RM19-6-000 Final Rule Press Release

RM19-6-000 Final Rule Press Release.pdf

FERC-505, (Final Rule in RM19-6-000) Small Hydropower Projects and Conduit Facilities including License/Relicense, Exemption, and Qualifying Conduit Facility Determination

RM19-6-000 Final Rule Press Release

OMB: 1902-0115

Document [pdf]
Download: pdf | pdf
April 18, 2019
News Media Contact
Celeste M. Miller | 202-502-8680
Docket No. RM19-6-000

FERC Finalizes Expedited Hydro Licensing Process
The Federal Energy Regulatory Commission (FERC) today issued a final rule establishing an expedited licensing process
for original hydropower licenses for certain qualifying facilities at existing non-powered dams and for closed-loop
pumped storage projects. The rule is part of the Commission’s successful implementation of the America’s Water
Infrastructure Act of 2018, and seeks to ensure a final licensing decision no later than two years after receipt of a
completed application.
In November 2018, FERC invited federal and state agencies and Native American tribes to participate in an interagency
task force (ITF) to coordinate the regulatory processes associated with the proposed expedited licensing process. The
Commission convened an ITF coordination session in December 2018. Informed by the coordination efforts of the ITF,
FERC issued a Notice of Proposed Rulemaking in January 2019 seeking comment on the proposed expedited licensing
process.
Under the final rule, an applicant interested in participating in the expedited process must file a request for
authorization to do so along with its license application. To qualify as a facility at an existing non-powered dam for the
purposes of the expedited licensing process, a facility cannot already be licensed or exempted from the licensing
requirements in the Federal Power Act. The applicant also must demonstrate that the facility will be associated with a
qualifying non-powered dam and will be constructed, operated, and maintained for the generation of electric power.
The facility must generate electricity by using withdrawals, diversions, releases or flows from the associated qualifying
non-powered dam and its operations must not make any material changes to the storage, release or flow operations of
the associated qualifying non-powered dam.
To qualify as a closed-loop pumped storage project under the expedited licensing process, the pumped storage project
must cause little or no change in existing surface and groundwater flows and uses and must be considered unlikely to
adversely affect threatened or endangered species or their designated critical habitat under the Endangered Species
Act. The final rule also adds qualifying criteria to ensure that a qualifying pumped storage project utilizes only
reservoirs situated at locations other than natural waterways, lakes, wetlands, and other natural surface water
features; and relies only on temporary withdrawals from surface waters or groundwater for the sole purposes of initial
fill and periodic recharge needed for project operation.
The application also must include consultation documentation with stakeholders, including federal and state agencies,
tribes and dam owners.
The final rule will take effect 90 days after publication in the Federal Register.
R-19-25

(30)


File Typeapplication/pdf
File Modified0000-00-00
File Created0000-00-00

© 2024 OMB.report | Privacy Policy