UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION
Docket No. IC18-7-000 (FERC-725L)
ERRATA NOTICE
(April 24, 2018)
The Commission issued 60-day1 and 30-day2 notices on 1/22/2018 and 4/11/2018 respectively, for the renewal of the FERC-725L (Mandatory Reliability Standards for the Bulk-Power System: MOD Reliability Standards) information collection. Both notices request comments on FERC-725L and indicate the Commission will submit the information collection to the Office of Management and Budget (OMB) for review.
This Errata Notice adds data related to MOD-031-2 Reliability Standard which was inadvertently omitted from those public notices, and corrects the total burden and cost for FERC-725L. The additional data and corrected totals follow:
Reliability Standard MOD-031-2 (Demand and Energy Data), included in FERC-725L |
||||||
Reliability Standard MOD-031-2 |
Number and Type of
Respondents |
Annual Number of Responses per Respondent (2) |
Total Number of Responses (1)*(2)=(3) |
Avg. Burden & Cost Per Response3 (4) |
Total Annual Burden Hours & Total Annual Cost (3)*(4)=(5) |
Cost per Respondent (5)÷(1) |
(On-going) Develop summary in accordance with Requirement R1, Subparts 1.5.4 and 1.5.5. |
561 (DP, LSE, TP and/or BA) |
1 |
561 |
8 hrs.; $545 |
4,488 hrs.; |
$545 |
The corrected total annual estimated burden and cost for the FERC-725L information collection (including Reliability Standard MOD-031-2, noted above) is 35,208 hours and $2,377,376 respectively.
Kimberly D. Bose,
Secretary.
1 83 FR 3699, 1/26/2018
2 83 FR 17171, 4/18/2018
3 The estimate uses the average hourly wage (plus benefits) of $68.12/hour for electrical engineers (Occupation Code: 17-2071) from the Bureau of Labor Statistics.
File Type | application/vnd.openxmlformats-officedocument.wordprocessingml.document |
Author | Anthony May |
File Modified | 0000-00-00 |
File Created | 2021-01-21 |