to Requirement R6 beyond the substitution of components that merely preserve the original functionality are functional modifications. RAS removal is essentially a form of RAS functional modification. Any RAS proposed for removal needs to be evaluated under the RAS Retirement section of the


Attachment 1 checklist.

To facilitate a review that promotes reliability, the RASentity must provide the reviewer with sufficient details of the RAS design, function, and operation. This data and supporting documentation are identified in Attachment 1 of this standard, and Requirement R1 mandates that the RASentity provide them to the reviewing Reliability Coordinator (RC). The RC that coordinates the area where the RAS is located is responsible for the review. In cases where a RAS crosses multiple RC Area boundaries, each affected RC is responsible for conducting either individual reviews or a coordinated review.


Requirement R1 does not specify how far in advance of implementation the RASentity must provide Attachment 1 data to the reviewing RC. The information will need to be submitted early enough to allow RC review in the allotted time pursuant to Requirement R2, including resolution of any issues that might be identified, in order to obtain approval

Supplemental Material

Draft 1 of PRC0122

August 2015


of the reviewing RC. Expeditious submittal of this information is in the interest of each RASowner to effect a timely implementation.


Requirement R2


Requirement R2 mandates that the RC perform reviews of all proposed new RAS and existing RAS proposed for functional modification, or retirement (removal from service) in its RC Area.


RAS are unique and customized assemblages of protection and control equipment. As such, they have a potential to introduce reliability risks to the BES, if not carefully planned, designed, and installed. A RAS may be installed to address a reliability issue, or achieve an economic or operational advantage, and could introduce reliability risks that might not be apparent to a RASowner(s). An independent review by a multidisciplinary panel of subject matter experts with planning, operations, protection, elecommunications, and equipment expertise is an effective means of identifying risks and recommending RAS modifications when necessary.


The RC is the functional entity best suited to perform the RAS reviews because it has the

widestarea reliability perspective of all functional entities and an awareness of reliability issues in neighboring RC Areas. This Wide Area purview provides continuity in the review process and facilitates the evaluation of interactions among separate RAS as well as interactions among the RAS and other protection and control systems. The selection of the RC also minimizes the possibility of a “conflict of interest” that could exist because of business relationships among the RASentity, Planning Coordinator (PC), Transmission Planner (TP), or other entities that are likely to be involved in the planning or implementation of a RAS. The RC may request assistance in RAS reviews from other parties such as the PC(s) or regional technical groups (e.g., Regional Entities); however, the RC retains responsibility for compliance with the requirement.


Attachment 2 of this standard is a checklist for assisting the RC in identifying design and

implementation aspects of a RAS, and for facilitating consistent reviews of each submitted RAS for review. The time frame of fourfullcalendar months is consistent with current utility practice; however, flexibility is provided by allowing the parties to negotiate a different schedule for the review. Note, an RC may need to include this task in its reliability plan(s) for the NERC Region(s) in which it is located.




Supplemental Material

Draft 1 of PRC0122

August 2015


Requirement R3


Requirement R3 mandates that the RASentity address all issues identified by the reviewing RC during the RAS review, and obtain approval from the reviewing RC that the RAS implementation can proceed. The review by the RC is intended to identify reliability issues that must be resolved before the RAS can be put in service. Examples of reliability issues include a lack of dependability, security, or coordination.

Dependability is a component of reliability and is the measure of certainty of a device to

operate when required. If a RAS is installed to meet performance requirements of NERC

Reliability Standards, a failure of the RAS to operate when intended would put the System at risk of violating NERC Reliability Standards if specified Contingency(ies) or System conditions occur.


This risk is mitigated by designing the RAS so that it will accomplish the intended purpose while experiencing a single RAS component failure. This is often accomplished through redundancy. Other strategies for providing dependability include “overtripping” load or generation, or alternative automatic backup schemes.


Security is a component of reliability and is the measure of certainty of a device to not operate inadvertently. False or inadvertent operation of a RAS results in taking a programmed action without the appropriate arming conditions, occurrence of specified Contingency(ies), or System conditions expected to trigger the RAS action. Typical RAS actions include shedding load or generation or reconfiguring the System. Such actions, if inadvertently taken, are undesirable and may put the System in a less secure state. Worst case impacts from inadvertent operation often occur if all programmed RAS actions occur. If the System performance still satisfies PRC0122 Requirement R4, Part 4.3, no additional mitigation is required. Security enhancements to the RAS design, such as voting schemes, are acceptable mitigations against inadvertent operations.


Any reliability issue identified during the review must be resolved before implementing the RAS to avoid placing the System at unacceptable risk. The RASentity (and any other RASowner) or the reviewing RC(s) may have alternative ideas or methods available to resolve the issue(s). In either case, the concern needs to be resolved in deference to reliability, and the RC has the final decision.


A specific time period for the RASentity to respond to the RC(s) review is not necessary

because an expeditious response is in the interest of each RASowner to effect a timely

implementation.


Supplemental Material

Draft 1 of PRC0122

August 2015


Requirement R4


Requirement R4 mandates that an evaluation of each RAS be performed at least once every 60fullcalendar months. The purpose of a periodic RAS evaluation is to verify the continued effectiveness and coordination of the RAS, as well as to verify that requirements for BES performance following inadvertent RAS operation and single component failure continue to be satisfied. A periodic evaluation is required because changes in system topology or operating conditions that have occurred since the previous RAS evaluation (or initial review) may change the effectiveness of a RAS or the way it interacts with and impacts the BES.


A period of sixtyfullcalendar months was selected as the maximum time frame between

evaluations based on similar requirements in NERC Reliability Standards PRC006, PRC010, and PRC014. The RAS evaluation should be performed sooner if it is determined that material changes to System topology or System operating conditions that could potentially impact the effectiveness or coordination of the RAS have occurred since the previous RAS evaluation or will occur before the next scheduled evaluation.


The periodic RAS evaluation will lead to one of the following outcomes:

1) affirmation that the existing RAS is effective; 2) identification of changes

needed to the existing RAS; or 3) justification for RAS retirement.


The items required to be addressed in the evaluations (Requirement R4, Parts 4.1 through 4.4) are planning analyses that involve modeling of the interconnected transmission system to assess BES performance; consequently, the TP is the functional entity best suited to perform the analyses. To promote reliability, the TP is required to provide the RASowner(s) and the reviewing RC(s) with the results of each evaluation.


The intent of Requirement R4, Part 4.3 is to require that the possible inadvertent operation of the RAS, caused by the malfunction of a single component of the RAS, meet the same System performance requirements as those required for the Contingency(ies) or System conditions for which it is designed. If the RAS is designed to meet one of the planning events (P0P7) in TPL0014, the possible inadvertent operation of the RAS must meet the same performance requirements listed in the standard for that planning event. The requirement clarifies that the inadvertent operation to be considered is only that caused by the malfunction of a single RAS component. This allows features to be designed into the RAS to improve security, such that inadvertent operation due to malfunction of a single component is prevented or else the RAS inadvertent operation satisfies Requirement R4, Part 4.3.

Supplemental Material

Draft 1 of PRC0122

August 2015


The intent of Requirement R4, Part 4.3 is also to require that the possible inadvertent operation of the RAS installed for an extreme event in TPL0014 or for some other Contingency or System conditions not defined in TPL0014 (therefore without performance requirements), meet the minimum System performance requirements of Category P7 in Table 1 of NERC Reliability Standard TPL0014. However, instead of referring to the TPL standard, the requirement lists the System performance requirements that a potential inadvertent operation must satisfy.The performance requirements listed (Requirement R4, Parts 4.3.1 – 4.3.5) are the ones that are common to all planning events P0P7 listed in TPL0014.


With reference to Requirement 4, Part 4.3, note that the only differences in performance

requirements among the TPL P0P7 events (not common to all of them) concern Non

Consequential Load Loss and interruption of Firm Transmission Service. Performance

requirements in these areas are not relevant. A RAS is only allowed to drop nonconsequential load or interrupt Firm Transmission Service can do that only if that action is allowed for the Contingency for which it is designed. Therefore, the inadvertent operation should automatically meet NonConsequential Load Loss or interrupting Firm Transmission Service performance requirements for the Contingency(ies) for which it was designed.


Part 4.4 requires that a single component failure in the RAS, when the RAS is intended to

operate, does not prevent the BES from meeting the same performance requirements (defined in Reliability Standard TPL0014 or its successor) as those required for the events and conditions for which the RAS is designed. This analysis is needed to ensure that changing System conditions do not result in the single component failure requirement not being met.


Requirements for inadvertent RAS operation (Requirement R4, Part 4.3) and single component failure (Requirement R4, Part 4.4) are reviewed by the reviewing RC(s) before a new or functionally modified RAS is placed in service, and are typically satisfied by specific design considerations. Although the scope of the periodic evaluation does not include a new design review, it is possible that a design which previously satisfied requirements for inadvertent RAS operation and single component failure may fail to satisfy these requirements at a later point in time, and must be evaluated with respect to the current System. For example, if the actions of a

particular RAS include tripping load, System changes could occur over time that impact the amount of load originally tripped by a particular RAS output. These changes could result in inadvertent activation of that output, therefore, tripping too much load and result in violations of Facility Ratings. Alternatively, the RAS might be designed to trip more

Supplemental Material

Draft 1 of PRC0122

August 2015


load than necessary (i.e., “over trip”) in order to satisfy singlecomponentfailure requirements. System changes could result in too little load being tripped at affected locations and result in unacceptable BES performance if one of the loads failed to trip.


Requirement R5


The correct operation of a RAS is important to maintain the reliability and integrity of the BES. Any incorrect operation of a RAS indicates the RAS effectiveness and/or coordination may have been compromised. Therefore, all operations of a RAS and failures of a RAS to operate when expected must be analyzed to verify that the RAS operation was consistent with its intended functionality and design.


A RAS operational performance analysis is intended to: (1) verify RAS operation is consistent with implemented design; or (2) identify RAS performance deficiency(ies) that manifested in the incorrect RAS operation or failure of RAS to operate when expected.


The 120calendar day time frame for the completion of RAS operational performance analysis aligns with the time frame established in Requirement R1 from PRC0044 regarding the investigation of a Protection System Misoperation. To promote reliability, the RASowner(s) is required to provide the results of RAS operational performance analyses to its reviewing RC(s).


The RASowner(s) may need to collaborate with their associated TP to comprehensively analyze RAS operational performance. This is because a RAS operational performance analysis involves verifying that the RAS operation triggers and responds (Parts 5.1, 5.2) and that the resulting BES response (Parts 5.3, 5.4) is consistent with the intended functionality and design of the RAS.


Requirement R6


Deficiencies identified either in the periodic RAS evaluation conducted by the TP in

Requirement R4, or in the analysis conducted by the RASowner(s) pursuant to Requirement R5, are likely to pose a reliability risk to the BES. To mitigate this reliability risk, Requirement R6 mandates that each RASowner develop a CAP that establishes the mitigation actions and timetable to address the deficiency. If the CAP requires that a functional change be made to a RAS, Attachment 1 information must be submitted to the reviewing RC(s) prior to placing RAS modifications in service per Requirement R1.


Supplemental Material

Draft 1 of PRC0122

August 2015


Depending on the complexity of the issues, development of a CAP may require study,

engineering, or consulting work. A timeframe of sixfullcalendar months is allotted to allow enough time for RASowner collaboration on the CAP development, while ensuring that deficiencies are addressed in a reasonable time. A RAS deficiency may require the RC or Transmission Operator to impose operating restrictions so the System can operate in a reliable way until the RAS deficiency is resolved. Such operating restrictions will incent the RASowner to resolve the issue as quickly as possible.

A CAP documents a RAS performance deficiency, the actions to correct the deficiency with identified tasks, and the time frame for completion.


The following are example situations of when a CAP is required:

A determination after a RAS operation/nonoperation investigation that the RAS did not meet performance expectations. The RAS did not operate as designed.

Periodic planning assessment reveals RAS changes are necessary to correct performance or coordination issues.

Equipment failures.


Requirement R7

Implementation of a CAP ensures that RAS deficiencies are corrected by following a

documented timetable of identified actions. If necessary, the CAP can be modified to account for adjustments to the actions or scheduled timetable of activities. Operating restrictions imposed by the RC also incents RASowners to mitigate the issues and provide assurance that implementation is completed in a timely manner.


Requirement R8

The reliability objective of Requirement R8 is to test the nonProtection System components of a RAS (controllers such as programmable logic controllers (PLCs)) and to verify the overall performance of the RAS through functional testing. Functional tests validate RAS operation by ensuring System states are detected and processed, and that actions taken by the controls are correct and within the expected time using the inservice settings and logic. Functional testing is aimed at assuring overall RAS performance and not the component focused testing contained in the PRC005 maintenance standard.


Since the functional test operates the RAS under controlled conditions with known System states and expected results, testing and analysis can be performed without impact to the BES and should align with expected results. The RASowner is in the best position to determine the testing procedure and schedule due to their overall knowledge of the RAS design, installation, and functionality. Periodic testing provides the RASowner


Supplemental Material

Draft 1 of PRC0122

August 2015


assurance that latent failures may be identified and also promotes identification of changes in the System that may have introduced latent failures.


While the sixcalendaryear functional testing interval is greater than the annual or biannual periodic testing performed in some NERC Regions, the drafting team selected it because it is consistent with some of the maintenance intervals of various Protection System and Automatic Reclosing components established in PRC005. Consequently, this interval provides entities the opportunity to design their RAS functional testing programs such that it coincides with the testing of any associated PRC005 components. The sixcalendaryear interval is a balance between the resources required to perform the testing and the potential reliability impacts to the BES created by undiscovered latent failures that could cause an incorrect operation of the RAS.

Functional testing is not synonymous with endtoend testing. Endtoend testing is acceptable but it may not feasible for many RAS. When endtoend testing is not possible, a RASowner may use a segmented functional testing approach. The segments can be tested individually negating the need for complex maintenance schedules. In addition, actual RAS operation(s) can be used to fulfill the functional testing requirement. If a RAS does not operate in its entirety during a System event or System conditions do not allow an endtoend system test—the, the segmented approach should be used to fulfill this Requirement. Functional testing includes the testing of all RAS inputs used for detection, arming, operating, and data collection. Functional testing also includes the processing by the logic and infrastructure of a RAS as well as the action initiation by RAS outputs to address the System condition(s) for which the RAS is designed. All

segments and components of a RAS must be tested or have proven operations within a sixcalendaryear interval to demonstrate compliance with the Requirement.

As an example, consider a RAS implemented with one PLC that senses System conditions such as loading and line status from many locations. At one of these locations, a line protective relay (a component of a Protection System and included in the Protection System Maintenance Program (PSMP) of a RASowner) receives commands from the RAS PLC and sends data over nonProtection System communications infrastructure to operate a breaker. A functional test would send signals of simulated System conditions to the PLC to initiate an operate command to the protective relay, thus operating its associated breaker. This action verifies RAS action, verifies PLC control logic, and verifies RAS communications from PLC to relay. To complete this portion of a functional test, application of external testing signals to the protective relay, verified at the PLC are necessary to confirm full functioning of the RAS segment being tested.

This example describes a test for one segment of the RAS, the remaining segments would also require testing.


Supplemental Material

Draft 1 of PRC0122

August 2015


IEEE C37.233, “IEEE Guide for Power System Protection Testing,” 2009 section 8 (particularly 8.38.5), provides an overview of functional testing. The following opens section 8.3: Proper implementation requires a welldefined and coordinated test plan for performance evaluation of the overall system during agreed maintenance intervals. The maintenance test plan, also referred to as functional system testing, should include inputs, outputs, communication, logic, and throughput timing tests. The functional tests are generally not componentlevel testing, rather overall system testing. Some of the input tests may need to be done ahead of overall system testing to the extent that the tests affect the overall performance.


The test coordinator or coordinators need to have full knowledge of the intent of the scheme, isolation points, simulation scenarios, and restoration to normal procedures.

The concept is to validate the overall performance of the scheme, including the logic where applicable, to validate the overall throughput times against system modeling for different types of contingencies, and to verify scheme performance as well as the inputs and outputs.

If a RAS passes a functional test, it is not necessary to provide that specific information to the RC because that is the expected result and requires no further action. If a segment of a RAS fails a functional test, the status of that degraded RAS is required to be reported (in Realtime) to the Transmission Operator via PRC001, Requirement R6, then to the RC via TOP0012, Requirement R5. Consequently, it is not necessary to include a similar requirement in this standard.


Requirement R9

The RAS database required to be maintained by the RC in Requirement R9 ensures information regarding existing RAS is available to entities with a potential reliability need. Attachment 3 contains the minimum information that is required to be included about each RAS listed in the database. Additional information can be requested by the RC.


The information provided is sufficient for an entity with a reliability need to evaluate whether the RAS can impact its System. For example, a RAS performing generation rejection to mitigate an overload on a transmission line may cause a power flow change within an adjacent entity area. This entity should be able to evaluate the risk that a RAS poses to its System from the highlevel information provided in the RAS database.


The RAS database does not need to list detailed settings or modeling information, but the



Supplemental Material

Draft 1 of PRC0122

August 2015


description of the System performance issues, System conditions, and the intended corrective actions must be included. If additional details about the RAS operation are required, the entity may obtain the contact information of the RASentity from the RC.


The following diagrams depict the process flow of the PRC0122 requirements.


Technical Justifications for Attachment 1 Content

Supporting Documentation for RAS Review

To perform an adequate review of the expected reliability implications of a Remedial Action Scheme (RAS), it is necessary for the RASowner(s) to provide a detailed list of information describing the RAS to the designated RASentity. If there are multiple owners of the RAS, information may be needed from all owners, but a single RASowner (designated as the RASentity) is assigned the responsibility of compiling the RAS data and presenting it to the reviewing RC(s). Other RASowners may participate in the review, if they choose.


The necessary data ranges from a general overview of the RAS to summarized results of

transmission planning studies, to information about hardware used to implement the RAS.


Coordination between the RAS and other RAS and protection and control systems will be

examined for possible adverse interactions. This review can include wideranging electrical design issues involving the specific hardware, logic, telecommunications, and other relevant equipment and controls that make up the RAS.


Attachment 1

The following checklist identifies important RAS information for each new or functionally modified3 RAS that the RASentity shall document and provide to the RC for review pursuant to Requirement R1. When a RAS has been previously reviewed, only the proposed modifications to that RAS require review; however, it will be helpful to each reviewing RC if the RASentity provides a summary of the previously approved RAS functionality.


I. General

1. Information such as maps, oneline drawings, substation and schematic drawings that

identify the physical and electrical location of the RAS and related facilities.

Provide a description of the RAS to give an overall understanding of the functionality

and a map showing the location of the RAS. Identify other protection and control

systems requiring coordination with the RAS. See RAS Design below for additional

Supplemental Material

Draft 1 of PRC0122

August 2015


information. Provide a singleline drawing(s) showing all sites involved. The drawing(s) should provide sufficient information to allow the RC review team to assess design reliability, and should include information such as the bus arrangement, circuit breakers, the associated switches, etc. For each site, indicate whether detection, logic, action, or a

combination of these is present.

2. Functionality of new RAS or proposed functional modifications to existing RAS and

documentation of the pre and postmodified functionality of the RAS.

3Functionally Modified: Any modification to a RAS beyond the replacement of components that preserve the original functionality is a functional modification.

3. The Corrective Action Plan (CAP) if RAS modifications are proposed in a CAP.

[Reference NERC Reliability Standard PRC0122, Requirements R5 and R7]

Provide a description of any functional modifications to a RAS that are part of a CAP that

are proposed to address performance deficiency(ies) identified in the periodic

evaluation pursuant to Requirement R4, or the analysis of an actual RAS operation

pursuant to Requirement R5. A copy of the most recent CAP must be submitted in

addition to the other data specified in Attachment 1.

4. Initial data to populate the RAS database.

a. RAS name

b. RASentity and contact information

c. Expected or actual inservice date; most recent (Requirement R3) RCapproval date;

most recent 60fullcalendarmonth (Requirement R4) evaluation date; and, date of

retirement, if applicable

d. System performance issue or reason for installing the RAS (e.g., thermal overload,

angular instability, poor oscillation damping, voltage instability, under/overvoltage,

slow voltage recovery)

e. Description of the contingencies or System conditions for which the RAS was

designed (initiating conditions)

f. Corrective action taken by the RAS

g. Any additional explanation relevant to high level understanding of the RAS

Note: This is the same information as is identified in Attachment 3. Supplying the

data at this point in the review process ensures a more complete review and

minimizes any administrative burden on the reviewing RC(s).


II. Functional Description and Transmission Planning Information

1. Contingencies and system conditions that the RAS is intended to remedy.

[Reference NERC Reliability Standards PRC012, R1.2 and PRC013, R1.1]

a. The System conditions that would result if no RAS action occurred should be

identified.

b. Include a description of the System conditions that should arm the RAS so as to be

Supplemental Material

Draft 1 of PRC0122

August 2015


ready to take action upon subsequent occurrence of the critical system

contingencies or other operating conditions when RAS action is intended to occur. If

no arming conditions are required, this should also be stated.

c. Eventbased RAS are triggered by specific contingencies that initiate mitigating

action. Conditionbased RAS may also be initiated by specific contingencies, but

specific Contingencies are not always required. These triggering Contingencies

and/or conditions should be identified.

2. The actions to be taken by the RAS in response to disturbance conditions.

[Reference NERC Reliability Standards PRC012, R1.2 and PRC013, R1.2]

Mitigating actions are designed to result in acceptable System performance. These

actions should be identified, including any time constraints and/or “backup” mitigating

measures that may be required in case of a single RAS component failure.

3. A summary of technical studies, if applicable, demonstrating that the proposed RAS

actions satisfy System performance objectives for the scope of System events and

conditions that the RAS is intended to remedy. The technical studies summary shall also

include information such as the study year(s), system conditions, and contingencies

analyzed on which the RAS design is based, and when those technical studies were

performed. [Reference NEC Reliability Standard PRC014, R3.2]

Review the scheme purpose and impact to ensure it is (still) necessary, serves the

intended purposes, and meets current performance requirements. While copies of the

full, detailed studies may not be necessary, any abbreviated descriptions of the studies

must be detailed enough to allow the reviewing RC(s) to be convinced of the need for

the scheme and the results of RASrelated operations.

4. Information regarding any future system plans that will impact the RAS.

[Reference NERC Reliability Standard PRC014, R3.2]

The RC’s other responsibilities under the NERC Reliability Standards focus on the

Operating Horizon, rather than the Planning Horizon. As such, the RC is less likely to be

aware of any longer range plans that may have an impact on the proposed RAS. Such

knowledge of future Plans is helpful to provide perspective on the capabilities of the

RAS.

5. Documentation showing that the possible inadvertent operation of the RAS resulting

from any single RAS component malfunction satisfies all of the following:

[Reference NERC Reliability Standard PRC012, R1.4]

a. The BES shall remain stable.

b. Cascading shall not occur.

c. Applicable Facility Ratings shall not be exceeded.

d. BES voltages shall be within postContingency voltage limits and postContingency

voltage deviation limits as established by the Transmission Planner and the Planning

Coordinator.

Supplemental Material

Draft 1 of PRC0122

August 2015


e. Transient voltage responses shall be within acceptable limits as established by the

Transmission Planner and the Planning Coordinator.

6. An evaluation indicating that the RAS settings and operation avoids adverse interactions

with other RAS, and protection and control systems.

[Reference NERC Reliability Standards PRC012, R1.5 and PRC014, R3.4]

RAS are complex schemes that may take action such as tripping load or generation or reconfiguring the system. Many RAS depend on sensing specific System configurations to determine whether they need to arm or take actions. An examples of an adverse

interaction: A RAS that reconfigures the System also changes the available fault duty,

which can affect distance relay overcurrent (“fault detector”) supervision and ground

overcurrent protection coordination.

7. Identification of other affected RCs.

This information is needed to aid in information exchange among all affected entities

and coordination of the RAS with other RAS and protection and control systems.


III. Implementation

1. Documentation describing the applicable equipment used for detection,

telecommunications, transfer trip, logic processing, and monitoring.


Detection

Detection and initiating devices, whether for arming or triggering action, should be designed to be secure. Several types of devices have been commonly used as disturbance, condition, or status detectors:

Line open status (event detectors),

Protective relay inputs and outputs (event and parameter detectors),

Transducer and IED (analog) inputs (parameter and response detectors),

Rate of change (parameter and response detectors).


Telecommunications Channels and Transfer Trip Equipment

Telecommunications channels used for sending and receiving RAS information between

sites and/or transfer trip devices should meet at least the same criteria as other relaying

protection communication channels. Discuss performance of any nondeterministic

communication systems used (such as Ethernet). The scheme logic should be designed so that loss of the channel, noise, or other channel or equipment failure will not result in a false operation of the scheme.


It is highly desirable that the channel equipment and communications media (power line

carrier, microwave, optical fiber, etc.) be owned and maintained by the RASowner, or

Supplemental Material

Draft 1 of PRC0122

August 2015


perhaps leased from another entity familiar with the necessary reliability requirements. All channel equipment should be monitored and alarmed to the dispatch center so that timely diagnostic and repair action shall take place upon failure. Publicly switched telephone networks are generally an undesirable option.

Communication channels should be well labeled or identified so that the personnel working on the channel can readily identify the proper circuit. Channels between entities should be identified with a common name at all terminals. Transfer trip equipment, when separate from other RAS equipment, should be monitored and labeled similarly to the channel equipment.


Logic Processing

All RAS require some form of logic processing to determine the action to take when the

scheme is triggered. Required actions are always scheme dependent. Different actions may be required at different arming levels or for different contingencies. Scheme logic may be achievable by something as simple as wiring a few auxiliary relay contacts or by much more complex logic processing.


Platforms that have been used reliably and successfully include PLCs in various forms,

personal computers (PCs), microprocessor protective relays, remote terminal units (RTUs), and logic processors. Singlefunction relays have been used historically to implement RAS, but this approach is now less common except for very simple new RAS or minor additions to existing RAS.


Monitoring by SCADA/EMS should include at least

Whether the scheme is inservice or out of service.

For RAS that are armed manually, the arming status may be the same as whether

the RAS is inservice or out of service.

For RAS that are armed automatically, these two states are independent because a

RAS that has been placed in service may be armed or unarmed based on whether

the automatic arming criteria have been met.

The current operational state of the scheme (available or not).

In cases where the RAS requires singlecomponent failure performance (redundancy),

the minimal status indications should be provided separately for each system.

The minimum status is generally sufficient for operational purposes; however,

where possible it may be useful to provide additional information regarding partial

failures or the status of critical components to allow the RASowner to more

efficiently troubleshoot a reported failure. Whether this capability exists will depend

in part on the design and vintage of equipment used in the RAS. While all schemes

should provide the minimum level of monitoring, new schemes should be designed

Supplemental Material

Draft 1 of PRC0122

August 2015


with the objective of providing monitoring at least similar to what is provided for

microprocessorbased Protection Systems.

2. Information on detection logic and settings/parameters that control the operation of

the RAS. [Reference NERC Reliability Standards PRC012, R1.2 and PRC013, R1.3]

Several methods to determine line or other equipment status are in common use, often

in combination:

a. Auxiliary switch contacts from circuit breakers and disconnect switches (52a/b,

89a/b)—the most common status monitor; “a” contacts exactly emulate actual

breaker status, while “b” contacts are opposite to the status of the breaker;

b. Undercurrent detection—a low level indicates an open condition, including at the far

end of a line; pickup is typically slightly above the total linecharging current;

c. Breaker trip coil current monitoring—typically used when highspeed RAS response

is required, but usually in combination with auxiliary switch contacts and/or other

detection because the trip coil current ceases when the breaker opens; and

d. Other detectors such as angle, voltage, power, frequency, rate of change of these,

out of step, etc.—very dependent on specific scheme requirements, but some forms

may substitute for or enhance current monitoring detection.

Both RAS arming and action triggers often require monitoring of analog quantities such

as power, current, and voltage at one or more locations and are set to detect a specific

level of the pertinent quantity. These monitors may be relays, meters, transducers, or

other devices

3. Documentation showing that any multifunction device used to perform RAS function(s),

in addition to other functions such as protective relaying or SCADA, does not

compromise the reliability of the RAS when the device is not in service or is being

maintained.

In this context, a multifunction device (e.g., microprocessorbased relay) is a single

component that is used to perform the function of a RAS in addition to protective

relaying and/or SCADA simultaneously. It is important that other applications in the

multifunction device do not compromise the functionality of the RAS when the device is

in service or when it is being maintained. The following list outlines considerations when

the RAS function is applied in the same microprocessorbased relay as equipment

protection functions:

a. Describe how the multifunction device is applied in the RAS.

b. Show the general arrangement and describe how the multifunction device is

labeled in the design and application, so as to identify the RAS and other device

functions.

c. Describe the procedures used to isolate the RAS function from other functions in the

device.

Supplemental Material

Draft 1 of PRC0122

August 2015


d. Describe the procedures used when each multifunction device is removed from

service and whether coordination with other protection schemes is required.

e. Describe how each multifunction device is tested, both for commissioning and

during periodic maintenance testing, with regard to each function of the device.

f. Describe how overall periodic RAS functional and throughput tests are performed if

multifunction devices are used for both local protection and RAS.

g. Describe how upgrades to the multifunction device, such as firmware upgrades, are

accomplished. How is the RAS function taken into consideration?

Other devices that are usually not considered multifunction devices such as auxiliary

relays, control switches, and instrument transformers may serve multiple purposes such

as protection and RAS. Similar concerns apply for these applications as noted above.

4. Documentation showing that a singlecomponent failure in a RAS, when the RAS is

intended to operate, does not prevent the BES from meeting the same performance

requirements (defined in Reliability Standard TPL0014 or its successor) as those

required for the events and conditions for which the RAS is designed. The

documentation should describe or illustrate how the implementation design achieves

this objective. [Reference NERC Reliability Standard PRC012, R1.3]

RAS automatic arming, if applicable, is vital to RAS and System performance and is

therefore included in this requirement.

Acceptable methods to achieve this objective include the following:

a. Providing redundancy of RAS components listed below:

i. Protective or auxiliary relays used by the RAS.

ii. Communications systems necessary for correct operation of the RAS.

iii. Sensing devices used to measure electrical quantities used by the RAS.

iv. Station dc supply associated with RAS functions.

v. Control circuitry associated with RAS functions through the trip coil(s) of the

circuit breakers or other interrupting devices.

vi. Computers or programmable logic devices used to analyze information and

provide RAS operational output.

b. Arming more load or generation than necessary such that failure of the RAS to drop

a portion of load or generation would not be an issue, if tripping the total armed

amount of load or generation does not cause other adverse impacts to reliability.

c. Using alternative automatic actions to back up failures of single RAS components.

d. Manual backup operations, using planned System adjustments such as Transmission

configuration changes and redispatch of generation, if such adjustments are

executable within the time duration applicable to the Facility Ratings.

5. Documentation describing the functional testing process.



Supplemental Material

Draft 1 of PRC0122

August 2015


The following checklist identifies important RAS information for each existing RAS to be retired that the RASentity shall document and provide to the Reliability Coordinator for review pursuant to Requirement R1.

1. Information necessary to ensure that the Reliability Coordinator is able to understand

the physical and electrical location of the RAS and related facilities.

2. A summary of technical studies, if applicable, upon which the decision to retire the RAS is based.

3. Anticipated date of RAS retirement.

While the documentation necessary to evaluate RAS removals is not as extensive as for

new or functionally modified RAS, it is still vital that, when the RAS is no longer

available, System performance will still meet the appropriate (usually TPL) requirements

for the Contingencies or System conditions that the RAS had been installed to

remediate.


Technical Justification for Attachment 2 Content

Reliability Coordinator RAS Review Checklist

Attachment 2 is a checklist provided to assist the RC in identifying reliability considerations generally relevant to aspects of RAS design and implementation, and also for the purpose of facilitating consistent reviews continentwide for each RAS to be installed or functionally modified. Most of the checklist items should be applicable to most RAS. There may be checklist items that are not applicable to a given RAS in which case they may be noted as not applicable and skipped in the RC review. Depending on the specifics of the RAS under review, it is possible that other reliability considerations may be identified during the review. Any other reliability considerations, along with their resolution with respect to the particular RAS under review, should be documented along with the Attachment 2 items that were applicable to the specific RAS under review.

File Typeapplication/vnd.openxmlformats-officedocument.wordprocessingml.document
AuthorMichele Chambers
File Modified0000-00-00
File Created2021-01-22

© 2024 OMB.report | Privacy Policy