National Science Foundation Large Facilities Manual

National Science Foundation Large Facilities Manual

Exhibit 1 - Major Facilities Guide May 2019_Final Draft

National Science Foundation Large Facilities Manual

OMB: 3145-0239

Document [pdf]
Download: pdf | pdf
MAJOR FACILITIES GUIDE 

Prepared by the Large Facilities Office in the Budget, 
Finance, and Award Management Office (BFA‐LFO)

Draft for OMB Approval 
NSF 19‐68 
May 2019

Major Facilities Guide: NSF 19-68 (May 2019)
Summary of Significant Changes
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

SUMMARY OF SIGNIFICANT CHANGES
This document has been cleared for publication under OMB al number 1315-0239, which
expires 6/30/2020. The purpose of this revision is to update the material and to improve the
clarity and legibility of the guide for the targeted audience of users both inside and outside NSF.
A summary of the changes for this revision is given below. Footers within each section of this
document indicate the last revision date of the content in that section, while all page headers in
the document include the date and NSF number of the current version of the Major Facilities
Guide.
1.

Replaced the title of this document from “Large Facilities Manual” to “Major Facilities
Guide” and “Large Facility” to “Major Facility” throughout the document to align with the
American Innovation and Competitiveness Act (AICA) terminology.

2.

Revised Section 1.1, Purpose and Scope, to provide the basis for the use of cooperative
agreements and contracts.

3.

Revised Section 1.2, Precedence, to clarify the order of precedence for regulations and
NSF documents.

4.

Updated and moved the NSB Policies on Recompetition and No Cost Overrun from other
sections of the guide to Section 1.4, Applicable Legislation and NSF Policy.

5.

In Section 1.4, Applicable Legislation and NSF Policy, added the definition for mid-scale
project.

6.

Revised Section 2.1.3, The Major Facility Life Cycle, to clarify the five different stages of a
facility’s life cycle and the exit process from the Development Stage to Design Stage.

7.

New material was introduced in Section 2.1.4, Summary of the Major Facility
Implementation Process, on spiral development.

8.

Figure 2.1.4-1, Summary Timeline for Major Facility Projects (Development and Design),
was revised to clarify the two levels of oversight of major facilities within NSF.

9.

In Section 2.1.6, Roles and Responsibilities for NSF Staff for Management and Oversight
of Major Facilities, various edits and updated Figures were made throughout to add the
Chief Officer for Research Facilities position, the Major Facilities Working Group, the
Facilities Readiness Panel and the Facilities Governance Board and to delete the Large
Facilities Working Group and the MREFC Panel.

10. Previous LFM version Section 2.4.2, Commissioning Plan, was moved to Section 3.4.2,
Detailed Guidelines for Project Execution Plans.
11. New material was added to the reserved subsection 2.4.2.1, Project Close-out Process.

Section Revision:
May 30, 2019

i

Major Facilities Guide: NSF 19-68 (May 2019)
Summary of Significant Changes
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

12. Moved material on annual reporting compared to planned from Section 4.2 to Section
2.5.1 under Annual Work Plan.
13. Moved the material on application of the guide to non-major facility projects from
Section 2 to Section 5 Guidance for Mid-Scale Research Infrastructure Projects and
revised content.
14. Material was removed from Section 3.2, NSF Facility Plan [Reserved], and this section is
reserved.
15. Revised Section 3.3, NSF Internal Management Plans for the Major Facility Life Cycle, to
clarify NSF expectations for internal management plans.
16. Revised Section 3.4.1, Components of a Project Execution Plan, and added material to
the reserved Section 3.4.2, Detailed Guidelines for Project Execution Plans, to clarify
Commissioning and to add a requirement for a segregation of funds plan.
17. In Section 3.5.2, Procedures for Renewal or Recompetition of an Operating Major Facility,
updated the issues for reconsideration for alignment with internal guidelines.
18. New material was added to reserved Section 3.6, Facility Divestment Plan, to describe
potential elements of a transition plan from NSF stewardship to divestment. Sections
2.1.3 and 9.2 were revised to clarify the range of options for the Divestment Stage.
19. In Section 4.2, Cost Estimating and Analysis, major revisions were made to Sections 4.2.1
through 4.2.4 to clarify NSF guidance and requirements to ensure alignment with GAO
guidelines and subsection 4.2.2.3 was added on the application of GAO’s twelve steps of
a high-quality cost estimating process.
20. Edited subsection 4.2.2.4, Supplementary Guidance for NSF Budget Categories from the
PAPPG, to clarify the difference between subawards and contracts for alignment with the
Uniform Guidance 2 CFR § 200.331, to emphasize Subrecipient monitoring requirements,
and to update the NSF Budget Categories as related to Fee.
21. Subsections 4.2.5.1 and 4.2.5.2 were edited to move the “No Cost Overrun” policy
language to Section 1.4 and clarify when the total project cost is established.
22. Revisions were made to Subsections 4.2.5.1 and 6.2.3.1 and the Lexicon, Section 9.2, to
clarify the definitions of management reserve and contingency.
23. Subsection 4.2.5.8, Reporting Requirements, and Section 4.6.2, Recipient Performance
Reports, was edited to clarify the required content of the monthly construction stage
reports and to remove redundancies.
24. Section 4.2.6, Budget Contingency Planning during the Operations Stage, was revised to
include strategies to handle risks on operations awards.

Section Revision:
May 30, 2019

ii

Major Facilities Guide: NSF 19-68 (May 2019)
Summary of Significant Changes
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

25. Section 4.3, Schedule Development, Estimating, and Analysis, was created and reserved
for future content to provide NSF guidance and requirements for construction schedules
and to ensure alignment with GAO guidelines.
26. Edited subsection 4.6.3.3, Business Systems Reviews (BSR), to delete the five-year cycle
requirement for BSRs and add language regarding the annual major facility portfolio risk
assessment.
27. Edited subsection 4.6.3.4, Incurred Cost Audits, to change the threshold for incurred cost
audits to $70M and the name of the financial data collection tool and update Figure
4.6.3-1.
28. New material was added to the reserved Section 4.6.3.6, Earned Value Management
Verification, Acceptance, and Surveillance, on the NSF requirements and process for
verifying construction project EVM systems.
29. New material was added to the reserved Section 6.3, Guidelines for Cyber-Security of
NSF’s Major Facilities, on the implementation and monitoring of cyber-security good
practices.
30. New material was added to the reserved Section 6.6, Guidelines for Property
Management, on requirements for managing and disposing of property furnished by the
Federal government or whose cost was charged to a project supported by a Federal
award.
31. New material was added to the reserved Section 6.8, Guidelines for Earned Value
Management Systems, on implementation and scalability for effective project
management controls.
32. New acronyms (5) for new roles introduced in Section 2.1.6 were added to Section 8, List
of Acronyms.
33. Section 9, Lexicon, contains a revised and updated Large Facility definition to Major
Facility, additional terms, Independent Cost Estimate Review and Research
Infrastructure, and updated definitions of terms (5) used in Section 4.2.
34. Revised numerous references to MREFC used to reference the construction stage of a
major facility’s life cycle to reflect the definition in Section 1.4.3, Major Multi-User
Research Facility Project (Major Facility).
35. Corrections were made to various minor typographical errors and formatting errors.
Document references were updated to latest versions where applicable.

Section Revision:
May 30, 2019

iii

Major Facilities Guide: NSF 19-68 (May 2019)
Table of Contents
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

TABLE OF CONTENTS
1 INTRODUCTION........................................................................................................... 1.1-1
1.1 Purpose and Scope........................................................................................................ 1.1-1
1.2 Precedence.................................................................................................................... 1.2-1
1.3 Document Structure ..................................................................................................... 1.3-1
1.4 Applicable Legislation and NSF Policy ........................................................................... 1.4-1
Research Infrastructure .................................................................................... 1.4-1
MREFC Threshold .............................................................................................. 1.4-1
Major Multi-User Research Facility Project (Major Facility)............................. 1.4-1
Mid-Scale Project .............................................................................................. 1.4-1
National Science Board Policy on Recompetition............................................. 1.4-2
NSF “No Cost Overrun” Policy........................................................................... 1.4-2
2 MAJOR FACILITY LIFE CYCLE AND MAJOR FACILITY OVERSIGHT .................................... 2.1-1
2.1 Process Introduction ..................................................................................................... 2.1-1
Definition of the MREFC Account .................................................................. 2.1.1-1
Eligibility for MREFC Funding ......................................................................... 2.1.2-1
The Major Facility Life Cycle .......................................................................... 2.1.3-1
Summary of the Major Facility Implementation Process .............................. 2.1.4-1
Timeline and Flowcharts for the Major Facilities Approval Process ............. 2.1.5-1
Roles and Responsibilities for NSF Staff for Management and Oversight of Major
Facilities.......................................................................................................... 2.1.6-1
2.1.6.1 Overview ......................................................................................... 2.1.6-1
2.1.6.2 Main Participants ............................................................................ 2.1.6-8
2.1.6.3 Coordinating and Advisory Bodies................................................ 2.1.6-17
2.1.6.4 Governing Bodies .......................................................................... 2.1.6-20
2.2 Development Stage.................................................................................................... 2.2.1-1
Initiation of a Potential Major Facility Project ............................................... 2.2.1-1
Exit from Development to Design Stage ........................................................ 2.2.2-1
2.3 Design Stage – Conceptual, Preliminary, and Final Design Phases ........................... 2.3.1-1
Conceptual Design Phase ............................................................................... 2.3.1-1
2.3.1.1 Introduction – Conceptual Design Phase........................................ 2.3.1-1
2.3.1.2 Conceptual Design Phase Activities ................................................ 2.3.1-2
2.3.1.3 Conceptual Design Review (CDR) ................................................... 2.3.1-4
2.3.1.4 Exit from the Conceptual Design Phase.......................................... 2.3.1-5
Preliminary Design Phase............................................................................... 2.3.2-1
2.3.2.1 Introduction – Preliminary Design Phase ....................................... 2.3.2-1
2.3.2.2 Preliminary Design Phase Activities ................................................ 2.3.2-2
2.3.2.3 Preliminary Design Review (PDR) ................................................... 2.3.2-3
2.3.2.4 Exit from Preliminary Design Phase ................................................ 2.3.2-4
2.3.2.5 NSF Director’s Recommendation for Advancement to Final
Design ............................................................................................. 2.3.2-4
2.3.2.6 National Science Board Authorization ............................................ 2.3.2-5

Section Revision:
May 30, 2019

iv

Major Facilities Guide: NSF 19-68 (May 2019)
Table of Contents
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

2.3.2.7 Inclusion in an NSF Budget Request ............................................... 2.3.2-5
Final Design Phase ......................................................................................... 2.3.3-1
2.3.3.1 Introduction – Final Design Phase .................................................. 2.3.3-1
2.3.3.2 Final Design Review (FDR) .............................................................. 2.3.3-1
2.3.3.3 Exit from the Final Design Phase .................................................... 2.3.3-3
2.4 Construction Stage ..................................................................................................... 2.4.1-1
Construction Award Management and Oversight ......................................... 2.4.1-1
Construction Award Close-out ....................................................................... 2.4.2-1
2.4.2.1 Project Close-out Process ............................................................... 2.4.2-1
2.4.2.2 Request for No-Cost Extension ....................................................... 2.4.2-1
2.5 Operations Stage........................................................................................................ 2.5.1-1
Operations Management and Oversight ....................................................... 2.5.1-1
Renewal/Recompetition ................................................................................ 2.5.2-1
2.6 Divestment Stage .......................................................................................................... 2.6-1
3 FACILITY LIFE CYCLE MANAGEMENT PLANS FOR MAJOR FACILITIES ............................. 3.1-1
3.1 Introduction .................................................................................................................. 3.1-1
3.2 NSF Facility Plan [Reserved] .......................................................................................... 3.2-1
3.3 NSF Internal Management Plans for the Major Facility Life Cycle ............................... 3.3-1
3.4 Project Execution Plan ............................................................................................... 3.4.1-1
Components of a Project Execution Plan....................................................... 3.4.1-1
Detailed Guidelines for Project Execution Plans ........................................... 3.4.2-1
3.4.2.1 Introduction [Reserved] .................................................................. 3.4.2-1
3.4.2.2 Organization [Reserved].................................................................. 3.4.2-1
3.4.2.3 Design and Development [Reserved].............................................. 3.4.2-1
3.4.2.4 Construction Project Definition ...................................................... 3.4.2-1
3.4.2.5 Staffing [Reserved] .......................................................................... 3.4.2-1
3.4.2.6 Risk and Opportunity Management ............................................... 3.4.2-1
3.4.2.7 Systems Engineering [Reserved] ..................................................... 3.4.2-1
3.4.2.8 Configuration Control ..................................................................... 3.4.2-1
3.4.2.9 Acquisitions [Reserved] ................................................................... 3.4.2-1
3.4.2.10 Project Management Controls........................................................ 3.4.2-1
3.4.2.11 Site and Environment [Reserved] ................................................... 3.4.2-1
3.4.2.12 Cyber-Infrastructure ....................................................................... 3.4.2-1
3.4.2.13 Environmental, Safety and Health [Reserved] ................................ 3.4.2-2
3.4.2.14 Review and Reporting ..................................................................... 3.4.2-2
3.4.2.15 Commissioning................................................................................ 3.4.2-2
3.4.2.16 Project Close-out Plan..................................................................... 3.4.2-3
3.5 Operations Planning................................................................................................... 3.5.1-1
Preparation of Proposals for Operations and Management ......................... 3.5.1-1
Procedures for Renewal or Recompetition of an Operating Major Facility .. 3.5.2-1
Detailed Guidelines for Oversight of Operations .......................................... 3.5.3-1
3.6 Facility Divestment Plan................................................................................................ 3.6-1

Section Revision:
May 30, 2019

v

Major Facilities Guide: NSF 19-68 (May 2019)
Table of Contents
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

4 KEY MANAGEMENT PRINCIPLES AND REQUIREMENTS FOR MAJOR FACILITIES ............. 4.1-1
4.1 Introduction .................................................................................................................. 4.1-1
4.2 Cost Estimating and Analysis ..................................................................................... 4.2.1-1
Overview of Guidance and Process for Both Construction and Operations Awards
........................................................................................................................ 4.2.1-1
Elements of Both Construction and Operations Estimates ........................... 4.2.2-1
4.2.2.1 Cost Estimating Plan ....................................................................... 4.2.2-1
4.2.2.2 Estimate Formats ............................................................................ 4.2.2-4
4.2.2.3 Application of GAO Cost Guidance to Major Facilities ................... 4.2.2-6
4.2.2.4 Supplementary Guidance for NSF Budget Categories from the PAPPG
...................................................................................................... 4.2.2-10
4.2.2.5 Fee................................................................................................. 4.2.2-16
4.2.2.6 Escalation ...................................................................................... 4.2.2-16
4.2.2.7 Work Breakdown Structure (WBS) ............................................... 4.2.2-17
Additional Guidance for Construction Estimates .......................................... 4.2.3-1
4.2.3.1 Purpose and Process ....................................................................... 4.2.3-1
4.2.3.2 Construction Cost Book – Introduction and Executive Summary .. 4.2.3-1
4.2.3.3 Construction Cost Book – Format ................................................... 4.2.3-2
4.2.3.4 Construction Cost Book – Detail ..................................................... 4.2.3-3
Additional Guidance for Operations Estimates ............................................. 4.2.4-1
4.2.4.1 Purpose and Process ....................................................................... 4.2.4-1
4.2.4.2 Operations Awards Proposals – Overview ..................................... 4.2.4-1
4.2.4.3 Operations Awards Proposals – Format ......................................... 4.2.4-2
4.2.4.4 Operations Awards Proposals – Detail ........................................... 4.2.4-4
Budget Contingency Planning for the Construction Stage ............................ 4.2.5-1
4.2.5.1 NSF Policy Positions ........................................................................ 4.2.5-1
4.2.5.2 Introduction .................................................................................... 4.2.5-1
4.2.5.3 Contingency Planning and Assessment during Conceptual Design 4.2.5-5
4.2.5.4 Contingency Planning and Assessment during Preliminary Design 4.2.5-6
4.2.5.5 Development of the Contingency Use Process .............................. 4.2.5-8
4.2.5.6 Contingency Planning and Assessment during Final Design .......... 4.2.5-8
4.2.5.7 Contingency Use and NSF Oversight during Construction ............. 4.2.5-9
4.2.5.8 Reporting Requirements............................................................... 4.2.5-10
4.2.5.9 Partnership Considerations .......................................................... 4.2.5-11
Budget Contingency Planning during the Operations Stage ......................... 4.2.6-1
4.3 Schedule Development, Estimating, and Analysis ........................................................ 4.3-1
4.4 System Integration, Commissioning, Testing and Acceptance ..................................... 4.4-1
4.5 Documentation Requirements ..................................................................................... 4.5-1
4.6 Requirements for NSF Performance Oversight, Reviews, Audits, and Reporting ..... 4.6.1-1
Introduction to Oversight, Reviews, Audits and Reporting ........................... 4.6.1-1
Recipient Performance Reports ..................................................................... 4.6.2-1
Recipient Performance Reviews and Audits .................................................. 4.6.3-1
4.6.3.1 Recipient Internal Reviews ............................................................. 4.6.3-1

Section Revision:
May 30, 2019

vi

Major Facilities Guide: NSF 19-68 (May 2019)
Table of Contents
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

4.6.3.2
4.6.3.3
4.6.3.4
4.6.3.5
4.6.3.6

NSF External Reviews ...................................................................... 4.6.3-1
Business Systems Reviews (BSR) .................................................... 4.6.3-2
Incurred Cost Audits ....................................................................... 4.6.3-3
Accounting System Review or Audits ............................................. 4.6.3-4
Earned Value Management Verification, Acceptance, and Surveillance
........................................................................................................ 4.6.3-5
NSF Performance Metric for Construction .................................................... 4.6.4-1
Re-Baselining.................................................................................................. 4.6.5-1
4.7 Partnerships ............................................................................................................... 4.7.1-1
Partnerships Overview ................................................................................... 4.7.1-1
Partnership Funding....................................................................................... 4.7.2-1
Memorandum of Understanding (MOU) with NSF........................................ 4.7.3-1
5 GUIDANCE FOR MID-SCALE RESEARCH INFRASTRUCTURE PROJECTS ............................... 5-1
6 SPECIAL TOPICS AND SUPPLEMENTARY MATERIALS .................................................... 6.1-1
6.1 Introduction .................................................................................................................. 6.1-1
6.2 Risk Management Guidelines FOR CONSTRUCTION STAGE ...................................... 6.2.1-1
Introduction ................................................................................................... 6.2.1-1
Definition of Project Risk and Risk Exposure ................................................. 6.2.2-1
Definition of Allowable Contingencies .......................................................... 6.2.3-1
6.2.3.1 Allowable Contingency ................................................................... 6.2.3-1
6.2.3.2 Contingency Definitions.................................................................. 6.2.3-1
Risk Management Steps and Methodology ................................................... 6.2.4-1
Risk Management Planning ........................................................................... 6.2.5-1
6.2.5.1 Risk Management Plan (RMP) ........................................................ 6.2.5-2
6.2.5.2 Roles and Responsibilities............................................................... 6.2.5-4
Risk Identification .......................................................................................... 6.2.6-1
6.2.6.1 Risk Identification Process .............................................................. 6.2.6-1
6.2.6.2 Risk Identification and the Risk Register ........................................ 6.2.6-2
6.2.6.3 Risk Description .............................................................................. 6.2.6-3
6.2.6.4 Risk Identification Concerns ........................................................... 6.2.6-4
Qualitative Risk Analysis – Risk Register Ranking .......................................... 6.2.7-1
6.2.7.1 Purpose of Qualitative Risk Analysis ............................................... 6.2.7-1
6.2.7.2 Considerations When Performing Qualitative Risk Analysis .......... 6.2.7-1
6.2.7.3 Limitations of Qualitative Analysis ................................................. 6.2.7-3
6.2.7.4 Qualitative Risk Analysis – Probability and Impact Assessment .... 6.2.7-3
6.2.7.5 Alternative Approach to Qualitative Risk Impact Analysis ‒ Maxwell
........................................................................................................ 6.2.7-7
6.2.7.6 Qualitative Risk Analysis – Risk Level Matrix .................................. 6.2.7-8
6.2.7.7 Risk Level Input to the Risk Register ............................................. 6.2.7-11
6.2.7.8 Other Qualitative Risk Analysis Methods ..................................... 6.2.7-14
Quantitative Risk Analysis – Estimating Contingency .................................... 6.2.8-1
6.2.8.1 The Purpose of Quantitative Risk Analysis ..................................... 6.2.8-1
6.2.8.2 Key Elements in Quantitative Risk Analysis .................................... 6.2.8-4
Section Revision:
May 30, 2019

vii

Major Facilities Guide: NSF 19-68 (May 2019)
Table of Contents
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

6.3

6.4
6.5
6.6
6.7
6.8

6.2.8.3 Platforms for a Project Quantitative Risk Analysis ......................... 6.2.8-6
6.2.8.4 Case Study: Quantitative Risk Analysis Exercise ............................. 6.2.8-8
6.2.8.5 Schedule Risk Analysis ‒ Uncertainty ............................................. 6.2.8-9
6.2.8.6 Schedule Risk Analysis ‒ Discrete Risks Added as Drivers ............ 6.2.8-12
6.2.8.7 Cost Risk Analysis ‒ Uncertainty and Discrete Risk Drivers .......... 6.2.8-14
6.2.8.8 Handling Inflation ......................................................................... 6.2.8-17
6.2.8.9 Prioritizing the Discrete Risks ‒ Risk Mitigation Workshop.......... 6.2.8-18
Risk Response Planning.................................................................................. 6.2.9-1
Risk Monitoring and Control ........................................................................ 6.2.10-1
Contingency Management for Risk Mitigation ............................................ 6.2.11-1
6.2.11.1 Contingency Budget Timeline ....................................................... 6.2.11-1
6.2.11.2 Change Control for Contingency Adjustments ............................. 6.2.11-1
6.2.11.3 Liens List: Forecasting and Opportunity Management ................ 6.2.11-2
6.2.11.4 Updates of the Estimate at Complete and Risk Exposure ............ 6.2.11-3
6.2.11.5 Contingency Use and NSF Oversight during Construction ........... 6.2.11-4
6.2.11.6 Documentation and Reporting of Contingency Use ..................... 6.2.11-4
Partnership Considerations for Contingency Management ........................ 6.2.12-1
Guidelines for Cyber-Security of NSF’s Major Facilities............................................. 6.3.1-1
Introduction ................................................................................................... 6.3.1-1
Major Facility Cybersecurity Program ........................................................... 6.3.2-1
Governance .................................................................................................... 6.3.3-1
6.3.3.1 Roles and Responsibilities............................................................... 6.3.3-1
6.3.3.2 Policies ............................................................................................ 6.3.3-1
6.3.3.3 Risk Management and Acceptance ................................................ 6.3.3-2
6.3.3.4 Evaluation ....................................................................................... 6.3.3-2
Resources ....................................................................................................... 6.3.4-1
6.3.4.1 Budget ............................................................................................. 6.3.4-1
6.3.4.2 Personnel ........................................................................................ 6.3.4-1
Controls .......................................................................................................... 6.3.5-1
6.3.5.1 Information Asset Inventory ........................................................... 6.3.5-1
6.3.5.2 Information Classification ............................................................... 6.3.5-2
6.3.5.3 Control Set ...................................................................................... 6.3.5-2
Guidelines for Planning and Executing External Reviews of NSF's Major Facilities ..... 6.4-1
Environmental Considerations in Major Facility Planning ............................................ 6.5-1
Guidelines for Property Management .......................................................................... 6.6-1
Guidelines for Financial Management .......................................................................... 6.7-1
Guidelines for Earned Value Management Systems .................................................... 6.8-1
EVMS Requirements ......................................................................................... 6.8-1
Scaled Application of EVMS Guidelines ............................................................ 6.8-2
Guidelines for Establishing an EVMS ................................................................ 6.8-3

Section Revision:
May 30, 2019

viii

Major Facilities Guide: NSF 19-68 (May 2019)
Table of Contents
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

7 REFERENCES............................................................................................................. 7-1
8 LIST OF ACRONYMS .................................................................................................. 8-1
9 LEXICON................................................................................................................... 9-1
9.1 Lexicon Preface
9-1
9.2 Terms and Definitions
9-2
10 APPENDICES............................................................................................................. A-1
APPENDIX A. RANKING CRITERIA FOR PRIORITIZING MAJOR FACILITY PROJECTS ........... A-1

Section Revision:
May 30, 2019

ix

Major Facilities Guide: NSF 19-68 (May 2019)
List of Figures
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

LIST OF FIGURES
Figure 2.1.3-1
Figure 2.1.3-2
Figure 2.1.4-1
Figure 2.1.4-2
Figure 2.1.4-3
Figure 2.1.4-4
Figure 2.1.6-1
Figure 2.1.6-2
Figure 2.1.6-3
Figure 2.1.6-4

Figure 4.2.1-1
Figure 4.2.2-1
Figure 4.2.2-2
Figure 4.2.3-1
Figure 4.2.3-2
Figure 4.2.4-1
Figure 4.2.5-1
Figure 4.6.3-1

Figure 6.2.4-1
Figure 6.2.6-1
Figure 6.2.6-2
Section Revision:
May 30, 2019

Progressive steps in the facility life cycle, showing the high-level review
and decision points for exit and entry into each stage. The Design Stage is
further broken down into phases. .......................................................... 2.1.3-1
Progressive Phases within the Design Stage, showing review and decision
points for advancement to the next phase and NSB authorization for
budgeting and award. ............................................................................. 2.1.3-3
Summary Timeline for Major Facility Projects (Development and
Design) ..................................................................................................... 2.1.4-2
Summary Timeline for Major Facility Projects (Construction, Operations,
and Divestment) ...................................................................................... 2.1.4-3
Linear Design-Construct Process is Classic "Waterfall Model"
Implementation ....................................................................................... 2.1.4-4
Spiral Development Process .................................................................... 2.1.4-5
NSF organization chart highlighting staff who have primary oversight and
management roles and responsibilities for major facilities and mid-scale
research infrastructure............................................................................ 2.1.6-2
NSF organization chart showing coordinating and advisory bodies for
major facilities and mid-scale research infrastructure. .......................... 2.1.6-3
NSF organization chart showing policy and approval bodies for major
facilities and mid-scale research infrastructure. ..................................... 2.1.6-4
An Integrated Project Team (IPT), chaired by the Program Officer, is
composed of three subgroups, with appointed Award Management
Group members from BFA, Science and Technology Group members from
the sponsoring program offices, and Strategic Group members from the
Office of the Director. ........................................................................... 2.1.6-18
NSF Cost Analysis Process ....................................................................... 4.2.1-4
Sample Project Management Control Systems Relationship Diagram ... 4.2.2-3
NSF Budget Categories Sample Format................................................... 4.2.2-5
Construction WBS and Cost Book Sample Format .................................. 4.2.3-3
Construction Cost Book Sheet Sample Format ....................................... 4.2.3-7
Operations WBS and Budget Sample Format ......................................... 4.2.4-3
Sample of a Change Control Request Form, with instructions for filling out
the various sections............................................................................... 4.2.5-12
NSF Financial Data Collection Tool for Major Facilities Process Flow
Diagram, identifying the core data sources Recipients should utilize to
complete the worksheets to accurately capture the data. Progressing
through the tool's worksheets from left to right will streamline the data
capture and submission process. ............................................................ 4.6.3-4
Picture of Six Risk Management Processes (According to PMI).............. 6.2.4-1
Risk Identification Process ....................................................................... 6.2.6-1
Typical Risk Breakdown Structure (RBS) ................................................. 6.2.6-5
x

Major Facilities Guide: NSF 19-68 (May 2019)
List of Figures
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Figure 6.2.6-3
Figure 6.2.7-1
Figure 6.2.7-2
Figure 6.2.7-3
Figure 6.2.7-4
Figure 6.2.7-5
Figure 6.2.7-6
Figure 6.2.7-7
Figure 6.2.8-1
Figure 6.2.8-2
Figure 6.2.8-3
Figure 6.2.8-4
Figure 6.2.8-5
Figure 6.2.8-6
Figure 6.2.8-7
Figure 6.2.8-8
Figure 6.2.8-9
Figure 6.2.8-10
Figure 6.2.8-11
Figure 6.2.8-12
Figure 6.2.8-13
Figure 6.2.9-1
Figure 6.2.10-1

Section Revision:
May 30, 2019

OMB Risk Categories: to be used as a starting point for projects to select
their own categories................................................................................ 6.2.6-6
Qualitative Risk Analysis Process ............................................................ 6.2.7-1
Overlap in Risk Probability of Occurring When Descriptors Are Used.... 6.2.7-6
Symmetrical Risk Level Matrix ................................................................ 6.2.7-9
Asymmetrical Risk Level Matrix .............................................................. 6.2.7-9
Probability and Impact Matrix including Threats and Opportunities ... 6.2.7-10
Sample Risk Register with Risk ID Number, Associated WBS Identification,
Qualitative Probability and Impact for Initial and Post-mitigation States,
and Mitigation Actions .......................................................................... 6.2.7-12
Sample Top Risk Matrix and Status Report, showing list of project risks
selected as most significant to monitor on a frequent basis, with ranking
and trend data ....................................................................................... 6.2.7-13
Quantitative Risk Analysis Process .......................................................... 6.2.8-1
Typical Result of a Quantitative Schedule Risk Analysis ......................... 6.2.8-3
Time-Cost Scatter Diagram: Each data point represents one realization of
the simulation.......................................................................................... 6.2.8-4
Resource Loaded Schedule Used for a Simple Case Study of an Integrated
Cost-Schedule Risk Analysis for Design, Fabrication, Testing, and Delivery
of a Space Vehicle.................................................................................... 6.2.8-8
End Date Results for Schedule Duration Uncertainties ........................ 6.2.8-10
Cost Result for Schedule Duration Uncertainties.................................. 6.2.8-11
Total Cost and End Date Scatterplot for Schedule Uncertainties ......... 6.2.8-12
Schedule Risk Drivers – Organizational Risk.......................................... 6.2.8-13
Total Cost and End Date Scatterplot Showing Greater Correlation of Time
and Cost Risk ......................................................................................... 6.2.8-14
Uncertainty in the Burn Rate and Total Cost ........................................ 6.2.8-15
Screenshot of Risk Driver Editor ............................................................ 6.2.8-16
Scatterplot Showing Less Connection between Time and Cost ............ 6.2.8-17
Scatterplot with Addition of Cost Inflation Factor ................................ 6.2.8-18
Risk Response Planning Process .............................................................. 6.2.9-1
Risk Monitoring and Control Process .................................................... 6.2.10-1

xi

Major Facilities Guide: NSF 19-68 (May 2019)
List of Tables
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

LIST OF TABLES
Table 2.1.6-1
Table 2.4.2-1
Table 3.4.1-1
Table 6.2.5-1
Table 6.2.5-2
Table 6.2.7-1
Table 6.2.7-2
Table 6.2.7-3
Table 6.2.8-1
Table 6.2.8-2
Table 6.2.8-3
Table 6.2.8-4
Table 6.2.8-5
Table 6.2.8-6
Table 6.2.9-1

Section Revision:
May 30, 2019

Summary of Principal Roles and Responsibilities of the core members of
the IPT (PO, G/AO or CO, and LFO) Liaison by Facility Life Cycle Stage .. 2.1.6-5
Sample of a No-Cost Extension Tasks Table ............................................ 2.4.2-4
List of the Typical Components of a Project Execution Plan, with SubTopics and Descriptions........................................................................... 3.4.1-2
Sample Format for a Risk Management Plan .......................................... 6.2.5-2
Example of a Risk Management Roles and Responsibilities Table ......... 6.2.5-4
Sample Risk Probabilities Table ............................................................... 6.2.7-5
Sample Risk Consequences Table............................................................ 6.2.7-5
Maxwell Risk Driver Assessment Framework ......................................... 6.2.7-7
Resources for Quantitative Risk Analysis Example ....................................... 6.2.8-9
Schedule Duration Risk Reference Ranges.............................................. 6.2.8-9
Results with Schedule Uncertainties Assigned...................................... 6.2.8-11
Results with Schedule Uncertainties and Discrete Risks Assigned ....... 6.2.8-14
Results with Uncertainties and Cost Risks Assigned ............................. 6.2.8-16
Savings and Days Saved ......................................................................... 6.2.8-19
Impact of Risk Handling on Project Cost ................................................. 6.2.9-3

xii

Major Facilities Guide: NSF 19-68 (May 2019)
1.1 Purpose and Scope
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

1

INTRODUCTION

1.1

PURPOSE AND SCOPE

A major responsibility of the National Science Foundation (NSF) is the support of scientific
facilities as an essential part of science and engineering enterprise. Facilities are defined as
shared-use infrastructure, instrumentation and equipment that are accessible to a broad
community of researchers and/or educators. These facilities are generally intended to serve the
science community that is critical to supporting innovation across the nation. Facilities
supported by NSF may be centralized or may consist of distributed-but-integrated installations.
They may incorporate large-scale networking or computational infrastructure, multi-user
instruments or networks of such instruments, or other infrastructure, instrumentation, and
equipment having a major impact on a broad segment of a scientific or engineering discipline.
Historically, NSF has supported such diverse projects as particle accelerators, telescopes,
remote research stations, research vessels, aircraft, and geographically distributed but
networked observatory systems.
In general, NSF does not directly construct or operate the facilities it supports. The National
Science Foundation Act of 1950 (“Organic Act,” Public Law 81-507) establishes that the
“principal purpose” of NSF’s relationship with award Recipients is to fund and facilitate
scientific and engineering research and education programs, and to appraise the impact of
research upon industrial development and upon the general welfare. It states that NSF “shall
not, itself, operate any laboratories or pilot plants”. NSF makes awards to external Recipients
that include nonprofit organizations, universities, and private sector (industry) to undertake
construction, management, and operation of facilities. Such awards frequently take the form of
cooperative agreements but may also be made in the form of contracts. The reasons underlying
the selection of the cooperative agreement as the preferred award instrument are:
•

Scientific justifications, design and specifications for facilities are prepared by science
and engineering communities, and management and operations are conducted on their
behalf;

•

The facilities do not support NSF nor does NSF permanently station government
personnel on-site;

•

NSF involvement is to assure sufficiency of progress to justify continued sponsorship,
and its award administration and oversight activities are not conducted for purposes of
inspection or acceptance; and

•

NSF does not maintain the unilateral right to change or redirect work under the
agreement.

However, NSF’s responsibility is for overseeing the Recipient’s development and management
of the facility as well as assuring the successful performance of the funded activities. The
Recipient is responsible for the day-to-day management of the facility.

Section Revision:
May 30, 2019

1.1-1

Major Facilities Guide: NSF 19-68 (May 2019)
1.1 Purpose and Scope
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Cooperative agreement is the legal award instrument that reflects the above described
relationship. Federal Grant and Cooperative Agreement Act (“Grant Act,” Public Law 95-224)
requires that executive agencies use cooperative agreements when the “principal purpose” of
the relationship between the agency and a non-federal entity is to “transfer a thing of value” to
the non-federal entity “to carry out a public purpose of support or stimulation authorized by a
law of the United States,” and “substantial involvement is expected” between the agency and
the non-federal entity in carrying out the activity contemplated by the agreement.
NSF uses cooperative agreements (CAs) to fund the construction and operation and
maintenance (O&M) of large-scale research facilities. Cooperative agreements with universities,
consortia of universities or non-profit organizations are governed by OMB Uniform Guidance. 1
Under the Uniform Guidance, cooperative agreements structure allows for additional oversight
and accountability mechanism to be built into the agreements. Cooperative agreements also
afford flexibility to tailor project-specific requirements and performance metrics. Unlike a
contract, these can be readily adjusted as needed to ensure the appropriate rigor in oversight
with relatively minimum administrative and time burdens.
Many major facility awards, including those for NSF-supported Federally Funded Research and
Development Centers (FFRDCs), consist of a cooperative agreement as an umbrella award,
establishing the overall basic provisions of the award, and separate cooperative support
agreements. The cooperative support agreements contain specific terms and conditions for
construction activities, management and operations, research activities that are co-sponsored
by other agencies, and any other focused activities that NSF needs to monitor separately from
the overall objectives of the cooperative agreement.
Procurement contracts could be used in circumstances where the agency “decides in a specific
instance that use of a procurement contract is appropriate.” Federal Acquisition Regulation
(FAR) states that “contracts shall be used only when the principal purpose is the acquisition of
supplies or services for the direct benefit or use of the Federal Government”. The policies and
procedures in this Guide apply to research infrastructure projects regardless of the award
instrument employed. When using contracts, the FAR will take precedence in event of conflict.2

2 Code of Federal Regulation (CFR) § 200. The Office of Management and Budget's (OMB) Uniform Administrative
Requirements, Cost Principles, and Audit Requirements for Federal Awards (commonly called "Uniform Guidance") was
officially implemented in December 2014 by the Council on Financial Assistance Reform (COFAR). The Uniform Guidance – a
"government-wide framework for grants management" – synthesizes and supersedes guidance from earlier OMB circulars

1

2

See Guide to the NSF Contracting Process for information related to NSF contracts.

Section Revision:
May 30, 2019

1.1-2

Major Facilities Guide: NSF 19-68 (May 2019)
1.1 Purpose and Scope
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

The Major Facilities Guide (MFG) contains NSF policy on the planning and management of
major facilities through their full life cycle 1. The purpose of the Guide is to:
•

Provide guidance to NSF staff on conducting oversight of major facilities and to
Recipients in carrying out effective project planning and management, and

•

Clearly state the required policies and procedures as well as pertinent guidance and
practices at each stage of a facility’s life cycle.

NSF typically supports facility construction from two appropriations accounts: the Major
Research Equipment and Facility Construction (MREFC) Account and the Research and Related
Activities (R&RA) Account, but additional support may come from Education and Human
Resources (EHR) Accounts. The MREFC Account was created in 1995 to fund the acquisition,
construction, commissioning, and upgrading of major science and engineering infrastructure
projects that could not be otherwise supported by Directorate level budgets without a severe
negative impact on funded science. MREFC projects generally range in cost from seventy million
to several hundred million dollars expended over a multi-year period. The R&RA account is used
to support other activities involving a major facility that the MREFC Account cannot support,
including planning and development, design, operations and maintenance, and scientific
research. Construction and acquisition projects at a smaller scale, usually of a scale ranging
from millions to tens of millions of dollars, are also normally supported from the R&RA Account.
The provisions and principles in the Major Facilities Guide should also be applied to these
smaller-scale facilities funded through the R&RA Account, but procedures should be modified
appropriately to fit the needs of each facility (see Section 5).
The policies in the Major Facilities Guide apply to the full life cycle of all major facility projects
funded by NSF, including:
•

Facilities and infrastructure projects constructed or acquired with funds from the
MREFC Account;

•

Facilities and infrastructure projects constructed or acquired with funds from the R&RA
(and/or leveraged with EHR Accounts) with a total project cost (TPC) greater than $100
million or that require National Science Board (NSB) authorization; whichever is less.

The policies in this Guide are also tailored for mid-scale research infrastructure projects as
described in Section 5.
If, on a case-by-case basis, departures from the policies in this Guide are considered necessary
or prudent, the Recipient must provide a written justification and discuss proposed deviations
with the Program Officer, Large Facilities Officer (LFO) Liaison, and Grants and Agreements
Officer or Contracting Officer as early as possible. Agreed upon deviations should be
There are five stages in a facility’s life cycle – development, design, construction, operations, and divestment. Section 2 of this
Guide describes each of these stages in detail.

1

Section Revision:
May 30, 2019

1.1-3

Major Facilities Guide: NSF 19-68 (May 2019)
1.1 Purpose and Scope
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

documented as part of the NSF Internal Management Plan (IMP) or the Recipient’s Project
Execution Plan (PEP), as appropriate.

Section Revision:
May 30, 2019

1.1-4

Major Facilities Guide: NSF 19-68 (May 2019)
1.2 Precedence
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

1.2

PRECEDENCE

The Major Facilities Guide (MFG) comprises Chapter II.E.11 of the Proposal and Award Policies
and Procedures Guide (PAPPG) and published as a public document under separate title. The
MFG is managed by the Office of Budget, Finance and Award Management’s (BFA) Large
Facilities Office (LFO) and available on the LFO public website
(https://www.nsf.gov/bfa/lfo/index.jsp) as well as through the internal LFO website. This
version replaces the Large Facilities Manual, NSF 17-066, published in 2017, and incorporates
changes in organization and content intended to clarify the policies and procedures by which
Major Facility candidate projects are identified, developed, prioritized and selected. 1
The MFG requirements flow from other NSF policies and statutory requirements. The hierarchy
of documentation 2, in order of precedence, is as follows:
1. 2 CFR, part 200: Uniform Administrative Requirements, Cost Principles, and Audit
Requirement for Federal Awards (Uniform Guidance).
2. NSF Proposal & Award Policies and Procedures Guide (PAPPG): The PAPPG is comprised
of documents relating to the Foundation's proposal and award process for the
assistance programs of NSF. The PAPPG, in conjunction with the applicable award terms
and conditions, serves as the Foundation’s implementation of the Uniform Guidance.
3. Major Facilities Guide (MFG): Referenced in Chapter II.E.11 of the PAPPG
4. Business Systems Review (BSR) Guide
The MFG does not replace existing formal procedures required for all NSF awards, which are
described in the publically available Proposal and Award Policies and Procedures Guide
(PAPPG). Instead, it draws upon and supplements them for the purpose of providing detailed
guidance regarding NSF management and oversight of facilities projects.
All facilities projects require merit review, programmatic/technical review, and a substantial
approval process. This level of review and approval differs substantially from standard grants,
as does the level of oversight needed to ensure appropriate and proper accountability for
federal funds. The policies, requirements, recommended procedures, and good practices
presented herein apply to any facility large enough to require interaction with the NSB or any
facility so designated by the Director, the Deputy Director, or the Assistant Director/Office Head
of the Sponsoring Organization(s). 3 For all other facilities, NSF staff members should use their
See the Joint National Science Board —National Science Foundation Management Report: Setting Priorities for Large Facility
Projects Supported by the National Science Foundation (NSB-05-77); September 2005

1

Assumes assistance awards, contract awards are governed by the Federal Acquisition Regulation (FAR) and requirements will
be tailored as applicable to FAR.

2

See Section 2.1.6 for definition of this and other key terms. It also describes the NSF organizations and officers that are
involved throughout the initiation, development, approval and implementation of a major facility project. Readers not familiar
with NSF and its processes should review this material before proceeding.

3

Section Revision:
May 30, 2019

1.2-1

Major Facilities Guide: NSF 19-68 (May 2019)
1.2 Precedence
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

judgment in proportionately scaling the requirements and recommended procedures for
specific projects.
This Guide will be updated periodically to reflect changes in requirements and/or policies. As
part of the NSF Major Facilities Knowledge Management program, NSF will continue to identify
and adopt good practices aimed at improving agency oversight and Recipient management of
major facilities projects and at enabling the most efficient and cost-effective delivery of tools to
the research and education communities.

Section Revision:
May 30, 2019

1.2-2

Major Facilities Guide: NSF 19-68 (May 2019)
1.3 Document Structure
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

1.3

DOCUMENT STRUCTURE

This Guide is organized as follows:
•

Section 1 introduces the purpose, scope, and historical perspective of this document.

•

Section 2 describes the life cycle stages and the process and principles NSF uses to plan,
construct and operate major facilities. The steps for approval and execution of major
research facility projects and the roles and responsibilities of NSF staff are detailed.

•

Section 3 describes the requirements for preparing and following the various detailed
management plans required during the life cycle of a major facility, including Recipient’s
plans and guidance for NSF’s Internal Management Plans (IMPs).

•

Section 4 is an expanded compendium of several NSF key requirements and principles
listed in Sections 2 and 3. It includes detailed descriptions of processes used to plan,
acquire, and manage major facilities.

•

Section 5 is guidance on scaling the Major Facilities Guide’s principles to mid-scale
projects.

•

Section 6 contains extensive supplementary information on specific topics concerning
NSF’s role in the planning, oversight, and assurance of major facility projects. It consists
of sections containing important explanatory and procedural information and pointers
to separate documents (or modules) with similar information. The information in the
documents is presented in a tutorial format that should be of particular benefit to
individuals who are newly involved with major facility projects.

•

Sections 7, 8, and 9 contain reference material: document references, list of acronyms,
and a lexicon.

•

Section 10 contains appendices contain other information relevant to construction
projects and major facilities.

This Guide is intended for use by NSF staff and by external proponents of major facility projects
for use in planning. However, there are occasional references to materials, such as the NSF
Proposal and Award Manual 1 (PAM) and internal operating guidance documents, which are
available only internally to NSF staff and refer to details of NSF administrative practices and
procedures that are not relevant to external project proponents. Wherever these internal
references are included, they are clearly noted as such. Any questions about the content of
internal NSF documents by external proponents or Recipients should be addressed to the
appropriate Program Officer.
Owing to the rigor of merit and programmatic review, constraints on funding, changing
priorities and competing interests of NSF and the research community, only a limited number
of projects will proceed successfully through all stages described herein. To improve the
possibility of success, facility advocates should be thoroughly familiar with the entire contents
1

The NSF Proposal and Award Manual is a compendium of internal policies and procedures.

Section Revision:
November 25, 2016

1.3-1

Major Facilities Guide: NSF 19-68 (May 2019)
1.3 Document Structure
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

of this Guide even if the proposed project is in the earliest stages of formulation. Anticipating
downstream requirements will dramatically improve the efficiency of the process.

Section Revision:
November 25, 2016

1.3-2

Major Facilities Guide: NSF 19-68 (May 2019)
1.4 Applicable Legislation and NSF Policy
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

1.4

APPLICABLE LEGISLATION AND NSF POLICY
Research Infrastructure

NSF defines Research Infrastructure (RI) as any combination of facilities, equipment,
instrumentation, computational hardware and software, and the necessary human capital in
support of the same. Major facilities and mid-scale projects are subsets of research
infrastructure. NSF's Research Infrastructure investments are described in the agency's annual
budget request to Congress.
MREFC Threshold
NSF Director Memo NSB-2016-46 to the National Science Board dated October 20, 2016
informed the Board of the Director’s decision to reduce the Total Project Cost (TPC) threshold
for MREFC account eligibility to $70 million. This modification to the previous threshold of 10%
of a Directorate’s or Office’s Current Plan was intended to enable innovative infrastructure
projects.
Major Multi-User Research Facility Project (Major Facility)
Per Section 110 of the 2017 American Innovation and Competitiveness Act (AICA), a major
multi-user research facility project is a science and engineering facility project that:
(A) exceeds the lesser of (i) 10 percent of a Directorate’s annual budget; or (ii)
$100,000,000 in total project costs; or
(B) is funded by the major research equipment and facilities construction account, or any
successor account.
For the purposes of this Guide, the term Major Facility is used throughout to equate to the
Congressional term Major Multi-User Research Facility Project.
NSF interprets this to mean the Total Project Costs (TPC) as defined by the Construction Stage;
NOT the full life-cycle cost. This aligns with the allowable use of MREFC account which is for
construction, acquisition and commissioning. This interpretation applies to projects funded
through MREFC or R&RA.
Mid-Scale Project
Per Section 109 of AICA, a mid-scale project means research instrumentation, equipment, and
upgrades to major research facilities or other research infrastructure investments that exceeds
the maximum funded by the Major Research Instrumentation program (MRI) and are below
that of a major multi-user research facility project. The definition of major multi-user research
facility projects is given in Section 1.4.3 of this Guide.

Section Revision:
May 30, 2019

1.4-1

Major Facilities Guide: NSF 19-68 (May 2019)
1.4 Applicable Legislation and NSF Policy
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

NSF interprets this to mean the Total Project Cost (TPC) as defined by the investment in
construction or acquisition; not the operations or associated science program costs.
National Science Board Policy on Recompetition
NSB statement 2015-45 and resolution 2015-46 address competition, renewal, and divestment
of major facilities. The NSB issued a statement that the question of whether to recompete or
not should be assessed at the time of every potential renewal. Competitions would be launched
when the NSF, in consultation with the NSB, judges that it is necessary to ensure the optimum
scientific impact and the most effective use of taxpayer dollars. 1
NSF “No Cost Overrun” Policy
NSF’s “No Cost Overrun” policy was originally codified for major facility projects in the Fiscal
Year (FY) 2009 Budget Request to Congress2 which reads:
“NSF is implementing a ‘no cost overrun’ policy, which will require that the cost estimate
developed at the Preliminary Design Stage have adequate contingency to cover all
foreseeable risks, and that any cost increases not covered by contingency be
accommodated by reductions in scope. NSF senior management is developing
procedures to assure that the cost tracking and management processes are robust and
that the project management oversight has sufficient authority to meet this objective. As
project estimates for the current slate of projects are revised, NSF will identify potential
mechanisms for offsetting any cost increases in accordance with this policy.”
The policy has been continually reinforced in subsequent budget requests to Congress for the
purpose of instilling diligence and rigor in establishing the Total Project Cost (TPC) at award and
a strong NSF oversight position for major facility projects.

See NSB Statement on Recompetition of Major Facilities NSB-2015-45, https://www.nsf.gov/nsb/publications/2015/NSBStatementRecompetitionFacilities_2015-11-19.pdf, and
NSB Resolution on Recompetition of Ongoing Facilities NSB-2015-46, https://www.nsf.gov/nsb/publications/2015/NSBResolutionRecompetitionFacilities_2015-11-19.pdf
2 See the MREFC Section of the NSF’s 2009 Budget Request to Congress, page 3, available online.
1

Section Revision:
May 30, 2019

1.4-2

Major Facilities Guide: NSF 19-68 (May 2019)
2.1 Process Introduction
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

2
2.1

MAJOR FACILITY LIFE CYCLE AND MAJOR FACILITY OVERSIGHT
PROCESS INTRODUCTION

National Science Foundation (NSF) investments through the Major Research Equipment and
Facility Construction (MREFC) Account provide state-of-the-art infrastructure for research and
education, such as laboratory and field instrumentation and equipment, multi-user research
facilities, remote research stations, distributed instrumentation networks and arrays, and
mobile research platforms. In addition, investment is increasing in highly sophisticated
information technology (IT)-based infrastructure, including distributed sensor networks,
extensive data-storage and transmission capabilities, advanced computing resources, and
Internet-based distributed user facilities.1
This section describes the overall major facility life cycle as well as the roles and responsibilities
of the various participants for oversight. It provides guidelines for planning and managing major
research infrastructure facilities. Because each facility has unique aspects, each project
necessarily requires adaptation of general principles. NSF promotes flexibility in the application
of these guidelines but requires justification and substantiation for the specific approach taken
in each case. That is accomplished through the processes of formal planning, documentation,
and review.

1

These resources, many of which are now in development, are collectively known as “cyber infrastructure.”

Section Revision:
November 25, 2016

2.1-1

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.1 Definition of the MREFC Account
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Definition of the MREFC Account
The MREFC Account is an agency-wide capital account, created in 1995 with Congressional
approval, which provides funding to establish major science and engineering infrastructure
projects. Specifically, the MREFC Account is intended to:
•

In accordance with legislation, provide a special account specifically for acquisition,
construction and commissioning of major facilities and other infrastructure projects,
including major upgrades;

•

Prevent large periodic obligations from distorting the budgets of NSF Directorates and
program offices; and

•

Ensure availability of resources to complete large projects that are funded over several
years. 1

The MREFC Account funding is specifically for the construction stage. It cannot be used to
support other activities related to the development, design, operations or divestment stages as
defined in other sections of this Guide.
The MREFC threshold is set by internal NSF Policy (See Section 1.4.2).

Reliable long-term funding commitments are essential to maintaining partnerships and for preventing cost overruns due to
schedule delays.

1

Section Revision:
November 25, 2016

2.1.1-1

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.2 Eligibility for MREFC Funding
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Eligibility for MREFC Funding
To be eligible for consideration for MREFC funding, each candidate project should represent an
outstanding opportunity to enable research and innovation, as well as education and broader
societal impacts. Each project should offer the possibility of transformative knowledge and the
potential to shift existing paradigms in scientific understanding, engineering processes and/or
infrastructure technology. Moreover, each should serve an urgent contemporary research and
education need that will persist for years beyond the often lengthy process of planning and
development.
In addition, a candidate project should:

1

•

Be consistent with the goals, strategies and priorities of the NSF Strategic Plan; 1

•

Establish a long-term tools capability accessible to an appropriately broad community of
users on the basis of merit;

•

Require large investments for construction/ acquisition, over a limited period of time,
such that the project cannot be supported within one or more NSF Directorate(s)/
Office(s) without severe financial disruption of their portfolios of activities;

•

Have received strong endorsement of the appropriate science and engineering
communities, based upon a thorough external review, including an assessment of
(1) scientific and engineering research merit, (2) broader societal impacts,
(3) importance and priority within the relevant Science and Engineering communities,
(4) technical and engineering feasibility, and (5) management, cost, and schedule issues;

•

Be of sufficient importance that the Sponsoring NSF Organization 2 is prepared to fully
fund the costs of pre-construction planning, design and development, operation and
maintenance, and associated programmatic activities (with full awareness that, for a
long-lived facility, operations costs may ultimately amount to many times the
construction costs); and

•

Have been coordinated with other organizations, agencies and countries to ensure
complementarity and integration of objectives and potential opportunities for
collaboration and sharing of costs.

Empowering the Nation Through Discovery and Innovation: NSF Strategic Plan for Fiscal Years (FY) 2011-2016.

See Section 2.1.6 for definition of this and other key terms. It describes the NSF organizations and officers that are involved
throughout the conception, development, approval and implementation of a major facility project.

2

Section Revision:
June 17, 2015

2.1.2-1

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.3 The Major Facility Life Cycle
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

The Major Facility Life Cycle
A facility’s life cycle is characterized by the following five stages:
1. Development 1
2. Design
3. Construction
4. Operation
5. Divestment
Each life cycle stage involves different activities as well as certain actions by NSF and the
Recipient that are necessary to advance the project to the next stage. These activities include
reviews and approvals needed to obtain NSF funding, and the creation of budgets and NSF
awards to support these activities. Entry and exit from each life cycle stage are defined in this
Guide, including the required documents and deliverables. A high-level graphic of the
progression through the stages is given below in Figure 2.1.3-1.
Figure 2.1.3-1

Progressive steps in the facility life cycle, showing the high-level review and decision points for
exit and entry into each stage. The Design Stage is further broken down into phases.

Design Phase Reviews
(Program, Facilities
Readiness Panel & DRB, OD
& NSB)

Annual
Construction
Reviews

Annual
Operations
Reviews

(Program)

(Program)

Renewal &
Re-competition Reviews
(Program, DRB, OD & NSB)

= Review (Stage gate, annual construction, etc.)
= NSF Decision Point (Program, Director, NSB)

Descriptions for each stage are given below. See Sections 2.2 to 2.6 for detailed discussions of
the various procedures and deliverables for progression through each stage in the facility life
cycle.

A project in the Development Stage may be referred to as a “Horizon” or a Conceptual Development project in earlier NSF
documents and references.

1

Section Revision:
May 30, 2019

2.1.3-1

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.3 The Major Facility Life Cycle
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Development Stage
The development stage is where initial ideas emerge and a broad consensus built for the
potential long-term needs, priorities, and general requirements for Research Infrastructure (RI)
of interest to NSF. Investments in development by NSF, other government agencies, or private
interests can be focused or sporadic, but these annual investments are generally smaller than in
the Design Stage. The effort is focused on the high-level ideas, building community consensus
on requirements, and setting priorities across a broad landscape of potential needs. This stage
can last 10 years or more and consequently the cumulative investment over this period can be
quite substantial. Next to the Divestment Stage, the Development Stage is often the most
challenging to navigate depending upon how federal agencies and science communities are
organized. The exit process from this stage occurs when the Sponsoring Organization sends a
memorandum to the Chief Officer for Research Facilities (CORF) recommending that a project is
ready to enter Design Stage, normally at the Conceptual Design Phase. At that point, the CORF
conducts a senior leadership review focusing on strategic agency and science community issues
followed by a recommendation to the NSF Director. If the NSF Director approves the transition
to the Design Stage, it always carries the provision of no commitment to advance the project to
the Construction Stage.
Design Stage
The design stage is where detailed, construction-ready budget estimates, schedules, technical
specification and drawings, and management processes are developed by the Recipient. This is
also the stage where the project is formally approved by NSF as a candidate for a future budget
request and potential obligation of construction funding. Entrance into the Design stage occurs
when NSF recognizes the proposed project as a national priority and the Sponsoring
Organization obligates the necessary funding to advance refinement of the scope and the
estimated cost and schedule. This stage generally lasts 3-5 years and can cost 10% or more of
the estimated construction cost depending on the nature of the project. It is also the stage
where estimated budgets are presented to Congress and where partnerships are generally
formalized.
The Design Stage is divided into three phases – Conceptual Design, Preliminary Design, and
Final Design; each with a formal and rigorous NSF review at the end of each phase to show
readiness for advancement to the next design phase or construction stage, as shown in Figure
2.1.3-2 below. Advancement to the next phase is based on successful completion of the current
phase by the Recipient and is not guaranteed. Review at the end of each phase is a potential
off-ramp for the project.
Conceptual Design Phase: This phase advances the approximate definition of the cost,
scope and technical requirements from the Development Stage, determines feasibility
(often through the development and testing of prototypes), and produces updated
drafts of most elements of the Project Execution Plan, including parametric cost
estimates, notional integrated master schedules, and a preliminary risk analysis.
Section Revision:
May 30, 2019

2.1.3-2

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.3 The Major Facility Life Cycle
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Preliminary Design Phase: This phase further advances the project baseline definition
and the Project Execution Plan. It produces a bottom-up scope, cost, schedule, and risk
analysis of sufficient maturity to allow determination of the Project Total Cost and
overall duration for a given Fiscal Year start and to establish the budget request to
Congress. The Preliminary Design Phase ends with a thorough review of the design, the
Preliminary Design Review (PDR), and NSF approval to continue on to development of a
final design.
Final Design Phase: This phase further refines the project baseline definition and the
Project Execution Plan and demonstrates that project planning and management meet
requirements for readiness to receive funding and begin construction. The Final Design
phase ends with a Final Design Review (FDR) and subsequently an NSF recommendation
to approve the obligation of construction funds.
Figure 2.1.3-2

Progressive Phases within the Design Stage, showing review and decision points for
advancement to the next phase and NSB authorization for budgeting and award.

For projects that have received previous development and design funding from NSF, other
agencies, or private sources, a Sponsoring Organization can propose entrance to the Design
Stage at the Conceptual Design Review (bypassing the Conceptual Design Phase) or the
Preliminary Design Review (bypassing the Preliminary Design Phase) based on the technical
readiness of the project. In either case, the strategic review by the CORF must be conducted in
conjunction with a CDR or PDR-like review in accordance with Sections 2.3.1.3 and 2.3.2.3 of
this Guide. The Preliminary Design Review is the latest point at which a project can be

Section Revision:
May 30, 2019

2.1.3-3

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.3 The Major Facility Life Cycle
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

considered a candidate for major facility funding since this phase is tied to the budget request.
The Final Design Phase must always be conducted (see Section 2.3.3).
Construction Stage
The construction stage begins when funds are obligated for the acquisition and/or construction
of the research infrastructure in accordance with the terms and conditions set forth in an award
instrument between NSF and the Recipient(s). Depending on the technical nature and scale of
the infrastructure or major facility, construction typically lasts 2-6 years and costs range from
$70M to $800M, or possibly more. This stage has the most stringent requirements for
overseeing Recipient performance in managing the scope, cost and schedule against plan, for
reporting progress, and for formality of oversight and assurance by NSF. Progress is reported
against the approved Performance Measurement Baseline (PMB) in the Recipient’s Project
Execution Plan (PEP). The project status is reviewed periodically to assess whether the project is
capable of finishing within budget and schedule and what corrective actions (if any) might need
to be taken. The Construction Stage normally includes activities to transition the facility to
operations. Construction ends after final delivery and acceptance of the defined scope of work
and an assessment facility performance per the terms of the award instrument.
Operations Stage
The operations stage includes the day-to-day activities needed to operate and maintain the
infrastructure and to support scientific research. During this stage, the facility is actively
collecting and distributing data for use by the science community. Operations may include
activities necessary to complete the transition from construction to full operational capability
(depending on the technical nature of the facility and how the construction scope is defined)
and, during the lifetime of the facility, routine refurbishment activities, and major upgrade
project development. The operations stage may also include activities that support transition to
the Divestment Stage. The operations stage typically lasts 20-40 years, the total cost of which
often greatly exceeds the cost of construction. It normally includes a series of periodic status
reviews that assess performance. These reviews may be accompanied by decisions on
continued investment, recompetition, or divestment. The Concept of Operations Plan refined
during the Construction Stage (including robust operations and maintenance cost estimates and
agreements between parties for funding, data sharing, etc.) should be finalized in preparation
for entering this stage. The decision to divest is generally made when NSF, with input from the
scientific community, determines that the facility is no longer considered an operational priority
with regard to advancing science. This final decision is often the most challenging.
Divestment Stage
The decision to divest is generally made when NSF, with input from the scientific community,
determines that the facility is no longer considered an operational priority for the Foundation.
However, divestment does not necessarily lead to a reduction in project scope or in the
performance or scientific output of a facility. As part of the divestment process, additional

Section Revision:
May 30, 2019

2.1.3-4

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.3 The Major Facility Life Cycle
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

support is often sought from other agencies or non-governmental entities, such as Universities,
state-run programs, or charitable foundations. This decision to divest is often the most
challenging step in the Operations Stage.
The decision to divest may be made at any time during the Operations Stage, though it is
expected to occur after a project’s primary science goals have been achieved (usually after
many years of operations). Divestment options may include partial or complete transfer of a
facility to another entity’s operational and financial control (with or without reduction in
project scope), “moth-balling” the facility so that operations can be restarted at a later date, or
decommissioning. This last option may include complete removal of the infrastructure and site
restoration. The cost of decommissioning can be substantial and must be thoroughly
researched. The decommissioning process may also be very complex, and must include careful
assessment of the risks, benefits, and environmental impacts (in the form of an environmental
impact statement). Entrance into the Divestment Stage occurs when an award is made to cover
the costs of decommissioning or transitioning the facility to its new role. This generally takes
the form of an award that ramps down NSF’s investment over the award duration with the
expectation by all parties that no further operations award from NSF will be forthcoming, other
than potential scientific use through individual investigator awards.
It is important that NSF devise plans to address the specific issues that arise as part of the
divestment of a facility. It is recommended that the Sponsoring Organization develop a plan
that follows NSF policy on divestment decisions, engages the science community for the
anticipated divestment of the facility, and includes the estimated costs and associated legal
requirements. The first version of this plan should be developed as part of the construction
Project Execution Plan. Periodic review of an evolving plan for the decommissioning of the
facility, disposal of assets and other environmental obligations of the Government should be
conducted during the Operations Stage. While not part of the annual budgeting process, this
document informs the longer‐term strategic planning for the agency.

Section Revision:
May 30, 2019

2.1.3-5

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.4 Summary of the Major Facility Implementation Process
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Summary of the Major Facility Implementation Process
Major facility projects cover a wide range of disciplines and activities in science and
engineering, so they can require different approaches to the development and implementation.
The approach described in this Guide is derived largely from experience with large acquisition
and construction projects and operations defined by the following characteristics:
•

They serve a relatively broad and substantial community or collaboration, whose
members have self-organized and agree on the basic parameters of the project

•

They result from proposals to NSF, either solicited through a targeted NSF program or
unsolicited, for the design and construction of research infrastructure

•

Operation of research infrastructure may be carried out by the construction
organization or, in some cases, by another organization

As the diagrams in Figures 2.1.4-1 and 2.1.4-2 indicate, the typical process for pre-construction
development and design for a candidate major facility project progresses through a sequence
of stage-gates with increasing investment, planning, assessment, oversight, and assurance.
These stages help ensure that the technical evolution of a candidate project is coordinated with
science community needs and NSF requirements; increasing the likelihood that it will be able to
qualify for funding of continued planning and eventual construction.
NSF supports scientific investigation at the frontiers of human knowledge where the necessary
technologies and methodologies are often not firmly established. The agency is also responsible
for nurturing the various science and engineering disciplines that it supports. As a result, the
various project life cycle stages may best be achieved through the expertise of different
organizations such as educational institutions, non-profit, or the private sector (industry)
depending upon the technical nature of the facility or infrastructure. For example, NSF may
provide researchers the funding sufficient to develop compelling research agendas, to refine
and prioritize their technical requirements, and to complete research and development on
prototypes and other needed technologies, without assuming those researchers will have a
direct role in managing either construction or operations. Following successful research and
development by scientists and engineers in an educational institution, the entire project may
then be further designed and constructed by an award made directly to a competent managing
organization, including industry.

Section Revision:
December 14, 2018

2.1.4-1

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.4 Summary of the Major Facility Implementation Process
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)
Figure 2.1.4-1

Summary Timeline for Major Facility Projects (Development and Design)
Development

Final Design Phase

Budget evolution

Preconstruction Planning Funded via R&RA and EHR funds
Develop construction budget based on conceptual
design
Develop budget requirements for advanced
planning

Expend ~5-25% of construction cost on planning & design activities
Construction estimate based on preliminary design

Final design over approximately 2 years

Update operations cost estimate

Construction-ready budget & contingency estimates
Update operations cost estimate

Estimate operations costs
Initial ideas emerge

Project evolution

Preliminary Design Phase

Conceptual Design Phase

Broad science community
consensus built for potential longterm needs, priorities, and general
requirements
High level concept developed

Formulate science goals: define requirements,
prioritize, review
Develop conceptual design identify critical
technologies, high risk items
Formulate initial risk assessment
Develop top-down parametric cost and contingency
estimates
Initial proposal submission to NSF
Initial Project Execution Plan (PEP)

Proponents development strategy defined in Project Development Plan
Develop site-specific preliminary design, environmental
assessments/ impacts (NEPA)
Develop enabling technologies
Bottom-up cost and contingency estimates, updated risk
analysis

Develop final construction-ready design & PEP
Verify key technologies are ready for production or
detailed production design
Refine bottom-up cost and contingency estimates

Develop Project Management Control System

Finalize Risk Assessment & Mitigation, Management
Plans

Develop preliminary operations cost estimate

Complete key staff recruitment

Update PEP

Recommends to the NSF Director
that a project advance to
Conceptual Design

Establish interim review plan and competition
milestones

Preliminary Design Review (PDR) – external
panel review and internal review

Forecast international and interagency participation,
issues

Establish target total project cost (TPC)

Develop Internal Management Plan (IMP), estimate
PD costs, timeline

Initial analysis of NSF opportunities, risks
Conceptual Design Review (CDR) – external
panel review and internal review
CDR Cost Analysis

FRP, DRB, OD
& NSB

Merit review, apply 1st and 2nd ranking criteria

Approve Project Development Plan (PDP) &
budget

OMB/Congress negotiations on proposed
project and budget profile

Forecast external partner decision milestones

Evaluate design costs, schedules; and
operations cost estimate.

PDR Cost Analysis
Project Definition established – cost, scope,
schedule, plans, risks, & contingency

NSF approves submission to NSB

Integrated Project Team (IPT) organized

NSF Director approves PD phase

Program oversight

NSF oversight defined in Internal Management Plan (IMP) updated at each development phase.
Interface with the research
community to nurture concepts for
development

Semi-annual assessment of baseline and
projected operations budget for projects not in
construction
Finalization of interagency and international
requirements, agreements
Final Design Review (FDR) - external panel
review and internal review
FDR Cost Analysis - informed by an
Independent Cost Estimate (ICE) if not done
earlier
EVMS Acceptance
Establish project construction baseline

Internal review regarding
advancement to design stage.

Apply 3rd ranking criteria

Facilities Readiness Panel Review

Facilities Readiness Panel Review

NSF Director approval to start
Conceptual Design

Facilities Readiness Panel Review

DRB Review

DRB Review

NSF Director approval for advancement to
Preliminary Design

NSF Director requests NSB approval for MREFC
request & approves advancement to Final Design

NSF Director approves advancement to
construction stage

NSB authorization for inclusion in MREFC Budget
Request and to proceed with final design

NSB authorizes NSF Director to make a
construction award

Section Revision:
December 14, 2018

2.1.4-2

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.4 Summary of the Major Facility Implementation Process
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)
Figure 2.1.4-2

Summary Timeline for Major Facility Projects (Construction, Operations, and Divestment)

Project evolution

Budget evolution

Construction
MREFC or R&RA funds
Expend budget & contingency per baseline, PEP, and
Award document
Refine operations budget

Operations

Divestment

R&RA, EHR funds

R&RA, EHR funds

Yearly budgets with out-year projects

Transition from operations budget to
decommissioning and disposal costs

Congress appropriates MREFC funds

Construction per baseline and PEP

Annual Work Plans with goal setting
Annual Reports that track progress relative to
goals

Update Facility Divestment Plan
developed as part of the construction
PEP.
Develop transition plan for transfer
and/or decommissioning and disposal
Execute the Divestment Plan

Review monthly project performance reports

Annual Operations Review

Review periodic financial reports

Preparation for facility re-competition, renewal or
disposal/divestment

Annual external panel reviews and internal
assessment

Congress appropriates funds

FRP, DRB, OD &
NSB

Program Oversight

NSF oversight defined in Internal Management Plan (IMP), updated at each lifecycle stage.

Site visit and assessment

Award Proposal Cost Analysis – informed by an
independent cost assessment

Approves usage of contingency above
established thresholds

Accounting System Review, as determined
Business Systems Review, as determined

Allocation of contingency funds

Cost Incurred Audits, as determined

Review commissioning plans

Identify and devise plans for
divestment of a facility at the end of
its scientifically competitive life.
Annual review of evolving plan for
decommissioning and/or disposal of
facility assets and environmental
obligations
External panel reviews as appropriate
Cost analysis as appropriate
Recommends to the NSF Director
that a facility move into the
Divestment stage.

EVMS Surveillance, generally annually
Accounting System Review, as determined
Business Systems Review, as determined
Cost Incurred Audits, as determined
Review bi-monthly facilities report
NSF Director “deep-dive” reviews, as
appropriate

DRB review of Renewal and Re-competition
packages
NSF Director approval for award

NSB Facilities Portal with bi-monthly facilities
report and EVM trend data

NSB authorization of renewals and recompetitions

NSB authorization for re-baselining that exceed
thresholds

NSB authorization for awards that exceed
thresholds

Section Revision:
December 14, 2018

NSF Director authorizes transition
into Divestment

2.1.4-3

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.4 Summary of the Major Facility Implementation Process
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Although all major facility projects progress though the five life cycle stages described in
Section 2.1.3 above, there are appropriate alternate approaches to the Development and
Design Stages, as well as alternate approaches to upgrade during the Operations Stage.
Facilities at the leading-edge of the scientific endeavor never remain stagnant. It is not
uncommon for major facilities and smaller research infrastructure to be in an almost
continuous state of upgrade following transition to operations. Therefore, the more linear
“waterfall” method described above is not always the most appropriate process to follow,
particularly in fields where the technologies are unproven or changing rapidly.
When proposing to NSF, candidate projects should consider whether a “spiral
development” model is more appropriate than the classic “waterfall” method as shown in
Figure 2.1.4-3. Spiral development refers to the process of designing, building, testing and
using a technology to increase understanding and reduce risk; and then repeating the
process again. Although, almost all facilities use spiral development for various components
and sub-systems during development, design and, at times, construction, the process
described here is intentionally planned for and executed at the macro scale, with each spiral
having a discrete total project cost (TPC). Figure 2.1.4-4 illustrates this concept of one
project leading into follow-on projects.
The duration of the spirals can be relatively short (2 years) or quite long (a decade or more)
depending on technical maturity and the rate of technological change. Risk is reduced
following the completion of each spiral to improve confidence in the ability to meet the
technical objectives of the next spiral within budget. A spiral development approach is
generally imbedded within the Operations Stage and may combine aspects of the Design
and Construction Stages. NSF oversight is based on the TPC and associated authorization
thresholds.
Figure 2.1.4-3

Section Revision:
December 14, 2018

Linear Design-Construct Process is Classic "Waterfall Model" Implementation

2.1.4-4

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.4 Summary of the Major Facility Implementation Process
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)
Figure 2.1.4-4

Spiral Development Process

In all cases, NSF is committed to the principle that flexibility does not preclude rigor. Every
candidate major facility project – including those that call for novel treatment – is subject to
the highest standards of merit review and technical evaluation. The approach used should
be identified early in either the project Development or Design Stages and documented as
part of the managing organization’s proposal and eventually the Project Execution Plan
(PEP), as well as NSF’s Internal Management Plan (IMP). Proposing organizations should
discuss the approach envisioned with the cognizant NSF Program Officer.

Section Revision:
December 14, 2018

2.1.4-5

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.5 Timeline and Flowcharts for the Major Facilities Approval Process
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Timeline and Flowcharts for the Major Facilities Approval Process
This section, to be written, will illustrate when various preconstruction planning activities
should be completed in order to commence construction in a particular future fiscal year.
Although the majority of those activities proceed at a pace specific to the needs of an individual
project, late-stage planning activities following completion of a project’s Preliminary Design are
paced by the process for developing NSF’s annual Budget Request to Congress. This section will
also explain key features of that process that are of particular interest to those involved with
major facility projects.

Section Revision:
June 17, 2015

2.1.5-1

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.6 Roles and Responsibilities for NSF Staff for Management and Oversight of Major Facilities
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Roles and Responsibilities for NSF Staff for Management and Oversight of Major
Facilities
2.1.6.1 Overview
The Major Facilities Guide (MFG) describes the actions NSF takes to carry out its oversight and
assurance responsibilities for major facility projects. One key element is the definition of the
roles and responsibilities of the NSF participants who carry out those actions. The participants
with primary oversight and management roles and responsibilities are listed below and
highlighted in the NSF organizational chart in Figure 2.1.6-1:
•

Program Officer (PO) – A scientist or engineer having primary oversight responsibility
within NSF for all aspects of the project.1

•

Sponsoring Organization – The NSF Division, Directorate, or Office which proposes
projects for funding through the MREFC Account or other funding source and is
committed to pre-construction planning activities and eventual facility operation and
use.

•

Senior Management of the Sponsoring Organization – The leadership individuals who
utilize community inputs, discipline-specific studies, advisory committee
recommendations and internal NSF considerations to prioritize the opportunities
represented by the candidate project relative to competing opportunities and demands
for available resources.

•

Grants and Agreements Officer (G/AO) – NSF Grants and Agreements Officer who has
legal responsibility and authority for the business and financial management of grants
and cooperative agreements.

•

Contracting Officer (CO) – NSF Contracting Officer which has legal responsibility and
authority for the business and financial management of award contracts.

•

Cost Analyst – NSF staff from the Cost Analysis and Pre-Award Branch (CAP) Branch of
the Division of Institution and Award Support (DIAS), which perform cost assurance
reviews of proposals and monitor Recipient financial practices.

•

Chief Officer for Research Facilities (CORF) – The individual who advises the NSF
Director on all aspects of the agency's support for major and mid-scale research facilities
throughout their life cycle and collaborates with NSF employees involved in oversight
and assistance of the NSF multi-user research facilities portfolio.

•

Head, Large Facilities Office (HLFO) – The individual who heads the Large Facilities
Office (LFO). The LFO provides an NSF-wide resource for assistance with project
oversight and assurance that agency policies and procedures are followed. The LFO is

The PO may have a title such as Program Manager or Program Director. The PO is administratively part of a Directorate or
Office, comprised of Divisions, which serves a range of research disciplines. These are referred to as the “Sponsoring
Organization” in this document.

1

Section Revision:
May 30, 2019

2.1.6-1

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.6 Roles and Responsibilities for NSF Staff for Management and Oversight of Major Facilities
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

located in the Office of Budget, Finance, and Award (BFA) and reports to the Chief
Financial Officer.
•

Large Facilities Office Liaison – The designated project management advisor from the
LFO, who is assigned as project liaison by the HLFO. This individual is the PO’s primary
resource for assistance with all policy, process, and procedural issues related to the
development, implementation, and oversight of major facility projects.

Figure 2.1.6-1

NSF organization chart highlighting staff who have primary oversight and management roles
and responsibilities for major facilities and mid-scale research infrastructure.

As shown in Figure 2.1.6-2, various bodies within NSF provide coordination, assistance,
assurance, and advice to the main participants and to the agency as a whole:
•

Integrated Project Team (IPT) – Three primary NSF groups comprise the IPT and
represent the major oversight organizations within NSF: Science and Technical, Award
Management, and Strategic. The Strategic group includes representatives from the
Office of the Director (OD), Office of the General Counsel (OGC), the Office of Legislative
and Public Affairs (OLPA), the Office of International Science and Engineering (OISE), and
other offices under OD as deemed appropriate. The composition and size of each IPT
depends on the risks, scope, and complexity of the project. The IPT is a coordinating
body that provides internal agency assurance and guidance to the PO in the planning,
review, and oversight of that project. The members of the IPT are selected by the
management of the cognizant directorates and offices, in consultation with the PO, at
the beginning of the Conceptual Design Phase. The IPT is chaired by the PO.

•

Major Facilities Working Group (MFWG) – The purpose of the Major Facilities Working
Group (MFWG) is to assure the uniform and effective programmatic oversight of major
and mid-scale research infrastructure of the National Science Foundation throughout

Section Revision:
May 30, 2019

2.1.6-2

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.6 Roles and Responsibilities for NSF Staff for Management and Oversight of Major Facilities
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

their entire life cycles. Specifically, the MFWG provides input to the Facilities
Governance Board regarding all strategy, governance, and implementation issues under
consideration by that Board, establishes and maintains a list of NSF’s major research
infrastructure at all life cycle stages, supports the Head of the Large Facilities Office in
reviewing the Major Facilities Guide, internal operating guidance, and procedures for
NSF facility oversight, advises the Facilities Governance Board on the sufficiency and
appropriateness of these documents, and shares good practices for the oversight of
facilities across the Science directorates.
•

Advisory Committee of the Sponsoring Organization – Comprised of researchers from
the community (external to NSF), it advises the sponsoring Directorate or Office in a
wide variety of programmatic areas, including major facilities.

Figure 2.1.6-2

NSF organization chart showing coordinating and advisory bodies for major facilities and midscale research infrastructure.

There are also planning and assurance bodies, shown in Figure 2.1.6-3, that review and make
recommendations on the suitability and readiness as well as on the allocation of resources for
the development, funding, and operation of major facility projects, according to the NSF
strategic objectives:
•

Facilities Readiness Panel (FRP)- advise the Director on Recipient and Programmatic
readiness to advance major and mid-scale facilities projects within the formal Design
Stage as described in NSF’s Major Facilities Guide (MFG); this includes the transition
from Final Design to Construction. Readiness to enter the Design stage and whether or
not to include in a future budget request are strategic decisions made separately.

Section Revision:
May 30, 2019

2.1.6-3

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.6 Roles and Responsibilities for NSF Staff for Management and Oversight of Major Facilities
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

•

Facilities Governance Board (FGB) - Oversee and make recommendations on all aspects
of governance of major multi-user research facilities and mid-scale research
infrastructure of the National Science Foundation.

•

Director’s Review Board – Comprised of Senior Management Representatives from the
Directorates and Offices of NSF, it reviews and approves the package of materials
associated with all topics to be submitted to the National Science Board (NSB) for
information or action, including major facility projects.

Finally, there are entities also shown in Figure 2.1.6-3 that set NSF policy and that approve the
advancement, funding requests, and obligation of funds for the development, construction, and
operation of major facility projects:
•

NSF Director – Responsible for the implementation of NSF policies and practice for
agency oversight of major facilities, and for proposing new major facility projects to the
NSB, the Office of Management and Budget (OMB), and Congress.

•

NSB – Establishes agency policy for major facilities, and reviews and authorizes the
advancement of major facility projects including budget requests and Construction
Stage awards. The Board also authorizes Operations Stage awards that are above
certain thresholds. By statute, all projects funded from the MREFC account require
Board authorization.

Figure 2.1.6-3

NSF organization chart showing policy and approval bodies for major facilities 1 and mid-scale
research infrastructure.

Refer to Figures 2.1.4-1 and 2.1.4-2 for a mapping of the Panels and Boards to the major facility life cycle stage and NSF
oversight responsibilities.

1

Section Revision:
May 30, 2019

2.1.6-4

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.6 Roles and Responsibilities for NSF Staff for Management and Oversight of Major Facilities
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

The PO, G/AO or CO, and LFO staff members are the individuals that interact most frequently to
carry out NSF’s oversight and assurance role for major facility projects. Their roles and
responsibilities are summarized, by life cycle stage, in Table 2.1.6-1. Fuller descriptions of their
roles (and those of senior management in the sponsoring Directorate or Office, and the
support, advisory, policy making, and approving entities) are provided in individual sections of
this document following Table 2.1.6-1.
Table 2.1.6-1

Summary of Principal Roles and Responsibilities of the core members of the IPT (PO, G/AO or
CO, and LFO) Liaison by Facility Life Cycle Stage

Program Officer (PO)

Grants and Agreements (G/AO)
or Contracts Officer (CO)

LFO Liaison

Summary
• Primary responsibility for all
oversight aspects of a major
facility project
• Experienced or trained in
management of projects.
• Appointed by the Division Director
(DD) or Section Head
• Must not be a temporary
employee of the NSF

• Primary representative of the
NSF in all business dealings
with the Recipient
• Assigned to a project on a
long-term basis
• Experienced with Federal
regulations and unique NSF
requirements needed for
adequate NSF oversight of
major facility projects

• Program’s primary resource
for all policy or process
issues related to the
development,
implementation, and
oversight of major facility
projects
• Experienced and trained in
project management of
major facilities.
• Advises POs on project
management issues during
project development and
oversight

• Becomes acquainted with the
anticipated scope of the
proposed project
• Participates in planning
meetings to work out details
of partnerships, international
or multi-agency agreements,
property issues, etc.
• Participates in the
development of the IMP
• Serves on the IPT throughout
the project to expedite
financial and administrative
actions and decisions
concerning the project

• In collaboration with PO,
plans CDR
• Independently assesses the
CDR outcome for the LFO
• Serves on the IPT
throughout the project to
advise on management,
business, and administrative
issues
• Participates in the
development of the IMP

Conceptual Design Phase
• Determines the importance and
research priority to the affected
research community of the
science objectives motivating
consideration of a future major
facility
• Works with the research
community to develop an overall
scope for a major facility project.
• Develops the IMP
• Organizes and chairs the IPT
• Formulates a plan for eventual
divestment of the facility
• Devises and carries out strategies
for renewal or closeout strategy
that implements recompetition of
the operating award wherever
feasible

Section Revision:
May 30, 2019

2.1.6-5

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.6 Roles and Responsibilities for NSF Staff for Management and Oversight of Major Facilities
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Program Officer (PO)

Grants and Agreements (G/AO)
or Contracts Officer (CO)

LFO Liaison

• Advises PO on creation of
solicitations for any enabling
research, workshop, summer
study, or other activity of the
research community that
supports proposal
development
• Responsible for the business
aspects of the proposal review
and cost analysis and
mentoring of the proposing
institutions
• Participates in preparation of
materials for the FRP Review
and Director’s Review Board
(DRB)
• Serves on the IPT

• Advises PO
• In collaboration with PO,
plans Preliminary Design
Review (PDR)
• Independently assesses
outcome of PDR for the LFO
• Receives monthly reports on
project development from
PO, and provides
independent assessment to
the Head, LFO
• Contributes to business
aspects of the proposal
review and cost analysis and
in surveillance or mentoring
of the proposing institutions
• Serves on the IPT

• Instigates as required
proposal review, cost analysis,
and mentoring necessary to
ensure that the Recipient
follows NSF business and
budgeting policies and
requirements
• Participates in periodic cost
update reviews.
• Participates in preparation of
materials for the FRP Review
and DRB
• Serves on the IPT

• Continues to monitor
project
• Receives monthly project
status updates from the PO,
adds comments and
evaluation
• Aids the PO with the
organization of the periodic
cost update reviews in
interval between PDR and
FDR.
• In collaboration with PO,
plans FDR and
independently assesses
outcome
• Contributes to business
aspects of the proposal
review and cost analysis and
in surveillance or mentoring
of the proposing institutions
• Serves on the IPT

Preliminary Design Phase
• Creates solicitations for any
enabling research, workshop,
summer study, or other activity of
the research community that
supports proposal development
• Works with the research
community to develop a proposal
that includes a preliminary Project
Execution Plan (PEP)
• Arranges external peer review of
the proposal
• Presents the proposed project to
the Facilities Readiness Panel
• Updates the IMP
• Continues to meet with the IPT
• Reports monthly to HLFO on
project’s technical and financial
status
Final Design Phase
• Continues to monitor project in
accordance with the IMP
• Provides monthly project status
updates to the HLFO
• Organizes periodic cost update
reviews
• Organizes the Final Design Review
(FDR)

Section Revision:
May 30, 2019

2.1.6-6

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.6 Roles and Responsibilities for NSF Staff for Management and Oversight of Major Facilities
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Program Officer (PO)

Grants and Agreements (G/AO)
or Contracts Officer (CO)

LFO Liaison

Construction/Implementation Stage
• Works with the G/AO to develop
the award agreement
(Cooperative Agreement (CA) or
contract agreement)
• Approves the establishment of a
project baseline scope, cost, and
schedule and other updates to the
PEP
• Approves significant changes to
the project baseline
• Receives monthly financial and
technical status reports, quarterly
and annual progress reports
• Reports monthly to HLFO on
project’s technical and financial
status
• Conducts periodic reviews of
project progress using an external
ad hoc panel
• Arranges internal review of
Memorandums of Understanding
(MOUs)
• Regularly visits the project
• Updates the IMP
• Ensures compliance with
Government Performance and
Results Modernization Act
(GPRAMA)

• Works with the PO to develop
the award agreement
(Cooperative Agreement (CA)
or contract agreement)
• Approves submittals from
Recipient
• Reviews the scope of activities
associated with each award to
ensure that the financial and
administrative framework
aligns with NSF’s expectations
for stewardship and reporting.
• Receives and provides
approval to the Recipient on
award documents
• Participates in baseline review
and subsequent periodic
reviews as necessary to assure
the NSF that the Recipient
follows agency financial
policies
• Serves on the IPT

• Advises PO
• In collaboration with PO,
plans construction reviews
and independently assesses
outcome
• Receives monthly project
status reports from the PO
• Visits the project site
periodically in coordination
with PO
• Participates in baseline
review and subsequent
periodic reviews as
necessary to assure the NSF
that the Recipient follows
agency major facility
management policies
• Serves on the IPT

Divestment Stage

Reserved for future content

Section Revision:
May 30, 2019

2.1.6-7

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.6 Roles and Responsibilities for NSF Staff for Management and Oversight of Major Facilities
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Program Officer (PO)

Grants and Agreements (G/AO)
or Contracts Officer (CO)

LFO Liaison

Operations Stage
• Prepares and participates in
solicitation of award for
Operations and Maintenance
(O&M) CA or contract agreement
• Ensures compliance with GPRAMA
• Approves the Annual Work Plan
(which includes high level
performance goals) developed by
the Recipient
• Reviews and approves the Annual
Report
• Develops budgets that operate
and maintain facilities
• Obtains Condition Assessment
reports
• Monitors planning for IT and
property security, and validates
through periodic review
• Organizes and participates in
periodic reviews of the facility
including annual operations
reviews
• Formulates a plan for eventual
divestment of the facility
• Devises and carries out a renewal
or recompetition and closeout
strategy of the operating award
• Updates the IMP

• Advises the PO in
development of solicitation
for O&M award (shared
responsibility with PO)
• Creates special terms and
conditions in the CA or
contract agreement to capture
requirements for annual
performance goals (shared
responsibility with the PO)
• Defines business practices for
renewal, recompetition,
closeout, or termination of
Award
• Attends periodic reviews
including operations and
business systems reviews
(BSRs) as appropriate
• Assists in developing financial
strategy, as appropriate, to
budget for facility
maintenance and replacement
or refurbishment of long-lived
capital-assets (shared
responsibility with PO)
• Prepares Decision Memo and
performs independent cost
analyses as required
• Serves on the IPT

• Advises PO and G/AO or CO
on effective operational
oversight strategies,
renewal and recompetition
strategies, closeout, or
termination
• Periodically visits operating
facilities in coordination
with PO
• In collaboration with PO and
G/AO or CO, insures
implementation of
performance measures
within the CA for operation
• Assists with organizing and
evaluating the results of
operational reviews of
major facilities
• Advises PO and G/AO or CO
on related project
management issues in the
event of recompetition of
award for facility operation
• Serves on the IPT

2.1.6.2 Main Participants
Program Officer (PO)
The PO is the research community’s primary interface to the NSF. The PO’s responsibilities are
substantial, and crucial to NSF’s success. Examples of these responsibilities are listed below: 1
•

They are typically the main contact a principal investigator (PI) has with NSF.

•

They are the link between what is happening in the research community and the
appropriately responsive program solicitation from NSF.

•

They are the catalysts for the increasing amount of research that crosses traditional
single-discipline boundaries.

Paraphrased from National Science Foundation: Governance and Management for the Future, a report by a panel of the
National Academy of Public Administration, April 2004. pp. 10-11.

1

Section Revision:
May 30, 2019

2.1.6-8

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.6 Roles and Responsibilities for NSF Staff for Management and Oversight of Major Facilities
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

•

They are the coaches and encouragers for proposals from less experienced researchers
– particularly ones with innovative ideas – as well as those from underrepresented
segments of the research community.

•

They are the recruiters and managers of a peer review process that involves numerous
experts from the research community to assess the intellectual merit and broader
impacts of proposals from the community for new research.

•

They are the post-award managers and monitors for awarded research.

NSF’s Authorization Act of 2002, 42 U.S.C.1862n-4I, signed into law on December 19, 2002,
restricts the choice of POs (also referred to within the NSF as Program Directors or Program
Managers) to be regular employees of the NSF. The statutory language of the Act states:
“PROJECT MANAGEMENT. No national research facility project funded under the major
research equipment and facilities construction account shall be managed by an
individual whose appointment to NSF is temporary.”
Administratively, the PO is part of a Directorate or Office that provides supervisory oversight
and the budgetary authority to fund PO actions. Depending on the administrative structure of
the Sponsoring Organization, a Section Head, Division Director, Assistant Director (AD), or
Office Head may assign a PO (or POs) 1 to oversee a particular facility-related initiative and will
directly or indirectly oversee and guide the activities of the PO. Actions of the PO described
here implicitly recognize the authority of the individuals within this supervisory structure to
appropriately guide, direct, and approve the actions of the PO.
The PO exercises primary responsibility within NSF for all aspects of a major facility project,
including:
•

Project planning, both internally and in coordination with the relevant research
community;

•

Serving as the NSF interface with the research community to nurture concepts for
development and utilization by the community of a facility;

•

Formulating an IMP that defines NSF strategy for conducting project oversight,
managing NSF risk, and providing project funding;

•

Coordinating contact between the project proponents and other NSF staff members
that may need to have direct contact with the project or that the project may wish to
contact;

•

Chairing the IPT;

•

Conducting merit and programmatic/technical reviews of proposals for development,
implementation, operation, and utilization of a facility (Conceptual Design Review (CDR),

In some cases, more than one individual will be designated as a PO for a facility related initiative. Wherever the PO is
referenced in this guide, it should be understood that the reference is to all the relevant assigned POs.

1

Section Revision:
May 30, 2019

2.1.6-9

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.6 Roles and Responsibilities for NSF Staff for Management and Oversight of Major Facilities
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Preliminary Design Review (PDR), Final Design Review (FDR), construction and
operational reviews);
•

Preparing all required documentation for internal project review and approval within
the NSF;

•

Participating in developing the estimated costs of planning, construction, operations,
maintenance and related programmatic activities, and, under management direction of
the Sponsoring Organization, assigns budgets to these tasks; and

•

Overseeing implementation, operation, and eventual divestment and closeout of NSF
support for the project.

Senior Management of the Sponsoring Division, Directorate, or Office Assistant Director or
Office Head
Assistant Directors (ADs) and Office Heads lead Directorates or Offices, and by extension their
Divisions or Sections, which propose projects for funding through the MREFC Account or other
funding source.
The AD (or Office Head) of the Sponsoring Organization utilizes community inputs, disciplinespecific studies, advisory committee recommendations and internal NSF considerations to
prioritize the opportunities represented by the candidate project relative to competing
opportunities and demands for NSF resources. The AD determines that the scientific merit and
relative importance of the proposed facility are sufficiently strong to justify advancement of the
project to Readiness Stage (i.e., ready to begin Preliminary Design activities), and authorizes the
PO to proceed with organizing the development and external review of a Project Execution Plan
and with updating the IMP to explain how NSF will oversee and fund further development. The
AD reviews and approves the IMP. The AD determines whether to propose a project to the
Facilities Readiness Panel as a candidate for future construction funding, based on the project’s
relative scientific importance and on the Sponsoring Organization’s commitment to preconstruction planning activities and eventual facility operation and use. The AD is regularly
updated by the PO on the status of the project throughout the remainder of its life cycle phases
and brings critical issues to the attention of the NSF Office of the Director (OD) and NSB as
appropriate.
The AD has overall responsibility for advancing prospective projects for consideration of
construction funding. In this capacity, the AD formulates strategic planning and budget
development within the sponsoring Directorate or Office. This strategic planning includes
prioritizing across the research objectives of the range of disciplines served by the Directorate
or Office. The AD oversees and monitors development of NSF’s project planning, with the
assistance of supporting staff, advisory committees, and direct interactions with the broader
community affected by the facility.

Section Revision:
May 30, 2019

2.1.6-10

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.6 Roles and Responsibilities for NSF Staff for Management and Oversight of Major Facilities
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Unless delegated to a lower level, the AD oversees development of MOUs with other agencies,
international partners, private foundations, and other entities and, with the approval of the NSF
OD, enters into negotiations with those parties and either signs or delegates signature authority
for these agreements on behalf of NSF when authority to do so is delegated by NSF OD.
Throughout a project’s life, the AD has a primary responsibility to keep all major stakeholders in
the project informed. Interested parties include policy stakeholders (the NSF, OD); funding
stakeholders (OMB, Congress); and community stakeholders (scientific organizations and the
relevant research community).
At each stage of project development, the AD has the responsibility for making key decisions
within the Sponsoring Organization that advance a project or remove it from consideration for
further development.
Specific responsibilities include, but are not limited to:
•

Approving the IMP at the Directorate level;

•

Ensuring that the qualifications of the relevant Division Directors reflect the
requirements and expectations of the MFG and NSF policy, and the necessity to provide
an environment of open communication and transparency in the management of
research infrastructure;

•

Assuring the evaluation and endorsement of a candidate project by the Directorate or
Office advisory committee prior to submission of the project to the Facilities Readiness
Panel for entry into the readiness stage;

•

Overseeing the Division’s organization of all design reviews including appointment of
review panels, charges to the panels, and Directorate responses to review panel
recommendations;

•

Reviewing and approving all Director's Review Board packages and organizing
representation of the project before NSF internal approval bodies, i.e., FRP, DRB, and
the NSB;

•

Representing the sponsoring Directorate or Office in decisions to recompete
management of an operating facility, terminate support, admit new partners, and other
major decisions affecting the facility;

•

Selecting members of Directorate Office staff to serve as representatives on an IPT; and

•

Establishing appropriate Delegation of Authority for awards following NSB action.

Division Director
The Division Director (DD), assisted by Divisional Staff, has primary responsibility for overseeing
planning, review, oversight and funding of major facilities. This responsibility includes
coordination of planning; serving as the interface with relevant scientific and engineering
communities; preparing all required documentation for project consideration and approval;

Section Revision:
May 30, 2019

2.1.6-11

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.6 Roles and Responsibilities for NSF Staff for Management and Oversight of Major Facilities
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

conducting merit review of proposals; fully funding costs of operations, maintenance and
relevant programmatic activities; and overseeing the project.
Administratively, a major facility in planning, construction, or operation, is under the purview of
a Sponsoring1 Organization, a Directorate, Division, or Office. The Sponsoring Organization
provides supervisory oversight and budgetary authority. Depending on the administrative
structure of the Sponsoring Organization, the cognizant PO is usually selected by the Divisional
management (e.g., Section Head and DD collaborate in the selection) with concurrence of the
AD. The PO’s superiors directly or indirectly oversee and guide the activities of the PO.
The DD has overall responsibility for the conduct of programs in a related range of disciplines
within NSF, and for the NSF interfaces between these programs and the scientific communities
in these disciplines. For major facility projects, the DD:
•

Evaluates and maintains, through appropriate mechanisms, the proper balance between
the totality of life cycle costs for major facilities and the rest of the division’s activity;

•

Establishes and continually examines, through appropriate mechanisms and forums, the
priorities among candidate projects within the discipline (those in development, under
construction, and in operation);

•

Appoints a cognizant PO for each project;

•

Ensures that the program officer has the requisite experience and/or training to respond
to the responsibilities of the position;

•

Ensures that the cognizant PO follows appropriate good practices;

•

Ensures that the PO is responding appropriately to the requirements of the Major
Facilities Guide and other NSF policies and practices;

•

Ensures that the PO is managing interfaces with other NSF units effectively and
productively;

•

Ensures that the performance plan of the program officer reflects the requirements and
expectations of the MFG and other NSF policy statements; and

•

Facilitates the flow of information at an appropriate level of detail and timescale to keep
all NSF stakeholders appropriately informed of project progress, status, and problems.

Grants and Agreements Officer
The Grants and Agreements Officer (G/AO) has authority, subject to statutory limitations, to
award and administer cooperative agreements (CA). The G/AO holds a cooperative agreements
warrant and is the only individual authorized to obligate or de-obligate Federal funds. The
G/AO, through their warrant, has the sole authority to award and administer the construction
agreements(s) used in support of Major Facility projects. The G/AO is administratively part of
DACS in BFA, except for mid-scale projects where they may be part of DGA (See Section 5 of this
1

This is the “lead organization” in the case where more than one Division participates in sponsoring a project.

Section Revision:
May 30, 2019

2.1.6-12

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.6 Roles and Responsibilities for NSF Staff for Management and Oversight of Major Facilities
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Guide). The timing of this assignment is at the discretion of the DGA or DACS DD, but should be
early enough in the planning stage of a major facility project to allow the participation of the
G/AO in the strategic planning and development of the IMP for a major facility project (i.e.,
during the Conceptual Design Stage when NSF begins to consider strategies for the business
aspects of managing oversight of the proposed project).
The G/AO is an integral member of the IPT for a facility project when the award instrument is a
cooperative agreement, in order to expedite NSF action on business and administrative issues
related to the project. The G/AO participates in management reviews, risk assessments and
issues affecting the management of the award. The G/AO plans and coordinates development
of award instruments from early planning stages through award administration and closeout.
The G/AO negotiates terms and conditions, interprets Federal and NSF policy, and reviews
business proposals and budgets, subawards1, MOUs, and partnership agreements. The G/AO
also monitors awards for compliance with the most current NSF financial and administrative
policies and procedures.
The G/AO is the primary point of contact at the NSF with the Recipient institution for all
business and financial matters. The G/AO represents the NSF in conducting all of the financial
and administrative business-related oversight of the Recipient, including:
•

Providing approval or authorization for all financial transactions,

•

Ensuring compliance with financial and administrative award terms and conditions,

•

Accepting submittals or reports from the Recipient,

•

Leading the cost analysis process of proposals and negotiating the budget, and

•

Negotiating any specific terms and conditions which define the conduct and execution
of a project, such as CAs and subsequent amendments, MOUs, property leases, etc.

The G/AO is responsible for oversight of the financial and administrative terms and conditions
of the assistance award,2 just as the PO is responsible for scientific and technical oversight.
Unlike the PO, he/she holds the warrant to obligate Federal funds. The G/AO and the PO jointly
share the principal technical and financial responsibilities for the oversight and assurance of a
major facility project. In this capacity, the G/AO is jointly responsible with the PO for the
success of a project.
The G/AO confers with the PO and other relevant offices to ensure that the NSF’s technical and
administrative oversight activities are well coordinated. The G/AO and the PO collaborate on
Except for the purchase of materials and supplies, equipment or general support services allowable under the award, no
portion of the proposed activity may be subawarded to another organization without written prior NSF authorization. All
proposing organizations are required to make a case-by-case determination regarding the role of a Subrecipient versus
contractor for each agreement it makes. See PAPPG II.C.2g (vi) e for further guidance.

1

An assistance award is a grant or cooperative agreement (CA) to a non-Federal organization with fiduciary responsibility for
the project or facility.

2

Section Revision:
May 30, 2019

2.1.6-13

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.6 Roles and Responsibilities for NSF Staff for Management and Oversight of Major Facilities
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

the preparation of solicitations and the proposal and award process. The G/AO has individual
responsibility for developing and overseeing the implementation of financial and administrative
aspects of the award process, and joint responsibility with the PO for recompetition planning
and execution and for award termination or closeout.
The G/AO develops the CAs that establish a business relationship between the NSF and the
Recipient. Consequently, the G/AO has an oversight responsibility that extends to the business
practices of that Recipient, in addition to the specific business operations and oversight
practices of the particular project that may be based with that Recipient.1
The G/AO, with the assistance of BFA resources, establishes that the financial stewardship and
reporting practices of the Recipient institution, as they pertain to NSF instruments, are
consistent with NSF requirements, 2 CFR § 200 (Uniform Administrative Requirements, Cost
Principles, and Audit Requirements for Federal Awards), or Federal Acquisition Rules, as
appropriate. 2
Contracting Officer
The Contracting Officer (CO) has authority, subject to statutory limitations, to award and
administer contracts for the construction and operations of facilities that are managed through
contract rather than Cooperative Agreements (CAs). The CO is appointed by the agency Senior
Procurement Executive and is administratively part of the Division of Acquisition and
Cooperative Support within BFA. The CO is solely responsible for oversight of the terms and
conditions of the contractual agreement.
The CO holds the warrant and is the only individual authorized to obligate or de-obligate
Federal funds. The CO, through their warrant, has the sole authority to award and administer
the prime construction contract(s) used in support of Major Facility projects.
The CO is an integral member of the IPT for a facility project when the award instrument is a
contract, in order to expedite NSF action on business and administrative issues related to the
project.
Cost Analyst
The G/AO or CO requests assistance from a NSF Cost Analyst from the Cost Analysis and PreAward (CAP) Branch of the Division of Institution and Award Support (DIAS), located within BFA,
when cumulative or individual awards exceed certain thresholds or for Recipients with
previously identified risks. The PO, G/AO or CO, and Cost Analyst all review proposed budgets
to help determine if they are allowable, allocable, reasonable, and realistic for the scope of
Refer to the Business Systems Review (BSR) Guide described in Section 4.6.3.3 for discussion on this point. When NSF is not the
cognizant audit agency for the Recipient institution, its oversight of Recipient business practices is narrowly defined.

1

2

Refer to the Business Systems Review (BSR) Guides for more details on the criteria and processes for this assessment.

Section Revision:
May 30, 2019

2.1.6-14

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.6 Roles and Responsibilities for NSF Staff for Management and Oversight of Major Facilities
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

work. However, the primary purpose of the NSF Cost Analyst’s budgetary review is to support
the G/AO or CO to ensure that the Recipient has properly estimated and calculated costs and
that they are supported and documented with sufficient rigor. The Cost Analyst provides a
written recommendation to the G/AO or CO stating whether costs are supported or
unsupported. The recommendation may include advice on award terms and conditions or
limitations or other concerns identified.
The Cost Analyst may also help determine if the Recipient has adequate business and
accounting systems in place, assess a Recipient’s financial capability and viability, validate
indirect cost rates, or assist in other areas of concern as identified by the requesting G/AO or
CO.
While the G/AO or CO is the primary point of contact with the Recipient for all award and cost
analysis issues, this should not inhibit direct communications between the Cost Analyst and
Recipient when necessary. Cost analysis communications with the Recipient should include the
Cost Analyst, G/AO or CO, and PO to help ensure efficient resolution, close collaboration, and
clear and consistent direction.
Chief Officer for Research Facilities (CORF)
The position of Chief Officer for Research Facilities (CORF) is within the Office of the Director
and reports directly to the Director and has full life cycle oversight responsibility for NSF major
research facilities. The CORF advises the NSF Director on all aspects of NSF major and mid-scale
facilities throughout their life-cycle and collaborates with all at NSF who are involved in
oversight and assistance for the NSF research facilities portfolio. The CORF chairs the Facilities
Readiness Panel, the Major Facilities Working Group and the Facilities Governance Board.
This position also fills the previous statutory requirement for NSF to have a Deputy Director for
Large Facility Projects.
Head, Large Facilities Office (HLFO) and BFA’s Large Facilities Office
The NSF’s Head, Large Facilities Office (HLFO), and the LFO supporting staff are the NSF’s
primary resource for all policies or processes related to the development, implementation, and
oversight of research infrastructure. LFO is the Foundation’s primary resource for all oversight
practices related to major facility projects and is the NSF-wide resource on project management
good practices. The LFO has the institutional authority and resources to effectively develop
mandatory policies, practices and procedures, which are approved by senior management, for
all stages of the facility life-cycle. The LFO works closely with the BFA and NSF Senior
Management Officers, providing expert assistance on non-scientific and non-technical aspects
of project planning, budgeting, and implementation for major facilities. It also provides
assurance that all applicable requirements are followed in order to give credence to NSF’s
oversight capabilities. The LFO also facilitates the use of good practices by fostering

Section Revision:
May 30, 2019

2.1.6-15

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.6 Roles and Responsibilities for NSF Staff for Management and Oversight of Major Facilities
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

coordination and collaboration throughout NSF to share application of lessons learned from
prior major facility projects.
The LFO develops and implements processes for insuring that all facility award instruments
include, at a minimum, four performance evaluation and measurement components:
1. Clear and agreed-upon goals and objectives;
2. Performance measures and, where appropriate, performance targets;
3. Periodic reporting; and
4. Evaluation and feedback to assess progress.
Prior to NSF requesting NSB authorization to include a proposed project in a future budget
request, the HLFO contributes to agency assurance that the project plans are construction
ready, and that the construction and operations budgets are satisfactorily justified.1 This
assurance comes through assignment of the LFO Liaison to the IPT and membership (as
assigned) on various governance bodies such as the Facilities Readiness Panel and the Director’s
Review Board.
The HLFO prepares a periodic status report for NSF Leadership on all ongoing major facility
projects, candidate projects in planning, and other major facility projects designated by the
Sponsoring Organization. Inputs to the monthly report are provided by each cognizant PO and
their associated Directorate/Division. The Recipient submits a monthly report to the PO that
summarizes the technical and financial status of the project, pending near-term milestones, and
any other issues that should be brought to the attention of the LFO. The PO reviews the report
and prepares a written response to the monthly report that is uploaded into eJacket. The HLFO
combines all of these inputs into a single report, summarizes the key technical and financial
status information, and provides an independent commentary on project management issues
as necessary.
Under the direction of the NSF Senior Management, the HLFO prepares and presents a variety
of information to the National Science Board (NSB) related to the status and plans for the
portfolio of major multi-user facility projects that are either receiving or are candidates for
receiving MREFC funds. This information supplements information contained in the NSF’s
annual Budget Request to Congress.
LFO Liaison
For each major facility project, the HLFO designates an LFO Liaison to work closely with the PO
and the G/AO or CO, providing expert assistance on non-scientific and non-technical aspects of
project planning, budgeting, implementation, and management to further strengthen the
oversight capabilities of NSF. The LFO Liaison participates in each project IPT and also advises
the cognizant PO of mitigating steps when project management challenges arise. The LFO
See “Priority Setting for Large Facility Projects” (NSB-04-96), National Science Board White Paper, May 2004, Attachment 5 to
NSB Meeting Report, https://www.nsf.gov/nsb/meetings/2004/may_srprt.doc.

1

Section Revision:
May 30, 2019

2.1.6-16

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.6 Roles and Responsibilities for NSF Staff for Management and Oversight of Major Facilities
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Liaison works with the PO and the G/AO or CO, not directly with the Recipient or their project
staff.
The LFO Liaison also collaborates with the PO and G/AO or CO to plan and carry out key project
reviews including CDR, PDR, FDR, operations reviews, and other ad hoc project reviews in all life
cycle stages as appropriate. While the PO is responsible for planning, carrying out, and
assessing the full range of topics addressed in the review, LFO Liaison focuses on project
management, business, and administrative issues, and assists the PO and G/AO or CO in these
areas. The LFO Liaison independently assesses and reports to the HLFO on the outcome of
these reviews with respect to project management issues.
The LFO Liaison participates in site visits in coordination with the PO and Sponsoring
Organization, to strengthen project management and affirm aspects of NSF’s oversight and
assurance role. During these interactions, the PO is the single point of contact with the project
for all programmatic issues, and the G/AO or CO is the point of contact with the Recipient
institution for administrative issues. Any project-specific communications between the LFO
Liaison and the project is coordinated through the respective PO, G/AO, or CO, and generally as
part of the IPT process.
LFO also carries out BSRs of Recipient business systems for major facilities in design,
construction or operation based on a regular review cycle and other potential risks, such as
building institutional capacity in advance of a construction award. BSRs may also be conducted
at smaller scale facilities at the request of NSF Leadership or the Sponsoring Organization. BSR
objectives and processes are described in detail in NSF’s Business Systems Review (BSR) Guide,
described in Section 4.6.3.3.
2.1.6.3 Coordinating and Advisory Bodies
The Integrated Project Team
The Integrated Project Team (IPT) serves as a formal internal NSF coordinating body for major
facilities oversight throughout the Design, Construction, and Operations Stages. The IPT consists
of three primary sub-groups:
1. Science and Technical Group led by Program with primary responsibility for project
oversight. This group may include other Staff from the Division and/or Directorate as
deemed appropriate by Program (budget, science program, etc.).
2. Award Management Group comprised of various Offices and Divisions within the BFA.
This group is primary responsible for assurance. The linkage with the Science and
Technical Group is with the review and monitoring of cost, scope and schedule as well
as the Project Execution Plan and Recipient performance. The linkage with the Strategic
Group is related to internal NSF processes and procedures.

Section Revision:
May 30, 2019

2.1.6-17

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.6 Roles and Responsibilities for NSF Staff for Management and Oversight of Major Facilities
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

3. Strategic Group comprised of various offices within the OD. This group’s role is primarily

with assessing risk. The linkage with the Science and Technical Group is with
communication with external stakeholders.

The IPT is chaired by the PO, see Figure 2.1.6-4. Members are selected by the DDs, ADs or Office
Heads, in consultation with the PO. The PO will convene the IPT at least quarterly to address
any project-related issues.
Figure 2.1.6-4

An Integrated Project Team (IPT), chaired by the Program Officer, is composed of three
subgroups, with appointed Award Management Group members from BFA, Science and
Technology Group members from the sponsoring program offices, and Strategic Group
members from the Office of the Director.

Major Facilities Working Group
The Major Facilities Working Group (MFWG) assures the uniform and effective programmatic
oversight of major and mid-scale research infrastructure of the National Science Foundation
throughout their entire life cycles.
The MFWG is chaired by the Chief Officer for Research Facilities (CORF). The MFWG meets
approximately monthly and at other times as required and carries out the following duties:
•

Provide input to the Facilities Governance Board regarding all strategy, governance, and
implementation issues under consideration by that Board.

•

Establish and maintain a list of NSF’s major research infrastructure at all life cycle stages,
development through divestment, and the major upcoming decision points for those
facilities.

Section Revision:
May 30, 2019

2.1.6-18

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.6 Roles and Responsibilities for NSF Staff for Management and Oversight of Major Facilities
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

•

Support the Head of the Large Facilities Office in reviewing the Major Facilities Guide
(MFG), Standard Operating Guidance (SOG), and Standard Operating Procedures for NSF
facility oversight, and advise the Facilities Governance Board on the sufficiency and
appropriateness of these documents.

•

Provide concurrence on a bi-monthly report produced by the Large Facilities Office
summarizing the status of all major research infrastructure facilities in their operation
and divestment stages.

•

Provide input, as appropriate, for the Large Facilities Office bi-monthly report
summarizing the status of major facilities and related projects at stages ranging from
development through the completion of construction.

•

Maintain situational awareness of each relevant major research infrastructure in their
home directorate and communicate important information via the CORF and the
cognizant Assistant Directors in a timely way.

•

Share good practices for the proper oversight of major research infrastructure, and work
with the cognizant Assistant Directors to implement good practices across their
directorates.

The MFWG membership consists of the following members:
•
•
•
•
•
•
•
•

Chief Officer for Research Facilities (Chair);
Head, Large Facilities Office (Vice-Chair);
Accountable Directorate Representative (ADR), Directorate for Mathematical and
Physical Sciences (MPS);
Accountable Directorate Representative, Directorate for Geosciences (GEO);
Accountable Directorate Representative, Directorate for Biological Science (BIO);
Accountable Directorate Representative, Directorate for Computer and Information
Science and Engineering (CISE);
Accountable Directorate Representative, Directorate for Engineering (ENG), and
Executive Secretary

Advisory Committee of the Sponsoring Organization
The Advisory Committee of the Sponsoring Organization provides input to the NSF AD, or Office
Head of the Sponsoring Organization concerning priorities among and between projects and
other activities sponsored by the Directorate. The NSF Director requires the endorsement of
the Advisory Committee of the Sponsoring Organization prior to requesting NSB action
authorizing a project’s inclusion (at the Director’s discretion) in a future NSF budget request to
Congress.

Section Revision:
May 30, 2019

2.1.6-19

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.6 Roles and Responsibilities for NSF Staff for Management and Oversight of Major Facilities
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

2.1.6.4 Governing Bodies
Facilities Readiness Panel
The Facilities Readiness Panel (FRP) advises the Director on Recipient and Programmatic
readiness to advance major and mid-scale facilities projects within the formal Design Stage as
described in NSF’s Major Facilities Guide (MFG); this includes the transition from Final Design to
Construction. Readiness to enter the Design stage and whether or not to include in a budget
request are strategic decisions made separately. Projects include the major multi-user research
facilities as defined in the American Innovation and Competitiveness Act. Members of the FRP
include:
•
•
•
•
•
•

Chief Officer for Research Facilities (Chair);
Head, Large Facilities Office, HLFO;
Head, Office of General Counsel (or Designee);
Division Director, Division of Acquisition & Cooperative Support (or Designee); and
At least 4 senior Program Officers, Section Heads, Deputy Division Directors or Division
Directors (at least 3 from MPS, GEO, BIO, CISE, or ENG)
Executive Secretary

The primary duties include:
•

Assess overall project readiness to advance based on the requirements and guidelines in
the MFG and other internal NSF policies and procedures. This includes technical
readiness of the project itself, business system and management readiness of the
Recipient, and programmatic readiness with regard to adequate oversight.

•

Assess whether or not agency risks, including significant project risks managed by the
Recipient that may impact the agency, have been identified and properly considered by
the Sponsoring Organization in developing the Internal Management Plan.

Facilities Governance Board
The Facilities Governance Board (FGB) oversees and makes recommendations on all aspects of
governance of major multi-user research facilities and mid-scale research infrastructure of the
National Science Foundation.
Members of the Board are:
•
•
•
•

Chief Officer for Research Facilities (Chair);
Assistant Directors for MPS, GEO, BIO, CISE, ENG;
Chief Financial Officer; and
Executive Secretary

Section Revision:
May 30, 2019

2.1.6-20

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.6 Roles and Responsibilities for NSF Staff for Management and Oversight of Major Facilities
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

The primary duties include:
•

Advise the Director on all aspects of strategy, governance, and implementation of major
multi-user research facilities and mid-scale research infrastructure.

•

Approve the NSF Major Facilities Guide (MFG) and all agency-wide Standard Operating
Guidance (SOG) and supporting Standard Operating Procedures for implementation of
facilities oversight, with input from the Major Facilities Working Group.

•

Maintain situational awareness for major multi-user research facilities and mid-scale
research infrastructure at all life cycle stages, from development through divestment,
and advise the Chief Officer for Research Facilities on oversight issues.

•

Recommend to Director on renewal, recompetition, or divestment of major multi-user
research facilities, based on the Guidelines for Competition of Major Research Facilities
and subsequent Standard Operating Guidance.

Director’s Review Board
The purpose of the Director’s Review Board (DRB) is to assure the Director that all
recommendations and proposed action items have undergone thorough review, assessment
and discussion. The DRB reviews proposed actions for adequacy of review and documentation
and for consonance with Foundation policies, procedures and strategies. The DRB also brings to
the Director’s attention any policy issues that have been identified.
The DRB is the Director’s forum for reviewing timely recommendations to the NSB on a variety
of critical NSF awards, actions, and information items, including those related to major facilities.
The DRB reviews for responsiveness to questions that may be raised by the NSB.
Members of the DRB may include:
•
•
•
•
•
•

Chairperson (NSF Deputy Director or other);
Three ADs, serving on a rotating basis;
Chief Financial Officer;
Staff Advisor, OD;
Executive Secretary, DRB; and
Such other persons as the Director may designate (i.e., OGCs, Legislative and Public
Affairs, etc.).

Joint meetings between the FRP and DRB may be scheduled as the particular situation
warrants, but keeping in mind their distinct roles and responsibilities as described above.
NSF Director
The NSF Director has ultimate responsibility for the approval of the obligation of funds from the
MREFC Account and for proposing new MREFC projects to the NSB, OMB and Congress. The
Director approves all materials submitted to the NSB, OMB or Congress.

Section Revision:
May 30, 2019

2.1.6-21

Major Facilities Guide: NSF 19-68 (May 2019)
2.1.6 Roles and Responsibilities for NSF Staff for Management and Oversight of Major Facilities
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

National Science Board
The National Science Board (NSB) establishes policy, reviews and authorizes construction stage
budgets, and reviews and authorizes specific large awards for funding, including major facility
projects.1 NSB is an independent body established by Congress in 1950 to set policies for NSF.
Along with the Director, the NSB oversees NSF and establishes NSF policies within the
framework of applicable national priorities set forth by the President and the Congress. In this
capacity, the NSB identifies issues that are critical to NSF’s future, authorizes NSF’s strategic
directions, annual budget requests, new major programs and awards, and provides guidance on
the balance between initiatives, infrastructure investments and core programs. 2
NSB has established processes for reviewing and authorizes recommended actions and funding
requests from NSF regarding major facility projects.3 The NSB performs certain reviews,
including a periodic review of facilities, and prioritizes projects as necessary. NSB involvement
at each life cycle stage includes:
•

Setting Board-level policies and procedures for overseeing all life cycle stages of NSF’s
major facilities;

•

Being kept apprised of the status of all major facilities funded by NSF through oral and
written information items, particularly projects in the design and construction stages.

•

Authorizes advancement through certain design phases;

•

Authorizes inclusion of a candidate project in a future NSF Budget Request to Congress,
after a PDR and NSF Director approval;

•

If necessary, recommend priorities for construction start among projects;

•

Authorizes the Director to obligate appropriated construction funding to the Recipient;

•

Authorizes award of funds to operate major facilities if above the NSB threshold; and

•

Authorizes recompetition strategies, divestment, or major reorganization for operations
awards if above the NSB threshold.

NSF policy requires the following items to be submitted to the NSB for authorization: (1) Large Awards. Proposed awards
where the average annual award amount is 1% or more of the awarding Directorate or Office's prior year current plan
(including any funds transferred from other Federal agencies to be awarded through NSF funding actions); (2) Major
Construction Projects. NSB authorization is required when the resulting cost is expected to exceed the percentage threshold for
NSB award authorization; (3) Awards Involving Policy Issues or Unusual Sensitivity. NSB interests may include the establishment
of new centers, institutes, or facilities that have the potential for rapid growth in funding or special budgetary initiatives. (Note:
In determining whether anticipated future commitments beyond an initial award amount for any award instrument meet or
exceed the threshold for NSB authorization, every additional anticipated funding action should be added to the initial award
amount. Awards should be submitted for NSB authorization under this criterion as soon as Program staff anticipate that the
total ultimately to be committed is likely to exceed the threshold established for their Directorate or Office.)

1

2

More about the NSB is available online at https://www.nsf.gov/nsb/

See NSB’s meeting minutes with “Annual Timeline for Integration of Board MREFC Process with NSF Budget Process” (NSB-1066, approved August 2010).

3

Section Revision:
May 30, 2019

2.1.6-22

Major Facilities Guide: NSF 19-68 (May 2019)
2.2.1 Initiation of a Potential Major Facility Project
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

2.2

DEVELOPMENT STAGE
Initiation of a Potential Major Facility Project

As in all NSF endeavors, inquiry begins with the research communities, whose members alert
NSF program staff to the most promising and exciting questions and the most important
equipment needed to explore them.
NSF POs, who work closely with those communities, should be attentive to the emergence of
breakthrough concepts and actively encourage discussion and planning. In addition, NSF uses
National Academies’ studies, community workshop reports, professional society activities,
Directorate advisory committees and many other methods to identify opportunities and ensure
continuous community input.
Ideas and opportunities identified by the research communities typically have a 5- to 20-year
forward look and are brought to NSF in the form of a submitted proposal requesting funding for
development. When there are competing concepts, it may be appropriate for NSF to issue a
solicitation inviting proposals.
In most cases, program staff will take a proactive role in facilitating proposal submission, merit
review, recommendations and decision. In so doing, however, a PO should maintain the
position of a neutral, unbiased agent of NSF. Project advocacy should rightly come from the
community, which also participates in the merit review process and whose input is a significant
contributing factor in NSF’s funding decisions.
During the early development stage, there should be sufficient investment by the Sponsoring
Organization (Directorate and/or Division) so that the project is reasonably well defined and/or
described in preparation for the formal design stage.

Section Revision:
June 17, 2015

2.2.1-1

Major Facilities Guide: NSF 19-68 (May 2019)
2.2.2 Exit from Development to Design Stage
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Exit from Development to Design Stage
Formal start of the Design Stage for a facility project occurs following a recommendation by the
Chief Officer for Research Facilities (CORF) with input from the Facilities Governance Board
(FGB) and other senior agency officials and written approval by the NSF Director is received.
This process is initiated by a request from the Sponsoring Organization to the Director’s Office
once a project is determined to be ready. Generally, such a request is made when the
Sponsoring Organization has determined that: (1) the project is a high priority for further
development, (2) the project is eligible for MREFC funding (see criteria) and the MREFC funding
route is preferred, and (3) the Sponsoring Organization is committed to begin explicit
investment in more detailed design activities in the current or upcoming budget cycle using
Directorate or Divisional funding (R&RA).
The CORF’s recommendation (as Chair of the FGB) will focus on providing the Director with
answers to the following questions:
Science
•

Is there a compelling science case, and are the project’s goals well-articulated?

•

Does the project fit solidly within the NSF “mission,” within the strategic plans of the
NSF and that of the Sponsoring Organization, and within the broader NSF facility
portfolio?

Planning
•

Is the sponsor’s plan for stewardship of the Conceptual Design Phase consistent with the
guidelines set out in the Major Facilities Guide?

•

Does the preliminary timeline for development and implementation include
programmatic, NSB, budget and any necessary partnering milestones, including explicit
project off ramps?

•

Are potential opportunities for internal and or external partnering being considered, if
not already underway?

•

Are there any other major challenges regarding this project that the Director needs to
be aware of?

Based on the CORF’s recommendation and any further examination, the Director then approves
(or disapproves) the project entering the Conceptual Design Phase as a “candidate” project.
Note that no NSF commitment is implied beyond support for the development of a Conceptual
Design. The CORF or Director might alternatively advise the Sponsoring Organization to look
further into any issues and then return for further consideration.

Section Revision:
May 30, 2019

2.2.2-1

Major Facilities Guide: NSF 19-68 (May 2019)
2.3.1 Conceptual Design Phase
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

2.3

DESIGN STAGE – CONCEPTUAL, PRELIMINARY, AND FINAL DESIGN PHASES
Conceptual Design Phase

2.3.1.1 Introduction – Conceptual Design Phase
The goal of this first phase of the major facility design stage is the creation of a comprehensive
Conceptual Design that clearly articulates project elements that NSF will consider, including:
•

Description of the research infrastructure and technical requirements needed to meet
the science, including a definition and relative prioritization of the research objectives
and science questions the proposed facility will address. Technical requirements must
flow down from the science requirements. This description may be site-independent or
site-specific depending on the nature of the project;

•

System-level design, including definition of all functional requirements and major
systems;

•

Concept of operations including an estimate of annual operations and maintenance
costs, staffing levels, and other activities

•

Initial risk analysis and mitigation strategy for construction, identifying enabling
technologies, high-risk or long-lead items, and research and development (R&D) needed
to reduce project risk to acceptable levels;

•

Potential environmental and safety impacts to be considered in site selection (see
“Compliance with Environmental, Cultural and Historical Statues,” at the end of this
section);

•

Description of the proposed construction performance baseline (scope of work, budget
and schedule) needed to evaluate readiness and continue planning in preparation for
the Preliminary Design Phase. This includes budget and contingency estimates
appropriate to a Conceptual Design 1 level and based on the initial Risk Analysis and
initial projections for the construction and commissioning schedule;

•

Description of proposed Educational Outreach and Broader Societal Impact, included in
the proposed scope of work, budget and schedule.

Many of these details are included as part of the PEP as described in greater detail in following
sections and in Section 3.4. This Phase may take several years depending on development
activities.

The budget information should be provided using a Work Breakdown Structure (WBS) format, identifying the basis for
estimates and including a WBS dictionary that defines the scope associated with each WBS element. Contingency estimates
should include an explanation of the methodology used to calculate the estimate.

1

Section Revision:
December 14, 2018

2.3.1-1

Major Facilities Guide: NSF 19-68 (May 2019)
2.3.1 Conceptual Design Phase
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

2.3.1.2 Conceptual Design Phase Activities
During the Conceptual Design phase there may be a number of coordinated and complimentary
activities taking place with the various entities involved: (1) community activities, (2) NSF staff
activities, and (3) funding considerations.
(1) Community Activities. Proponents of a project should provide NSF with an early concept
proposal that makes a compelling case for the research that would necessitate development of
a facility, and that describes, in general terms, its essential characteristics if the proposal is
unsolicited. Generally speaking, major facilities projects are solicited. In that case, the proposal
must respond to all NSF and programmatic requirements which generally include references to
the Major Facilities Guide if it is already known as a major facility project. These initial proposals
identify what is known at that point in project development, as well as what tasks remain to be
accomplished in order for NSF to consider a project for eventual funding. In the near term, they
also define what work should be done to develop the project to the Conceptual Design level of
maturity.
An NSF PO1 will be assigned to be the primary point of contact with the Principle Investigator
(PI) and/or Project Manager. The NSF PO conducts a merit and technical/programmatic review
of the proponents’ proposal, and either recommends or declines the request for funding. If
funded, the PO will work with their Directorate and/or Division to organize an Integrated
Project Team to provide coordination on project oversight and assurance.
Proponents should acquaint themselves with NSF’s expectations for the essential elements of a
construction-ready PEP as described in Section 3. Proponents should also develop a skeletal
plan that will result in the future definition of each of these elements, should NSF encourage
further pre-construction planning. The plan should address, even if only in the most cursory
way, each of the essential elements that should be realized in a formal construction-ready PEP.
For example, proponents may wish to develop a “straw man” PEP that contains sections labeled
using each of the entries in Section 3.4, with as much supporting information provided based
on the outputs from the Development Stage (if any) and/or the requirements in the solicitation.
This serves to illustrate an understanding to all parties of the range and magnitude of the tasks
ahead.

Administratively, the Program Officer (PO) is part of a Directorate or Office that provides supervisory oversight and the
budgetary authority to fund PO actions. Actions of the PO described here and in subsequent life cycle stages of facility
development implicitly recognize the authority of the individuals within this supervisory structure to appropriately guide, direct,
and approve the actions of the PO. In particular, when the phrase “PO concurrence” is used in the following text, this assumes
concurrence at whatever management level the AD or Office Head has required. Refer to Section 2.1.6 for a brief description of
the duties of the PO, AD, and others referred to in the Major Facilities Guide.

1

Section Revision:
December 14, 2018

2.3.1-2

Major Facilities Guide: NSF 19-68 (May 2019)
2.3.1 Conceptual Design Phase
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

(2) NSF Staff Activities: In response to the development of an early version of a PEP, the PO,
with the advice of the IPT, develops an Internal Management Plan (IMP). 1
This internal document specifies how NSF will conduct its oversight and assurance of the
project, and provides budgetary estimates for developing, constructing and operating the
facility. It also identifies critical issues and risks facing the project (for example: project
management issues, completion of essential R&D activities, partnership agreements, award
closeout or divestment liabilities) and lays out a strategy for financing these activities.
The PO develops the IMP with advice and assistance from the IPT, following internal operating
guidance. The IMP is approved by the cognizant NSF AD after review and approval within the
Sponsoring Organization. The IMP describes the plan for NSF management and funding of the
project to CDR, proposes transitional steps to be taken if the project is admitted to the
Preliminary Design Phase, and lays out NSF’s plan to oversee development of the project
including internal and external review. Each major facility project undertaken by NSF has
unique characteristics. Accordingly, the IMP should be adapted to meet the specific needs of a
particular project. The IMP should state the justification for pursuing alternatives to the
guidelines contained in the Major Facilities Guide.
3) Funding Considerations. During the Conceptual Design Phase, NSF and/or other institutions
and agencies begin to invest research and development funds in design development, and in
efforts that promote community building and planning. Investment in fundamental research
activities, community building, and initial planning activities may occur over many years, and
some are recognized as having contributed to the conceptual design effort only in retrospect. 2
The cumulative pre-construction investment in research, planning and development that occurs
during the Conceptual Design, Preliminary Design, and Final Design phases may range from five
to 25 percent of total construction cost, depending on the complexity of the project, and
typically amounts to about 10 percent of the construction cost. The technology needed to
construct a facility may be uncertain, unproven or immature, requiring substantial development
over a period of years.
NSF may decide to fund additional planning and development efforts for particular projects
depending on the outcomes of the review and whether or not the Conceptual Design Phase was
funded. 3 Such activities might include workshops in one or more disciplines, National
1

Questions about Internal Management Plans should be addressed to the relevant PO.”

Some projects come to NSF very well developed, requiring little in the way of conceptual design phase support. They are
subjected to the same rigorous scrutiny, however, as they are developed by the responsible NSF Directorates or Offices.

2

Relevant program solicitations may be released to announce funding opportunities for these planning and development
efforts.

3

Section Revision:
December 14, 2018

2.3.1-3

Major Facilities Guide: NSF 19-68 (May 2019)
2.3.1 Conceptual Design Phase
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Academies’ studies, and research projects related to the development of new technologies.1
These activities might be funded as part of the Conceptual Design Phase award, or through a
separate proposal submission.
2.3.1.3 Conceptual Design Review (CDR)
The Conceptual Design Phase is complete when a package containing the Conceptual Design
and funding request leading to a Preliminary Design is received, reviewed, negotiated and
approved for funding. The funding request will generally be submitted as a supplemental
request to the original award.
The package should include the refined PEP and any additional information required by
Program to assess the project readiness and management to-date. Components of the PEP are
given in Section 3.4.
NSF will subject the Conceptual Design package to external review, applying standard NSF
criteria (Intellectual Merit and Broader Impacts) as well as other programmatic and technical
criteria as given in the original solicitation and the panel charge. Projects that review well will
be further evaluated by NSF to apply the second ranking criteria (agency strategic fit), in
accordance with the principles stated in the joint NSB/NSF Management Report: Setting
Priorities for Large Research Projects Supported by the National Science Foundation
(NSB-05-77). (See Appendix A for discussion of ranking criteria.)
The review panel will, as appropriate, involve external experts, consulting firms, and in-house
expertise in the science, technology and business communities to scrutinize and validate the
supporting planning documents. The scope of this review includes assessment of the scientific,
technical and project-management aspects of the proposal.
The review is organized and conducted by the PO in consultation with the LFO Liaison and
G/AO. The PO has overall responsibility for organizing the review, and throughout the review
process acts as the interface between the NSF and the Recipient. The PO authors the review
charge and organizes the review panel. The LFO Liaison and G/AO strengthens the review
process by specifying language for incorporation within the charge and for aspects of the
review agenda pertaining to project management issues and recommending panelists able to
advise NSF in non-science related areas of the review. The PO, LFO Liaison, and G/AO concur on
the implementation of these recommendations. Following the review, the PO and the LFO
Liaison will each independently assess the review, confer on areas of concern, share their
views, and report their observations through their respective supervisory chains – the PO via
the administrative structure of the Sponsoring Organization and the LFO Liaison via the HLFO.
NSF encourages disciplinary and interdisciplinary science planning by all of the research communities that NSF supports. In
particular, NSF encourages formal planning in fields in which scientists and engineers have traditionally not been organized to
identify major facility projects needed for breakthrough advances.

1

Section Revision:
December 14, 2018

2.3.1-4

Major Facilities Guide: NSF 19-68 (May 2019)
2.3.1 Conceptual Design Phase
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

At this point, the conceptual design baseline is likely to have significant uncertainties. Cost
estimates at CDR are generally parametric in nature. Contingency estimates, representing work
scope not yet defined but nevertheless essential to the completion of the project, will be a
significant fraction of the total project budget estimate. Significant unknowns and uncertainties
often remain to be addressed in more advanced stages of planning and development. The
conceptual design, system requirements, supporting budget estimates, risk analysis, and
forecasts of interagency and international partnerships should be detailed enough for NSF
program officials to decide whether the project concept warrants further funding for
development.
Immediately following CDR, the initial high-level NSF Cost Analysis will be initiated and
conducted jointly with key assurance members of the IPT; namely DACS, the Division of
Institution and Award Support (DIAS), and the LFO. The Cost Analysis will be conducted following
NSF internal operating guidance. Guidance on refinements to the Recipient’s Cost Book will be
provided as necessary in preparation for the Preliminary Design Phase.
2.3.1.4 Exit from the Conceptual Design Phase
Formal exit from the Conceptual Design Phase typically entails four NSF actions:
1. Successful completion of the CDR as described above,
2. Recommendation for advancement by the sponsoring Directorate,
3. Facilities Readiness Panel Review and Recommendation, and
4. Approval for advancement to the Preliminary Design Phase by the Director
Recommendation for Advancement by the Sponsoring Directorate
The AD relies on community inputs, discipline-specific studies, advisory committee recommendations and internal NSF considerations to prioritize the opportunities represented by the project
relative to competing opportunities and demands for resources. If, in the judgment of the AD, the
scientific merit and relative importance of the proposed facility are sufficiently strong to justify
advancement of the project into the Preliminary Design Phase, the AD will submit a
memorandum to the Facilities Readiness Panel recommending the project for support, that
explains how it meets the requirements for construction funding and how it satisfies the
following criteria:
•

The project’s science (research) program addresses one or more science objectives,
clearly demonstrating a compelling need for the project;

•

The project has been reviewed by the research community and by NSF, in consultation
with Directorate Advisory Committees, and has been assigned a very high priority; 1 and

Evaluation by NSF includes external merit review, using the NSF merit review criteria and the 1st ranking Criteria and
evaluation by the Facilities Readiness Panel, using the 2nd ranking Criteria in Appendix A.

1

Section Revision:
December 14, 2018

2.3.1-5

Major Facilities Guide: NSF 19-68 (May 2019)
2.3.1 Conceptual Design Phase
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

•

The project’s CDR indicates that: (1) the engineering design and construction plans are
appropriately defined at the conceptual design level of project maturity and that the
management plans and budget estimates for further planning and development, as well
as constructing and operating the facility are reasonable; (2) the sponsoring Directorate
endorses the IMP and Project Development Plan 1 (PDP) for further development to the
Preliminary Design Phase; (3) the technology to create the facility exists or can exist
shortly, and can be used without excessive risk; (4) other risks to development are
satisfactorily defined and minimized or otherwise addressed in the IMP, and (5) there
are no better alternatives to the facility (i.e., with a better mix of cost and quality) that
would address the science objectives in a timely manner.

Supporting documentation, including the approved IMP, relevant review evaluations, and any
other supporting information should accompany this memorandum. All materials are
transmitted to the Facilities Readiness Panel (FRP) by the AD or Office Head of the Sponsoring
Organization.
Approval by the Director
The Director evaluates the FRP recommendation and, if satisfied, approves advancement to the
Preliminary Design Phase.
At its May meeting, the NSB reviews the portfolio of projects which are being considered for
future funding and evaluates relative priorities that guide NSF’s investment looking across the
entire range of disciplines served by NSF within the constellation of other competing
opportunities, existing facilities, and the balance of support for infrastructure, its utilization,
and individual investigator-led research.
More information about the role of the NSB in selecting and prioritizing major facility projects is
available in Section 2.1.6 on Roles and Responsibilities.

The Project Development Plan is part of the PEP, providing the plan to develop the project design and definition to readiness
for construction. See Section 3.4 for details.

1

Section Revision:
December 14, 2018

2.3.1-6

Major Facilities Guide: NSF 19-68 (May 2019)
2.3.2 Preliminary Design Phase
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Preliminary Design Phase
2.3.2.1 Introduction – Preliminary Design Phase
The Preliminary Design Phase further develops concepts to a level of maturity in which there
are: a fully elaborated definition of the motivating research questions; a clearly defined sitespecific scope; a PEP and an IMP that address major anticipated risks in the completion of
design and development activities and in the undertaking of construction; and an accurate
budget estimate that can be presented with high confidence to the NSF Director, NSB, the
Office of Management and Budget (OMB), and
Congress for consideration for inclusion in a future
“Off-ramps”
NSF budget request.
Projects may be removed from the Preliminary
To satisfy these requirements, the project is
developed to a Preliminary Design 1 level of
maturity. Results of this development are reflected
in a revised and updated PEP.2 Components of the
updated PEP that deserve particular emphasis at
this stage include:
•

Update of the project development plan
budget and timeline, with major
anticipated risks in the completion of
design and development activities;

Design Phase by the NSF Director due to:
•
•

•
•
•
•
•
•

Insufficient priority over the long term;
Failure to satisfy milestones or other
criteria defined in the IMP/PEP;
Eclipse by other projects;
Collapse of major external agreements;
Extensive estimated or actual cost
increases;
Significant changes in schedule for design
readiness or eventual construction;
Unexpected technical challenges;
Changes in the research community that
indicate eroding support for the project;
Any other reason that the Director deems
sufficiently well-founded.

•

Refinement of the research objectives and
priorities of the proposed facility;

•

Update of the description of the required
infrastructure, site-specific design, and
definition of interconnections of all major subsystems;

•

Environmental Assessments or Environmental Impact Statement (if applicable);

•

Bottom-up budget and contingency estimates for construction, presented using a Work
Breakdown Structure (WBS) structure and supported by a WBS dictionary defining the
scope of individual elements;

•

Scope management plans that include de-scoping options and scope opportunities that
can be implemented depending upon available contingency levels.

•

NSF utilizes the conventional definition of preliminary design as used by project managers – a site-specific design defining all
major subsystems and their interconnections, a level of design completeness that allows final construction drawings to
proceed, cost estimation based on construction bidding, and bottom-up estimates of cost and contingency. Preliminary design
usually has a specific meaning within a particular industry or discipline, and NSF adopts the definition most appropriate to each
particular project, as defined in the Project Development Plan part of the PEP.

1

2

See Section 3.4 for a description of the PEP.

Section Revision:
November 25, 2016

2.3.2-1

Major Facilities Guide: NSF 19-68 (May 2019)
2.3.2 Preliminary Design Phase
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

•

Updated construction schedule with contingency estimate;

•

Updated Educational Outreach and Broader Societal Impact plan that includes the scope
of work, required budget and schedule to implement the plan, plus the budget and
schedule needed to develop the plan from preliminary design to final design;

•

Implementation of a Project Management Control System (PMCS) 1 and inclusion within
the preliminary design of a resource-loaded schedule;

•

Updated risk analysis, including regulatory issues affecting construction or operation,
and time-dependent factors such as inflation indices, price volatility of commodities,
etc. (The preliminary design budget estimate will be the basis for a future NSF budget
request to Congress if the project successfully emerges from the Preliminary Design
phase. Costs and risks should be projected forward to the anticipated award date for
construction funds.)

•

Demonstration that key technologies are feasible and can be industrialized if required;

•

Plans for management of the project during construction, including preliminary
partnership arrangements and international participation, oversight of major subawards
and contracts, organizational structure and management of change control; 2 and

•

Updated estimates for future operating costs, anticipated future upgrades, or possible
decommissioning costs of the facility at the end of its operating life.

2.3.2.2 Preliminary Design Phase Activities
During the Preliminary Design Phase, the earlier conceptual design evolves into a more mature
plan with respect to the baseline and contingency definitions. The WBS elements and resource
estimates benefit from additional knowledge and planning. Consequently, budget uncertainty
for projected construction is much reduced relative to the earlier conceptual design. At the end
of the Preliminary Design Phase, the resulting total project cost is used to inform the budget
request to Congress. Typically, a significant proportion (often one-third or more) of the total
pre-construction planning budget is expended achieving the preliminary baseline estimate.
Interim reviews 3 during the Preliminary Design Phase will be conducted by NSF as described in
the IMP. This stage culminates in a Preliminary Design Review (PDR), conducted by NSF, to
ensure that all aspects of the project definition and planning are robust. The results of the PDR
are reported by the Facilities Readiness Panel, followed by a recommendation from the CORF to
The PMCS involves both the software tools for development of the project databases and the processes and procedures
needed to organize and manage the project; schedule and optimize project resources; compute and track Earned Value and
evaluate project risk factors; and manage the change process by evaluating the effects of alterations to the baseline on the
project’s planned budget and schedule. See Figure 4.2.2-1 for examples of project controls systems inputs and outputs.

1

These plans are a preliminary, but relatively mature version of the Project Execution Plan that defines how the project will
conduct itself during the construction stage – see Section 3.4.

2

Interim reviews are typically held semi-annually. Exceptions to this, dictated by the needs of a particular project, may be
justified and will be listed in the award terms and conditions.

3

Section Revision:
November 25, 2016

2.3.2-2

Major Facilities Guide: NSF 19-68 (May 2019)
2.3.2 Preliminary Design Phase
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

the Director for decision on forwarding to the NSB for possible inclusion in a future budget
request.
2.3.2.3 Preliminary Design Review (PDR)
NSF conducts a PDR, organized and led by the PO, to assess the robustness of the technical
design and completeness of the budget and construction planning. Like CDR, the review is
organized and conducted by the PO in consultation with the LFO Liaison and G/AO. The PO has
overall responsibility for organizing the review, and throughout the review process acts as the
interface between the NSF and the Recipient. The PO authors the review charge and organizes
the review panel. The LFO Liaison and G/AO strengthens the review process by specifying
language for incorporation within the charge and for aspects of the review agenda pertaining to
project management issues and recommending panelists able to advise NSF in non-science
related areas of the review. Following the review, the PO and the LFO Liaison will each
independently assess the review, confer on areas of concern, share their views, and report their
observations through their respective supervisory chains – the PO via the administrative
structure of the Sponsoring Organization and the LFO Liaison via the HLFO.
The review scrutinizes the effectiveness of project management through this phase of
development, as well as plans for completion of final design and eventual construction and
operation. The PDR may utilize, as appropriate, external experts, consultants and outside firms
to evaluate proposed plans and budgets. The PDR also examines the management structure
and credentials of key staff to assure NSF that an appropriately skilled management
organization is ready to complete final design activities and execute the construction phase of
the project.
Once the project has satisfied any recommendations made by NSF as a result of external
review, and resolved any outstanding issues, the Directorate recommends to the Facilities
Readiness Panel that the project is ready for advancement to the Final Design Phase of
development and is a candidate for NSB authorization for inclusion in a future NSF budget
request for construction funding. At any time, the Facilities Readiness Panel or the OD may
request further external review.
Following the PDR, the PO updates the IMP to describe proposed plans for budgeting and
oversight, and to finalize commitments from interagency and international partners during final
design. The PO directs the Recipient to update the Project Development Plan (PEP-3.1) to lay
out the work scope, budget and schedule necessary to bring the project to Final Design.
Immediately following the PDR, the second, more detailed NSF Cost Analysis will be initiated
and conducted jointly with key assurance members of the IPT; namely the Division of
Acquisition and Cooperative Support (DACS), the DIAS, and the LFO. The Cost Analysis will be
conducted following NSF internal operating guidance. Guidance to the Recipient on

Section Revision:
November 25, 2016

2.3.2-3

Major Facilities Guide: NSF 19-68 (May 2019)
2.3.2 Preliminary Design Phase
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

refinements to the Cost Book will be provided as necessary in preparation for the Final Design
Phase.
The completion of project planning and development, culminating in a Final Design, should be
aligned with the expected time-scale for requesting and appropriating construction funds. The
NSF Budget Office is the coordinator for this critical planning activity, bringing projects forward
for construction only if OMB and Congress are likely to approve the request and appropriation
of funds within the time period in which the Preliminary Design plans and cost estimate remain
valid.
2.3.2.4 Exit from Preliminary Design Phase
A candidate project exits from the Preliminary Design phase and enters the Final Design phase
after the following have been completed:
1. A successful PDR and subsequent support from the Directorate,
2. A review and recommendation by the Facilities Readiness Panel for advancement to the
Final Design Phase,
3. A review and recommendation by the DRB for advancement to the Final Design Phase,
4. The NSF Director approves advancement and recommends to the NSB inclusion of the
project in a future year budget request, and
5. The NSB authorizes inclusion in a future construction budget request.
2.3.2.5 NSF Director’s Recommendation for Advancement to Final Design
The Facilities Readiness Panel and the Director should first be satisfied that the following
conditions have been met before making a recommendation to the NSB for authorization:
•

The AD of the sponsoring Directorate continues to assert the high scientific merit and
importance of the project and has a sound financial plan for supporting the remaining
pre-construction planning activities and the future operations and use of the facility.

•

The Preliminary Design has been successfully reviewed internally and by an external
panel of experts in order to obtain the best possible objective advice from authorities in
the fields and disciplines utilized by the project.

•

The Facilities Readiness Panel concurs that the Preliminary Design is reasonable and
poses an acceptable level of risk, and that anticipated costs for construction and
operation are sufficiently well known.

•

An appropriate Integrated Project Team (IPT) is in place and has provided assurance that
the Preliminary Design total project cost has been satisfactorily analyzed at a high
degree of confidence to support the budget request.

•

The NSF Director is satisfied that external participation in all phases of the project (other
agencies, international and/or private sector entities, etc.) is well planned.

•

Updated IMP and PEP have been reviewed and commented on by the IPT.

Section Revision:
November 25, 2016

2.3.2-4

Major Facilities Guide: NSF 19-68 (May 2019)
2.3.2 Preliminary Design Phase
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

2.3.2.6 National Science Board Authorization
The final steps for exit from the Preliminary Design Phase are review and authorization by the
NSB for advancement into the Final Design phase and inclusion in a request to the OMB for
future year funding.
The Sponsoring Organization is responsible for preparing the documentation needed for the
NSB to review and authorize a proposed major facility project for advancement to Final Design
and inclusion in a future budget request.1 Prior to NSB submission, the Director’s Review Board
(DRB) 2 reviews the completeness and appropriateness of the documentation supporting
advancement of the project (such as prior phase reviews, committee evaluations, PEP
evaluation and reviewed proposal ratings) to ensure adherence to NSF processes and policies.
As NSB considers projects for advancement to Final Design, NSF makes available to the NSB,
upon request, the PEP and IMP, and the reviews from the community, the Major Facilities
Working Group, the LFO, the Facilities Readiness Panel and other relevant parties. The NSB
considers the following elements, applying primarily the third ranking criteria identified in
Appendix A, as appropriate:
•
•
•
•
•

The priority of the project in advancing NSF’s strategic goals;
The research and science enabled by the proposed facility;
Construction readiness and risks to the agency;
Budget justification for construction and operation of the facility; and
The likelihood that funding will be available in the next few years.

As with all NSF proposals, the quality of the Intellectual Merit and Broader Impact activities,
including educational outreach, plays an important role in funding decisions. If NSB authorizes a
project for future-year funding, it specifies its priority among all projects in the approved
stage. 3 If a project is not approved, or if an approved project’s plans are no longer deemed to
be clearly and fully construction-ready, NSB will remand that project to the Preliminary Design
phase for further work or recommend that the project be terminated.
2.3.2.7 Inclusion in an NSF Budget Request
Each year, the NSF Director proposes, in priority order, the NSB-authorized construction-ready
projects for the MREFC Account. If an MREFC “new start” is approved for inclusion in the
President’s Budget Request to Congress, then Congress may ask for additional information

1

NSF Proposal and Award Manual (PAM) and internal operating guidance documents provide guidance on the DRB package.

2

See Section 2 and Section 2.1.6 on Roles and Responsibilities.

The Board assigns the very highest priority to projects that are under construction. There is no priority among active projects;
they should all move forward at a suitable pace.

3

Section Revision:
November 25, 2016

2.3.2-5

Major Facilities Guide: NSF 19-68 (May 2019)
2.3.2 Preliminary Design Phase
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

through formal hearings and/or informal briefings. Once Congress passes an appropriations act
for NSF and the President signs it into law, NSF may then obligate funds.

Section Revision:
November 25, 2016

2.3.2-6

Major Facilities Guide: NSF 19-68 (May 2019)
2.3.3 Final Design Phase
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Final Design Phase
2.3.3.1 Introduction – Final Design Phase
The goal of the Final Design Phase is to meet the requirements necessary to advance the
proposed project to the subsequent Construction Stage. Budgetary and administrative
requirements for entry include NSF review and approval of the project’s preliminary design as
described in the PEP, and NSB authorization to include the project in a future NSF budget
request.
Technical requirements include:
•

Delivery of designs, specifications and work scope that can be placed for bid to industry;

•

Refined bottom-up cost estimates and contingency estimates;

•

Implementation of a PMCS for project technical and financial status reporting, including
Earned Value Management Systems (EVMS);

•

Completion of recruitment of key staff and cost account managers needed to undertake
construction of the project;

•

Industrialization of key technologies needed for construction;

•

Finalization of commitments with interagency and international partners; and

•

Submission to NSF of a PEP 1 for construction.

Successful exit occurs after the following steps are completed:
1. Successful review of the final design baseline including any receipt of bids;
2. Joint review by the DRB/Facilities Readiness Panel;
3. NSB review and authorization for the NSF Director to obligate construction funds; and
4. Final negotiation of the terms and conditions of the award instrument for the activities
in conformance with the final baseline.
2.3.3.2 Final Design Review (FDR)
Projects should continue to receive pre-construction development funds in order to produce a
Final Design, which includes the following elements:

1

•

A final construction-ready design;

•

Tools and technologies needed to construct the project;

•

A project management plan describing governance of the project, configuration control
plans, EVMS, and plans for reporting technical and financial status, managing subRecipients and working with interagency and international partners;

Refer to Section 3.4 for details of the PEP.

Section Revision:
May 30, 2019

2.3.3-1

Major Facilities Guide: NSF 19-68 (May 2019)
2.3.3 Final Design Phase
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

•

A fully implemented PMCS, including a final version of the resource-loaded schedule and
mechanisms for the project to generate reports – using an NSF verified Earned Value
Management System (EVMS) 1 – on a monthly basis and use them as a management
tool. Path dependencies, schedule float, and critical path are defined;

•

The scope of work captured in detailed WBS format, accompanied by a WBS dictionary
defining the scope of all entries, and a scope management plan including potential
descope options and scope opportunities;

•

Updated budget and schedule, with their respective contingencies, including detailed
risk analysis and methodology, presented in the detailed WBS format;

•

An updated Educational Outreach and Broader Societal Impact plan (including the scope
of work, budget and schedule) that also includes the capital investment required to
meet the needs of the proposed Educational Outreach and Broader Societal Impact
plan;

•

An appropriate proportion of the budget based on externally provided information such
as vendor estimates or quotes, publicly available supplier prices, and the like;

•

All necessary partnership agreements and MOUs;

•

Fit-up and installation details of major components and commissioning strategy;

•

Plans for Quality Assurance and Safety Management, integrated into the resourceloaded schedule;

•

Updated operating cost estimates; and

•

Certification that all of the pre-construction planning topics, including those listed in
Section 3, are fully complete and determined to be adequate.

The PO is responsible for organizing and leading the FDR. The review is conducted according to
the same standards and with the same respective roles for the PO and LFO Liaison as described
previously for the CDR and PDR.
The scope of the FDR includes assessment of the technical and project-management
components of the proposed project. A review panel may provide an objective view of the
project and a critical evaluation of the plans and risks embodied in the proposed program as
the schedule permits. In consultation with the IPT, the IMP should continue to be assessed
annually by the Program Officer and updated as required to ensure that the underlying
assumptions about the project remain valid. If construction funds fail to be appropriated as
planned, the NSF Director may choose to mandate annual project status reviews to assure NSF
of the continued viability of the project’s plan and budget for construction.

During construction, progress must be tracked and measured using an Earned Value Management System based on EIA-478
criteria (OMB A-11 Capital Programming Guide (2016)). This requirement applies to the award Recipient who acts as a prime
contractor. Secondary contractors to the award Recipient are not required to follow formal EVMS, but must be able to provide
the appropriate inputs to the prime for EV reporting.

1

Section Revision:
May 30, 2019

2.3.3-2

Major Facilities Guide: NSF 19-68 (May 2019)
2.3.3 Final Design Phase
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Following the review, the PO and the LFO Liaison will each independently assess the review,
confer on areas of concern, share their views, and report their observations through their
respective supervisory chains.
In the event the project’s construction plans are determined to be inconsistent with the
pending budget request, NSF will undertake remedial action. Should remedial action be
necessary following the review, the sponsoring Directorate recommends this to the OD after
consultation with the IPT, internal deliberation, and if appropriate, consultation with the
Facilities Readiness Panel. Remedial action may include, for example, revision of the project’s
budget, scope, and/or schedule, or withdrawal of NSF’s request for construction funding (off
ramp).
2.3.3.3 Exit from the Final Design Phase
Following a successful review of the final design baseline, the Director recommends to NSB that
it authorize construction award(s). NSB reviews the recommendation and authorizes the
making of the award(s). Following the Director’s approval, an award instrument, a Cooperative
Agreement or a contract agreement, between NSF and the Recipient(s) is negotiated, and
construction activities begin in conformance with the negotiated Performance Measurement
Baseline (PMB).
As part of NSF’s final negotiation of the award instrument, the award-level NSF Cost Analysis
will be initiated and conducted jointly with key assurance members of the IPT; namely the
Division of Acquisition and Cooperative Support (DACS), DIAS, and the LFO. The analysis will
encompass such things as negotiated subawards and contracts associated with initiating
construction and negotiation of final indirect cost and labor rates. The Cost Analysis will be
conducted following NSF internal guidelines. Questions about the Cost Analysis should be
directed to the PO and/or the relevant G/AO or CO.
The NSB authorized Total Project Cost (TPC) following the Final Design Review (FDR) establishes
the not-to-exceed cost under NSF’s “No Cost Overrun” policy. Section 4.2.5.2 describes NSF
practices to meet this policy.

Section Revision:
May 30, 2019

2.3.3-3

Major Facilities Guide: NSF 19-68 (May 2019)
2.4.1 Construction Award Management and Oversight
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

2.4

CONSTRUCTION STAGE
Construction Award Management and Oversight

After Congress appropriates funds for the project, NSF proceeds to award the cooperative
agreements (CAs) or contracts for construction, acquisition, and commissioning of the facility.
The policies and procedures in the publicly available NSF Proposal and Awards Policy and
Procedures Guide, apply to major facility projects awarded under a cooperative agreement.
Questions about the internal guidance that covers details of the internal award process from
proposal generation through merit review, DRB and NSB reviews, and final award should be
directed to the PO. The Recipient(s) provides periodic financial and technical status reports to
NSF according to the terms and conditions of the CA or contract. The project is subjected to
periodic post-award reviews that may examine any or all of the following topics: technical
performance, cost, schedule, and management performance. These reviews are typically held
at the facility and are conducted at least annually. More frequent reviews may take be
scheduled based on the project’s expenditure rate or due to any other technical or
management issues that arise.
NSF selects the annual review panel members who are typically external experts covering all
aspects of the project, and assess technical progress, cost, schedule, and management
performance. These panels report directly to NSF and provide advice on project direction and
any needed changes. The reviews are organized and conducted by the PO in consultation with
the LFO Liaison and G/AO. The PO has overall responsibility for organizing the review, and
throughout the review process acts as the interface between the NSF and the Recipient. The PO
authors the review charge and organizes the review panel. The LFO Liaison and G/AO
strengthens the review process by specifying language for incorporation within the charge and
for aspects of the review agenda pertaining to project management issues and recommending
panelists able to advise NSF in non-science related areas of the review. (Note: Many projects
invite panels of experts to review and advise on project plans and progress. Such panels report
to the Project Director and are not a substitute for NSF-organized external oversight reviews.)
Because panel recommendations are to NSF and not the Recipient, NSF will generally issue
written guidance to the Recipients for subsequent response and action.
Progress against the project plan is provided through the use of formal Earned Value
Management Systems (EVMS), which provide measurement of ongoing project status, including
deviations or variances from the PMB. The results of the EVM reporting and analysis and any
actions taken, are reported to NSF in the monthly progress report. The Recipient should consult
with the PO and GA/O or CO as necessary on the requirements for the monthly progress
reports. Further information is also provided in Sections 4.2.5.8 and 4.6.2 of this Guide.
Generally, when cost and/or schedule performance begins to deviate from plans, change

Section Revision:
November 25, 2016

2.4.1-1

Major Facilities Guide: NSF 19-68 (May 2019)
2.4.1 Construction Award Management and Oversight
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

control is exercised by the project through a Change Control Board (CCB) 1 action, resulting in
modifications to the project’s budget or schedule contingency. It is also normal practice for a
project to update its budget and schedule Estimates to Complete (ETC), which also may result in
PMB changes.
Whenever a project approves a change control action that results in allocating or returning
contingency to the pool of contingency funds, the PMB budget will also change.
Similar change-control actions affect the PMB schedule. They revise the project PMB schedule
and the available schedule contingency or “float” time – that is, the difference between
milestones on the schedule’s critical path and the expected completion dates for activities that
lead to the accomplishment of those milestones.
Modifications to the PMB that are within the defined scope and do not change the total project
duration or Total Project Cost are referred to as “re-planning”. Re-planning may be due to
adjustments or re-organization of the project plan and/or may signify that contingency is being
expended in an expected manner. If the allocations of budget and schedule contingency are
below the budget or schedule thresholds identified in the award instrument (CA or contract
agreement) between NSF and Recipient, the change requests are approved unilaterally by the
project. NSF approval is required when the CCB recommends re-planning change actions that
exceed the budget or schedule thresholds identified in the terms and conditions in the
agreement or contract between NSF and Recipient. Each will have a different threshold for
approval. Approval levels for scope changes are generally outlined in the award instrument.
Minor changes in scope may also fall under re-planning activities. The project maintains a scope
management plan (PEP-4.4) which describes the project process for maintaining control of
scope and outlines scope changes that can be implemented depending upon the project’s
forecast of its ability to complete the project within the approved TPC and duration. The project
can elect to implement minor de-scoping options or to defer scope through the change control
process if it needs to increase the amount of contingency as part of the strategy to prevent
potential cost overruns. It can also elect to implement project enhancements that are within
existing scope of work definitions, following the project change control process and approval
process as set in the award or contract terms and conditions.
It is essential for the project management to respect the project PMB rigorously, maintaining
each adjusted PMB in the project’s database along with the attributed CCB actions. This allows
the project and NSF to systematically track the evolution of the PMB from its initial release
through all subsequent changes.
A CCB comprises the senior project managers responsible for defining the project's resource requirements and allocating or
expending those resources. It typically consists of the Project Director, Project Manager, Business Manager, cost account
managers of principal work breakdown structure elements, chief scientist and engineer, and systems engineer. It may include
other project staff whose authority pertains to the range of activities considered by the Board.

1

Section Revision:
November 25, 2016

2.4.1-2

Major Facilities Guide: NSF 19-68 (May 2019)
2.4.1 Construction Award Management and Oversight
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

“Re-baselining” occurs when the changes involve:
1. Increases in the NSB-authorized TPC,
2. An extension beyond the total project duration, and/or
3. Major changes in scope.
When the proposed changes reach the re-baselining level, the approval process involves NSF
and may involve the NSB. Changes in project end date follow NSF’s No-Cost Extension (NCE)
policies. Major changes in scope should be part of the scope management plan and should
follow the project change control process, including NSF approval; if science goals are
significantly impacted, NSB authorization may also be required. An increase in TPC exceeding 20
percent of the NSB-authorized TPC or $10 million (whichever is less) must be reviewed and
authorized by the NSB following a recommendation by the Director. Prior to requesting
approval to re-baseline, a new external baseline review should be conducted to examine the
nature of the problems encountered, and to determine whether de-scoping should be
exercised per the approved scope management plan (PEP-4.4) or, if not, whether the problems
can be solved by use of budget and/or schedule contingency or other means. Upon review and
approval, scope, cost, and schedule are stabilized, and contingency is adjusted to appropriate
levels.
Whenever significant scope, cost, or schedule increases are foreseen, it is most important that
the LFO Liaison is consulted early, concurs with the PO on the details of the Sponsoring
Organization’s plan, and advises and concurs on details of the external re-baselining review.
Similarly, when there are indications that project cost or schedule contingency will fall below
reasonable standards, 1 the PO should discuss plans for dealing with the variance with the
Project Director. This information should be clearly noted in the monthly status report that
goes to the HLFO. The LFO is a resource for helping to deal with such problems and for helping
to identify steps that can be taken to restore adequate contingency.
In addition to supplying regular status reports required in the terms and conditions of the
award instrument, it is essential that project staff inform the PO and/or the G/AO (or CO) in a
timely manner of major issues or significant changes in project status, such as a potential rebaselining, problems with partnerships, or surprising research and development results. NSF
management, the Chief Officer of Research Facilities, and the NSB should in turn be informed of
such developments by the PO. The primary mechanism for coordinating both the transfer of
information and the coordination of any required actions by NSF is through the NSF Integrated
Project Team (IPT).
On rare occasions, major facility projects under construction may encounter unforeseen
budget, schedule, technical, or programmatic challenges that are of a substantial enough level
1

See details in Section 4.6, Requirements for Performance Oversight, Reviews and Reporting.

Section Revision:
November 25, 2016

2.4.1-3

Major Facilities Guide: NSF 19-68 (May 2019)
2.4.1 Construction Award Management and Oversight
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

to be considered grounds for termination or significant modification to the original project
goals. NSF will provide the NSB with appropriate information and a recommendation by the
Director. The NSB will decide whether termination or significant modification to the original
project goals is warranted. 1

Joint NSB-NSF Management Report: Setting Priorities for Large Facility Projects Supported by the National Science Foundation
(NSB-05-77); September 2005.

1

Section Revision:
November 25, 2016

2.4.1-4

Major Facilities Guide: NSF 19-68 (May 2019)
2.4.2 Construction Award Close-out
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Construction Award Close-out
2.4.2.1 Project Close-out Process
All NSF-funded research awards have final reporting and close-out procedures for the purpose
of ensuring funds have been properly used and to provide the public with information on the
research outcomes (PAM 2017, Chapter XIII). The close-out process for major multi-user
research facility construction awards has the same basic purpose and is governed by the same
NSF policy.
As part of the annual construction review process outlined above in section 2.4.1 Construction
Award Management and Oversight, at an appropriate time approaching or following
construction completion, NSF will conduct a final construction review. This review is intended
to assess the extent to which the required scope was delivered in accordance with the PEP and
award terms and conditions.
The first step in the formal award-close-out process for major multi-user research facility
construction assistance awards is for the Recipient to submit the Final Project Report and
Project Outcomes Report for the General Public per the reporting requirements detailed in the
Proposal and Award Policies & Procedures Guide (PAPPG). The Final Project Report should
clearly map project accomplishments and deliverables to the Programmatic Terms and
Conditions of the Cooperative Agreement and Cooperative Support Agreement and should be
informed by the final construction review. There may be additional close-out reporting
requirements detailed in the governing Cooperative Agreement (CA) or Cooperative Support
Agreement (CSA). It is the Recipient's responsibility to understand and satisfy all close-out
requirements.
The Program Officer reviews these reports and distributes, as appropriate, to other NSF offices
involved in award close-outs such as Office of General Counsel, and the Budget, Finance, and
Awards division. Once the PO is satisfied with the Final Project report as submitted, he/she
formally approves the report by accepting it in eJacket. Following this certification all financial
transactions with Recipient are closed and the award is closed-out.
2.4.2.2 Request for No-Cost Extension
The PO has the authority to recommend approval of the first NSF-Approved No-Cost Extension
(NCE). However, the PO will generally work closely with members of the NSF Integrated Project
Team (IPT) to ensure the request meets the requirements for major facility projects as
described herein. Any subsequent NCE’s must be approved by the Grants and Agreements
Officer (G/AO) or Contracting Officer (CO), who is also a core member of the IPT. As the project
nears completion, close-out activities will become a discussion item for the IPT.

Section Revision:
May 30, 2019

2.4.2-1

Major Facilities Guide: NSF 19-68 (May 2019)
2.4.2 Construction Award Close-out
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Only tasks within the approved project scope may be included in the NCE. As stated in Section
4.2.5, Budget Contingency Planning for the Construction Stage, any unused funds (either
contingency or positive cost variance) must be returned to the agency.
Many intended tasks will already be clearly contained within the approved project scope and
can be directly associated with a particular WBS element. Tasks which cannot be found to fall
within an approved WBS element will be allowed only after they have been reviewed and
approved as new scope through the change and/or configuration control processes contained
in the Project Execution Plan. Depending on the magnitude, this may require very high-level
approvals within the agency. It is highly recommended that the discussion of scope, and the
ability to assign to an approved WBS element, takes place prior to the NCE request.
Good practice suggests that all other project tasks, i.e. those not included in the NCE request,
should be closed out by the original award end date. This means that all risks and liens for those
tasks are also closed out, and that no funds are carried forward for remediation of problems
that arise in the future. The close-out of completed tasks also allows for a more precise
calculation of remaining cost variance and/or contingency which facilitates good decisions
making on the part of the Project and NSF. If any tasks slated for close-out are not completed
by the original award end date, then NSF must be notified that the tasks will be carried over
into the extension period as part of the NCE request.
It is anticipated that the list of tasks to be performed during the extension may change with
time as final negotiations and decisions are made and actual costs are realized. Some tasks may
be held back and subsequently removed as scope contingency options when available
resources or priorities change. Other tasks within the approved scope of the project may be
added (for example, as a result of a reprioritization exercise following final acceptance reviews
or because they are delayed past their close-out dates). Tasks may be added or removed from
the list with adequate justification and with the written approval of NSF. All final close-out
documentation will be saved to the official record by the PO.
Written requests for NCEs should be submitted to the PO and should include the information in
the following list:
1. List of the tasks to be completed during the extension period and justification that they
are within project scope.
a. Link the tasks to the associated WBS element and give a short justification of
how they fit within existing project scope. Risk mitigation effort should be
associated with an identified and documented risk element.
b. Provide the total burdened estimated cost for each task. Detailed cost estimates
do not have to be provided, but should be documented and available if
requested.
c. The justification for each task will typically fall into one or more of several
categories: (1) open purchase orders and invoices associated with items whose
Section Revision:
May 30, 2019

2.4.2-2

Major Facilities Guide: NSF 19-68 (May 2019)
2.4.2 Construction Award Close-out
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

delivery is delayed beyond the current period of performance, for example due
to subcontractor performance, (2) rework of existing tasks within the approved
scope, for example due to workmanship or performance issues, (3) existing tasks
within the approved scope that have not yet been completed, and (4) risk
mitigation to address in-scope performance issues. An example of a task list with
justifications is given in the sample Table 2.4.2-1 on the following page.
2. Indication of which tasks provide de-scoping options 1 if resources (time, staff, budget,
etc.) become limited. Briefly indicate why each task is a candidate for de-scoping and
give any deadlines for exercising the de-scope option. NSF must be notified when and if
the scope contingency option is taken and tasks are removed from scope, including the
impact on project deliverables or performance, if relevant.
3. Description of what funds will be used to cover the proposed tasks – remaining
contingency, unexpended PMB budget, positive Cost Variance, partner funds, etc. Give
the project PMB ETC with all tasks included and compare to remaining contingency and
TPC. State a confidence level for completing all work within budget, including the use of
any scope contingency options. Indicate if any tasks involve already obligated funds and
give the amount of those funds.
4. Summary schedule or schedule highlights of the extended tasks, including significant
milestones and the new project end date. Provide (BOE) for the new project end date,
including schedule contingency, and give a confidence level for completing by that date.

1

Scope contingency and management is defined in Section 6.2.3.

Section Revision:
May 30, 2019

2.4.2-3

Major Facilities Guide: NSF 19-68 (May 2019)
2.4.2 Construction Award Close-out
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)
Table 2.4.2-1
Task #

Sample of a No-Cost Extension Tasks Table
Burdened
Subtotals ($K) WBS

Task Description

Justification

1

Modifications to electronics
control boards

40.5

3.7
Environmental
Systems ADCs

Rework of existing in-scope
task; technology not
performing as intended

2

Delivery of 3 cryo-pumps

114.9

4.2 Vacuum
Systems

Existing in-scope task; Late
delivery on open contract with
obligated funds

3

General purpose utility carts

25.8

2.4.5 Monitoring
and Maintenance
Equipment

Existing in-scope task; Late
delivery; 1 unit added based
on revised needs estimate

4

Vendor contract to test
relationship of performance
versus temperature on
sample size widgets

32.4

5.2.3 Sys Eng:
Integrated
testing

Risk mitigation added to
address in-scope performance
issues for integrated systems.
Risk Register ID #14-31.

5

Labor extensions for project
management and business
offices

184.2

1.2 Project
Controls

Existing in-scope task; revised
effort, salary, and overhead
estimates, including escalation

TOTAL ($K)

Section Revision:
May 30, 2019

$397.8

2.4.2-4

Major Facilities Guide: NSF 19-68 (May 2019)
2.5.1 Operations Management and Oversight
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

2.5

OPERATIONS STAGE
Operations Management and Oversight

Although NSF does not directly manage the operations of the facilities it supports (with the
exception of Arctic and Antarctic activities), the agency engages in oversight and assurance of
facility awards during each stage of the facility’s life cycle. In oversight, NSF employs a teamoriented approach in which scientific and engineering staff work closely with business
operations staff. Additional detail on facility operations may be found in Section 3.5 of this
Guide 1 and among the special topics found in Section 4, Key Management Principles and
Requirements for Major Facilities.
The Recipient responsible for construction or acquisition of a new facility is normally the entity
that submits a proposal for operation of the facility during the construction stage. However, the
Operations Stage may be managed by a different entity, depending on circumstances stated in
the IMP.
The operations proposal is merit-reviewed following NSF’s guidelines. Operations activities are
funded through NSF’s R&RA and/or Education and Human Resources (EHR) account. Testing
and acceptance, user training and engineering studies occur as the facility transitions to full
operation. Operations include the day-to-day work required to: support and conduct research
and education activities; ensure that the facility is operating efficiently and cost-effectively; and
provide small- and intermediate-scale technical enhancements when needed to maintain stateof-the-art research capabilities.
The content of the operations proposal will be adapted to the specific nature of the facility, but
at a minimum it should be compatible with the Concept of Operations Plan (PEP-15.3)
established during construction and include:

1

•

A detailed bottom-up cost estimate for operations per Section 4.2 of this Guide.

•

A detailed description of how the operation of the facility will be managed, including the
roles of key staff and use of advisory committees. This could be included as part of the
proposal text or a separate Operations Plan.

•

Description of plan for education and outreach.

•

Description of research program supported through operations, if applicable.

•

A listing of which Environmental, Safety and Health (ES&H) standards will be followed by
the Recipient and a description of how adherence to those standards will be verified. A
policy for reporting to the NSF accidents or environmental releases should also be given.
This may be given as a reference to an existing ES&H plan (PEP-13.1) for the project.

•

A listing of which cyber-security standards will be followed by the Recipient and a
description of how adherence to those standards will be verified. A policy for reporting

Further development of these sections is planned for MFG future version.

Section Revision:
May 30, 2019

2.5.1-1

Major Facilities Guide: NSF 19-68 (May 2019)
2.5.1 Operations Management and Oversight
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

to NSF of any breaches of cyber-security should also be given. This may be given as a
reference to an existing Cyber-Security Plan (PEP-12.1) for the project.
•

A discussion of how major overhaul, repair or replacement of long-lived capital assets or
components who useful life extends beyond the duration of the CA will be handled.

•

A discussion and acknowledgement of the current plan for re-competition or
divestment.

•

A set of performance goals and metrics sufficient to establish that the facility is
operating successfully. The Facility’s performance against these metrics will be reported
periodically as required by Program.

•

Discussion on plans or progress toward major upgrades to the Facility to increase
science capabilities.

Given the long operations stage of most major facilities, upgrades and refurbishment of
equipment may be required over time in order to stay at the research frontier. In the case of an
observatory, this may include new instruments and cameras. For a sensor network, it may
include the deployment of additional sensors or renewal of cyber-infrastructure. At an
accelerator facility, the upgrades may take the form of higher energy or luminosity or new
detectors. In general, these upgrades and renewals will be funded from R&RA funds, either
from a portion of the operating funds designed for such purposes or from separate equipment
and instrumentation programs. Funding for more significant upgrades (if they exceed the major
facility threshold) may come from the MREFC account. In that case, the approval process is the
same as that for a new major facility project.
The PO should be closely involved in monitoring and assessing the facility’s evolution and in
supporting advanced R&D planning and budgeting. Evaluation of each NSF major facility, as part
of its yearly operations review, should include a section on the plans for advanced R&D and
should relate these plans to the anticipated evolving mission of the facility. This evaluation
helps guide the PO in formulating a budget strategy for funding advanced R&D efforts.
A Program Officer (PO) may also request a periodic formal Condition Assessment report (an
evaluation of capital assets requiring significant expenditures for periodic replacement or
refurbishment and having a lifetime longer than the usual five-year award cycle), accompanied
by an Asset Management Plan (a strategic plan for dealing with these issues), to inform NSF and
the facility management of anticipated major and infrequent maintenance expenses that cause
a significant departure from the routine funding profile. This allows NSF, as part of its budget
allocation process, to proactively address these issues before they become immediate needs.
Generally speaking, there are three key aspects of NSF oversight and assurance of major facility
operations, which are codified in and required by the CA: (1) Annual Work Plans, (2) Annual
Reports, and (3) annual operations reviews. NSF or the cognizant agency may also conduct
periodic audits or Business Systems Reviews.

Section Revision:
May 30, 2019

2.5.1-2

Major Facilities Guide: NSF 19-68 (May 2019)
2.5.1 Operations Management and Oversight
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Annual Work Plan
The Annual Work Plan (AWP) describes what the facility expects to accomplish in the coming
fiscal year. For many facilities, the AWP, annual operations proposal, and Cost Estimating Plan
(per Sections 4.2.2 and 4.2.4) can be combined as one document, so long as all elements are
addressed. The AWP should include a series of high level performance goals (clear and agreed
upon goals and objectives, performance metrics and, where appropriate, performance targets)
for the coming year. The goals should include both scientific and operations issues (i.e.,
installation of new equipment or commissioning of new buildings, maintenance, Education and
Oversight Training and ES&H). The goals and metrics will naturally vary from facility to facility
and should be agreed upon between the Recipient and the NSF Program Officer (PO). The PO
will review the AWP goals to ensure they are aligned with the long-term scientific objectives of
the facility.
It is the Recipient’s responsibility to manage and maintain the NSF-funded facilities, equipment,
and instrumentation used in the conduct research regardless of ownership. See Section 6.6 of
this Guide. In accordance with federal guidance 1 on property that the government owns,
leases, or otherwise manages, Recipients should annually provide a brief discussion, cost
estimate, and actual expenditures at a high level for the following:
•

Recurring routine maintenance and repair.

•

Significant infrastructure changes, including modernization, overhaul, upgrade,
replacement, and/or expansion for science facilities, equipment, utilities, and/or
instrumentation.

•

Utilities (including facility operation and purchase of energy)

•

General support services (such as grounds and waste management).

Annual Report
The annual report describes in detail the activities of the facility in the previous year based on
the award date and the award terms and conditions. This report is required by NSF policy (see
PAPPG) and necessary to review progress on that year’s performance goals as described in the
AWP. Due to changing research priorities or external forces not all performance goals may be
met each year but an explanation of progress on each goal should be included. The Recipient
should also report all expenditures relative to the planned budget in accordance with award
terms and conditions. The PO reviews and approves the annual report.
Annual Operations Reviews
In most cases, NSF will annually conduct an operations review of its major facilities, utilizing an
external panel of experts spanning the principal range of functions necessary to sustain facility
operations, or carry out or participate in an alternate activity that accomplishes an equivalent
1

41 CFR 102-84 “Annual Real Property Inventory”, GSA Guidance for Real Property Inventory Reporting

Section Revision:
May 30, 2019

2.5.1-3

Major Facilities Guide: NSF 19-68 (May 2019)
2.5.1 Operations Management and Oversight
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

purpose. When NSF partners with other entities to fund operations, the MOU between the
partners defines the process for monitoring: (1) identification and accomplishment of
programmatic goals; (2) fiscal accountability; (3) stewardship of NSF assets; and (4) compliance
with laws and regulations. Operations reviews should determine the extent to which the facility
is meeting the goals of its Annual Plan, discuss any upcoming challenges for operations, and
highlight good practices that could be applied to other NSF major facilities. Metrics and
performance goals or targets should include objectives related to educational outreach and
broader societal impacts, in addition to research goals of the operating facility. Whenever
possible, the review should be conducted at the facility itself by an external panel comprised of
experts in the operations of similar large scientific facilities and representatives of the user
community served by the facility. The panel should produce a formal written report submitted
to NSF. Results of the review are used by NSF to provide written guidance to the facility
operator in the formulation of goals or targets for the coming year. (The operations review is
not meant to compete with the Business Systems Review 1 (BSR) which looks at business
processes.)
•

•

•

The review is organized and conducted by the PO in consultation with the LFO Liaison
and G/AO. The PO has overall responsibility for organizing the review (or representing
NSF’s interests in the case of a partnership), and for acting as the interface between the
NSF and the project’s proponents throughout the review process. The LFO Liaison and
G/AO advises the PO during the planning and execution of the review to ensure that
there is consistent practice across NSF in the formulation of performance goals, that
goals and objectives are clearly stated and represent quantifiable performance
measures or targets where practical, are periodically reported, and that an evaluation
and feedback mechanism is implemented as an essential part of an ongoing program of
continual performance enhancement.
Following the review, the PO and the LFO Liaison will share their views and confer on
areas of concern. As a result of internal NSF evaluation of the panel report and other
supporting assessments, the NSF Program Officer should issue clear written guidance to
the Recipient for subsequent response and action.
In most cases, observers of the review must include the PO, the G/AO or CO, the LFO
Liaison and other staff from the Large Facilities Office, and possibly other NSF staff from
the Integrated Project Team. Budget considerations, logistical constraints, or alternate
processes for review agreed to by NSF and its funding partners may result in exceptions
to the number and range of NSF staff participating.

See Section 4.6.3.3 for discussion of the BSR process as well as the NSF BSR Guide. To avoid duplication of effort, the scope of
the BSR is adapted to utilize relevant information stemming from other reviews and audits.

1

Section Revision:
May 30, 2019

2.5.1-4

Major Facilities Guide: NSF 19-68 (May 2019)
2.5.2 Renewal/Recompetition
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Renewal/Recompetition
Most NSF facilities will be operated by a managing organization. Because facility lifetimes are
long (some current facilities have operated in excess of 40 years), recompetition of
management is appropriate at intervals. Whenever practical, NSF seeks to make competitive
renewal awards for operation of major facilities after external merit review. See Section 3.5.2
for procedures for Renewal and Recompetition. The goal of competition is to stimulate new
approaches toward more effective management that may offset any potential for increased
costs, and ideally may achieve some cost savings. Important considerations beyond
performance of current management include how recompetition might affect the scientific
productivity of the facility and the burden it would place on the community. Even in cases
where the existing management has been explicitly and rigorously reviewed and found to be
effective, the benefits of competition may outweigh any short-term disadvantages of
recompetition. The determination of whether to compete the effort is based on the expert
advice of NSF staff and, where applicable, panel review and inputs from the user community of
the facility, and the recommendation should be presented to the NSB for authorization as part
the normal award process.

Section Revision:
June 17, 2015

2.5.2-1

Major Facilities Guide: NSF 19-68 (May 2019)
2.6 Divestment Stage
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

2.6

DIVESTMENT STAGE

To remain at the research frontier and support new facilities, NSF will consider retiring existing
facilities when the science they enable is of a lower strategic priority than science that could be
enabled by alternate use of the funds. Such decisions will be difficult to make, in part because
of the number of stakeholders and interested parties, and will require extensive community
consultation and input, which may come from “blue ribbon” panels, National Academies
committees and professional societies. In some cases in which a facility can continue to be
productive, it may be possible to transfer ownership or stewardship to another agency, a
university or a consortium of universities. It is the responsibility of the Directorates and
Divisions to periodically review their facilities portfolio and to consider which facilities may have
reached an appropriate end of NSF support.
While not part of the annual budgeting process, proposals may be requested to address partial
or full divestment of the facility following the award period, including property divestment,
decommissioning, and disposition costs and other costs related to employee separations.
Periodic reviews of these proposals should create and keep current a plan for the facility’s
divestment and closeout, along with its associated budget liability to inform the longer-term
strategic planning at the NSF Division and Directorate levels.
Guidelines and requirements for creating divestment transition plans are included in Section
3.6, Facility Divestment Plan of this Guide. Since divestment strategies and liabilities may
influence construction strategy, a divestment plan is a necessary element (PEP-1.5) for major
facility projects and thus a draft plan should be created early in the Design Stage planning.
When the decision is made to close or transfer ownership or stewardship of a facility, a detailed
transition plan will be developed, which includes all divestment costs and liabilities, including
disposal or transfer of equipment, environmental and site remediation or restoration, pension
and health care responsibilities, etc.

Section Revision:
November 25, 2016

2.6-1

Major Facilities Guide: NSF 19-68 (May 2019)
3.1 Introduction
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

3
3.1

FACILITY LIFE CYCLE MANAGEMENT PLANS FOR MAJOR FACILITIES
INTRODUCTION

Section 3 contains descriptions and guidelines for creating the plans and documents that NSF
and Recipients use in the management and oversight of major facilities. They include two plans
produced by NSF and three plans that are the product of the facility designers, constructors,
and operators.
The NSF Facility Plan, when requested by NSB, is as described in Section 3.2.
Section 3.3 describes an Internal Management Plan (IMP), the NSF document that captures how
NSF will oversee awards for major facilities throughout the life cycle, from candidate facility
projects in design, through construction and operation, and ultimately, through divestment. An
IMP also provides financial strategies for funding given the budgetary estimates. The created
IMPs are internal NSF documents.
The Project Execution Plan (PEP) is produced by the Recipient to detail how management and
execution of design and construction of a major facility will be accomplished. The PEP advances
in maturity from a rudimentary form required at the Conceptual Design Review to a fully
mature document ready to support construction at the Final Design Review. Section 3.4
provides a list of the required components of a PEP and guidelines for creating those
components.
Operations Plans are addressed in Section 3.5, including timelines for submission and review of
operations proposals from prospective Recipients and guidelines for content of proposals and
plans. Operation Plans cover all aspects of operations, maintenance, upgrades, and research
and education programs. Guidelines are also given for the procedures for renewal or
recompetition of an award for an operating facility.
Guidelines for plans to closeout operations under NSF awards are in Section 3.6, Facility
Divestment Plan, and closeout of NSF funding and oversight of a facility may be accomplished
through various options ranging from transfer to another agency or funding source to
decommissioning and removal of the infrastructure and site restoration.

Section Revision:
November 25, 2016

3.1-1

Major Facilities Guide: NSF 19-68 (May 2019)
3.2 NSF Facility Plan [Reserved]
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

3.2

NSF FACILITY PLAN [RESERVED]

Section Revision:
December 14, 2018

3.2-1

Major Facilities Guide: NSF 19-68 (May 2019)
3.3 NSF Internal Management Plans for the Major Facility Life Cycle
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

3.3

NSF INTERNAL MANAGEMENT PLANS FOR THE MAJOR FACILITY LIFE CYCLE

The Internal Management Plan (IMP) is the primary internal agency document that describes
how NSF will oversee development, construction, operation and eventually divestment. The
requirement to develop an IMP is described in Section 2.3.1 for major facilities. Three primary
purposes are served by development of an IMP:
•

It defines in specific detail how NSF will conduct oversight of a project;

•

It describes plans for managing NSF-specific risks, and

•

It provides budgetary estimates for developing, constructing and operating the facility,
identifies divestment liabilities, and lays out a strategy for financing these activities as
well as the concomitant NSF oversight requirements.

The IMP should be a living document that is updated at transition points between project life
cycle stages, or as often as needed, to define review criteria, decision points, strategies for
renewal or recompetition, plan for advanced R&D or technology refresh, upgrades, etc.

Section Revision:
December 14, 2018

3.3-1

Major Facilities Guide: NSF 19-68 (May 2019)
3.4.1 Components of a Project Execution Plan
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

3.4

PROJECT EXECUTION PLAN
Components of a Project Execution Plan

Typical components of a construction-ready Project Execution Plan (PEP), common to most
plans for construction of major facilities, are listed in Table 3.4.1-1 below, as an example of the
extensive nature of the pre-construction planning that should be conducted prior to expending
construction funds to execute the project. While many of the listed topics cannot be
substantively addressed at the earliest stage of project planning, it is important that project
advocates are aware, at the outset, of the full scope of pre-construction planning activities that
should be undertaken, and the consequent pre-resources required. As the project matures
through Conceptual Design, Preliminary and Final Design, these topics become correspondingly
better defined. Some topics will continue to be refined during the construction phase (for
example, Commissioning Plans - Integration and Testing, Operational Readiness, and Concept of
Operations).
The PEP should ideally contain or reference all project related documents and be the
standalone source explaining how and why the project meets all requirements and should
proceed as planned. Various components of the PEP may often be detailed in separate
documents, especially, living documents for future operations such as cybersecurity and data
management plans. The PEP should reference these separate documents to summarize the
complete scope of the pre-construction planning. In addition to referencing these separate
plans, the PEP should provide a high-level summary, outline the associated goals, and/or
identified responsibility for the specific plan.
It is important for PEP to document all assumptions and boundary conditions driving project
design and implementation. Additions or alterations to the typical PEP components listed below
are likely, due to the unique nature of each specific project. Any special construction elements
should be identified and addressed in the PEP or a separate document such as the work
breakdown structure dictionary or design requirements, drawings, and specification
documents.
The PEP at the end of the Final Design Phase is incorporated as part of the construction award
through reference to define the award scope, schedule, configuration and contingency control,
and project governance.

Section Revision:
May 30, 2019

3.4.1-1

Major Facilities Guide: NSF 19-68 (May 2019)
3.4.1 Components of a Project Execution Plan
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)
Table 3.4.1-1

List of the Typical Components of a Project Execution Plan, with Sub-Topics and Descriptions

Component

Sub-Topics

Description of Sub-Section Requirements

1. Introduction

1.1 Scientific Objectives

Description of the research objectives motivating the facility
proposal.

1. Introduction

1.2 Scientific
Requirements

Comprehensive statement of the Requirements Matrix/ Key
Science Requirements to be fulfilled by the proposed facility
(to the extent possible identifying minimum essential as well
as desirable quantitative requirements), which provide a
basis for determining the scope of the associated
infrastructure requirements.

1. Introduction

1.3 Facility /
Infrastructure

Description of the infrastructure necessary to obtain the
research and education objectives.

1. Introduction

1.4 Scientific & Broader
Societal Impacts

Description of the Broader Societal Impacts associated with
the purpose of the facility, including the scope of work,
budget and schedule related to science community or
society related actions or interactions.

1.5 Facility Divestment
Plan

Description of plans and estimate of divestment liabilities at
the end of facility life for transfer, demolition, site
remediation, decontamination, etc., where appropriate.

2. Organization

2.1 Internal
Governance &
Organization and
Communication

Internal Project Governance and Organization Structure with
clear lines of authority, responsibility, and communication
between Internal and institutional governance and oversight
and advisory committees.

2. Organization

2.2 External
Organization and
Communication

External Project Organizational Structure and Governance,
showing clear lines of authority, responsibility, and
communication between NSF, any partners, and the
Recipient.

2. Organization

2.3 Partnerships

Role of interagency or international partners in future
planning and development and/or construction. Plans,
agreements, and commitments for interagency and
international partnerships. Description of the project’s
stakeholders and their roles, responsibilities and meeting
schedules.

2. Organization

2.4 Roles and
Responsibilities

Roles and Responsibilities of key project personnel and
governance groups.

2. Organization

2.5 Community
Relations and Outreach

Community Relations and Outreach plans for building and
maintaining effective relationships with the broader
research community that will eventually utilize the facility to
conduct research and with the public. Description of
scientific and educational outreach programs.

3. Design and
Development

3.1 Project
Development Plan

Description of activities that will be undertaken in order to
achieve readiness for construction, such as design,
prototyping, manufacturing process validation, vendor
qualification, modeling and simulation, creation of required
project management plans, forming partnerships, etc.

Section Revision:
May 30, 2019

3.4.1-2

Major Facilities Guide: NSF 19-68 (May 2019)
3.4.1 Components of a Project Execution Plan
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)
Component

Sub-Topics

Description of Sub-Section Requirements

3. Design and
Development

3.2 Development
Budget and Funding
Sources

Estimate of total budget required to perform Design and
Development, including NSF funding and any contributions
from partners and other outside sources.

3. Design and
Development

3.3 Development
Schedule

Schedule of design and development activities and
milestones, at a level of detail appropriate to the maturity
and complexity of the work.

4. Construction
Project Definition

4.1 Summary of Total
Project Definition

Summary at Work Breakdown Structure (WBS) level II of
total construction project scope, cost, and schedule required
to complete the construction or implementation project,
indicating the baseline (pre-award) or Performance
Measurement Baseline (PMB) (post-award) and
contingencies funded by NSF as well as any associated scope
supported by other funding sources.

4. Construction
Project Definition

4.2 Work Breakdown
Structure (WBS)

WBS contains a product-oriented, hierarchical framework
that organizes and defines the total scope of the project into
individual project component that represent work to be
accomplished, aggregating the smallest levels of detail into a
unified project description. The WBS integrates and relates
all project work (cost, schedule and scope) and is used
throughout the project management to identify and monitor
project progress.

4. Construction
Project Definition

4.3 WBS Dictionary

WBS dictionary defining scope of each WBS element,
through all levels.

4. Construction
Project Definition

4.4 Scope Management
Plan and Scope
Contingency

The plan describes how the scope will be defined,
developed, monitored, controlled, and validated, and how
scoping opportunities and descoping options will be
realized. Scope Contingency compiles savings from potential
de-scoping options, with decision points for exercising
options and time-phased cost and schedule.

4. Construction Project Definition

4.5 Cost Estimating
Plan, Executive
Summary, and Baseline
Budget

A plan to establish and communicate how the preparation,
development, review and approval of the estimate will be
completed. An executive summary provides a summary of
the costs at a high level and an overall basis of estimate.

4. Construction
Project Definition

4.6 Budget Contingency

Contingency budget and description of method for
calculating contingency, including confidence level for
completing within budget.

4. Construction
Project Definition

4.7 Cost Book, Cost
Model Data Set, and
Basis of Estimate

The Cost Book is the comprehensive and well-documented
compilation of Cost Book Sheets for the total project cost.
The cost model data set is used as input to software tools
and/or project reports to organize, correlate, and calculate
different project management information. The Basis of
Estimate provides supporting documentation outlining the
details used in establishing project estimates such as
assumptions, constraints, and estimating methods, and
referencing the technical information used.

Section Revision:
May 30, 2019

3.4.1-3

Major Facilities Guide: NSF 19-68 (May 2019)
3.4.1 Components of a Project Execution Plan
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)
Component

Sub-Topics

Description of Sub-Section Requirements

4. Construction
Project Definition

4.8 Funding Profile

Show the proposed NSF Funding Profile by year with
baseline commitment and anticipated contingency
allocation profiles. Also provide a total funding profile from
all sources if applicable.

4. Construction
Project Definition

4.9 Baseline Schedule
Estimating Plan and
Integrated Schedule

Schedule (without contingency) for the overall project and
each major subsystem, including system integration,
commissioning, acceptance, testing and transition activities;
as well as major milestones and milestones for reviews,
critical decisions and deliverables. It uses formal scheduling
programs, is based on the WBS hierarchy, and is resourceloaded before the construction/implementation stage.
Baseline schedule does not include schedule contingency.

4. Construction
Project Definition

4.10 Schedule
Contingency

Schedule contingency amounts and project end date with
contingency; state method of calculating contingency,
including confidence level for meeting project end date.

5. Staffing

5.1 Staffing Plan

Staffing FTE plan, per NSF and other project-specific job
categories, over time. Application of indirect cost rates must
be articulated in Cost Estimating Plan (CEP) and Basis of
Estimate (BOE) per Section 4.2 of this Guide.

5. Staffing

5.2 Hiring and Staff
Transition Plan

Schedule and requirements for hiring and training staff,
including timelines for increasing or decreasing staffing
levels. Required qualifications for key staff.

6. Risk and
Opportunity Mgt

6.1 Risk Management
Plan

Risk Management Plan describes the methodology/process
for identifying, ranking, analyzing, tracking, controlling, and
mitigating risks. Describes both qualitative assessment and
quantitative analysis methods.

6. Risk and
Opportunity Mgt

6.2 Risk Register

A tracking document or tool that provides a ranked list of
identified risks, with risk impact analysis and prioritization,
responsibilities, mitigation plans and opportunities of risk
reduction, and risk status over time. Documents data and
assumptions used in risk analysis.

6. Risk and
Opportunity Mgt

6.3 Contingency
Management Plan

Contingency management plans and approval process using
change control. Describe NSF approval requirements per
cooperative agreements (CAs).

7. Systems
Engineering

7.1 Systems
Engineering Plan

Systems Engineering Management Plan; roles and
responsibilities.

7. Systems
Engineering

7.2 Systems
Engineering
Requirements

System-level design and technical feasibility study, including
definition of all functional requirements and major systems.
Identifies all technical design requirements, drawings, and
specifications.

7. Systems
Engineering

7.3 Interface
Management Plan

Identification of interfaces between major components or
WBS elements and plans for managing communication,
interferences, and interactions. Interface Management Plan
and Documentation.

7. Systems
Engineering

7. 4 QA/QC Plans

Quality assurance and quality control requirements and
description of processes.

Section Revision:
May 30, 2019

3.4.1-4

Major Facilities Guide: NSF 19-68 (May 2019)
3.4.1 Components of a Project Execution Plan
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)
Component

Sub-Topics

Description of Sub-Section Requirements

8. Configuration
Control

8.1 Configuration
Control Plan

Configuration Control plans.

8. Configuration
Control

8.2 Change Control Plan

Change Control Plan to manage accounting changes and
changes in the baseline or PMB plan: changes in scope,
modifications to budget or schedule, and movement of
contingencies into or out of the PMB. Includes approval and
documentation processes plus roles and responsibilities.

8. Configuration
Control

8.3 Document Control
Plan

Document Control Plan for managing version control, access,
and archiving of project related documentation.

9. Acquisitions

9.1 Acquisition Plans

Describe acquisition plans, processes, subawards, and
contracting strategy. Provide a time-based list of acquisitions
and procurement actions.

9. Acquisitions

9.2 Acquisition
Approval Process

Describe the approval process for acquisitions (NSF,
internal), and create a year by year Acquisition Plan of
actions that are estimated to require NSF approval.

10. Project Mgt.
Controls

10.1 Project Management Control Plan

Description of the project management organization and
processes.

10. Project Mgt.
Controls

10.2 Earned Value
Management System
(EVMS) Plan

Description of the EVMS plans, processes, software, and
tools.

10. Project Mgt.
Controls

10.3 Financial and
Business Controls

Description of Financial and Business processes and controls.

11. Site and
Environment

11.1 Site Selection

Site selection criteria and description of selected site(s).

11. Site and
Environment

11.2 Environmental
Aspects

List need for any Environmental Impact Statements,
permitting, site assessments, etc.

12. CyberInfrastructure

12.1 Cybersecurity Plan

Plan for protecting access, confidentiality, and integrity of
key information assets of the facility.

12. CyberInfrastructure

12.2 Code Development
Plan

Plan to enable critical scientific/engineering capabilities and
data flows within the facility as well as interoperability with
key external collaborators or stakeholders.

12. CyberInfrastructure

12.3 Data Management
Plan

Plans for acquisition and integration of equipment or
services from third parties.

13. Environmental,
Safety and Health

13.1 Environmental,
Safety and Health Plans

Environmental, Safety and Health plans (ES&H).

14. Review and
Reporting

14.1 Reporting
Requirements

Statement of reporting requirements, including notifications
for specific events and periodic reports on progress and
project technical and financial status per NSF contractual
requirements or CAs.

14. Review and
Reporting

14.2 Audits and
Reviews

Statement of the required and proposed reviews, audits,
and assessments for progressing during project life cycle
through project close-out.

Section Revision:
May 30, 2019

3.4.1-5

Major Facilities Guide: NSF 19-68 (May 2019)
3.4.1 Components of a Project Execution Plan
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)
Component

Sub-Topics

Description of Sub-Section Requirements

15. Commissioning

15.1 Integration and
Testing Plan

Describes the acceptance criteria and technical activities
that should be completed as part of construction to
transition the facility to operations.

15.2 Operational
Readiness Plan

Plan for determining operational readiness; includes
administrative (non-technical) acceptance procedures to
transition the facility from construction to operations such
as conducting the operational readiness review and the
authorities for making the determination(s).

15.3 Concept of
Operations Plan

Plans for, and estimate of, annual operations and
maintenance costs (staffing, services, material/supplies, etc.)
and funding sources that will be needed when the facility
has completed construction and is transitioned to
operations. This plan should include activities to bring the
facility to full science capability after acceptance.

15.4 Segregation of
Funding Plan

Financial accounting procedures for the Recipient to
properly expense the activities between construction and
operations funding per the Plans above.

16.1 Project Close-out
Plan

Procedures and criteria for closing out the project. Includes
acceptance of verification of technical performance as well
as documented completion of all scope contained in the
WBS dictionary. Includes procedures documentation for
closing out all acquisitions and financial accounting.

16. Project
Close-out

Section Revision:
May 30, 2019

3.4.1-6

Major Facilities Guide: NSF 19-68 (May 2019)
3.4.2 Detailed Guidelines for Project Execution Plans
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Detailed Guidelines for Project Execution Plans
This section elaborates on the various components outlined in the previous section,
Components of a Project Execution Plan, and offers additional information that should be
helpful to individuals newly involved in planning for construction and future operations. Each of
the sub-sections below are aligned to the PEP Components identified in Section 3.4.1 and
provides some cross-reference to other sections of this Guide.
3.4.2.1 Introduction [Reserved]
3.4.2.2 Organization [Reserved]
3.4.2.3 Design and Development [Reserved]
3.4.2.4 Construction Project Definition
Refer to Section 4.2.2.1 for guidance on the cost estimating plan (CEP). The cost estimate
should include an executive summary of the estimate, including narrative, figures, and tables
per Section 4.2.3.2.
3.4.2.5 Staffing [Reserved]
3.4.2.6 Risk and Opportunity Management
Refer to Section 6.2 for Risk Management Guidelines.
3.4.2.7 Systems Engineering [Reserved]
3.4.2.8 Configuration Control
Refer to Sections 2.4.1, 4.2.5.5, and 4.6.5 regarding changes to the performance measurement
baselines (PMB) and the use of budget and schedule contingency.
3.4.2.9 Acquisitions [Reserved]
3.4.2.10 Project Management Controls
Refer to Sections 4.6.3.6 and 6.8 for more information and guidelines on earned value
management systems (EVMS).
3.4.2.11 Site and Environment [Reserved]
3.4.2.12 Cyber-Infrastructure
Refer to Section 6.3 for guidelines on cybersecurity.

Section Revision:
May 30, 2019

3.4.2-1

Major Facilities Guide: NSF 19-68 (May 2019)
3.4.2 Detailed Guidelines for Project Execution Plans
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

3.4.2.13 Environmental, Safety and Health [Reserved]
3.4.2.14 Review and Reporting
Refer to Sections 4.2.5.8 and 4.6.2 for more information on reporting to NSF.
3.4.2.15 Commissioning
Every major facility has a unique set of systems and subsystems with associated technical
requirements and interfaces, both internal and external to the facility. Technical requirements
and interface control documentation created during project planning and design assist in
defining the inspection and test regimes necessary for commissioning and acceptance of the
facility. Therefore, the systems engineering documentation indicates the timing of and criteria
for the facility’s transition to operations. These principles should be applied to generate four
plans prior to the start of construction.
Transition from construction to operations could be a single acceptance event or multiple
depending on the nature of the project. Many facility projects require integration and testing,
followed by commissioning activities to bring the facility up to the design level of operation.
Depending upon the complexity and time needed to reach design specifications, commissioning
may be split between the construction effort and operations. Commissioning milestones should
be included in the resource-loaded schedule to identify key elements associated with this
transition. The scope of construction activities is defined in the project’s Integration and Testing
Plan (PEP-15.1) and the Operational Readiness Plan (PEP-15.2) and is included in the initial
construction budget request as part of the baseline. The PEP is included by reference in NSF’s
construction cooperative agreement (CA) or contract with the Recipient institution,
documenting the mutual understanding of the work scope funded under construction.
The Integration and Testing Plan is a comprehensive set of prescribed inspections and tests
within the project technical requirements and provides the means for a process of verification,
throughout commissioning activities, that the facility is complete and ready for operations.
Successful completion of all inspections and tests provides validation that the facility meets
technical requirements and therefore passes all acceptance criteria. These tests should be
included as part of the construction baseline and associated activities included in the resource
loaded schedule.
The Operational Readiness Plan defines the process for acceptance at the end of construction
and determining operational readiness. The Plan should include an overview of the acceptance
inspections and tests that verify and validate technical requirements and interfaces to
transition the facility from construction to operations. Verification is the process of checking
that the construction meets specification as defined in the Integration and Testing Plan.
Validation is the process of checking whether the construction meets the scientific objectives.
Administrative acceptance procedures are to identify the authorities, such as project team
members, review team or independent agents, for making the determination(s).
Section Revision:
May 30, 2019

3.4.2-2

Major Facilities Guide: NSF 19-68 (May 2019)
3.4.2 Detailed Guidelines for Project Execution Plans
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

A Concept of Operations Plan (PEP-15.3), also required by the PEP, defines the resources and
funding needs when the facility has completed construction and is transitioned to operations
and is refined during the Construction Stage in preparation for entering the Operation Stage 1.
In some cases, particularly with distributed facility projects, early operations funding begins to
increase as aspects of a facility come on line, although full construction funding may not have
concluded. Although these Stages may overlap in time, the hand-off from construction project
responsibility and funding to operations responsibility and funding must be defined and
managed separately due to segregation of funds requirements (PEP-15.4).
These plans are to be reviewed during conceptual, preliminary, and final design reviews. The
plans are updated as needed during the Construction Stage. At least one year prior to initial
commissioning activities, the plans must be updated and provided to NSF for review.
Commissioning verifies that the substantially complete facility operates over its full range of
capabilities as specified in the final design documents. Once the commissioning planning is
complete, an operations readiness review may be held (either separately or as part of a
Construction Stage review) to examine and comment on the plan. This can be conducted
separately or as a component of one of the required annual reviews. The review is organized
and conducted by the Program Officer (PO) in consultation with the LFO Liaison and Grants and
Agreements Officer (G/AO) similarly to other reviews.
Refer to Sections 3.5 and 4.4 for more information on operations planning and commissioning.
3.4.2.16 Project Close-out Plan
Refer to Section 2.4.2 for more information on project close-out.

1

See Section 3.5 for operations planning guidance.

Section Revision:
May 30, 2019

3.4.2-3

Major Facilities Guide: NSF 19-68 (May 2019)
3.5.1 Preparation of Proposals for Operations and Management
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

3.5

OPERATIONS PLANNING
Preparation of Proposals for Operations and Management

In order to avoid funding gaps, formal proposals to operate a facility should be prepared well in
advance of the anticipated start date for operations: as much as two years prior to the end of
construction and commissioning activities. Program Officers (PO) and Directorates/Offices are
encouraged to take into account the time needed for internal NSF review, including NSB review,
and offer guidance to the community. Estimates of the funds for operations and maintenance
are provided even in the planning stages of a facility. The potential Recipient and/or the PO
need to establish a dialogue with the user community to determine the resources needed to
fully exploit the facility. In addition, the proposal should include:
•

All costs to operate, maintain and periodically upgrade the facility, its instrumentation
and the IT components, including cost and approximate time of investment (Note: A PO
can expect that IT components will need to be upgraded at least every 3 to 5 years);

•

The costs of an in-house research program (as a separate line item in the budget), if
applicable, including an indication of how the overall research program will be managed
and how research program resources will be allocated;

•

Education and outreach plans and costs;

•

A detailed management plan for operations of the facility, including the roles of key
staff and plans for advisory committees.

Note that Section 4.2 provides requirements for cost estimating. The cost estimating plan may
be incorporated in the annual operations plan.
The review of the proposal includes a realistic assessment of the costs to operate and maintain
the facility in a safe and effective manner. The PO is also responsible for oversight of
operational facilities through the various reviews and reports described in the Internal
Management Plan (IMP) and the terms and conditions of the award instrument. In addition to
following the procedures referenced as appropriate to Chapters V and VI of the Proposal and
Award Manual (PAM), the PO considers (with the assistance of external reviewers with
expertise in managing comparably scaled facilities) these questions:
•

Is the facility ready for reliable operations and is the infrastructure (including personnel
requirements) adequate to execute the proposed work plan?

•

Do the operations and maintenance plans allow for optimal utilization of the facility by
users (e.g., scheduled operating time versus down-time)?

•

Is the data management plan in place and ready to support operations?

•

Is there an appropriate balance between in-house research and research of external
users?

•

Are safety (including cyber-security and security of the physical plant), environmental
and health issues, if any, addressed?

Section Revision:
November 25, 2016

3.5.1-1

Major Facilities Guide: NSF 19-68 (May 2019)
3.5.1 Preparation of Proposals for Operations and Management
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

•

Are plans for securing human subjects and/or vertebrate animal clearances included, if
applicable (e.g., assessments of education-related activities)?

•

Are the Educational Outreach and Broader Societal Impact plan and cost reasonable and
include an appropriate strategy to evaluate the outcomes?

•

Have all costs been considered and estimated and is the available funding sufficient, or
is some adjustment needed?

Initial operations awards are generally either a five (5) or ten (10) year duration. Throughout
the operational stage, the Recipient operates and maintains the facility in accordance with the
terms and conditions outlined in the cooperative agreement (CA). The PO, together with the
G/AO, drafts the CA that will govern the operational phase of the project in accordance with
the procedures contained in Chapter VIII of the PAM. The CA will include plans for NSF
oversight, reflect the needs of the facility users, and address how the user program will be
managed and how user time will be allocated. The PO provides oversight for all aspects of
operations, maintenance and the research and education program. The PO also maintains an
awareness of emerging technical, managerial and financial issues through contact with the
facility managers and users, and through oversight, reviews and reports.
Requests for annual funding increments may follow similar review and approval procedures as
initial operations awards depending on the particulars of the Facility and the annual funding
request. For some facilities, the annual report (submitted through FastLane) will constitute the
funding request/proposal for the next year of funding.

Section Revision:
November 25, 2016

3.5.1-2

Major Facilities Guide: NSF 19-68 (May 2019)
3.5.2 Procedures for Renewal or Recompetition of an Operating Major Facility
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Procedures for Renewal or Recompetition of an Operating Major Facility
At least two years prior to the expiration of an award for operations of a facility, 1 the Program
Officer (PO) will plan a review of the results of research and education, the affected
community’s needs, and the facility’s management, including the performance of its managing
organization. The reviews will be used to determine whether to renew the award, upgrade the
facility, recompete the award or terminate operation of the facility. If the reviews show that the
facility is of low priority relative to other funding opportunities within the field(s) of research
served by the facility, or is otherwise not meeting its goals and objectives, the PO, working with
the Division Director (DD) and Assistant Director (AD)/Office Head, will prepare a plan for either
upgrading the facility’s capabilities or divesting/closing out support.
The evaluation of the need for a competition for either a continuing or transitioning facility
should be deliberate and weigh the potential benefits of an effective management against the
tangible and intangible costs of that competition. The review should analyze the costs and
benefits of the facility, taking into consideration the following issues:
•

Given the state of the relevant discipline, community recommendations, overall facility
merit, and programmatic balance, should a major facility be continued, transitioned, or
sunset?

•

Is a change in awardee that could result from a competition feasible?

•

Has NSF program management clearly defined its goals for a possible competition?

•

Does the past performance of the incumbent facility operator, as evaluated by surveys,
review visits, and site audits, warrant a competition?

•

How long has it been since the last management competition?

•

Has NSF identified and evaluated all encumbrances that may create significant obstacles
to changes in the facility management?

•

Is there the potential for a meaningful competition?

•

In addition to the points raised above, are there other facility-specific issues and risks
that could affect the decision and/or timing on undertaking a competition?

Federally Funded Research and Development Centers (FFRDCs) follow a slightly different
process as outlined in the Federal Acquisition Regulations (FAR Part 35.017-4, Reviewing
FFRDCs): An FFRDC review should include the following: (1) an examination of the sponsor's
special technical needs and mission requirements that are performed by the FFRDC to
determine if and at what level they continue to exist; (2) consideration of alternative sources to
meet the sponsor's needs; (3) an assessment of the efficiency and effectiveness of the FFRDC in
meeting the sponsor's needs, including the FFRDC's ability to maintain its objectivity,
The PO should exercise judgment and consider the complexity of the facility in determining whether to begin the review
process earlier.

1

Section Revision:
November 25, 2016

3.5.2-1

Major Facilities Guide: NSF 19-68 (May 2019)
3.5.2 Procedures for Renewal or Recompetition of an Operating Major Facility
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

independence, quick response capability, currency in its field(s) of expertise, and familiarity
with the needs of its sponsor; (4) an assessment of the adequacy of the FFRDC management in
ensuring a cost-effective operation; and (5) a determination that the criteria for establishing the
FFRDC continue to be satisfied and that the sponsoring agreement is in compliance with FAR
35.017-1.
If the reviews show that the facility remains a high priority and has been successful in meeting
its goals and objectives, the Sponsoring Organization considers whether renewal of the
operating agreement with the Recipient institution, or recompetition, is in the best interests of
NSF and the affected community. Awards may be renewed without recompetition or with only
limited competition if there is sufficient justification (e.g., facilities or facility sites with special
features that preclude relocation or recompetition, or partnership-related complexities that
prevent recompetition).
After the appropriate review has been completed, the PO analyzes what can and what needs to
be done in light of the available funding, and recommends one of the following actions:
•

Recompete the award;

•

Renew NSF support;

•

Renew NSF support and plan upgrades to the facility;

•

Renew NSF support to allow operations to transition to self-sufficiency (through, for
example, institutional, industrial or other modes of support);

•

Renew NSF support to allow operations to ramp-down, leading to divestment; or

•

Closeout award, terminate NSF support and divest.

In the event that a decision is made to recompete or to closeout support for a facility, the PO
will give the incumbent Recipient as much notice as possible, but not less than one year, so that
all necessary arrangements to transfer (in the case of unsuccessful recompetition by the
incumbent management entity) or terminate obligations to vendors and employees can be
planned and implemented.
In most cases of recompetition, the managing organization of a facility is required to compete
with other organizations for continuation of the management of the facility and renewal
proposals are received from the Recipient institution and/or from other institutions. The
proposal(s) is (are) merit reviewed in accordance with procedures in Chapters V and VI of the
PAM. The normal thresholds for Director’s Review Board (DRB) and NSB award authorization
apply. 1

Refer to the footnotes in Section 2.1.6 for the National Science Board for award thresholds and properties requiring DRB
recommendation and NSB authorization.

1

Section Revision:
December 14, 2018

3.5.2-2

Major Facilities Guide: NSF 19-68 (May 2019)
3.5.3 Detailed Guidelines for Oversight of Operations
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Detailed Guidelines for Oversight of Operations
Please contact the cognizant NSF program officer for additional details regarding NSF’s
oversight of the operational phase of major facilities. Internal operating guidance elaborates on
the principles outlined in the Major Facilities Guide and offers additional information and
examples that should be especially helpful to individuals newly involved in operational
oversight.

Section Revision:
November 25, 2016

3.5.3-1

Major Facilities Guide: NSF 19-68 (May 2019)
3.6 Facility Divestment Plan
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

3.6

FACILITY DIVESTMENT PLAN

After a decision for divestment is made for the closeout of the facility operation under a NSF
award, the current operations management should start the preparation for the divestment.
The current management should consult stake holders and the program office to appoint
appropriate personnel or management team that will be responsible for managing the
transition activities in the divestment process. The transition team needs to develop a
transition plan and submit to NSF program office. To ensure the smooth and successful
transition, the current operations management should be involved and be an integral part in
the development of the transition plan. The transition plan should first specify the model of
divestment and the final goal of the transition, such as a new operation model under different
funding mechanism, or decommissioning. The following elements should be included in the
plan:
•

Target date for completing the transition;

•

Organizations involved in managing the transition activities

•

Estimated cost of transition, which includes labor and material cost, as well as the
estimated contingency based on the uncertainties and risks

•

Plan for environmental impact analysis;

•

Plan for resolving contractual issues and closing of contracts

•

Any additional costs and responsibilities (e.g., HR and personnel-related costs,
environmental remediation, etc.) associated with divestment/decommissioning should
be noted to the extent possible.”

The plan should identify key steps during the transition period with each step detailed with a
clearly defined goal and target timeline. The plan should identify the organizations that handle
the transition matter at each stage with clearly defined authorities and responsibilities. If the
divestment is accomplished through changing the funding source or a new model of operation,
the transition plan should identify the new management organization and include the following
elements:
•
•
•

Description of the new model of operation and NSF’s role under the new model;
The costs to NSF under the new operation model, and
A hand over procedure to the new management organization.

If the divestment is accomplished through decommissioning, the plan should identify the
equipment or facilities that need to be disposed and include the following elements:
•
•

Cost and procedures for proper disposal of equipment;
Cost and plan for environmental and site remediation.

If there are pension and health care responsibilities after the divestment, the plan should
describe how these responsibilities will be handled and the source of required funding.

Section Revision:
December 14, 2018

3.6-1

Major Facilities Guide: NSF 19-68 (May 2019)
3.6 Facility Divestment Plan
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

The transition plan should also include the risk management during the divestment transition
process. This includes list of risks, risk mitigation and management plan.

Section Revision:
December 14, 2018

3.6-2

Major Facilities Guide: NSF 19-68 (May 2019)
4.1 Introduction
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

4
4.1

KEY MANAGEMENT PRINCIPLES AND REQUIREMENTS FOR MAJOR FACILITIES
INTRODUCTION

This section provides greater detail about key management, budgeting, and reporting activities
that should be carried out throughout a project’s life cycle stages, for both Major Research
Equipment and Facilities Construction (MREFC) and non-MREFC projects, to ensure adherence
to principles established by National Science Foundation (NSF).
Some of these activities will be funded via MREFC and others via R&RA, depending on life cycle
stage.

Section Revision:
May 2, 2016

4.1-1

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.1 Overview of Guidance and Process for Both Construction and Operations Awards
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

4.2

COST ESTIMATING AND ANALYSIS
Overview of Guidance and Process for Both Construction and Operations Awards

As noted in Section 1.1, award instruments can take the form of cooperative agreements or
contracts. Unless otherwise noted, the guidance in this section applies to research
infrastructure projects regardless of the award instrument employed. Proposed budgets must
comply with the applicable federal regulations, as implemented by NSF in the MFG, the
Proposal and Award Policies and Procedures Guide (PAPPG) or the Guide to the NSF Contracting
Process. Recipients are required to follow the best practices within the GAO Cost Estimating
and Assessment Guide 1 and GAO Schedule Assessment Guide 2, taking into consideration NSF
policy and practice as provided in this Guide. These NSF and Government Accountability Office
(GAO) Guides are intended for all Stages in a facility’s life cycle. However, portions of these
Guides may be tailored depending on what is relevant to the particular facility estimate.
Accordingly, Recipients must note any departures from these NSF and GAO Guides and
explain their rationale in the Cost Estimating Plan (CEP) 3. Additional guidance on how to apply
the relevant practices from the GAO Cost Guide and examples of potential deviations are
provided in Section 4.2.2.3.
The guidance herein clarifies NSF expectations for the format, content, supporting justification,
and good practices for Recipient cost estimates. This guidance also explains the NSF cost
analysis process and timeline. By following this guidance Recipients should expect a better
estimate and a more efficient review by NSF, facilitating achievement of the science mission.
For existing awards, the Recipient should consult with the PO.
NSF uses internal staff, outside experts, and panel reviews to analyze estimates for construction
and operations awards. The Recipient estimates must meet two sets of criteria that also serve
as the basis of the NSF cost analysis: (1) the cost principles of either 2 CFR § 200, Subpart E for
non-profit entities or the Federal Acquisition Regulation, Part 31 for for-profit entities, and (2)
the GAO Cost Guide. Cooperative support agreement estimates must be allowable 4, allocable,
and reasonable per the 2 CFR §200, Subpart E, and realistic. To be deemed reasonable under
the cost principles, the estimate must be developed in accordance with the best practices and
twelve steps of the GAO Cost Guide to meet the four characteristics of a high-quality estimate
GAO Cost Estimating and Assessment Guide1: Best Practices for Developing and Managing Capital Program Costs (GAO-09-3SP
March 2009, or subsequent revision)

1

2

GAO Schedule Assessment Guide2: Best Practices for Project Schedules (GAO-16-89G December 2015, or subsequent revision)

Definition in Lexicon is adapted from AACE International Recommended Practice No 36R-08, Development of Cost Estimate
Plans – As Applied in Engineering, Procurement, and Construction for the Process Industries, Rev. June 12, 2009.

3

Allowable costs are defined by federal guidelines and relevant cost principles. Allocable costs must be logically related to the
particular award. Reasonable costs are what a prudent individual would pay in a competitive marketplace (i.e., costs are not too
high). Cost realism defines whether the costs are realistic for the work to be performed, reflect a clear understanding of the
requirements, and are consistent with the methods of performance and materials described in the Recipient’s technical
proposal (i.e., costs are not too low).

4

Section Revision:
May 30, 2019

4.2.1-1

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.1 Overview of Guidance and Process for Both Construction and Operations Awards
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

(well-documented, comprehensive, accurate, and credible), as outlined in Tables 2 and 25 of
the 2009 GAO Cost Guide.
As described in Section 2 of this guide, Recipients must develop estimates for design,
construction, operation and divestment of facilities. Estimates should be well documented,
comprehensive, accurate, and credible and should facilitate appropriate analyses from a wide
variety of reviewers at the various life cycle stages. It is understood that cost estimates will
undergo further refinement at each stage-gate review and the materials required herein will
evolve accordingly. NSF will review estimates at an appropriate level as the project advances
through the various facility life cycle stages.
Figure 4.2.1-1 below depicts the general NSF cost analysis process performed for construction
and operations awards. The NSF Program Officer (PO), Grants and Agreements Officer (G/AO)
or Contracting Officer (CO), Large Facilities Office (LFO) Liaison, and Cost Analyst conduct a
detailed analysis of the Recipient cost estimate. NSF may also utilize independent cost
estimates and cost estimate reviews 1 done by external panels and independent contractors or
agencies to inform the analysis. The G/AO or CO and Cost Analyst review includes the detailed
sub-elements, cost categories, and supporting basis of estimate discussed in this section of the
Guide. The PO review includes the technical scope, risks, level of effort, schedule, and
assumptions. The LFO Liaison supports analysis of any risks and proposed contingency budget.
The inputs from the various sources are integrated and addressed with the Recipient, which
could potentially result in a revised cost estimate or additional documentation. The PO
ultimately recommends the budget, funding profile, and internal and external sources of funds
based on the realism of the cost estimate, technical scope of the project, and the availability of
funds. The G/AO or CO approves the Recipients’ cost estimate and ultimately the award of the
proposal and approved budget based on the results of the cost analysis.
For construction awards, the NSF cost analysis is done at the end of each Design Phase, in
conjunction with CDR, PDR, and FDR, to support stage-gate reviews. For operations awards, the
NSF cost analysis is done on operations and management proposals for initial operations,
renewal, and recompetition of awards. NSF may also perform cost analyses at other times, as
necessary, based on a risk-based assessment. For example, cost analyses may be needed during
construction or operations to support significant changes in scope, schedule, cost, risk or
complexity. These latter types of analysis may only require review of targeted subsets of
information for specific changes. NSF typically requires 90 to 180 calendar days to complete a
full review and detailed cost analysis of a proposal budget prior to proceeding to the next
design phase or prior to award for operations or construction. This time will vary depending on
project scope, cost, risk, complexity, and relative importance. It will also depend upon whether
revisions to the estimate, due to errors or cost re-categorizations, for example, are needed.
During the review time window, the Cost Analysis and Pre-Award (CAP) Cost Analyst may
The definition for Independent Cost Estimate Review in Lexicon is adapted from Table 27 in GAO Cost Estimating and
Assessment Guide.

1

Section Revision:
May 30, 2019

4.2.1-2

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.1 Overview of Guidance and Process for Both Construction and Operations Awards
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

perform a cost analysis (typically 60 calendar days duration) in parallel with other review
activities to augment the G/AO review and target specific areas noted in Section 2.1.6.2 and
Figure 4.2.1-1.
If there are issues with the provided information, the PO, G/AO or CO, LFO, and/or Cost
Analysts may require additional documentation and justification and further interaction with
the Recipient prior to completing the analysis. Communication among all parties as well as a
sound initial basis of estimate are essential for timely and successful completion.
When submitting construction or operations estimates for cost analysis, Recipients must submit
the following as a minimum:
•
•
•
•
•

Cost Estimating Plan per Section 4.2.2.1.
“Cost Model Data Set” per Section 4.2.2.1.
Reports and Proposals per Sections 4.2.2.2 and either 4.2.3.2 or 4.2.4.2.
The Work Breakdown Structure (WBS) per Section 4.2.2.7.
Supporting information forming the Basis of Estimate (BOE) per Sections 4.2.2.3, 4.2.2.4,
4.2.2.5, 4.2.2.6, and either 4.2.3.4 or 4.2.4.4

For proposals that contain subawards1, each subaward must include a separate budget
justification.

See the Section 9 Lexicon for the difference between a “subaward”, which transfers significant effort from the Recipient to
another entity, and a “contract, which involves the purchase of materials and supplies, equipment or general support services
allowable under the award.

1

Section Revision:
May 30, 2019

4.2.1-3

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.1 Overview of Guidance and Process for Both Construction and Operations Awards
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative Support (BFA-DACS), & The Large Facilities
Office (BFA-LFO)
Figure 4.2.1-1

Section Revision:
May 30, 2019

NSF Cost Analysis Process

4.2.1-4

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.2 Elements of Both Construction and Operations Estimates
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

Elements of Both Construction and Operations Estimates
4.2.2.1 Cost Estimating Plan
For new construction and operations awards, Recipients must develop and submit a Cost
Estimating Plan (CEP) to establish and communicate how the preparation, development, review
and approval of the estimate will be or was completed. For existing awards, the Recipient
should consult with the PO regarding the CEP. Ideally the CEP will be developed and discussed
with NSF far in advance of submission (e.g., one year for major facility awards) to ensure that
that Recipient’s plans are aligned with NSF expectations and requirements outlined herein and
sufficient time is available to collect and package data. The CEP is the cornerstone of the
estimate(s) that come later and, along with the basis of estimate, critically important for
generating a high-quality estimate to facilitate management decisions and NSF cost analysis.
Recipients should contact their NSF PO, G/AO or CO, LFO Liaison, and/or Cost Analyst for more
information or guidance.
The CEP must state the purpose(s) of the estimate and describe how the guidance in Section 4.2
of this Guide, the PAPPG, “2 CFR Part 200, Subpart E – Cost Principles,” and the GAO Cost
Estimating and Assessment Guide will be or has been implemented. Recipients must note any
departures from these NSF and GAO Guides and explain their rationale in the CEP. The CEP
should also state the schedule of specific tasks, due dates, roles and responsibilities, practices,
systems, and calculations used to develop the cost estimate. The CEP should describe the
expected cost estimating methodology, maturity, and, if applicable, accuracy range 1 at each
Stage or Phase (e.g., expert opinion, analogy, parametric, engineering build-up, historical data).
The CEP should also explain any ground rules, assumptions and exclusions that apply broadly to
the estimate, allowances, and other sensitive or significant factors or considerations, including
their rationale and any references. Recipients should also discuss the independent cost
estimates and reviews, if any, they are planning to validate the project estimate.
The CEP should be tailored to the stage of the facility life cycle and address the most relevant
costs, from Development and Design through Construction, Operation, and Divestment. The
CEP should explain how the cost estimate may evolve over time. For example, the expected
level of funding needed for the Operations Stage should be identified at the Conceptual Design
Review. Operating cost estimates will be refined and updated throughout the design and
construction process as further discussed in the Concept of Operations Plan, developed as part
of the PEP described in Section 3.4 of this Guide. The CEP presented in an Operations Proposal,
whether submitted by the Recipient of the construction award or by a separate entity, should
be informed by the budget information and planning contained in the Concept of Operations
developed in the PEP.
For example, via classification levels in AACE International Recommended Practice No.18R-97, Cost Estimate Classification
System – As Applied in Engineering, Procurement, and Construction for the Process Industries, Rev. November 29, 2011

1

Section Revision:
May 30, 2019

4.2.2-1

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.2 Elements of Both Construction and Operations Estimates
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

The CEP should explain how the “Cost Model Data Set” will meet the various needs of the
facility. The “Cost Model Data Set” is the cost data used as input to software tools and/or
project reports to organize, correlate, and calculate different management information. Figure
4.2.2-1 provides an example of a how a “Cost Model Data Set,” Work Breakdown Structure,
and a Recipient’s institutional accounting systems can be used as inputs in conjunction with
scheduling, earned value, and risk analysis tools to generate a variety of output reports for
project purposes. Sections 4.2.2.7, 4.2.3 and 4.2.4 of this Guide refer specifically to the work
breakdown structure,“Cost Model Data Set,” and “Cost Reports” blocks encircled with dashed
lines in Figure 4.2.2-1. The CEP is included as part of the PEP as described in Section 3.4 of this
Guide.

Section Revision:
May 30, 2019

4.2.2-2

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.2 Elements of Both Construction and Operations Estimates
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative Support (BFA-DACS), & The Large Facilities Office
(BFA-LFO)
Figure 4.2.2-1

Section Revision:
May 30, 2019

Sample Project Control Systems Relationship Diagram

4.2.2-3

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.2 Elements of Both Construction and Operations Estimates
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

4.2.2.2 Estimate Formats
The Recipient must be capable of providing the cost estimate in multiple formats and reports,
including but not limited to the following:
•

Reports based on a deliverable-based work breakdown structure (WBS) for construction
and a functional, activity, and/or deliverable based WBS for operations, as further
described in Sections 4.2.2.7, 4.2.3.3, and 4.2.4.3 below. These reports support project
management and execution and detailed cost analysis of sub-elements and are referred
to as Cost Books.

•

Reports based on the standard NSF budget category format 1, depicted in Figure 4.2.2-2
and Section 4.2.2.4 below, per NSF budget and budget justification guidance from the
PAPPG. This format supports cost analysis of NSF budget categories. For contracts, NSF
proposal requests may specify alternate formatting in lieu of the NSF budget categories.

The estimate is built-up from the individual WBS elements and sub-elements. See Section
4.2.2.7 for guidance on work breakdown structures. If the costs associated with each WBS
element are binned into the appropriate NSF budget categories, then both of the above
reporting formats can be readily produced. For example, costs can be coded with NSF budget
format letters (A through I per Figure 4.2.2-2) to populate rolled-up NSF budget format
summaries as well as the Cost Book organized by WBS. The estimate should allow for
mathematical checks of the proposal budget calculations and should contain actual formulas
that allow manipulations to check calculations (i.e., the model should not display just the
results of the application of formulas or be locked such that calculations cannot be verified in
real time).
The cognizant NSF PO and G/AO, or CO can be contacted with questions or for other specific
programmatic requirements.

Projects may choose to use broad, summarized budget categories for internal planning and reporting, but reports with the
detailed breakout into NSF budget categories must be supplied when requested. (Examples: a single combined “E-Travel”
category for internal use rather than “E-1 Domestic travel” and “E-2. Foreign travel” in Figure 4.2.2-2; a single category “Labor”
combining all NSF labor categories A through B-6.

1

Section Revision:
May 30, 2019

4.2.2-4

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.2 Elements of Both Construction and Operations Estimates
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)
Figure 4.2.2-2

NSF Budget Categories Sample Format

A – Senior Personnel
B – Other Personnel
B.1 – Postdoctoral Scholars
B.2 – Other Professionals (Technicians, Programmers, Etc.)
B.3 – Graduate Students
B.4 – Undergraduate Students
B.5 – Secretarial – Clerical
B.6 – Other
C – Fringe Benefits
D – Equipment
E – Travel
E.1 – Domestic
E.2 – Foreign
F – Participant Support
F.1 – Stipends
F.2 – Travel
F.3 – Subsistence
F.4 – Other
G – Other Direct Costs
G.1 – Materials and Supplies
G.2 – Publication, Documentation, Dissemination
G.3 – Consultant Services
G.4 – Computer Services
G.5 – Subawards
G.6 – Other
H – Total Direct Costs
I – Indirect Costs

Section Revision:
May 30, 2019

4.2.2-5

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.2 Elements of Both Construction and Operations Estimates
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

4.2.2.3 Application of GAO Cost Guidance to Major Facilities
The MFG is intended to supplement not duplicate the GAO Cost Guide, PAPPG, and industry
good practices and standards. The best practices (twelve steps) of the GAO Cost Estimating and
Assessment Guide are highlighted below to help show how they can be applied or tailored to
NSF major facilities, including potential deviations, and how they should be integrated with NSF
processes. Concise summaries of GAO’s twelve steps and four characteristics of a high-quality
cost estimate can be found in Tables 2 and 25 of the 2009 GAO Cost Guide and additional
checklists are provided at the end of each chapter. By following the GAO Cost Guide, Recipients
should expect a better estimate and a more efficient review by NSF, facilitating achievement of
the science mission. NSF and independent reviewers use these GAO criteria and other methods
when analyzing Recipient cost estimates to determine whether to make an award. Application
of the GAO Schedule Assessment Guide is discussed further in Section 4.3.
GAO Cost Guide’s Twelve Steps / Best Practices:
1. Define estimate’s purpose:
o The purpose must be clearly defined. There are typically two general purposes:
(1) to help managers evaluate affordability and performance against plans, as
well as the selection of alternative systems and solutions, including value
engineering and scope management, and (2) to support the budget and award
processes by providing estimates of the funding required.
o Defining the purpose helps clarify the intended use and package the estimate to
facilitate review by a range of audiences, including managers and independent
reviewers. Reviewers not familiar with the facility will need a standalone
document with both the appropriate high level perspective and the detailed CEP,
BOE, and linkages via WBS so that someone unfamiliar with the program can
understand it, recreate it quickly with the same result, and be able to determine
if it meets the GAO’s twelve steps and four characteristics of a high-quality cost
estimate.
o Defining the purpose also helps determine its scope and level of detail, identify
appropriate performance measures for benchmarking progress, address the
benefits it intends to deliver, and link the estimate to NSF’s mission, goals, and
ideas.
o For additional descriptions and guidance on the purpose and context of the
estimate, including why it is developed and how NSF uses the estimate, see MFG
Sections 1.1, 2.3.1, 2.3.2, 2.3.3, 3.4, 4.2.1, 4.2.2.1, 4.2.3.1, 4.2.4.1, 6.2.1, 6.2.8.1,
and Figure 4.2.1-1 and Figure 4.2.2-1.
2. Develop an estimating plan: A CEP must be developed and address the details described
in Section 4.2.2.1.

Section Revision:
May 30, 2019

4.2.2-6

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.2 Elements of Both Construction and Operations Estimates
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

3. Define program characteristics: Characteristics of the program being estimated must be
defined for construction projects per the Project Execution Plan in Section 3.4 and for
operations awards per the Proposal and Work Plan in Sections 2.5 and 3.5.
4. Determine estimating structure:
o The estimate must be organized by both the WBS and NSF budget categories as
described further in Sections 4.2.2.2, 4.2.2.7, 4.2.3.3 and 4.2.4.3 and Figure
4.2.3-1 and Figure 4.2.4-1.
o The estimate structure must have clear traceability between WBS, CEP, and
BOEs, correctly roll-up to higher levels, and readily map between the WBS and
NSF Budget Categories.
5. Identify ground rules and assumptions (GR&As):
o The ground rules (a common set of agreed on estimating standards that provide
guidance and minimize conflicts in definitions) and assumptions (a set of
judgments about past, present, or future conditions) must be clearly defined and
documented in the CEP, as described in Section 4.2.2.1.
o The GR&As should be developed by estimators with input from experienced
program and technical personnel, based on information in the technical baseline
and WBS dictionary, vetted and approved by upper management, documented
to include the rationale behind the assumptions and backed up by historical
data.
o GR&As may be global, in which case they apply to the entire estimate and should
be clearly and consistently used throughout the. GR&As may also be programspecific or WBS element-specific, driven by the particular technical
requirements.
o The potential impacts from changing GR&As should be considered when
developing the sensitivity and risk analyses.
o For NSF major facilities, GR&As often include inflation, escalation, indirect rates,
travel, fringe benefits, schedule or budget constraints, acquisition strategy,
participation of other agencies or governments, level of technology maturity and
required research and development. GR&As also often define what is included
and excluded from the estimate, such as use of existing or multi-purpose
equipment and facilities.
6. Obtain data:
o The estimating methods, level of detail, accuracy range, availability of historical
and current cost data will evolve and improve through the design Phases and
Construction and Operations Stages. Current data should be routinely collected,
documented, and included in estimates.

Section Revision:
May 30, 2019

4.2.2-7

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.2 Elements of Both Construction and Operations Estimates
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

o Data should be collected from multiple sources, normalized, and assessed for
convergence and sensitivity. Cost drivers, trends, and outliers should be explored
and carefully analyzed for reliability and relevance. Primary data sources,
obtained from the original source and usually traceable to an audited document,
should be used when possible. Backup data should be collected and used to help
identify cost drivers and cross-check results.
o Recipients should carefully consider data sources and the applicability, potential
limitations, allowances, risks and uncertainty. This is especially true for NSF
major facilities where estimates often include research and development,
prototypes, university work, software and cyber-infrastructure, and unique,
complex, new and/or evolving technologies.
o The best estimating method should be chosen for each WBS element. The
following cost estimating methodologies should be used, in order of preference,
if the data exists: (1) Actual/historical data for the systems or operations being
estimated; (2) Detailed engineering build-up; (3) Parametric data with
adjustments to reflect differences (e.g., technical, size, weight, quantity,
location, schedule); (4) Analogous data with adjustments to reflect differences;
(5) Expert opinion, only if a secondary methodology is used to substantiate.
o Data sources, content, time, units, calculations and results, explanations for
choosing a particular estimating method or reference, and circumstances
affecting the data should be clearly documented in the CEP and Cost Book BOE.
7. Develop point estimate and compare it to an independent cost estimate:
o Recipients are encouraged to obtain independent cost estimates (ICEs) and cost
estimate reviews to help validate and improve the quality of the estimate before
submitting proposals to NSF. Recipients should address this as part of the CEP, as
described in Section 4.2.2.1. Operations proposals do not typically warrant an
ICE since analogous historical costs are readily available or the basis of estimate
will typically not have the breadth and depth of technical and cost detail that is
expected for a construction award.
o As noted in Sections 4.2.1 and 4.2.2.1, NSF utilizes ICEs and independent cost
estimate reviews done by external panels and independent contractors or
agencies. An ICE is required prior to construction awards. An independent cost
estimate review of some type is required of operations proposals prior to initial
operations, renewal, and recompetition of awards. These ICEs and independent
cost estimate reviews are used to validate the Recipient estimates, negotiate
awards, check for compliance with GAO best practices and Uniform Guidance
Cost Principles, and inform the NSF cost analysis. Far in advance of reviews, the
NSF PO, G/AO or CO, LFO Liaison, and Cost Analyst determine the type, timing,
scope, and team required. Recipients should be prepared to support these

Section Revision:
May 30, 2019

4.2.2-8

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.2 Elements of Both Construction and Operations Estimates
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

efforts, address any findings, and participate in reconciliations of proposals with
ICEs.
8. Conduct sensitivity analysis:
o Done to test the sensitivity of cost elements to changes in estimating input
values and key assumptions so that key cost drivers and the range of potential
costs can be identified, highlighted for Recipient management and NSF, and a
strategy can be developed to deal with them. Sensitive elements are those
where small changes in variables can create the greatest changes in cost.
o Can be done rigorously and quantitatively by examining the effect of changing
one assumption, ground rule, or cost driver at a time while holding all other
variables constant to understand which variable most affects the cost estimate.
The changes should not be arbitrary or subjective (e.g., +/- %), but rather
determined by subject matter experts based on available data.
o Sensitivity analysis tries to isolate the effects of changing one variable at a time,
while risk or uncertainty analysis examines the effects of many variables
changing all at once. The results of the sensitivity analysis can therefore be used
to help identify and quantify risks that are then used in a probabilistic risk
assessment to develop the contingency budget and confidence level.
o The results of the sensitivity analysis can also inform decisions when analyzing
alternatives for design, acquisition, construction, operations, and maintenance.
Analyses can also drive actions to avoid, mitigate, transfer, or accept a risk. .
o For operations estimates that may consist largely of level of effort work, a more
qualitative sensitivity review could be performed and justification provided that
there are no particularly sensitive elements and therefore little or no potential
impact.
o The major contributing variables within the highest percentage cost elements
are the key cost drivers that should be considered in the analysis. May be a
ground rule and assumption, especially those least understood or most at risk of
changing. For NSF major facilities, sensitive elements may include electricity,
fuel, major commodities, inflation, requirements changes, location, domestic
versus foreign sources/procurements, acquisition strategy.
9. Conduct risk and uncertainty analysis:
o Described further in Sections 4.2.5 and 6.2 below. The risk register data, basis of
estimate, assumptions, and detailed methodology used to calculate contingency
budgets must be documented and provided if contingency is requested. As
described in Section 3.4 for construction projects, this information is
documented in the Project Execution Plan components 4.6, 4.10, and 6.

Section Revision:
May 30, 2019

4.2.2-9

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.2 Elements of Both Construction and Operations Estimates
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

o For operations, also see Section 4.2.6. These analyses are not typically required
for operations awards, but can be used if risks are identified, e.g., for facility or
instrumentation upgrades or for replacement projects.
10. Document the estimate: Described throughout Section 4.2.
11. Present the estimate to management for approval: Described in Sections 2.3, 2.5, 3.4,
3.5, and 4.2.1.
12. Update the estimate to reflect actual costs and changes: Described throughout Section
4.2 and for EVM in Sections 3.4.1 and 6.8. Typically, not required for operations awards
though work plans and budgets may be adjusted annually to reflect actual work done
and updates to planned work.
4.2.2.4 Supplementary Guidance for NSF Budget Categories from the PAPPG
This section discusses types of additional detailed information typically needed by Recipients to
justify the estimates by the required NSF Budget Categories. This information is intended to
supplement the standard guidance for the NSF Budget Categories described in Chapter II.C.2.g
of the PAPPG and depicted in Figure 4.2.2-2. This guidance is not all inclusive nor is it required.
It is intended to clarify NSF expectations, assist Recipients, facilitate NSF review with fewer
iterative resubmissions, and prevent recurrent issues. For each NSF Budget Category, Recipients
should provide specific justifications to demonstrate costs are allowable, allocable, and
reasonable per the cost principles of 2 CFR §200, Subpart E, and realistic.
The PAPPG states that budget justifications must be no more than five pages per proposal.
However, most cooperative agreements for major facility projects (both construction and
operations) will require substantially more pages.
The following apply to the salary data listed below. All Personally Identifiable Information
should be removed from the documentation. If not already covered in the CEP, Recipients
should provide a salary escalation rate for multi-year proposals, which can include a component
for annual raises similar to Cost of Living Adjustments (COLAs) and other pay increases for
promotions within the position classification. Recipients should provide the rationale behind
the salary escalation rate. In some cases, NSF may provide a base escalation rate in the
solicitation for guidance, but Recipients should follow Section 4.2.2.6 of this Guide when
proposing rates. Recipients may contact their NSF PO, G/AO or CO, LFO Liaison, and/or Cost
Analyst for a “Master Labor Schedule” template spreadsheet that can be used to compile all
labor data for ease of estimating and justifying labor costs.

Section Revision:
May 30, 2019

4.2.2-10

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.2 Elements of Both Construction and Operations Estimates
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

A – Senior Personnel
•

Recipients should provide verification of actual salaries paid for named senior
personnel. Salary rates should be based on actual costs per current rate paid by payroll
register, W-2s, or appointment letters. Recipients should note Academic Year (9-10
month) versus Calendar Year (12 month) appointments or time available to conduct
independent research if such appointments so provide. The Recipient should also
provide documentation to support reasonableness of the salary rate paid, such as salary
rate surveys, salary comparators, Human Resource Department analysis, or other
information.

•

NSF has a policy which typically limits senior personnel to two months effort in any
given year for standard NSF-funded grants. However, most cooperative agreements for
major facility projects (both construction and operations) have senior personnel effort
well in excess of two months. Compensation in excess of two months, if anticipated,
should be disclosed in the proposal budget, and explained in the budget justification.

B.1 – Postdoctoral Scholars
•

Recipients should provide the average salary rate or rate range for postdoctoral
students at the organization in the field of science. Actual payroll data may not be
available as these may be to-be-hired positions.

B.2 – Other Professionals, Technicians, Programmer, Etc.)
•

Since the NSF budget format poses this as a total number of individuals for a total
number of months, additional explanation is generally required to disaggregate the total
for cost analysis. The level of effort will likely need to be obtained by individual or by
position for salary calculations. Recipients should also provide a spreadsheet with the
budget justification that includes: name or position number, location, WBS, title, salary
rate and period, level of effort as a percentage or in person-months, and calculation of
amount for each award year.

•

Recipients should provide supporting documentation for the salary rates of the
technicians, programmers, and other professionals proposed. For these types of
positions, NSF recommends the use of Bureau of Labor Statistics (BLS) Standard
Occupation Classification Codes (SOC) by position title and referencing their positions to
BLS salary rates to establish reasonableness of proposed salary rates. The BLS data is
also available by region or city. Other salary rate survey data may be used, and larger
Recipient organizations may already have established salary ranges and qualification
bases established internally by their Human Resources Departments.

Section Revision:
May 30, 2019

4.2.2-11

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.2 Elements of Both Construction and Operations Estimates
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

B.3 – Graduate Students
•

Recipients should provide the average salary rate or rate range for graduate students at
the organization in the field of science. Actual payroll data may not be available as these
may be to-be-hired positions.

B.4 – Undergraduate Students
•

Recipients should provide the average salary rate or rate range for undergraduate
students at the organization in the field of science. Actual payroll data may not be
available as these may be to-be-hired positions.

B.5 – Secretarial – Clerical
•

Recipients should provide the average salary rate or rate range for secretarial clerical
personnel at the organization.

B.6 – Other Personnel
•

Generally, the same as B.2 above but special classifications could justify different
treatment.

C – Fringe Benefits
•

Most Recipient organizations utilize a single tier fringe benefit rate or fringe benefit rate
by class of employee. Occasionally these fringe benefit rates are approved in the
Negotiated Indirect Cost Rate Agreement (NICRA). In such cases, the Recipient can verify
the rate and provide a fringe benefit calculation (rates by class) for a sample project
year. These cases should be noted in the CEP.

•

Some organizations use an actual fringe benefit amount by class of employee. These
amounts vary greatly by employee salary levels. While some fringe benefit costs are
based on a percentage of salaries (such as statutory withholding or contributions to
retirement and Paid Time Off (PTO)), other fringe benefits such as medical insurance
may be a lump sum amount and are not directly tied to salary paid. The Recipient should
provide an estimate of each fringe benefit provided as a percentage to salaries paid
along with a description of the fringe benefit provided as a means to gauge the
reasonableness of the fringe benefit package provided.

•

In both cases, Recipients should explain differences in the treatment of PTO. Some
organizations include this as a component of the fringe benefit rate and others include
the full cost of salary (including PTO) in the salaries as budgeted.

Section Revision:
May 30, 2019

4.2.2-12

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.2 Elements of Both Construction and Operations Estimates
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

D – Equipment
•

There can be equipment expenses or materials and supplies that individually are less
than the threshold but taken together exceed the equipment threshold, particularly
when installed or fabricated by a Recipient.

•

Recipients should list each item of equipment individually and include a description,
estimated cost, and justification of need. Recipients should typically provide vendor or
catalogue quotes for each item of equipment when available. These quotes should be
indexed and numbered to the equipment items proposed. For unique scientific
instrumentation or other equipment components where vendor quotes are not readily
available, a clear basis of estimate should be provided.

E – Travel
•

Generally, the cost estimate should be detailed by individual destinations, type of
transportation (airfare or mileage), per diem (lodging and meals) and other associated
expenses. The relation of the travel to the proposed activities should also be included.
For renewal projects, historical costs can be considered as a means of assessing the
reasonableness of travel costs. Where there are large numbers of trips and the actual
locations may not be known in advance, then cost estimating relationships (e.g., average
of $1,500 per traveler per trip) may be used.

F – Participant Support
•

Justification should include the number of participants, stipend amount, travel cost
estimate, and subsistence costs per participant. Recipients should also provide the
number of days or weeks of the training activities to provide a basis for determining
reasonableness of the proposed payments.

•

Participant support costs may not be used for personnel at the Recipient institution.

Note: All contracts for procurements or services needed to carry out the project must be listed
in G.1,2,3,4, to align with the type of budget activity or in G-6 Other. All contracts must follow
2 CFR § 200.317-326 including price and cost analysis, competition, competition, contacting
with women’s, small and minority businesses, and contract provisions. For procurements by
micro-purchase, i.e., purchase of supplies or services using simplified acquisition procedures,
the threshold amount for all awards is $10,000 based on the American Innovation and
Competitiveness Act. Contracts must not be listed in G.5 Subawards.
To assist Recipients in determining the difference between a subaward and a contract, please
refer to the “Subrecipient vs. Contractor Checklist,” developed by the Association of
Government Accountants.

Section Revision:
May 30, 2019

4.2.2-13

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.2 Elements of Both Construction and Operations Estimates
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

G.1 – Materials and Supplies
•

An itemized listing is not necessary unless an item represents a substantial amount of
costs. Vendor or catalogue quotes, historical costs, or other cost estimating
relationships may be used to establish reasonableness of the cost estimate.

G.2 – Publication, Documentation, Dissemination
•

Recipients should provide an estimate of publication and dissemination costs.

G.3 – Consultant Services
•

For each consultant identified, the Recipient should provide justification that the
proposed rate of pay is reasonable.

G.4 – Computer Services
•

Where it is established institutional policy to direct charge computer services, the
Recipient may justify and include such costs in the budget. Generally, such recharges
should be based on established internal institution usage rates. Recipients should
provide a supporting institutional statement or policy document and rates by units of
actual usage.

G.5 – Subawards1
•

Recipients of cooperative agreements are expected to conduct a pre-award risk review
of the subawards to include both cost and price analysis and to identify risk as outlined
in the Uniform Guidance, 2 CFR § 200.331.

•

Recipients should provide NSF with their pre-award analysis of each of the proposed
subawards when submitting for approval of each subaward. Such Recipient pre-award
analysis should include a determination of Subaward risk. This should include an
assessment of financial capability and ensuring the Subrecipient is not on any Federal
Government “do not pay” listing. The Recipient should also have performed a price or
cost analysis of the Subrecipient’s proposed work to ensure the reasonableness of costs.

•

NSF reviews the Recipient’s documentation on each Subrecipient to ensure sufficient
rigor and detail was performed.

•

The Recipient must keep copies of the risk assessment performed, which should detail
any key risks identified and how those risks were mitigated and resolved, cost and price

A subaward is for the purpose of carrying out a portion of a Federal award and creates a Federal assistance relationship with
the subrecipient. See 2 CFR § 200.92 Subaward. Characteristics which support the classification of a subrecipient versus
contractor can be found at 2 CFR § 200.330. See also PAPPG II C.2.g (vi)(e).

1

Section Revision:
May 30, 2019

4.2.2-14

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.2 Elements of Both Construction and Operations Estimates
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

analysis, and results of searches of the System for Award Management (SAM.gov), and
Federal Awardee Performance and Integrity Information System (FAPIIS).
G.6 – Other
•

Itemized Other costs per PAPPG II C.2.g (vi)(f), including the applicable budget
contingency, should be summed here and described separately in the Comments area of
the form.

•

Budget contingency, when applicable, should be presented as a part of the total amount
of Other Direct Costs under section G.6 on the standard NSF budget form. Budget
contingency budget estimates should be developed in accordance with Sections 4.2.5
and 6.2 of this Guide and should include all fully burdened contingency amounts. The
proposal should include adequate documentation on the basis of estimate for the
contingency amounts, indicating that they were developed in accordance with 4.2.5 and
6.2 and are supportable. Budget contingency and allocations of contingency will be
called out in the Cooperative Support Agreement by the G/AO under the “Contingency”
section, based on information provided in the negotiated budget justification.

H – Total Direct Costs
•

The total amount of direct costs requested in the budget, to include Lines A through G,
must be entered on Line H.

I – Indirect Costs
•

When the Recipient has a Negotiated Indirect Cost Rate Agreement (NICRA) established
with a cognizant federal agency, the rate and base in that agreement should be used to
compute indirect costs. A copy of the NICRA should be included in the CEP.

•

When a Recipient does not have a NICRA, the Recipient should provide a calculation and
an indirect cost rate proposal. The Recipient should ensure that indirect costs are in
accordance with NSF policies in NSF’s Indirect Cost Rate Proposal Submission
Procedures. Recipients should provide a clear description of rates and application bases.
Recipients should also provide spreadsheet calculation of rate or rates by year clearly
showing exclusions such as sub-contracts greater than $25,000, equipment or capital
expenditures, and participant support. If a Recipient has different indirect cost rates
across NSF budget categories in Figure 4.2.2-2, these rates should be clearly identified
and justified. Any deviation to a Recipient’s normal rate should also be justified.

K – Fee
•

When the Recipient is proposing a Fee amount, it should be presented in line K. A Fee
can only be proposed when the solicitation allows for it. Fee will be called out separately

Section Revision:
May 30, 2019

4.2.2-15

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.2 Elements of Both Construction and Operations Estimates
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

in the award terms and conditions and based on information provided in the negotiated
budget justification.
4.2.2.5 Fee
The payment of fee may be authorized for major facility construction and operations awards,
unless otherwise prohibited in specific circumstances by NSF. Fees will be evaluated for
reasonableness by the G/AO using a structured approach as prescribed by DACS. In part, the
G/AO may use information such as the negotiation objective set forth in the Decision Memo
and/or other cost negotiation memorandum as the basis for selecting the fee type and
determining the fee amount. The amount of fee will not exceed the statutory limitations
pertaining to cost contracts set forth at 41 U.S.C. 3905, notwithstanding that the fee is provided
through a cooperative agreement. NSF will also provide guidelines for Recipients that receive
fee to encourage the utmost discretion and appropriate consideration in the use of fee, to
include examples of inappropriate uses of fee (e.g., including but not limited to not using fee on
alcoholic beverages or lobbying as set forth at 2 CFR § 200.450 and 48 CFR 31.205-22). NSF will
reserve the authority to review a Recipient’s actual use of fee. Accordingly, Recipients must
separately track and account for uses of fee provided under NSF awards. The terms and
conditions of each award will specify the fee arrangement. NSF will consider reductions in
future fee if a Recipient’s actual use of fee is in contravention with the guidelines on
inappropriate uses.
4.2.2.6 Escalation
Recipients are not limited to using only broad and publicly available economic assumptions
when doing cost estimates. NSF encourages organizations to use escalation information
appropriate for the known situations or a particular industry as long as they can be justified. For
example, specialized data may be available from the Department of Energy, Department of
Defense, BLS, industry metrics, and/or historic experience with similar items. The justification
for all escalation assumptions and inflation factors (including use of standard OMB inflation
factors) should be included in the CEP and used consistently throughout the BOE.
Estimates should preferably be based on current information, but may include appropriate
escalation calculations and justifications to support the planned execution timeframe.
Escalation for raw materials and equipment in technological projects often runs higher than
broad measures of inflation (e.g., the consumer price index) due to inelasticity in pricing (i.e.,
there are few or no substitutes available in the marketplace and demand remains constant).
Recipients should consider establishing risks and associated contingency for future price
variability and developing mitigating actions.

Section Revision:
May 30, 2019

4.2.2-16

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.2 Elements of Both Construction and Operations Estimates
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

4.2.2.7 Work Breakdown Structure (WBS)
As described in the GAO Cost Estimating and Assessment Guide, a WBS is the essential
cornerstone of every project because it defines in detail the work necessary to accomplish a
project’s objectives. For construction, the WBS is a deliverable-based and hierarchical
framework structure that provides specific, manageable and schedulable tasks and may be
composed of products, material, equipment, services, data, and support facilities that the
project should yield. An operational WBS may be functional, activity, and/or deliverable based,
depending upon the type of work. Level of Effort tasks should be confined to only those tasks
that are not easily definable as deliverables. The WBS provides a consistent framework for
planning, estimating costs, developing schedules, identifying resources, and determining where
risks may occur. The WBS is a valuable communication tool and provides the means for
measuring program status, e.g., via using Earned Value Management for construction. WBSs are
developed at varying levels of detail but should include at least three levels. Generally, the
number of levels employed should be sufficient to identify and measure progress towards
achieving deliverables, assign responsibility, and enable effective management and reporting.
The number of decomposition levels varies depending on the project’s size and complexity,
technical maturity, organizational constraints, acquisition and construction strategies, and
management’s assessment of need.
Guidance and examples of common WBS elements can be adapted from GAO and other
guidance and tailored for NSF projects, as depicted in Figures 4.2.3-1 and 4.2.4-1. The benefits
of developing standardized or similar WBSs across the portfolio of facilities within an
organization include:
•

Consistent, clear, and familiar reporting structures and organizational relationships

•

Improved efficiency and effectiveness of NSF cost analyses

•

Better characterization of project schedule, scope, and cost

•

Ease of judging completeness and reasonableness

•

Better collection and sharing of data and analysis methods across multiple contractors
and projects to support future cost estimates

•

Better cost tracking over time, and identification of major cost drivers and systemic
problems across contractors and projects

Section Revision:
May 30, 2019

4.2.2-17

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.3 Additional Guidance for Construction Estimates
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

Additional Guidance for Construction Estimates
4.2.3.1 Purpose and Process
As discussed in Sections 4.2.1 and 4.2.2 above, NSF utilizes internal staff, outside experts, and
expert panels at the Conceptual Design, Preliminary Design and Final Design Reviews and
during the Construction Stage to assure that proposed construction cost estimates and budgets
meet expectations, incorporate relevant GAO Cost and Schedule Guide best practices, and are
allowable, allocable, reasonable, and realistic. Cost Estimating Plans and Cost Books should be
updated as necessary during each of the Phases in preparation for the Reviews. NSF documents
all the cost analysis work, technical reviews, audits, etc. for cost analysis as part of its oversight
and assurance roles.
The construction PDR estimate and subsequent NSF analysis must be sufficient to give NSF
confidence in the estimated Total Project Cost (TPC) that advances for National Science Board
authorization and potential inclusion in a future budget request. The FDR estimate and analysis
must be sufficient to give NSF confidence in constructing and commissioning the facility within
the TPC.
4.2.3.2 Construction Cost Book – Introduction and Executive Summary
Construction Cost Books are necessary at the CDR, PDR, and FDR, at minimum, to provide a
comprehensive, consolidated estimate of construction costs.
The Project Execution Plan described in Section 3.4 of this Guide includes a Construction Cost
Book (PEP-4.7) as one component of the overall Construction Project Definition. The Cost
Estimating Plan and Construction Cost Book provide assumptions and detailed information
forming the Basis of Estimate. The following additional high-level information should be
provided as an overview and executive summary (PEP-4.5) to assist with the review process
described in Section 2 of this Guide. Recipients should consult with the PO and G/AO or CO as
necessary to identify any other specific cost reports and content required to support the
review.
•

Overall high-level cost summary charts, tables, profiles, and reports; depicting total and
annual costs; reported both by WBS and in NSF budget format; providing Base Year and
Then Year costs.

•

A comparison of the current total project cost to past estimates and an explanation of
any major changes, including impacts to scope or design.

•

Explanation of how project costs by WBS map to the NSF budget format, including
detailed traceability or crosswalk matrix, described further below.

•

Other reports, as needed, e.g. costs by resource types (subcontract, labor, materials,
travel), cost profiles (total, labor, non-labor, by WBS sub-element), personnel profiles
(Full-time-equivalents by WBS sub-element).

Section Revision:
December 14, 2018

4.2.3-1

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.3 Additional Guidance for Construction Estimates
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

4.2.3.3 Construction Cost Book – Format

Major facility construction projects must employ a deliverable-based and hierarchical WBS that
provides specific, manageable and schedulable tasks and may be composed of products,
material, equipment, services, data, and support facilities that the project should yield. Level of
effort tasks should be minimized for optimizing tracking of spending against budget and
accomplishments against plan in the project Earned Value Management reports.
Examples of potential components of a WBS, common to many NSF plans for construction of
major facilities, are listed in Figure 4.2.3-1 and further described below. The intent is to provide
a standard format to the extent feasible with the vast array of different facility types while
noting that additions and/or alterations to this list are likely, due to the unique nature of each
specific facility.
A basic description of each WBS is as follows:
1.0 Project Administration and Management Office – Include activities related to the
management and administration of the project. This includes quality assurance and
safety, reliability, document control, cost/schedule reporting and control systems, and
configuration management.
2.0 Facility Infrastructure and Civil Construction – Includes the design, procurement,
construction, and integration, of the supporting infrastructure. One example is a
telescope and site construction, consisting of the facility enclosure, dome, and
telescope mount.
3.0 Scientific Equipment and Instrumentation – Includes unique and specialized scientific
equipment. For example, field sensors and gages.
4.0 Computers and Cyber-Infrastructure – Includes hardware and software needed to
operate the system and collect and analyze data.
5.0 Systems Integration, Testing, and Commissioning – Includes the overall systems
infrastructure and personnel needed to integrate other WBS elements to ensure they
work correctly together for testing, commissioning, training, and operations.

Section Revision:
December 14, 2018

4.2.3-2

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.3 Additional Guidance for Construction Estimates
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)
Figure 4.2.3-1

Construction WBS and Cost Book Sample Format

1.0 Project Administration and Management Office
1.1 Project Management Office
1.2 Site Office
1.3 Science Office
1.4 Education and Public Outreach
1.5 Safety and Environmental Assurance
2.0 Facility Infrastructure and Civil Construction
2.1 Sub-element X
2.2 Sub-element Y
2.3 Sub-element Z
3.0 Scientific Equipment and Instrumentation
3.1 Subcomponent X
3.2 Subcomponent Y
3.3 Subcomponent Z
4.0 Computers and Cyber-Infrastructure
4.1 Data Infrastructure
4.2 Data Products
5.0 Systems Integration, Testing, and Commissioning
5.1 Common Utilities and Support Equipment
5.2 Early System Assembly, Integration, and Testing
5.3 Acceptance Testing
5.4 Training
5.5 Science Verification
4.2.3.4 Construction Cost Book – Detail
This section discusses additional detailed information needed for a high-quality Recipient cost
estimate and NSF cost analysis. This information is intended to supplement the standard GAO
best practices, grant guidance in the PAPPG, and industry standards and good practices1. The
guidance should improve project execution, clarify NSF expectations, assist Recipients, facilitate
NSF review with fewer iterative resubmissions, and prevent recurrent issues. It is understood
that this information will become further refined as the Design Stages advance.

Examples: AACE International Recommended Practice No. 18R-97, COST ESTIMATE CLASSIFICATION SYSTEM – AS APPLIED IN
ENGINEERING, PROCUREMENT, AND CONSTRUCTIONS FOR THE PROCESS INDUSTRIES; and AACE International Recommended
Practice No. 34R-05, BASIS OF ESTIMATE

1

Section Revision:
December 14, 2018

4.2.3-3

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.3 Additional Guidance for Construction Estimates
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

Presentation and Linkages
•

Individual WBS element costs must have a sound, fully justified and documented, and
sufficiently detailed Basis of Estimate. Figure 4.2.3-2 below provides an example
Construction Cost Book Sheet depicting the format and content typically needed to
consolidate the “Cost Model Data Set” and to provide the appropriate level of detail and
BOE. This sheet includes the following information:
o WBS and activity codes and descriptions, per the WBS Dictionary, to index the
cost estimate to a specific deliverable
o Statement of Work describing the scope
o Estimator Name and Date of Estimate
o Resource Descriptions
o Cost Basis Codes describing the estimate methodology (e.g., expert opinion,
analogy, parametric, engineering build-up, historical data)
o Direct Costs with Units and Hours
o Associated Fringe and Indirect Costs
o NSF Budget Category Code corresponding to the budget categories depicted in
Figure 4.2.2-2 and Section 4.2.2.4 above, to allow mapping between WBS subelements in Construction Cost Book and NSF Budget Categories on NSF Budget
Forms
o Basis of Estimate source data, with breakout of sub-elements, typically including
direct input from technical experts in that area with calculations using material
and labor quantities and unit prices, with clear assumptions and sources
referenced
o Associated risk, uncertainty, sensitivity, or contingency information, if any.

•

Estimates must have clear traceability, including the following, as appropriate, for CDR,
PDR, FDR, and Construction:
o The total estimated cost should correlate to current drawings, specifications, and
schedules.
o Lower levels of the WBS must correctly roll-up to the higher levels, and the
application of rates and factors must be consistent with the Cost Estimating Plan,
basis of estimate, supporting rate agreements, and Recipient accounting
practices.

•

WBS sub-element costs should be readily mapped to NSF Budget Categories depicted in
Figure 4.2.2-2 and Section 4.2.2.4 above; for example:
o If each cost element on the Figure 4.2.3-2 Cost Book Sheet is assigned an NSF
Budget Category Code (e.g., “A for Senior Personnel,” “E1 for Domestic Travel,”
“G4 for Computer Services,” “I for Indirect Costs”), then the WBS elements can
readily be compiled into standard NSF Budget Forms, which depict total cost

Section Revision:
December 14, 2018

4.2.3-4

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.3 Additional Guidance for Construction Estimates
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

types across all WBS elements (e.g., all personnel, equipment, travel, indirect, or
computer services costs across all WBS elements)
o If databases are sufficiently detailed, documented, and traceable, then
automatic sorting and summarizing of costs will be facilitated for various
purposes and for different reporting formats.
•

Cost estimates may be directly linked to scheduling tools, to allow automatic cost
updates with schedule changes.

BOE Refinement Process
•

Because of the hierarchical nature of the WBS, it is possible, over time, to refine the
level of detail at which the project scope, schedule, and task-based costs are captured.
Throughout the Design Stage the task and cost fidelity will increase, and eventually,
during the construction of the Project, the plans will be fully detailed. As the project
moves through the phases, detailed engineering build-up estimates using current
quotes and prices should be collected, such that the proportion of estimated costs
based on expert opinion, analogy, or parametric estimates is reduced. As the project
finalizes plans for the start of construction the basis of estimate should include more
vendor catalogue, quoted, or proposed contract prices.

•

Direct labor rates, quantities, and skills mix should be justified, including information
from subawards.

•

If using consultants and contractors, Recipients should carefully justify substantial
consulting costs, including the type of work performed, quantity of time proposed, and
its cost, as compared to potentially less expensive current employee labor to accomplish
the proposed work.

•

Cost estimates should include adequate funding for project management, including the
use of appropriate project management tools such as project management control
software and associated staff support.

•

The major facility construction cost estimate may include commissioning (i.e.,
integration, testing, acceptance, and operational readiness), including funding for staff
to perform these activities and train the operations personnel. Roles change as a project
progresses from construction through commissioning and eventually to operations; time
and staffing requirements need to be carefully calculated in advance, with clear
demarcation between construction funded scope and operations scope as discussed in
Section 3.4.1, Components of a Project Execution Plan; Commissioning (Component 15
of the PEP).

•

Where partnerships are involved, monetary contributions to acquisition and eventual
operations and usage should be timely, sufficient, and well documented in the PEP and
IMP.

•

Cyber-infrastructure technical requirements and costs (both initial cost and continuing
costs of hardware, software, maintenance, upgrades and operations) should be carefully

Section Revision:
December 14, 2018

4.2.3-5

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.3 Additional Guidance for Construction Estimates
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

considered and periodically validated. Rapid advances in computing may require
upgrades as often as every 3 to 5 years.
•

Cost of evolving technologies should be considered as part of budget development and
through acquisition planning. For example, it may be appropriate to include higher
allowances in the BOE, or higher impacts as part of the budget contingency
development, and plan for procurement late in the construction stage.

Section Revision:
December 14, 2018

4.2.3-6

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.3 Additional Guidance for Construction Estimates
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative Support (BFA-DACS)
Figure 4.2.3-2

Section Revision:
December 14, 2018

Construction Cost Book Sheet Sample Format

4.2.3-7

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.4 Additional Guidance for Operations Estimates
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

Additional Guidance for Operations Estimates
4.2.4.1 Purpose and Process
In addition to the specialized scientific expertise required for operations, award solicitations can
also include expectations for estimating budgets, business systems, and operational and
financial reports. As discussed in the NSF PAPPG, individual solicitations, and Sections 2.5, 4.2.1,
and 4.2.2, these systems and reports help ensure the science mission can be met in a cost
effective way.
NSF utilizes internal staff, outside experts, and panel reviews to ensure cost estimates and
budgets meet expectations, incorporate relevant GAO Cost and Schedule Guide best practices,
and are allowable, allocable, reasonable, and realistic. The NSF Cost Analysis document is used
as an Award Decision tool that captures all the cost analysis work, technical reviews, audits, etc.
for cost analysis as part of its oversight and assurance roles. It is incumbent on NSF to plan and
budget for effective research and educational use of facilities, as well as the costs to operate
and maintain the facility long term. It is incumbent upon the Recipient to ensure their
operations proposal is complete, appropriate, and reasonable.
Operating budgets should include, when appropriate, resources to provide a continuing
program of advanced research and development (R&D) that will enable a facility to evolve its
scientific program and best meet the needs of the research community. Funding for these kinds
of up-grades may also come from separate equipment and/or instrumentation programs within
the Directorate or Division.
4.2.4.2 Operations Awards Proposals – Overview
In addition to the guidance for Annual Work Plans described in Section 2.5.1 of this Guide and
Proposals for Operations and Management described in Section 3.5, additional information may
be requested by the PO or via the operations and management award solicitation. Recipients
should consult with the PO and G/AO or CO as necessary to identify any other specific cost
reports and content required to support the review.
•

Periodic plans that may include an executive summary, narrative overview, strategic and
annual objectives correlated to NSF mission needs, and an annual operating budget
focusing on any significant changes from previous plans. Plans may also include
expected scope, milestones, outcomes and impacts, developments, challenges and
opportunities, as necessary.

•

Explanation of how program costs within functional areas are coded or otherwise
related to the NSF Budget Categories depicted in Figure 4.2.2-2 and Section 4.2.2.4
above.

•

Other reports, such as annual cost by resource types (subcontract, labor, materials,
travel), cost profiles (total, labor, non-labor, by sub-element), and personnel profiles
(Full-time-equivalents by sub-element).

Section Revision:
December 14, 2018

4.2.4-1

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.4 Additional Guidance for Operations Estimates
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

4.2.4.3 Operations Awards Proposals – Format
As discussed in Section 4.2.2.7, there are numerous benefits of standardizing the framework for
accomplishing operational goals with a Work Breakdown Structure (WBS). An operational WBS
may be functional, activity, and/or deliverable based, depending upon the type of work, but the
amount of scope assigned to Level of Effort tasks should be minimized for better tracking of
spending against budget and tracking of accomplishments against plan. An example of a
hierarchical WBS for an operations award is provided in Figure 4.2.4-1 below. The intent is to
provide a standard format to the extent feasible with the vast array of different facility types
while noting that additions and/or alterations to this list are likely, due to the unique nature of
each specific facility. The level of detail contained in the cost reports may vary depending on
Programmatic management requirements and cost analysis effort.

Section Revision:
December 14, 2018

4.2.4-2

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.4 Additional Guidance for Operations Estimates
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)
Figure 4.2.4-1

Operations WBS and Budget Sample Format

1.0 Project Director, Management, and Administration Office
1.1 Director’s Office
1.2 Project Management Office
1.3 Site Office
1.4 Education and Public Outreach
1.5 Safety and Environmental Assurance
1.6 Administrative Services
2.0 Science Operations
2.1 Research Planning
2.2 Experimental and Operations Support
2.3 Data Analysis
2.4 Calibrations and Data Quality
2.5 Special Projects
3.0 Significant/Important Infrastructure Modernization, Overhaul, Upgrade, Replacement,
Expansion
3.1 Equipment
3.2 Facilities/Infrastructure
3.3 Computer Systems, Instrumentation
4.0 Facility and Equipment Operations, Maintenance, Engineering, and Support Services
4.1 Operations
4.1.1 Scheduling
4.1.2 Operating
4.1.3 Testing
4.2 Maintenance
4.2.1 Corrective Maintenance
4.2.2 Preventive Maintenance
4.3 Utilities
4.3.1 Energy (e.g., electricity, natural gas, central heating, central cooling)
4.3.2 Information Technology, Communications, Cyber-Security
4.3.3 Security
4.3.4 Water
4.4 Other/General Support Services
5.0 Contingency (If justified, and supported by appropriate risk analysis and management)

Section Revision:
December 14, 2018

4.2.4-3

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.4 Additional Guidance for Operations Estimates
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

4.2.4.4 Operations Awards Proposals – Detail
This section discusses additional detailed information, as follows, typically needed for a highquality Recipient estimate and NSF cost analysis. This information is intended to supplement
the standard GAO best practices and guidance in the PAPPG. The guidance should improve
execution, clarify NSF expectations, assist Recipients, facilitate NSF review with fewer iterative
resubmissions, and prevent recurrent issues. For existing awards, the Recipient should consult
with the PO.
•

When power costs are significant and volatile, a strategy for dealing with price
fluctuation should be developed as part of the operations plan. Other examples of items
that may require separate consideration are expendables – such as cryogens, gases and
spare parts – and ancillary equipment such as refrigerators and IT equipment.

•

Separate funding sources and revenue streams (e.g., visitor center fees) should be
clearly delineated.

•

Education and Public Outreach costs should be explicitly identified and explained.

•

Multiyear budgets should take inflation into account, using factors discussed in Section
4.2.2.6 above.

Contingency, if requested, must be in compliance with Section 4.2.6 of this Guide.

Section Revision:
December 14, 2018

4.2.4-4

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.5 Budget Contingency Planning for the Construction Stage
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

Budget Contingency Planning for the Construction Stage
4.2.5.1 NSF Policy Positions
1. “Management reserve” is not allowable in the Recipient’s portion of the risk-adjusted
Total Project Cost (TPC) estimate; only “contingency.”
2. Directorates must be responsible for the first 10% of cost overruns which exceed the
Board authorized TPC, or some portion of the NSF-held management reserve (if needed
and included in the authorized TPC) as determined by the Director.
3. At the Preliminary Design Review (PDR), projects must have a time-phased, prioritized
de-scoping options that equates to at least 10% of the baseline scope budget.
4. In support of NSF’s “No Cost Overrun” policy, projects must use a confidence level for
contingency estimates between 70 and 90 percent (under a probabilistic approach)
based on the particulars of the project and the inherent ability to de-scope.
5. NSF will hold budget contingency through project completion, in an amount up to 100%
of the total NSF-approved contingency budget, until it can be justified for obligation.
6. Although the initial TPC becomes public (i.e. through the budget request) after PDR, the
TPC under the “No Cost Overrun” policy is set at award (post-FDR) to allow for
refinement during the Final Design Phase.
4.2.5.2 Introduction
The intent of NSF’s “No Cost Overrun” policy (see Section 1.4) is to instill diligence and rigor in
establishing the TPC and giving NSF a strong oversight position. Mechanisms for offsetting
potential cost increases are described herein and include, in order of precedence and assuming
appropriate use in accordance with NSF policy and practice:
1. Re-planning
2. Use of contingency
3. Use of management reserve (if authorized)
4. De-scoping
5. Request Board authorization to increase TPC
“Contingency” is a critical component of the comprehensive planning and execution of the
construction of major research facilities. This document describes the policies and procedures
concerning the planning, use, and oversight of budget contingency in the construction of
facilities fully funded by NSF and to the NSF-funded component of the scope when NSF partners
with other entities. It also describes the NSF’s process for assessing the sufficiency of
contingency, evaluating the effectiveness of management plans used for administration of
contingency, and NSF’s oversight role in the use of contingency funds.
For all assistance awards with academic institutions and non-profit organizations,
contingency is held by the Recipient in accordance with the Uniform Guidance (§ 200.433).

Section Revision:
May 30, 2019

4.2.5-1

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.5 Budget Contingency Planning for the Construction Stage
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

Federal Acquisition Regulation (FAR) governs the planning, use and oversight of contingency for
contracts with commercial organizations. Regardless of where contingency is held, the
requirement for a well substantiated risk assessment and contingency estimate, as well as a
robust oversight and administration is essential. Estimating contingency and managing risk is an
integral part of the project planning and execution process. NSF positions on contingency,
management reserve and de-scoping must be considered by the Program and the Recipient as
part of that process. Although strategies for other types of contingency are mentioned here,
this document is only intended to address management of the budget contingency.
The definition of contingency varies widely among project management practitioners and
federal agencies. For NSF, 1 budget contingency covers the “known unknowns” and is used to
mitigate identified cost or schedule risks as described in the Project Execution Plan 2 (PEP). The
estimated risk-adjusted TPC, as defined in Section 9 of this Guide, is developed in accordance
with the GAO Cost Estimating and Assessment Guide, 3 as explained elsewhere in this Guide.
OMB’s cost principles in the Uniform Guidance address budget contingency, and define it as:
… that part of a budget estimate of future costs (typically of large construction projects,
IT systems, or other items as approved by the Federal awarding agency) which is
associated with possible events or conditions arising from causes the precise outcome of
which is indeterminable at the time of estimate, and that experience shows will likely
result, in aggregate, in additional costs for the approved activity or project. Amounts for
major project scope changes, unforeseen risks, or extraordinary events may not be
included.
In contrast, “Management Reserve” 4 is often used by industry and other organizations to cover
the unforeseen risks, or the “unknown unknowns.” Except in rare circumstances, NSF does not
normally hold a management reserve for a specific project as part of the TPC. As a result, the
Directorate is responsible for the first 10% of costs which exceed the authorized TPC. To
mitigate this risk, the project’s prioritized and time-phased de-scoping plan should equal at
least 10% of the baseline budget when established at PDR. The ability to de-scope varies widely
by project and the impacts on the eventual scientific capabilities of the facility will also vary.
NSF terminology aligns with that of AACE International, the Association for the Advancement of Cost Engineering, and of the
Project Management Institute’s Project Management Body of Knowledge (PMBOK Guide). See Section 6.2.3.2 for NSF
definitions of contingency and management reserve.

1

See Section 3.4 for details regarding the PEP. Note that the PMBOK Guide refers to “Project Management Plan” rather than
PEP, but the NSF definition of PEP is equivalent.

2

Note that the NSF definitions and treatment of contingency and management reserves differ from those used in the GAO Cost
Estimating and Assessment Guide.

3

The GAO Cost Estimating and Assessment Guide (GAO-09-3SP, March 2009 uses the term “management reserve” for funds
held for mitigation of “known unknowns” whereas NSF uses the term “contingency.” For GAO, management reserves are
included in the budget baseline and are managed at the contractor level. The value of the contract includes these known
unknowns in the budget base, and the contractor decides how much money to set aside.
4

Section Revision:
May 30, 2019

4.2.5-2

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.5 Budget Contingency Planning for the Construction Stage
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

The scope contingency should be well considered and strive to minimize negative impacts. The
Directorate may also choose to cover the cost overrun from programmatic funding (and
increase the TPC) in lieu of de-scoping if it deems the science-support capabilities of the facility
would be too severely impacted.1 See Section 2.4.1 of this Guide for required approvals.
The PEP describes a construction project’s scope, budget, schedule, and identified risks. It also
articulates the project’s plans for accomplishing the intended scope while satisfying the
constraints of budget and schedule and managing those risks. An essential component of the
PEP is the Risk Management Plan (RMP), which describes the project’s procedures for risk
identification, analysis, monitoring, and handling (including de-scoping if required) so that the
project has a high likelihood of being accomplished within the total available budget. Budget
contingency is only one tool used to control project risk. The RMP will also include methods and
tools to manage scope contingency, schedule contingency, and provide robust risk handling and
monitoring processes. Refer to Section 5.2, Risk Management Guidelines, for additional
information.
The development of budget contingency entails estimating the future potential impacts of
identified possible adverse events to the project (i.e. risks) if those events are ultimately
realized. In accordance with the Uniform Guidance, NSF requires the use of widely accepted risk
management practices (including parametric and probabilistic methods depending on project
maturity) to estimate a range or distribution of contingency. An appropriate value is then
selected from that range that will enable the project to successfully complete the required
scope within the TPC that is sent forward for National Science Board (NSB) authorization. In
support of NSF’s “No Cost Overrun” policy, confidence levels must be in the 70-90% 2 range
following PDR depending on the nature of the project; including the ability to de-scope. This
applies even for higher risk projects. The resulting TPC estimate, including estimated
contingency required, will ultimately factor into NSF’s decision on whether or not to proceed
with the project. This policy position is in no way intended to discourage the construction of
cutting-edge, high risk facilities needed to advance scientific understanding. It is intended to
give a high degree of confidence that the project will come in on budget and clearly articulate
the level of risk involved so that sound decisions can be made. Following construction start, if
subsequent analysis shows that confidence is declining and the Board-authorized TPC will be
exceeded, NSF requires that a reduction in scope be considered as a strategy to bring the costs
back in line with the budget.

Directorates are able to do this as a result of NSF’s “transfer authority” which is dependent on continued inclusion in the
appropriation act. The language may require that congressional appropriation committees be notified in advance of any
reprogramming. Directorates should consult with the Budget Office during the decision-making process.

1

GAO Cost Estimating and Assessment Guide (GAO-09-3SP, March 2009, pg. 158) states that the use of confidence levels of 70
to 80 percent is now common practice, particularly with projects having higher design complexity and technology uncertainty
as with NSF-funded facilities.

2

Section Revision:
May 30, 2019

4.2.5-3

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.5 Budget Contingency Planning for the Construction Stage
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

Since development of contingency is statistically-based, there is a chance that not every risk
will be realized at its maximum impact. Therefore, it is possible that contingency dollars will
remain at the end of the project. Even if contingency is allocated, the Project may come in
under budget for other reasons. Once project objectives are met and the project completed,
any residual funds must be de-obligated and returned to NSF at which time NSF will request
possible re-allocation of those dollars to other agency priorities. Awarded contingency shall be
held by the Recipient until project completion, but no later. Budget, Finance and Award
Management (BFA), the Large Facilities Office (LFO), and the Program Office will conduct a
project close-out with the Recipient in accordance with NSF practice and as described in Section
2.4.2 of this Guide.
Major strategies used by NSF to ensure accountability in the management of contingency
budgets include:
1. Contingency budgets are developed in accordance with widely accepted standards for
risk assessment and planning. Contingency budget, scope, and schedule are similarly
derived from probabilistic, bottom-up assessments of the entire project scope.
2. Contingency budgets are evaluated for reasonableness by NSF through use of expert
review panels convened by the Program that examine the BOE and methodology, and
compare the cumulative contingency amounts with historical experience on similar
projects. This happens at each phase of the project (Conceptual, Preliminary, and Final
Design) at increasing levels of refinement. Other divisions within NSF, and potentially
contracted experts, will also evaluate the contingency estimate as part of the total
project cost assessment as it moves through these phases.
3. NSF will obligate and allocate contingency based on need and performance of the
Recipient. The overall status of remaining contingency, future liens on contingency, and
all allocations and returns of contingency funds (as risks are realized or retired) are
reported on a periodic basis as specified in the award instrument. Balances will be
measured against the total NSF-approved contingency budget and the allocated
contingency to date. This is part of the standard project reporting and requires archiving
in the permanent electronic record used by NSF (FastLane/eJacket).
4. Management and use of contingency is documented separately through the
configuration and change control process and must reference the associated Work
Breakdown Structure (WBS) elements and/or the previously identified Risk. The Earned
Value Management (EVM) framework for financial status reporting will eventually
reflect movement of contingency into the Performance Measurement Baseline (PMB)
budget (increase or decrease in Budget at Completion; BAC). Although traceable as
allocations or returns to the contingency budget, contingency dollars become part of
the PMB and are no longer separately identifiable as contingency once incorporated.
5. All project expenditures must be used only for scope as defined by the elements of the
NSF approved baseline, and all are subject to financial audit.

Section Revision:
May 30, 2019

4.2.5-4

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.5 Budget Contingency Planning for the Construction Stage
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

6. Management of contingency is described in the Configuration and/or Contingency
Management Plan (PEP-6.3). In this plan, thresholds are established (based on the
nature of the project) on who has the authority to approve the use of contingency.
These thresholds are also documented in the award instrument. Below the thresholds,
the Recipient has authority to manage and allocate contingency budget to specific inscope elements of the project WBS following the Configuration Change Control Process.
Above these thresholds, approvals from NSF are required, with the level of approval
corresponding to the magnitude of the proposed change.
7. Financial controls prevent the cumulative Recipient cash draws from exceeding the
obligated spending authority in NSF’s financial system.
4.2.5.3 Contingency Planning and Assessment during Conceptual Design
A budget estimate, like the measurement of a physical quantity, has a value and an uncertainty
dependent on where the project is in the design process. The uncertainty in the budget
estimate is a consequence of identification of foreseen project risks and other “known
unknowns” that are under the control of the project; including scope that is not cost effective
to define in detail during preconstruction planning or the earlier phases of design. The ability to
estimate these risks and uncertainties naturally changes over time as the design is refined and
the understanding of the project matures. Recipients are required to develop methods for
qualitative and quantitative assessment of these risks, and to develop an optimized risk
handling strategy that evolves with the project. 1 Regardless of the phase, the BOE for
contingency development must be sound and well documented, but remain appropriate for
that phase.
For the Conceptual Design Phase, both the baseline estimate and the uncertainty of that
estimate should be based on expert judgment and parametric models developed by the project
planners based on scaling and extrapolating historical data from projects with similar
characteristics. When NSF conducts the Conceptual Design Review (CDR), it expects that
Recipient will have developed a risk-based, budget contingency estimate at a similarly refined
level of detail; one that is based on estimates for major elements or functional components of
the proposed facility. NSF will conduct the CDR using a panel of experts able to apply prior
experience to assess the reasonableness of the budget and contingency estimates. The budget
contingency estimate will be evaluated by NSF as part of its first internal cost analysis for the
project based on the CDR deliverables. This initial cost analysis will help inform the cost book
and other deliverables developed during the Preliminary Design Phase.

See Section 6.2, Risk Management Guidelines, for more information about formulating and implementing Risk Management
Planning, and standard references on project management, such as the PMBOK Guide, for a detailed explanation of the
individual steps in Risk Management Planning: risk identifications, qualitative and quantitative risk analysis, risk handling, and risk
monitoring.

1

Section Revision:
May 30, 2019

4.2.5-5

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.5 Budget Contingency Planning for the Construction Stage
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

4.2.5.4 Contingency Planning and Assessment during Preliminary Design
During the Preliminary Design Phase, NSF requires Recipients to develop budget estimates and
associated risk estimates that are “bottom up” assessments1 that consider every element of the
entire project, using as inputs the definitions of the lowest appropriate WBS elements. For each
lowest level element, the project should estimate its expected cost, excluding unusual risks or
occurrences that are outside the control of the project. The project should also separately
estimate, at the appropriate WBS element for the risk described, the technical, cost and
schedule risks or uncertainties using a widely accepted method that is employed by all
estimators. NSF expects to see the project utilize a probabilistic method of calculating a range
of risk exposures appropriate to the project area in question and the maturity of the risk
assessment. Expert judgment should always be applied to both the inputs (BOE) and outputs of
this process, to the reasonableness of potential cost and schedule impacts, and to the
applicability of the process to specific areas of the project. In some circumstances, such as
where specialized knowledge of a particular technical area or market condition exists, it can be
appropriate to override the outputs based on expert intervention. Supporting documentation
should clearly articulate which risks elements were considered and how they were modified
when making any adjustments to the model outputs.
It is not always realistic or even feasible to mitigate all anticipated risks. It is extremely unlikely
that typical projects will encounter all of the risks and the full extent of possible consequences
that have been identified. The contingency estimate should be appropriate to manage only the
ensemble risk, which is much more likely to occur than the sum of the individual risks. This
approach produces a more likely estimate for the TPC compared to an approach where Cost
Account Managers increase individual WBS elements to cover risk. Use of rigorous probabilistic
cost estimating methods that estimate confidence levels for the TPC (such as Monte Carlo
methods based on probability distributions for risk) are preferred and NSF highly encourages
application of these methods where practical. As a result of these estimating activities, the
project should develop the contingency estimate that provides a high degree of confidence that
the project can be completed within budget per NSF’s “No Cost Overrun” policy.
Budget, scope, and schedule risk are usually correlated to some extent. A change in scope, for
instance, may mean more costs and additional schedule. Risk analysis and budget and schedule
contingency estimation methods should consider the degree of correlation in estimating an
appropriate level of budget contingency.

See Section 6.2, Risk Management Guidelines, for more information about formulating and implementing Risk Management
Planning, and standard references on project management, such as the PMBOK Guide, for a detailed explanation of the
individual steps in Risk Management Planning: risk identifications, qualitative and quantitative risk analysis, risk handling, and risk
monitoring.

1

Section Revision:
May 30, 2019

4.2.5-6

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.5 Budget Contingency Planning for the Construction Stage
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

Budget contingency is developed based on risk assessment of individual WBS elements, but
once defined; it loses its identification with any specific cost element and is fungible throughout
the project to manage the overall project risk. Until then, contingency is held separately from
the project baseline budget estimate 1 that is used for Earned Value Management reporting, but
is included in the total project cost, regardless of the award instrument.
NSF requires the PEP to contain a baseline that defines the project’s intended scope, budget,
schedule, risk, and management plans. The PEP will include provision of schedule and scope
contingency 2 for use by the Project Manager, developed according to the following additional
considerations:
Schedule contingency: The construction schedule should be developed in the same manner as
the budget contingency estimate, following the WBS structure at the
lowest available level of detail. The project should make a technical
estimate for each task’s duration and its dependence on other tasks.
Scope contingency:

NSF requires projects to assess possible use of scope contingency and
develop a plan to make effective use of scope contingency, if necessary,
during construction. This provides the project with an additional tool to
manage the overall project.

NSF requires, at Preliminary Design Review (PDR), that the contingency budget, schedule, and
scope are the outcome of detailed planning by the project for how best to handle the various
risks that have been identified. Some risks are most effectively handled proactively by investing
in additional developmental and design activities or resources intended to prevent the risk from
occurring.
At the PDR, NSF requires a funding profile by fiscal year that includes the commitment and
obligation of funds, plus anticipated contingency needs. The profile should be a consequence of
the project’s formulation of a resource-loaded schedule for EVM reporting. Since PDR informs
the budget request to Congress, this allows NSF to determine the year-by-year construction
funding profile. The annual Congressional appropriation must be sufficient to accomplish the
work proposed and provide the financial resources needed to manage the risk activities
foreseen during that period.
The budget contingency estimate will be further evaluated by NSF as part of its second internal
cost analysis for the project based on the PDR deliverables. This second cost analysis will give
assurance on the TPC brought forward to the NSB as well as help inform the cost book and
other deliverables developed during the Final Design Phase in preparation for award.
1

That is, contingency is not included within the Budget at Completion (BAC). TPC = BAC + contingency.

2

See Section 6.2.3 for definitions.

Section Revision:
May 30, 2019

4.2.5-7

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.5 Budget Contingency Planning for the Construction Stage
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

4.2.5.5 Development of the Contingency Use Process
NSF examines the RMP at PDR to ensure that the PEP describes a formal process for Change
Control 1 that includes the allocation of contingency within the project during construction. NSF
approval of the RMP, including the change control process, must be documented and
maintained in the agency’s permanent record. Under the RMP, the Project Manager (or other
designated individual) should have budget authority to transfer to or from 2 the contingency
category to specific WBS elements, via a process that follows the project’s Configuration
Change Control Plan. A typical change control process, for example, may involve written
application to the Project Manager by the affected Cost Account Manager(s) and formal review
and recommendation by a Change Control Board (CCB) consisting of all other system leads. The
Program Officer must have the authority to then approve the requested funds, reject the
request, or request a change in schedule, technical scope or other corrective action. All CCB
change requests are to be logged, documented, and archived by the project, with the logs and
documentation provided on a periodic, pre-determined basis to NSF for review. The defined
CCB process must include a provision for seeking prior written approval from NSF (Program
Officer or higher depending on the magnitude) for all actions that exceed the thresholds
specified in the award instrument or NSF policy.
The CCB change request document, whether forwarded to NSF for approval or not, must have
the minimum content requirements necessary to comply with relevant cost principles as well as
to maintain an audit trail. See the sample change control request form at the end of this
section. This process must be examined by NSF for compliance before approval of the Change
Control Plan. CCB documentation must specify all control accounts that budget is being
allocated to or recovered from, and tie to budgets itemized by cost element (i.e., labor,
materials, supplies, etc.). Contingency allocations must be supported by analysis demonstrating
that the proposed amounts to be allocated are considered reasonable and allowable and
should be linked to the WBS and/or Risk Register ID. Allocations from contingency and returns
to it change the PMB budget. Therefore, it is essential that historical information be logged and
maintained in a manner that allows NSF to systematically track the evolution of the PMB from
its initial release at award through all subsequent changes. In other words, PMB budgets must
be traceable through historical records to the initial PMB release.
4.2.5.6 Contingency Planning and Assessment during Final Design
NSF requires the project to refine its cost estimates following PDR, adding additional definition
and improved confidence with the tasks associated with accomplishing the project deliverables.
At the Final Design Review (FDR) the budget estimate should be substantially based on
1

Section 2.4, Construction Stage, contains additional information about NSF expectations for conducting change control.

Some realized costs will be lower than initial estimates. Once a work package is complete, any savings should be removed
from association with specific WBS elements and added to the contingency pool available to the Project Manager.

2

Section Revision:
May 30, 2019

4.2.5-8

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.5 Budget Contingency Planning for the Construction Stage
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

externally obtained cost estimates (vendor quotes, bids, historical data, etc.). This added
definition is expected to result in a change in the project’s estimated Budget at Completion
(BAC) and in the accompanying budget contingency, while keeping the sum of the two at or
below the PDR TPC used to inform the budget request. Also, as part of the FDR, NSF assesses
the methodology employed by the project to further refine its cost and contingency estimates
including schedule and scope adjustments. All of this information would then factor in to the
total project cost assessment being refined and evaluated by NSF to make the initial
construction award.
4.2.5.7 Contingency Use and NSF Oversight during Construction
NSF will negotiate the award instrument with the Recipient to fund project construction
activities (Construction Stage). This instrument will specify the contingency amounts and
include thresholds above which prior written NSF approval is required before the Project
Manager may allocate contingency (as described in the approved Change Control Process, PEP8.2) to, or from, specific WBS elements. 1 The thresholds will vary depending upon the
particulars of each project. Working with the Recipient, NSF will employ the following criteria
when establishing the threshold or thresholds. These considerations must be documented in
the award file as well as the PEP and the IMP.
•

Award and Subaward amounts – A larger award amount may warrant establishment of
higher thresholds to lower administrative burden.

•

Sufficiency of project plans and designs – More detailed project plans, specifications
and designs generally lead to higher confidence and better bids which may allow the
thresholds to be higher.

•

Nature of identified project risks – The more risk associated with the nature, timing and
the severity of certain project work packages may increase the need for establishing a
lower threshold.

•

Review Recommendations – Expert panel findings and recommendations should be
considered in setting thresholds.

•

Recipient or Subrecipient past performance history – Available past performance
information may help to indicate whether a Recipient’s change control process is
adequate or whether the Recipient has been successful in identifying contingencies,
e.g., use and accuracy of contingency logs, and therefore support a corresponding
appropriate threshold. Poor performance would support a lower threshold.

•

Known audit findings and their disposition – Relevant audit findings/dispositions
should be considered in establishing thresholds.

Thresholds are necessary to allow the project to respond in a timely way to small, immediate needs for use of contingency,
such as field changes during construction. This avoids potential cost escalation that could result from delay.

1

Section Revision:
May 30, 2019

4.2.5-9

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.5 Budget Contingency Planning for the Construction Stage
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

•

Sufficiency of Recipient administrative systems – The adequacy of compliance with
financial and administrative systems including accounting systems, historical cost data,
and financial reports may impact the thresholds.

•

Degree of NSF substantial involvement in the project – The complexity and risks
associated with the project may warrant more NSF involvement and hence lower
thresholds.

Once construction begins, the actual cost for some specific WBS elements may exceed the
estimated cost and the Project Manager can choose to allocate contingency in accordance with
the process defined in the PEP for Change Control. In other cases, the actual cost will be less
than the estimates, and the Project Manager may decide to transfer budgeted funds from the
affected WBS elements to contingency. In case, whether it’s a risk realized or a risk retired, the
Change Control documentation should tie this transfer back to an identified risk element in the
Risk Management Plan to be allowable.
Contingency funds are to be used only to support scope that is part of the NSF-approved
project baseline, as defined in the PEP and successive CCB actions. Depending on the
thresholds, Project Manager, CCB, NSF, and NSB approvals are required to modify the project
scope. Unexpended contingency funds may not be used to support operations or other outof-scope activities.
4.2.5.8 Reporting Requirements
Each project in construction must report monthly to NSF on the status of the project, while
projects in the Design stage are highly encouraged to submit a monthly report. Details on the
required information for the monthly reports are outlined in section 4.6.2, Recipient
Performance Reports.
Projects are expected to periodically compute and update the risk exposure, estimate to
complete (ETC), and estimate at completion (EAC), and compare these quantities to the BAC
and TPC. NSF will monitor the financial information provided and compare the available
contingency to the estimated remaining risk exposure. NSF may request corrective action if the
contingency budget appears inadequate to manage remaining risk. Recipients should consult
with the PO and GA/O or CO as necessary on the format for the monthly reports. The
information contained in the monthly report is not intended to supersede or replace other
reporting requirements as specified in the Cooperative Agreement or Cooperative Support
Agreement.
All CCB actions, irrespective of amount, or whether they increase or decrease the BAC, must be
reported directly to Program Officer at least quarterly. All CCB actions exceeding defined
thresholds for allocation of budget, schedule, or scope contingency must be approved by NSF as
codified in the PEP-8.2 and the CA. NSF-approved CCB actions must be made part of the
award’s permanent record. For all assistance awards, CCB documentation is maintained in
Section Revision:
May 30, 2019

4.2.5-10

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.5 Budget Contingency Planning for the Construction Stage
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

NSF’s electronic record system (eJacket) in accordance with the award terms and conditions.
NSF’s financial system controls prevent the cumulative Recipient cash draws from exceeding
the obligated spending authority. All funds are retained within NSF’s obligated award amount
to be drawn down by the Recipient for allowable expenses once needed. NSF conducts various
post-award monitoring activities, such as periodic external reviews (whose scope includes
financial as well as technical status), site visits, and single and program-specific audits to
monitor compliance.
4.2.5.9 Partnership Considerations
NSF may partner with other entities to plan and construct a major facility. The guidelines within
this document are applicable when NSF funds a particular scope of work within a larger overall
project. Risk assessment and contingency development processes are to be applied to those
WBS elements funded by NSF. Similarly, the Recipient managing construction must report on
the use of contingency during construction in accordance with the requirements regarding use
of contingency funds.
More complex situations may arise when NSF funds a proportion of the total project cost, or
where NSF contributes along with others to a common fund to build specific WBS elements
within the context of a larger project. Because overall project risk is reduced as more WBS
elements are aggregated into the risk analysis and managed through a centrally held
contingency fund during construction, NSF encourages the development of unified
management for project planning and execution of the entire project scope wherever practical.
However, NSF recognizes other partners may have different processes for planning, funding,
and conducting oversight, making it challenging to form a unified management structure.
Consequently, the award instrument must define the specific procedures for handling
contingency in those circumstances. Program Officers are advised to consult with the Division
of Acquisition and Cooperative Support to determine an effective approach consistent with the
principles of federal laws and regulations. The Large Facilities Office may be able to provide
models of various approaches that have been used successfully in other projects.

Section Revision:
May 30, 2019

4.2.5-11

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.5 Budget Contingency Planning for the Construction Stage
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)
Figure 4.2.5-1

Sample of a Change Control Request Form, with instructions for filling out the various sections

Section Revision:
May 30, 2019

4.2.5-12

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.5 Budget Contingency Planning for the Construction Stage
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

Section Revision:
May 30, 2019

4.2.5-13

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.5 Budget Contingency Planning for the Construction Stage
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

Section Revision:
May 30, 2019

4.2.5-14

Major Facilities Guide: NSF 19-68 (May 2019)
4.2.6 Budget Contingency Planning during the Operations Stage
Prepared by Budget, Finance, and Awards Management, Division of Acquisition and Cooperative
Support (BFA-DACS), & The Large Facilities Office (BFA-LFO)

Budget Contingency Planning during the Operations Stage
The processes and procedures to handle risk are very different between major facility
construction and operations awards. As with construction, there are many inherent risks with
operations. However, the risks are markedly different in nature. Estimates for operations are
usually based on well-understood historical information and experience with routine risk
exposure included in the Basis of Estimate (BOE) as part of the “most likely cost”. The work
itself is based on the day-to-day activities of science support staff and required consumables
rather than the production, assembly and testing of discrete deliverables.
Operations award use, in approximate order, the following strategies:
•

Routine risk impacts are included in the BOE as part of the most likely cost.

•

Re-budgeting authority is used by the Recipient per the award terms and conditions.

•

Recipient reduces the level of science support effort (with NSF approval if significant).

•

Recipient requests supplemental funding; assuming proper justification, availability of
funds and recommendation by Program.

In contrast, risk handling on construction awards uses the strategy per Section 4.2.5 and NSF’s
“No Cost Overrun” policy.
As stated above, it is generally more appropriate for operating budgets to include only explicitly
identified allowances 1 for repairs, replacement, maintenance and other factors such as
“technology refresh” for cyber-infrastructure or other similar up-grades. However, any request
for budget contingency must comply with paragraph § 200.433 of the Uniform Guidance.
Unless a separate contingency budget is justified and fully supported through a formal risk
assessment and a Risk Management Plan, projects should use a systematic program to identify
the potential costs and operational impacts of both recurring and non-recurring events to
develop these allowances and clearly articulate this information as part of the basis of estimate.
A separate contingency budget may be preferable if the operational plan includes significant
upgrade funded through R&RA that should be managed as a separate sub-project. Finally, since
“contingency” has a specific meaning under the Uniform Guidance, and “management reserve”
cannot be held by the Recipient, these terms should not be used in the basis of estimate.

Definition in Lexicon is adapted from AACE International Recommended Practice No. 10S‐90, Cost Engineering Terminology,
Rev. March 1, 2016 and AACE International Skills and Knowledge of Cost Engineering, 6th Edition.

1

Section Revision:
December 14, 2018

4.2.6-1

Major Facilities Guide: NSF 19-68 (May 2019)
4.3 Schedule Development, Estimating, and Analysis
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

4.3

SCHEDULE DEVELOPMENT, ESTIMATING, AND ANALYSIS

[Reserved for future content]

Section Revision:
December 14, 2018

4.3-1

Major Facilities Guide: NSF 19-68 (May 2019)
4.4 System Integration, Commissioning, Testing and Acceptance
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

4.4

SYSTEM INTEGRATION, COMMISSIONING, TESTING AND ACCEPTANCE

System integration, commissioning, testing and acceptance are Recipient functions, and are an
essential part of complex construction/acquisition projects. Failure to perform them, or to
adequately plan for them, can lead to serious cost and schedule overruns. The Recipient is
required to describe its plans for system integration, commissioning, testing and acceptance in
the PEP (Table 3.4.1-1, Component 15). The Program Officer (PO) approves these plans, but is
also required to include periodic review of progress in these areas:
•

System Integration – combining and coordinating the many physical and performance
interfaces in a project;

•

Commissioning – substantiating the capability of the facility to function as designed by
bringing various system components on line first sequentially and then in simultaneous
operations to study and affirm the interaction among subsystems;

•

Testing – assessing the operation of the facility by applying the criteria established in
the PEP to measure acceptable performance; and

•

Conditions for Acceptance – specifying the expected condition of the facility, its
performance attributes, the tests the Recipient will perform, and the data it will
consider prior to accepting the facility or components of the facility and declaring it
ready for Operations and Maintenance. In some cases, a phased approach to
acceptance will be required. For example, for distributed-but-integrated facilities or for
facilities with complex instrumentation and equipment, the PO will want the Recipient
to demonstrate performance and perform acceptance procedures for part of the system
prior to proceeding with construction and/or acquisition of other systems. The PO, in
consultation with the Integrated Project Team (IPT), will determine whether the
Recipient will conduct the tests and accept the facility or whether the PO will participate
in the testing and accept the facility on behalf of the government.

Frequently, some aspects of construction and/or acquisition overlap with initial operation. A
detailed Operational Readiness Plan (PEP-15.2) should be developed by the Recipient at least
one year prior to the anticipated commencement of commissioning activities. Elements of
commissioning and transition from Construction Stage to Operations Stage are first addressed
during Conceptual Design, and become progressively more detailed as planning evolves. During
construction, the PO reviews the plan, utilizing internal staff, external experts, consultants,
external review panels and the resources of the Large Facilities Office. The review of the plans
for commissioning and acceptance should consider the following questions:
•

Will the project have parallel periods of construction/acquisition and operations, with
some components coming on line earlier than others?

•

What is the project’s strategy for facility acceptance, operational readiness review, site
safety and security, and training of operational staff and members of the research
community utilizing the facility?

Section Revision:
May 30, 2019

4.4-1

Major Facilities Guide: NSF 19-68 (May 2019)
4.4 System Integration, Commissioning, Testing and Acceptance
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

•

What are the project plans for transitioning staff from construction to operational
support activities? Is there a plan to bring in personnel with the requisite technical skills
to operate and support the facility at appropriate times? Have training needs been
addressed?

•

What risks to the project might result from contractor interference during periods of
beneficial use or occupancy as construction activities conclude?

•

What risks to the project might result from operations delays?

•

What contracting strategies are employed to ensure that priority tasks are completed in
a timely way and do not delay operational readiness?

•

What are project plans for obtaining use and occupancy permits, or satisfying other local
regulatory criteria?

•

Do the budgets reflect a proper allocation between construction/acquisition and
operations?

Even if limited operations are undertaken, the changeover from construction funding to
operational funding does not have to occur until the facility has been accepted and the PO
ensures that the budget is estimated accordingly. Where operational funding will be used prior
to acceptance, the PO will ensure that the budget justification clearly describes the changeover
and that the earlier changeover is estimated and budgeted accordingly, per the Segregation of
Funding Plan (PEP-15.4).

Section Revision:
May 30, 2019

4.4-2

Major Facilities Guide: NSF 19-68 (May 2019)
4.5 Documentation Requirements
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

4.5

DOCUMENTATION REQUIREMENTS

The Recipient is responsible for ensuring that a document management system is in place that
provides for retention and retrieval of essential and significant documentation related to the
project. Recipient documentation may take many forms, from informal e-mail communications
to formal letters, bids and contracts. NSF strongly prefers that this system be electronically
accessible via Internet, rather than paper-based, but recognizes that some paper records are
necessary. The documentation system should not only aid in identifying the types of documents
to retain, but should also contain appropriate controls over official documents such as drawings
to ensure that only the most recent drawings are being used and that only authorized
personnel are able to access and modify them. A sound document management system will
help prevent miscommunications and misunderstandings and will ensure that the facility
operators have the information required to maintain the facility.
Recipients should retain financial records, supporting documents, statistical records and other
records pertinent to the award instrument (CAs, grants, subawards, and contracts) for a period
of three years after submission of the Final Project Report. In addition, access to any pertinent
books, documents, papers and records should be made available to the NSF Director, Office of
Inspector General, and the Comptroller General of the United States or any of their duly
authorized representatives to make audits, examinations, excerpts and transcripts in
accordance with either the Uniform Guidance or Federal Acquisition Regulation (FAR)
requirements.
The documentation required, and the responsibility for producing and maintaining it, varies
within the facility life cycle. During the Design and Development Stage, the Program Officer
(PO) is responsible for producing and maintaining documentation related to review and
approval of awards. Managing the documentation pertaining to the review and processing of
proposals and awards is the PO’s responsibility throughout the life of the project. Chapter VI of
the Proposal and Award Manual (PAM) requires that proposal decisions be clearly documented.
Chapter XII of the PAM requires that NSF award records be retained and either retired or
disposed of in accordance with Federal law and regulation. NSF documentation should include
all partnership and other agreements, standard eJacket submission in the NSF-required format,
the Internal Management Plan (IMP), the Baseline Project Definition (typically defined in the
PEP), the record of oversight (including all reviews and reports), and all significant project
correspondence.
During the Construction Stage, essential and significant documentation includes the record of
any decision affecting the cost, schedule or baseline. At a minimum, the following forms of
documentation should be retained:
•
•
•
•

Memorandum of Understanding (MOU) and any other project agreements or deals;
Architectural, engineering, shop and as-built drawings;
Correspondence identifying problems, the resolution process, and the final decision;
Contingency use log;

Section Revision:
May 2, 2016

4.5-1

Major Facilities Guide: NSF 19-68 (May 2019)
4.5 Documentation Requirements
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

•
•

Change requests and approvals; and
System integration, commissioning, testing and acceptance plans and results.

During the Operations & Maintenance Stage, the Recipient documents facility performance in
terms of:
•

The facility itself – e. g., historical record of all costs related to maintenance (preventive,
deferred, repairs and/or emergency), operating time, and scheduled as well as
unscheduled downtime, and

•

Use of the facility for research and education (including a record of users that includes
the name, affiliation, funding agency, award number and annual award amount for each
user).

Section Revision:
May 2, 2016

4.5-2

Major Facilities Guide: NSF 19-68 (May 2019)
4.6.1 Introduction to Oversight, Reviews, Audits and Reporting
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

4.6

REQUIREMENTS FOR NSF PERFORMANCE OVERSIGHT, REVIEWS, AUDITS, AND
REPORTING
Introduction to Oversight, Reviews, Audits and Reporting

Oversight, reviews, audits, and reporting requirements change as a facility moves through its
life cycle and differ substantially between the Design, Construction, and Operations Stages. The
Recipient is responsible for complying with the reporting requirements contained in the award
instrument (e.g., technical and financial reporting), this Guide, and in the Proposal and Award
Policy and Procedures Guide (PAPPG) – particularly with respect to property management and
final reporting and requirements for closeout of the award. The Recipient is also responsible for
managing the project and providing internal oversight of its own activities. This may require
internal reporting and reviews by committees established by the Recipient institution. NSF is
responsible for reporting its performance goals for construction projects based on Recipient
EVM reports, per the Government Performance and Results Modernization Act (GPRAMA) of
2010.
Reviews and reporting are an important part of the oversight process that allows the PO to
monitor performance against the project plan and goals. Due to the complex nature of major
facilities, the level of oversight will be considerably greater than for a typical NSF research
grant. The Program Officer (PO) has primary responsibility for oversight of the facility in
accordance with the Internal Management Plan (IMP) and through various reviews and reports,
such as consultation and coordination with the Large Facilities Office, coordination of assurance
through the NSF Integrated Project Team (IPT), and periodic updates to the Facilities
Governance Board (coordinated through the CORF) and the NSB.
Reviews and reporting incur certain costs. Depending on the size of the project and the
distribution of the information, these costs may be significant enough to warrant explicit
inclusion in the project budget. Review and reporting plans and costs should be identified in the
PO’s IMP and in the Recipient’s PEP so that they can be adequately considered in the project
budget and schedule. The PO should clearly define the reporting requirements that are the
responsibility of the Recipient in the award instrument and these requirements should be noted
as milestones on the project master schedule for construction. The Recipient’s Project Director
adheres to their internal practices regarding financial and business operations controls,1 and
internal reporting (e.g., to the Principal Investigator, Dean, etc., as applicable and required).
It is important that consideration be given to Conflict of Interest rules and Privacy Act
restrictions when distributing and sharing reports containing proprietary or confidential
information.

1

See NSF "Business Systems Review (BSR) Guide.”

Section Revision:
November 25, 2016

4.6.1-1

Major Facilities Guide: NSF 19-68 (May 2019)
4.6.2 Recipient Performance Reports
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Recipient Performance Reports
Reporting requirements vary by facility life-cycle stage (Design, Construction, Operation, and
Divestment) and are specified, either explicitly or by reference, in the Terms and Conditions
associated with the award between NSF and the Recipient. Performance reports are generally
provided on a monthly and/or quarterly basis, with a comprehensive annual report provided by
a predetermined date. Separate reporting activities are required for MREFC funds used for
construction activity if the facility also receives Research and Related Activities (R&RA) funds.
These are specified in the Terms and Conditions of the separate cooperative agreements for
each type of funding.
NSF may occasionally request that Recipients provide additional information on a specific
activity, often as a result of a unique request from within the government. Such requests may
not be specifically included in the cooperative agreements due to their ad hoc and individual
nature, nevertheless a Recipient must be prepared to respond. Examples include responses to
audit requests from the Office of Inspector General and queries from the US Congress and
Executive Branch agencies. Some projects, particularly those with construction activities or
frequent changes in design, will need more frequent reporting intervals. For example, providing
the written minutes from a weekly construction meeting is common practice.
During the Construction Stage, the Project Director, who is responsible for executing and
controlling the project in accordance with the PEP and the award instrument, reports to the
Program Officer (PO) on a periodic basis (monthly for MREFC-funded projects and no less than
quarterly in other cases). Those reports should include the following:
•

PROJECT STATUS. A narrative to include the accomplishments and challenges during the
reporting period, including major scientific and/or technical accomplishments and
milestones achieved. Management information such as changes in key personnel,
budget issues, subaward/contractor performance, as well as any other information
about which the PO needs to be aware should also be included;

•

CURRENT PHOTOS. Recent photos with a written description and photographer
acknowledgements;

•

INTEGRATED PROJECT SCHEDULE. Chart or table of performance reporting milestones,
indicating which are on the critical path, the current projected project completion date
and other key milestones on which the EVM is based;

•

FINANCIAL SUMMARY AND PROJECTIONS. A narrative describing the amount of
construction funding to date and the amount of costs incurred thus far; a discussion of
Earned Value metrics with attention to changes from prior month, an estimate of the
amount of contingency funds needed to complete the project, and a funding summary
and projections indicating actual funding and projected funding by fiscal year;

•

EVM DATA TABLE. Earned Value metrics (BAC, PV, EV, AC, CV, CPI, SV, SPI, EAC, ETC),
Planned, Actual, and Spent percentage complete, PMB completion date, Award
completion date, and risk exposure, at least at the second level of detail in the WBS;

Section Revision:
December 14, 2018

4.6.2-1

Major Facilities Guide: NSF 19-68 (May 2019)
4.6.2 Recipient Performance Reports
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

•

STAGE TIMELINE OF TOTAL CONSTRUCTION SCHEDULE. “S” curve table comparison of
the Actual Cost of Work Performed (ACWP) with the Budgeted Cost of Work Performed
(BCWP) by quarter within each fiscal year up until the present quarter; and the
Budgeted Cost of Work Scheduled (BCWS) for those quarters and extending to the end
of the construction phase;

•

ROLLING TWELVE-MONTH WINDOW. “S” curve table depicting the same data as the
previous table in a twelve-month snapshot centered on the month of the report;

•

SV AND CV TREND GRAPH. Cost and schedule variances and performance indexes (CV &
CPI and SV & SPI) over a twelve-month period;

•

DISCUSSION OF VARIANCE AND CORRECTIVE ACTIONS AT THE WBS LEVEL. Review of
current or anticipated problem areas and corrective actions in a variance report at an
appropriate cost account, work package, or WBS level as agreed upon with NSF for all
cost and schedule variances > ±10%, including explanation of causes and
remediation/recovery plans 1;

•

BUDGET CONTINGENCY. Available balances of budget and schedule contingency, as a
total amount (dollars or calendar days), and for budget contingency as a percentage of
the estimated cost to complete (ETC) the project. A “liens” list of projected amounts of
possible future calls on contingency and an updated change log indicating all
contingency allocations (“puts and takes”).

For major facility projects in the Construction Stage, the PO is responsible for providing to the
LFO a written monthly summary of this information in a standard format provided by the Head,
Large Facility Office (HLFO). Smaller-scale projects will provide status reports to the PO with a
frequency and level of detail defined in their respective Internal Management Plans (IMPs). In
every case, the PO is responsible for keeping the appropriate NSF staff (Grants and Agreements
or Contracting Officer, Division Director (DD), Assistant Directors (ADs), Integrated Project Team
(IPT) members, etc.) informed of the project status.
In executing and controlling the project, the Recipient manages the project to the Performance
Measurement Baseline (PMB) definition for cost, schedule, and scope. As part of routine
reporting process, the Recipient will notify the PO of project cost and schedule variances
exceeding ±10%, including explanations of causes and any correction actions, at the WBS levels
agreed upon between NSF and the Recipient. Per Section 4.6.4 NSF’s Performance Metric for
Construction, the Recipient will notify the PO of total project cost and schedule variances, at
Level 1 of the WBS, exceeding ±10%, including a recovery plan, with an associated timeline.

Variance reports provided by Recipients are used by NSF in its metrics for construction project performance goals, In
accordance with the GPRA Modernization Act of 2010. See Section 4.6.4, NSF Performance metric for Construction.

1

Section Revision:
December 14, 2018

4.6.2-2

Major Facilities Guide: NSF 19-68 (May 2019)
4.6.3 Recipient Performance Reviews and Audits
Prepared by the Large Facilities Office (BFA-LFO) and the Cooperative Support Branch (BFA-CSB) in the
Budget, Finance, and Award Management Office

Recipient Performance Reviews and Audits
4.6.3.1 Recipient Internal Reviews
The Recipient will demonstrate appropriate internal management by conducting its own
reviews and internal audits in conformance with generally accepted accounting standards,
project or operations management practices, and State and Federal regulations as appropriate.
These reviews include, but are not limited to, technical, design readiness, procurement
readiness, progress and planning, risk, safety and acceptance reviews as well as self-audits. The
kind and frequency of all reviews and audits should be addressed in the Project Execution Plan
(PEP-14.2). Although internal review team’s members are typically project staff, consideration
should be given to the inclusion of outside subject matter experts, who can provide a valuable
independent perspective. Consideration should also be given to inviting NSF staff as observers.
4.6.3.2 NSF External Reviews
NSF requires periodic external reviews that provide advice on the status and anticipated future
performance of the facility activities. The frequency and content of these reviews are specified
in the terms and conditions of the award instrument. Typically, the periodic reports (monthly,
quarterly, annual) are used to help evaluate and monitor progress and provide information to
review panels. Additional ad hoc reviews may be conducted by the PO under certain
circumstances, such as significant re-planning of construction projects, changes in management
structure, and major changes in research technical design, direction, or scope. These reviews
should determine the extent to which the facility is meeting the goals of their Annual Work Plan
as well as the overall goals for the award, discuss any upcoming challenges and highlight good
practices and lessons learned that could be applied to other NSF major facilities. Whenever
possible, the review should be conducted at the facility itself by an external panel with
expertise in the construction and operations of large scientific facilities.1 The panel should
produce a formal written report to NSF. In all cases, NSF should develop a review charge
written to elicit advice matched to the specific needs and challenges of the facility at the time.
Invitees to the review must include the PO, the Grants and Agreements or Contracting Officer,
and staff from the Large Facilities Office. These reviews should be coordinated other reviews
and audits listed in Section 4.6.3, such as the Business Systems Review (BSR).
Careful consideration should be given to the selection of independent reviewers, and in all
cases the skill sets of the reviewers should be matched to the type and kind of review to be
conducted. Broad programmatic review panels charged with reviewing all aspects of a project
will generally have representation from the academic and broader national/international
research community, as well as experts in administrative aspects of facilities/project

Consult with the NSF Program Officer for guidance and good practices with respect to planning and executing External
Reviews of NSF’s major facilities.

1

Section Revision:
May 30, 2019

4.6.3-1

Major Facilities Guide: NSF 19-68 (May 2019)
4.6.3 Recipient Performance Reviews and Audits
Prepared by the Large Facilities Office (BFA-LFO) and the Cooperative Support Branch (BFA-CSB) in the
Budget, Finance, and Award Management Office

management. A review panel focusing on specific administrative or technical aspects of a
project would have a different set of skills.
The PO may use a standard review “template” 1 developed by the Division or Directorate. These
provide a broad outline against which the project can be compared and may include checklists
that can be used to assess the status of the project. These formats can be particularly helpful in
the pre-award phase in ensuring that the project is ready to be implemented.
4.6.3.3 Business Systems Reviews (BSR)
The BSR is one of NSF’s advanced monitoring activities that assist with oversight and provide
assurance of the suite of business systems that support the administrative management of a
major facility. These reviews are designed to provide reasonable assurance that the business
systems (people, processes, and technologies) of NSF Recipients are effective in meeting
administrative responsibilities and satisfying federal regulatory requirements including those
requirements listed in NSF’s Proposal & Award Policies & Procedures Guide (PAPPG).
Specifically, a BSR verifies that administrative, including financial, policies and procedures are
written; evaluates the extent to which these policies and procedures conform to OMB
requirements, NSF expectations, and other applicable federal regulations; and validates they
are being used to administratively manage the major facility in each of the core functional
areas. BSRs are also intended to provide an opportunity for cross-fertilization of ideas through
the identification of good practices and serve to refocus Recipients on the importance of
administrative quality.
The LFO has the lead role in coordinating the assessment of these systems by using desk
reviews and site visits to determine if the administrative business systems used in managing the
facility meet NSF expectations and are in compliance with federal regulations.
BSRs are conducted on a regular review cycle which is informed by the internal NSF annual
Major Facility Portfolio Risk Assessment. For major facility projects, the BSR can be used to
strengthen the Institutional capacity in advance of a construction award. Risk factors reviewed
during the annual Major Facility Portfolio Risk Assessment typically include:
•

The timing and associated findings of other related reviews or audits of administrative
business systems;

•

Management structure providing administrative business systems support, and;

•

Significant changes in funding levels or the Recipient’s award administration.

Further information and various details of the BSR process are provided in the BSR Guide, 2
which defines and establishes the procedures for the planning, execution and follow-up
1

Please contact the cognizant NSF PO for details and a description of good practices and/or preferred templates.

2

See "Business Systems Review (BSR) Guide” at the NSF Large Facilities Office website.

Section Revision:
May 30, 2019

4.6.3-2

Major Facilities Guide: NSF 19-68 (May 2019)
4.6.3 Recipient Performance Reviews and Audits
Prepared by the Large Facilities Office (BFA-LFO) and the Cooperative Support Branch (BFA-CSB) in the
Budget, Finance, and Award Management Office

activities associated with conducting BSRs. The Guide also defines the roles and responsibilities
of NSF staff assigned to BSR activities and identifies core functional and targeted review areas.
4.6.3.4 Incurred Cost Audits
For cooperative agreements, NSF conducts an incurred cost audit for major facility awards
above $70M at the end of the award and potentially during execution of the award based on an
annual risk assessment conducted by the Large Facilities Office and the Cooperative Support
Branch at NSF. These incurred cost audits are required for construction awards. Recipients
should be prepared for such an audit at any time based on 2 CFR § 200.205-7 of the Uniform
Administrative Requirements, Cost Principles and Audit Requirements for Federal Awards and
as stated in the terms and conditions in the Cooperative Agreement. For contracts, incurred
cost audits are performed in accordance with in the FAR, the cognizant Federal Agency
procedures, and terms and conditions of the contract.
The purpose of the Incurred Cost Audit is to provide prudent oversight for those responsible for
the effectiveness, efficiency, and economy of the Recipients' operations and the use of Federal
funds. The Incurred Cost Audit is performed to assure the existence of adequate controls which
will prevent or avoid waste, fraud, and abuse and inefficient practices.
In preparation for an incurred cost audit, Recipients are required to submit financial
expenditures (incurred cost) data to NSF on a frequency to be determined by the Grants and
Agreements Officer and the Cooperative Agreement’s Terms and Conditions. It will be no less
frequently than annually. NSF Financial Data Collection Tool for Major Facilities, created by NSF
to assist Recipients in preparing and recording financial expenditure information for its
cooperative agreements for major facilities, is required for submission of the financial
expenditures data. The NSF Financial Data Collection Tool for Major Facilities is a macroenabled Excel workbook that provides Recipients a single, standardized method for submitting
direct and indirect expenditure data with minimal effort and help to ensure data quality and
accuracy. It will enable NSF and independent auditors to more easily and consistently collect
the financial data required to maintain proper oversight and stewardship over funds and
facilitate Recipient compliance in meeting its reporting requirements.
To complete the data collection, Recipients will need to collect expenditure information for all
active Cooperative Agreements and Cooperative Support Agreements during the awards
performance period. Suggested sources from which to collect this data include the Recipient’s
Chart of Accounts, General Ledger, Project Cost Ledger, NSF Award budget, and the award
organization’s Negotiated Indirect Cost Rate Agreement. To submit expenditure data,
Recipients can download the NSF Financial Data Collection Tool for Major Facilities file from
NSF at: http://www.nsf.gov/bfa/lfo/lfo_documents.jsp
Once downloaded, Recipients should save the file and then begin to enter data following the
guidance provided in the tool. See Figure 4.6.3-1 for a flow diagram for data entry. Recipients
Section Revision:
May 30, 2019

4.6.3-3

Major Facilities Guide: NSF 19-68 (May 2019)
4.6.3 Recipient Performance Reviews and Audits
Prepared by the Large Facilities Office (BFA-LFO) and the Cooperative Support Branch (BFA-CSB) in the
Budget, Finance, and Award Management Office

are instructed to submit this data collection annually to NSF as well at the end of your project
or based on the Terms and Conditions of the award. When completed, this NSF Financial Data
Collection Tool for Major Facilities will allow submission financial data electronically to the NSF
Grants and Agreements Officer or an independent auditor. Questions regarding this collection
should also be directed to the responsible NSF Grants and Agreements Officer.
Figure 4.6.3-1

NSF Financial Data Collection Tool for Major Facilities Process Flow Diagram, identifying the
core data sources Recipients should utilize to complete the worksheets to accurately capture
the data. Progressing through the tool's worksheets from left to right will streamline the data
capture and submission process.

4.6.3.5 Accounting System Review or Audits
Recipients must maintain adequate internal controls, policies and procedures, and reliable
accounting systems. NSF’s efforts to implement additional procedures to enhance oversight
capability include requiring accounting system analysis in certain circumstances. Specifically, in
order to assess and determine if a Recipient’s accounting system is adequate for use with cost
reimbursement type agreements, NSF will analyze the Recipients’ accounting systems /
practices prior to entering into any new major facility construction cooperative agreements
totaling $70 million or more, in those cases where such a review has not been performed within
the past two years.
NSF may also procure accounting system reviews or analysis for Recipients when a Grants and
Agreements Officer cannot conclude whether a Recipient’s accounting systems are adequate or

Section Revision:
May 30, 2019

4.6.3-4

Major Facilities Guide: NSF 19-68 (May 2019)
4.6.3 Recipient Performance Reviews and Audits
Prepared by the Large Facilities Office (BFA-LFO) and the Cooperative Support Branch (BFA-CSB) in the
Budget, Finance, and Award Management Office

determined needed during the annual risk assessment. NSF will review any recent accounting
analysis or audit submitted by the Recipient, and to the extent such reviews meet NSF’s needs,
we will be used in lieu of a new review.
4.6.3.6 Earned Value Management Verification, Acceptance, and Surveillance
NSF requires major facility project Recipients use EIA-748 compliant Earned Value Management
System (EVMS) as an integrated management tool for successful project planning and
execution. To ensure that the Recipient’s EVM data provide timely, accurate, and reliable
performance information, NSF conducts project EVMS verification, acceptance, and surveillance
based on the processes recommended in the National Defense Industrial Association (NDIA)
Earned Value Management (EVM) Guides1 as part of the project oversight and monitoring
activities. Section 6.8 of this Guide discusses basic principles and guidelines for implementation
of EVMS.
The project should demonstrate it has a structured management process that follows the
principles of EIA-748 EVMS standards and provides a sound basis for performance
measurement, problem identification, corrective actions, and management re-planning
activities as required. NSF’s EVMS verification and acceptance of a project is intended to ensure
that the implementation of EVMS for the project is appropriately tailored to the project’s
management needs. For the project to utilize the full benefits of EVMS and aid the successful
execution of the project plan, the EVMS should be properly scaled and the 32 guidelines applied
in a way that reflects the size, complexity, risk, and nature of the work. NSF’s acceptance of a
project’s EVMS is not intended to be a certification of a Recipient’s EVMS. As a result, it should
not be used by other government or contracting agencies, nor can it be extended to other NSF
projects managed by the Recipient. If a Recipient has a current EVMS certification from another
Federal Agency, the NSF EVMS verification review may be modified, but NSF acceptance will
still need to be documented and on-going surveillance performed.
The project’s EVMS verification is performed through a Compliance Evaluation Review (CER)
process. NSF strongly encourages projects to utilize EVM to the extent practicable during the
Design Stage to prepare for full implementation during the Construction Stage. NSF will
complete the CER well in advance of the award of construction funds. The NSF acceptance of
the project’s EVMS should occur before actual physical construction or major acquisitions
commence and will be based on acceptable resolution of the findings from the CER.
The LFO has responsibility for NSF’s EVMS verification, acceptance and surveillance process.
Working closely with the Project Team, the LFO Liaison and the Program Officer will determine
the best time for conducting the initial CER and any follow-up activities for acceptance. After
acceptance, periodical surveillance reviews should be conducted during the construction stage
to ensure that the accepted EVMS is being maintained and followed, and that the EVM data
1

Refer to Section 7 Refences of this Guide for a list of these NDIA guides.

Section Revision:
May 30, 2019

4.6.3-5

Major Facilities Guide: NSF 19-68 (May 2019)
4.6.3 Recipient Performance Reviews and Audits
Prepared by the Large Facilities Office (BFA-LFO) and the Cooperative Support Branch (BFA-CSB) in the
Budget, Finance, and Award Management Office

and information are being used to inform project management decision making. The frequency
and focus of surveillance reviews are determined by the Program Officer in consultation with
the Large Facilities Office via the LFO Liaison, but are generally conducted as part of the annual
construction review to minimize burden. The scope of the surveillance reviews can be inclusive
of all EIA-748 guidelines or can concentrate on specific areas of interests. Targeted surveillance
reviews may result from corrective actions, new procedures, and/or demonstration of practice.

Section Revision:
May 30, 2019

4.6.3-6

Major Facilities Guide: NSF 19-68 (May 2019)
4.6.4 NSF Performance Metric for Construction
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

NSF Performance Metric for Construction
In accordance with the Government Performance and Results Modernization Act (GPRAMA) of
2010 (Public Law 111-352); Empowering the Nation Through Discovery and Innovation: NSF
Strategic Plan for Fiscal Years (FY) 2011-2016; and OMB requirements, NSF developed goals to
measure construction/upgrade performance based on EVM systems used to monitor project
cost and schedule. For MREFC-funded projects 1 under construction and more than 10 percent
complete, the NSF performance metric goal (using EVM) is keeping both the total project cost
and schedule variances against the Performance Measurement Baseline at, or better than,
negative 10 percent. Projects that are less than 10 percent complete are not held to this goal
because EVM data is less meaningful statistically in the very early stages of a project.
Total project variances exceeding 10 percent (positive or negative) should be reported to NSF
by the Recipient and be accompanied by an explanation and a proposed plan and timeline for
recovery or accommodation of the cost and schedule shortfalls (e.g., use of contingency, descope). 2

This includes facilities whose construction is partially supported by funds or in-kind contributions from outside agencies. In
such cases, the variance for the total project and the variance for the NSF-funded portion should be reported separately. For
example, if the total project variance is -7% and the NSF portion is -12%, then the -12% would be reported, accompanied by a
recovery plan. Alternatively, if the total project variance is -15% and the NSF variance is -11%, then both variances would be
reported with appropriate recovery plans with timelines.

1

2

See section 4.6.2 for requirements on variance reporting at lower WBS levels for monthly progress reports.

Section Revision:
November 25, 2016

4.6.4-1

Major Facilities Guide: NSF 19-68 (May 2019)
4.6.5 Re-Baselining
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Re-Baselining
If maintaining the original PMB via re-planning is no longer possible, and the scope, total
project cost, or approved project end date are in jeopardy, the Recipient will consult with the
PO to determine whether re-baselining the project is warranted. When deciding which course
of action to pursue, the PO will need to balance the effect of failing to achieve the project’s
performance goals against the impact on the research and education proposed for the
completed facility.
The PO should consult with the NSF Integrated Project Team and the Directorate/Division
Leadership, prior to authorizing re-baselining a project. Variances may result from many
factors – for example, inadequate project planning or management, or factors not within the
Project Director’s (or manager’s) control. Examples include failure to identify the complexity in
particular tasks (such as integration), failure to budget for adequate labor, materials or time
versus unexpected increases in the cost of labor and/or materials, unavailability of labor and/or
materials, unusually severe weather, etc.
For construction projects, uncertainties are normally managed through re-planning1 and the
use of contingency, per Section 4.2.5. Re-baselining for construction projects occurs for
variances that result in:
1. Increases above the NSB-authorized Total Project Cost (TPC),
2. A change in the total project duration, and/or
3. Major changes in scope.
NSF approvals are required per Section 2.4.1 of this Guide. If only the schedule is extended
without an increase in TPC, the terms and conditions of the award instrument apply (i.e. NSF
policy on No-Cost Extension for CAs).
Re-baselined projects will generally go through external panel review depending on the timing
and expediency required, all stage complete NSF cost analysis, and Board authorization. Once a
re-baselined Project Definition has been authorized, the re-baselined requirements replace the
Baseline Project Definition as the standard against which progress is measured. Consequently,
costs exceeding budgeted amounts in the initial Baseline Project Definition are not referred as
“overruns” once a new project PMB has been implemented by the project management and
accepted by NSF.

1

See Section 2.4.1 for the definitions of “re-baselining” and “re-planning”.

Section Revision:
November 25, 2016

4.6.5-1

Major Facilities Guide: NSF 19-68 (May 2019)
4.7.1 Partnerships Overview
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

4.7

PARTNERSHIPS
Partnerships Overview

For both major facility and smaller projects, partnerships are an essential consideration –
beginning at project development and all the way through divestment. Partnerships may take
many forms, but typically include coordinated funding from states or state institutions, other
federal agencies, 1 non-governmental entities, and foreign funding agencies. International
partnerships are generally the most complex.
Key issues in these partnerships, whether international or the result of interagency or state
collaboration, present several important challenges that the Recipient and PO need to consider
carefully.
The first is “culture shock.” The science or engineering cultures in different countries will
generally exhibit great variations in procedures when it comes to funding, managing and
overseeing, constructing and operating a facility. Differences often include lack of mutual
understanding or considerably different contexts for defining the role and function of project
management. It is typically very challenging for each nation to manage its part of the project
unless there is a means for integrated management and oversight by the central Project
Manager.
The Project Director or Manager should be in place before funds are released and, to be most
effective, should be given budget authority (or authority over in-kind resources) and should not
simply act as a coordinator. In terms of oversight, reviews of project status by U.S. agencies are
not universally accepted. U.S. agencies use reviews heavily, but not all countries do. In some
countries, reviews that uncover problems may be received without a sense of urgency and may
not be acted upon quickly. U.S. partner agencies may be able to insist upon resolution of issues
when playing a majority role in funding; if not, other steps should be taken. Full project
transparency is essential to success.
A second important issue is early negotiation with international partners. There is a need to
start with a clear understanding by all partners as to how the construction project is to be
managed, or, in the case of operations, how the facility is to be operated. It is also important to
know how agencies (ministries) in different countries view the project in terms of shared goals,
the science or engineering case for the project, and its priority. If participating partner countries
all rate the priority of a project at the highest level, then commitments carry more weight.
Funding risks associated with international partnerships should be assessed and fall-back plans
developed regarding potential changes in commitment. Finally, early negotiation also provides
See “Best Practices for Federal Research and Development Facility Partnerships,” IDA Science & Technology Policy Institute,
IDA Paper P-5148 Log: H 14-000676, for guidance or models on forming interagency federal partnerships.

1

Section Revision:
November 25, 2016

4.7.1-1

Major Facilities Guide: NSF 19-68 (May 2019)
4.7.1 Partnerships Overview
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

a means to establish and maintain regular agency-to-agency contacts, providing an early
understanding of funding pressures and other emerging pressures in each country.
The cognizant NSF Program Officer should be informed of potential international partnerships
early in the process and kept apprised of significant developments. The cognizant Program
Officer will coordinate with the NSF Office of International Science and Engineering to ensure
that potential international partnerships are in compliance with U.S. law, NSF policy, and
current foreign policy and geo-political considerations.

Section Revision:
November 25, 2016

4.7.1-2

Major Facilities Guide: NSF 19-68 (May 2019)
4.7.2 Partnership Funding
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Partnership Funding
Funding of projects involving partnerships is obviously a central consideration. International
partner agencies need to understand the funding processes in the different countries involved.
The complexity of the NSF process can lead to misunderstandings regarding the schedule of
funding and project approvals. Because of the great variation among countries as to how labor
costs are counted, it is good practice to adopt standard costing techniques for equipment,
labor, commissioning and operations. MOUs need to be developed, detailing the foreign
contributions. In some cases, these contributions may be in cash or in-kind level of effort; but
deliverables should be clearly specified and the contributions should be valued in U.S.
equivalent terms (including all labor costs) for projects in which NSF is the lead agency. To aid
project management and eventual close-out, it should also be made clear what scope NSF and
the other partner are either paying for or contributing (by WBS element) and proper
segregation of funding rules employed as appropriate.
As with all such projects, contingency funds (or their equivalent) need to be identified by all
partners. There is great variation in practice among countries, again because labor costs may or
may not be included in contributions to the project. This can have a great impact. For example,
in a cost-overrun situation it may become expeditious to simply stretch the project out. This
may work for one country, resulting in less focus on schedule issues; but it generally does not
work for U.S. projects where “standing army” costs are directly allocated to the total cost for
construction of a facility.
In addition, when partner funding is in cash, variations in exchange rate can have a large effect
on the ability of a given country to meet its commitment on deliverables. Therefore, scope
contingencies need to be explored. When international partners do not include adequate
contingency, and the U.S. does, funding “caps” (agreed upon in advance) are an appropriate
practice. Although caps may enforce discipline, they may have other effects. For example, when
there are schedule slips and “standing army” costs rise, caps can limit the deliverables that may
be provided. Strict adherence to caps may therefore compromise the overall performance
goals.
Finally, a facility’s project management and operations plans should be well understood by all
partners. When different countries have responsibilities for separate subsystems, strong system
integration and comprehensive interface documents become very important. The changecontrol process needs to be clearly understood. Change control is made very complex because
performers in one country may be ill equipped to handle or adapt to required changes. It is also
very important to establish a sound schedule baseline and adhere to it.
For partnerships with organizations or agencies in the United States, the following activities are
advised:
•

Evaluate NSF’s role (NSF’s authority and responsibility vary depending on its status as
executive agent or as a majority, equal or minority partner). Assess risks and develop a

Section Revision:
June 17, 2015

4.7.2-1

Major Facilities Guide: NSF 19-68 (May 2019)
4.7.2 Partnership Funding
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

plan to address them, e.g., implementation of controls that limit NSF’s exposure to
overruns (see Section 5.2, Risk Management Guidelines).
•

Ensure that all partners understand the review and approval processes of the other
partners.

•

Prior to entering into a partnership, develop and execute an MOU.

Section Revision:
June 17, 2015

4.7.2-2

Major Facilities Guide: NSF 19-68 (May 2019)
4.7.3 Memorandum of Understanding (MOU) with NSF
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Memorandum of Understanding (MOU) with NSF
MOUs are broad, general agreements between NSF and other parties to pursue activities of
mutual interest and benefit; cooperate in areas where science and engineering interests
coincide; and provide a framework for cooperation. A typical MOU includes:
•

The purpose of the Understanding; authority of the parties to enter into an
Understanding;

•

Scope of the Understanding, including a project description and the respective
responsibilities of each party for funding, management and oversight (including
procedures for resolving conflicts and dealing with defaults);

•

Rights of each party with respect to access, ownership and intellectual property
(Chapter VII of the PAM); means for resolving disputes; and

•

A termination clause.

MOUs are developed by the PO and cleared according to procedures outlined in Chapter VIII of
the Proposal and Award Manual (PAM).

Section Revision:
December 14, 2018

4.7.3-1

Major Facilities Guide: NSF 19-68 (May 2019)
5 Guidance for Mid-Scale Research Infrastructure Projects
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

5

GUIDANCE FOR MID-SCALE RESEARCH INFRASTRUCTURE PROJECTS

This section addresses guidance for the planning and oversight of mid-scale research
infrastructure projects as defined in Section 1.4 of this Guide. These oversight processes draw
on the well-established good practices within sponsoring directorates and divisions for such
projects, which follow the requirements in the PAPPG.
Mid-scale project oversight requirements are to be tailored based on each project’s unique
characteristics such as the technical scope, the type and mix of work performed (e.g. standard
procurement by the Recipient, software development, or civil construction), and an assessment
of the associated technical and programmatic risks. However, NSF is committed to the principle
that this flexibility does not preclude the requirement for appropriate rigor on the part of NSF
or the Recipient. Appropriate use of NSF major facility oversight practices will be determined on
a case-by-case basis as outlined below.
Similar to major facilities, mid-scale project proposals should include actual costs and budget
estimates for all stages of the project life cycle: development and design, construction or
acquisition, operations, and divestment, although these stages may be less rigorously defined
depending on the project scope and history. For example, actual costs should be included for
investments previously made during development and design when submitting a proposal for
the construction or acquisition. Mid-scale project proposals should also include a Concept of
Operations discussion and the strategy and timeline for eventual divestment so the proposal
can include estimates for eventual operations and divestment. See the Project Execution Plan
(PEP) discussion below. The detailed programmatic requirements for these estimates will be
included in solicitations calling for mid-scale infrastructure.
Budgets should be supported by well-documented Basis of Estimates (BoE) developed in
accordance with the best practices and twelve steps outlined in the GAO Cost Estimating and
Assessment Guide to meet the four characteristics of a high-quality estimate: welldocumented; comprehensive; accurate; and credible (see Section 4.2 of this Guide). If use of
Earned Value Management (EVM) is proposed, schedules should be developed following the
best practices outlined in the GAO Schedule Assessment Guide (See Section 4.3 of this Guide).
Selection Criteria: Mid-scale projects are selected based on the merit review criteria detailed in
the program solicitation. However, some typical project characteristics that may be considered
are listed below.
•
•
•
•
•

Opportunity to enable frontier science and engineering (S&E) research and education;
Compelling research needs;
Priority within the relevant science communities;
Accessibility to an appropriately broad user community;
Level of maturity on collaboration of partnerships;

Section Revision:
May 30, 2019

5-1

Major Facilities Guide: NSF 19-68 (May 2019)
5 Guidance for Mid-Scale Research Infrastructure Projects
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

•
•
•

Budget alignment with solicitation and life cycle cost impacts;
Technical feasibility and consideration of risks; and
A Project Execution Plan (PEP) appropriately scaled to the project.

Unless a risk for award is identified by Office of Budget, Finance, and Award Management (BFA)
or Program during proposal review, there are generally no additional pre-award review
requirements once the NSF review and selection process are complete and a subsequent award
is made.
Review Process: Mid-scale projects are not subject to the formal stage-gate review process
given in Section 2.3 of this Guide. However, the internal proposal review process used by NSF
for construction/acquisition proposals should be sufficiently robust to assess readiness using a
similar philosophy to the Final Design Review but scaled appropriately to the program. This
review process will also include an assessment against the programmatic selection criteria given
in the solicitation.
These reviews, as well as reporting to assess progress against plan during implementation, will
be determined by the Program Officer in consultation with the Grants and Agreements Officer
and LFO Liaison (if applicable, see below). Reporting and progress review requirement will be
codified in the award.
Programmatic Deliverables: Mid-scale projects should be executed using well-established
project management methodology. The specific project management approach used should be
scaled to the needs of the project. For example, project management controls used to manage
project resources and schedules, the use of EVM, financial and progress reporting
requirements, and risk management techniques should be carefully considered such that
burden does not outweigh the benefit.
A Project Execution Plan (PEP) is required for all mid-scale projects in order to document the
foundation for how the project will be managed by the Recipient. Concurrence on an initial PEP
must be reached between NSF and the proposing organization. It is reasonable to expect the
PEP to evolve during the execution of the award.
The following list provides the minimum required components of the PEP for a mid-scale
project as compared to Section 3.4.1 of this Guide. The contents of each PEP component should
be tailored in both detail and scope to the specifics of the project. Refer to Section 3.4.1 of this
Guide for descriptions of typical elements of each PEP component. Unless otherwise noted in
the solicitation, the sub-topics within each PEP component should be included. Although, some
of the material may also be included in the mid-scale proposal itself, inclusion in the PEP allows
for completeness and reference in the award terms and conditions.
1.

Section Revision:
May 30, 2019

Introduction

5-2

Major Facilities Guide: NSF 19-68 (May 2019)
5 Guidance for Mid-Scale Research Infrastructure Projects
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

2.
4.
6.
8.
9.
10.
12.
13.

Organization
Construction Project Definition
Risk and Opportunity Management
Configuration Control
Acquisitions
Project Management Controls. The scope, complexity, budget profile, and
duration of a project should be assessed to determine the benefits for Earned
Value reporting versus its reporting burden.
Cyber-Infrastructure
Commissioning, including Concept of Operations

The PEP should be included in the Supplementary Information section of the proposal.
If the project will be integrated into a larger facility or instrument, the proposal should include a
section discussing planned system engineering activities. If the site selected has any known or
potential requirements for permitting or environmental impact studies, a discussion of this
should be included in the PEP. Section 6.5 of this Guide discusses environmental regulations
associated with construction or modification of facilities. Inclusion of other PEP components
detailed in Section 3.4.1 of this Guide is optional and should consider the unique attributes of
the project.
The Performance Measurement Baseline (PMB) for the project is set by the proposed scope,
budget, and schedule as defined at the time of the award. All reporting is done against this
project baseline. The baseline budget, budget contingency and fee (if any) comprise the Total
Project Cost (TPC). The estimation and use of budget contingency (if proposed) must follow
Section 4.2.5.7 of this Guide.
Although substantial rigor is required in establishing the TPC, mid-scale research infrastructure
projects are not subject to NSF’s “No-Cost Overrun” policy used for major facilities projects as
defined in Section 1.4.5.
PO Oversight: At the earliest practical point, each mid-scale project is assigned a cognizant NSF
Program Officer (PO) 1 with primary responsibility for award management and project oversight.
The PO (or POs) creates a Management Plan (MP) to document key project characteristics, the
planned oversight approach, and any extraordinary exceptions or additions to the guidance
presented in this section as part of the program solicitation development in accordance with
NSF policy. Formal Internal Management Plans (IMP) used for major facilities are not required.
Depending on the funding account, the PO assigned to manage mid-scale projects may be
required to be permanent NSF employees, as required by statute. The technical background
1

Also referred to within NSF as Program Director or Program Manager.

Section Revision:
May 30, 2019

5-3

Major Facilities Guide: NSF 19-68 (May 2019)
5 Guidance for Mid-Scale Research Infrastructure Projects
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

and experience of the cognizant NSF PO for a mid-scale project should be appropriate to latestage design and construction activities as determined by the Sponsoring Organization.
Interaction with the Office of Budget, Finance and Award Management (BFA): Program
Officers recommending mid-scale projects as defined in Section 1.4 of this Guide with a TPC
over $20 million must consult with BFA prior to award. To support oversight of stand-alone
mid-scale projects, the Large Facilities Office (LFO) will generally appoint one LFO liaison to
assist Programs and the Grants and Agreements Officers in the appropriate BFA unit, either
Division of Grants and Agreements (DGA) or Division of Acquisition and Cooperative Support
(DACS), depending on the nature of the project and the funding program. For mid-scale projects
that are upgrades to major facilities, the LFO Liaison assigned to that facility will provide
support to Program and the Grants and Agreements (or Contracting) Officer.
Integrated Project Teams: Mid-scale projects consisting of upgrades to existing NSF major
facilities should be coordinated through the NSF Integrated Project Team (IPT) for that facility.
Formal IPT’s are not required for stand-alone mid-scale projects.
Budget Inclusion and the National Science Board: Inclusion in the NSF budget is either done as
part of a Directorate-level or agency-wide program as described in the solicitation. While major
facilities require formal NSB authorization for future budget inclusion, the level of engagement
for mid-scale projects by the National Science Board is based on the annual award amount, the
current Board award authorization thresholds, and the account from which the project is
funded.

Section Revision:
May 30, 2019

5-4

Major Facilities Guide: NSF 19-68 (May 2019)
6.1 Introduction
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

6
6.1

SPECIAL TOPICS AND SUPPLEMENTARY MATERIALS
INTRODUCTION

This section contains extensive supplementary information on special topics having to do with
the National Science Foundation (NSF) role in planning, oversight, and assurance of major
facility projects. The materials are presented in a tutorial format to be of particular benefit to
individuals newly involved with major facility projects. They are based primarily on current
standards and good practices for project management.

Section Revision:
July 17, 2015

6.1-1

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.1 Introduction
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

6.2

RISK MANAGEMENT GUIDELINES FOR CONSTRUCTION STAGE
Introduction

Project risk management is a process which increases the probability of a successful project by
identifying threats to the project, assessing the nature of those threats, and identifying actions
that can be taken to either reduce the probability of those threats occurring or reduce the
impact of the threats to the project. Even on a simple project, things seldom go as planned.
With the highly-technical, scientifically ground breaking, and long duration projects undertaken
by the NSF there will be many changes required to the baseline plan as a project matures.
Successful projects anticipate problems, work to avoid those problems, and limit the impact
those problems will have on a project.
Risk management serves two purposes; one is to forecast impacts of possible events on the
project’s cost and schedule, the other is to prioritize and inform project decisions on alternate
strategies to mitigate the cost or schedule impact of a possible event or increase the technical
performance margin of a system or subsystem. The former (quantitative risk analysis) creates a
framework for quantifying the risks to the project goals in terms of cost in dollars, schedule in
days, and performance for the purpose of forecasting the final cost, schedule, and performance
of the complete project. The latter (qualitative risk analysis) helps the team sort through the
hundreds and perhaps thousands of risks to identify and address the ones that are most likely
to have the most significant impact on the project.
Qualitative risk analysis practices have remained relatively unchanged recently while
quantitative risk analyses have been evolving rapidly as the software tools and their integration
with scheduling software packages have evolved. While quantitative risk analysis has become
easier and more sophisticated, it is unlikely to fully replace qualitative risk analysis because the
quantitative analysis requires validated inputs that are more labor intensive to produce. Most
projects utilize the qualitative risk analysis practices for their month-to-month risk management
and implement quantitative risk analysis only when they need to re-forecast the estimate at
complete cost and completion date of the project.
Risk management involves all project personnel. With an effective risk management project
every project team member should be able to state the top project risks as well as the top risks
to their subsystem. Risk management has an inherent Malmquist (completeness) bias – there
will always be more risks to a project then are reflected in the risk register. To minimize this
effect every project team member from every perspective in the program should be
contributing threats, opportunities, and mitigation ideas to the risk board. The team also needs
to be well aware of the risks associated with their subsystems so they recognize how a mistake
in their area would impact the overall project (an aspect of human error prevention and project
safety).

Section Revision:
November 25, 2016

6.2.1-1

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.1 Introduction
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Some projects refer to risk management as risk and opportunity management, to emphasis to
the team that they should also be thinking about opportunities for changes in the baseline plan
that could save cost, save schedule, or improve performance. This section follows the Hulett
definition of risk that is in the Project Management Body of Knowledge (PMBOK) that includes
opportunities in the definition of risk. Project teams should remind each other to keep thinking
about new opportunities as well as threats to the project.
Risk and opportunity management feeds into the key decisions that make a project successful.
It is a core activity for project managers, systems engineers, subsystem leads, program officers,
and review panels.
NSF requires major facility Recipients to develop and follow formalized Risk Management
during the design and construction stages of major facility projects.
Successful Risk Management entails early recognition, proactive planning, and aggressive
execution of all risk management processes. Ideally Risk Management begins as early as the
initiation stage of the project life cycle. This Guide provides detailed information on the Risk
Management 1 methodologies and strategies commonly applied during project planning and
execution.
There are three key products of Risk Management as applied to NSF construction projects:
•

A Risk Management Plan that sets out how risks will be identified and managed by the
project following standard risk management processes and practices,

•

A Risk Register, or tracking tool, that documents identified risks, and

•

A determination of Risk Exposure and the related amount of Contingency needed to
control risks, based on quantitative risk analysis.

The Risk Management Plan (RMP) is a required element of the Project Execution Plan (PEP)
described in Section 3.4 of this Guide (often as a separate document). A RMP should be
included in the project planning and proposals no later than the start of the conceptual design
phase. The Plan should identify the responsibilities for risk management and describe the Risk
Management process that will be followed— including roles and responsibilities, procedures,
criteria, tools, and techniques to be used to identify, analyze, respond to, and track project
risks. The level of detail in the plan, and the scope, timing, and level of risk analysis should be
commensurate with the maturity and complexity of the project and may evolve and change
over time. An example of an acceptable RMP outline is shown in Table 6.2.5-1.
The Risk Register – typically a spreadsheet or data base – is a tracking tool that includes a
description of all risks that are deemed to be important to achieving project success, along with
The NSF Program Officer, as part of oversight responsibilities, identifies project-related agency risks to NSF, formulates
mitigation strategies, and documents them in an Internal Management Plan (IMP), accessible only to NSF staff.

1

Section Revision:
November 25, 2016

6.2.1-2

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.1 Introduction
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

an assessment of those risks that allows them to be prioritized for effective management. The
Risk Register also includes the risk handling strategy, the person to whom each risk has been
assigned for accountability purposes, the current status of the risk handling strategy, and
comments. An example of a commonly used style for a Risk Register is given in Table 6.2.5-1. It
should be noted that appropriate tracking tools will vary among projects because the types of
information and indicators being monitored vary from project to project. The selection and
definition of a tracking system to be used in a project should be commensurate with the size
and complexity of the project and should be defined in the project’s RMP.
Risk Management strategy involves the estimation of overall risk exposure and the
determination of an adequate amount of contingency – a quantity of money, scheduled time,
or reductions in scope intended to recover project objectives if uncertainties and risks occur
with negative impacts. The values for cost and schedule contingencies are taken from
distributions generated by Monte Carlo simulations with probability and impact ranges for
uncertainty and risks for activities defined in the baseline. The confidence levels for meeting a
chosen project end date and total cost should lie between 70% and 90%. Scope contingency
involves identifying lower priority tasks that can be delayed or dropped from the project
without a crippling impact to project objectives. De-scoping may be used if the project forecast
indicates that cost or schedule overruns are likely. For NSF major facility projects, these
contingencies are held separately from the project Performance Measurement Baseline (PMB) 1
budget, schedule, and scope. Strategies for using contingency are detailed in the project Risk
Management Plan. Contingency is controlled and managed through the project
Configuration/Change Control Process (CCP). The use of contingency is subject to approval by
project leadership, and by NSF, if amounts are above certain thresholds, as defined in the
cooperative agreement (CA).
While the text of this section tends to refer to projects in construction, good risk management
practices can be useful throughout a project’s life cycle, including during operations. “The best
laid schemes of mice and men / Often go awry.” Implementing preventative mitigations and
pre-planning alternative strategies will reduce the likelihood and impact of these events.
The following subsections provide guidelines for planning the Risk Management processes,
developing the RMP, creating a Risk Register, and calculating a quantized measure of risk
exposure that leads to the establishment of contingencies. Examples of accepted or good
practices are included as guidelines.

Performance Measurement Baseline (PMB) is the approved cost and schedule plan established at award for accomplishing the
scope that can be changed only through formal change control process.

1

Section Revision:
November 25, 2016

6.2.1-3

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.2 Definition of Project Risk and Risk Exposure
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Definition of Project Risk and Risk Exposure
Risks are defined many ways. One of the most inclusive definitions, and the one used in these
guidelines, is; “… an uncertain event or condition that, if it occurs, has a positive or negative
effect on at least one project objective.” 1
Most international standards agree that risk is made up of both threats and opportunities.
Capturing and capitalizing on opportunities to reduce costs, save time, and improve technical
performance may improve the possibility of finishing on time, budget, scope and quality by
offsetting the negative impact of threats to those objectives. The tools and methods employed
in managing threats are also used to identify and take advantage of these opportunities for
reducing project cost or schedule or improving technical performance. NSF requires
Opportunity Management as a necessary component of risk management.
Project Risk Exposure is the quantized result on project objectives of various risks and
uncertainties occurring. Project risk exposure is usually expressed as an amount of budget or
time that is the output of a Quantitative Risk Analysis that combines probability of occurrence
with consequence. Project risk exposure diminishes over time as risks are realized or avoided
and should always be less than or equal to remaining contingency amounts.

1 This definition is used in the Guide to the Project Management Body of Knowledge, (PMBOK® Guide), Project Management
Institute, 5th Edition, 2013, Chapter 11.

Section Revision:
May 2, 2016

6.2.2-1

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.3 Definition of Allowable Contingencies
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Definition of Allowable Contingencies
Contingencies are a necessary component of risk management for NSF projects – they provide
the wherewithal and flexibility to control risks and realize opportunities. Contingency
allocations are for in-scope deliverables and are to be used to mitigate identified risks and
uncertainties that may impact a projects ability to achieve approved project objectives.
6.2.3.1 Allowable Contingency
Most risk management guides define two general types of budget and schedule contingency:
Contingency: “a planned amount of money or time which is added to a baseline
estimate to address specific, identified risks.” 1 It is an estimated amount based on
various risk management techniques and managed by the project.
Management reserve: “a planned amount of money or time which is in addition to the
baseline estimate and contingency to address unforeseeable events.” 2 It is not managed
by the project.
NSF does not normally carry management reserves as defined above. For NSF projects, only the
first type, Contingency, is allowed in the Recipient’s portion of the NSB authorized Total Project
Cost (TPC). This means that the estimation of contingency amounts should be tied to risks
identified at the time the total budget and duration are set, and that such contingency can only
be used to mitigate those pre-identified risks. See Section 6.2.7 for using proper quantitative
estimating methodologies for determining risk-based contingencies.
In addition to budget and schedule contingency planning, NSF requires projects to assess
possible use of scope contingency and to develop a plan to make effective use of scope
contingency options, if necessary, during construction. This provides the project with an
additional tool to manage the overall project. Use of all contingency is managed through formal
change control processes, as described in Section 4.2.5.
6.2.3.2 Contingency Definitions
Contingency for NSF projects includes cost, schedule, and scope amounts, as defined below:
Budget Contingency: An amount added to a baseline budget estimate to allow for identified
items, conditions, or events for which the state, occurrence, or effect is uncertain and that

Identified risks are often referred to as “known unknowns” in the literature. In other words, a risk that can be identified during
planning is “known,” but the probability of occurrence and the extent of its impact cannot be determined with accuracy and are
therefore “unknown.”

1

Unforeseeable events are those that are not or cannot be identified during planning and are typically referred to as “unknown
unknowns” in the literature. They may also include low probability, extreme events that are beyond project control, such as the
effects of terrorism and war, natural disasters with impacts beyond expected historical ranges, or global economic crises.

2

Section Revision:
May 30, 2019

6.2.3-1

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.3 Definition of Allowable Contingencies
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

experience shows will likely result, in aggregate, in additional costs. Typically estimated
using statistical analysis or judgment based on past asset or project experience.
For major facility construction projects, the amount of budget contingency is determined by
performing a probabilistic risk analysis on the baseline cost and schedule and selecting a total
project cost with an acceptable confidence level (typically between 70%-90%). See Section 4.2.5
for details on total project cost requirements. Budget contingency is held separately from the
Performance Measurement Baseline (PMB) and allocations of budget contingency to and from
the PMB are managed through formal change control.
Schedule contingency: An amount added to a baseline schedule estimate to allow for
identified delays, conditions, or events for which the state, occurrence, or effect is uncertain
and that experience shows will likely result, in aggregate. Typically estimated using
statistical analysis or judgment based on past asset or project experience.
For major facility construction projects, the amount of schedule contingency is determined by
performing a probabilistic risk analysis on the baseline schedule of activities and selecting a
commitment finish date with a confidence level between 70%-90%. The project end date is
determined by the sum of the baseline duration and the selected contingency amount.
Schedule contingency is held separately from the PMB and allocations of schedule contingency
to and from the PMB are managed through formal change control.
Scope contingency: Scope included in the project baseline definition that can be removed
without affecting the overall project’s objectives, but that may still have undesirable effects
on facility performance. Identified scope contingency should have a value equal to at least
10% of the baseline budget.
Scope contingency can be retained or deleted, depending on project risk performance and
available contingency, in order to stay within the total project cost. A scope management plan
includes a time-phased estimate of available budget and or time from de-scoping options,
based on key decision points. See Section 4.2.5 for details on requirements. Implementation of
scope contingency options is managed through formal change control.

Section Revision:
May 30, 2019

6.2.3-2

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.4 Risk Management Steps and Methodology
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Risk Management Steps and Methodology
The steps involved in the Risk Management process have been defined variously by different
practitioners. For the purposes of these guidelines, the Risk Management process is defined as
comprising the following steps: 1
•
•
•
•
•
•

Risk Management Planning
Risk Identification
Qualitative Risk Analysis
Quantitative Risk Analysis
Risk Response Planning
Risk Monitoring and Control

The relationship between these steps is shown in Figure 6.2.4-1.
Figure 6.2.4-1

Picture of Six Risk Management Processes (According to PMI) 2

Risk Management
Planning

Risk
Identification

Risk Monitoring
and Control

Qualitative Risk
Analysis

Risk Response
Planning

Quantitative Risk
Analysis

The Risk Management steps outlined above are iterative and continuous and any one step, or
all of the steps, could be active at any given time. Risk analysis is performed continuously
throughout the project life cycle. For example, a conceptual risk analysis may be conducted to
1

The six steps are the same as the processes described in the PMBOK® Guide Chapter 11.

Risk Handling and the Project Management Institute’s Risk Response Planning process are somewhat equivalent. Risk Handling
includes implementing the risk mitigation and other responses, whereas Risk Response Planning envisions that these actions
will be included in the Project Execution Plan and implemented as part of the PEP.

2

Section Revision:
May 2, 2016

6.2.4-1

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.4 Risk Management Steps and Methodology
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

facilitate selection between alternative options, to determine the level of project management
required, to identify where the challenges lie, and to determine the level of technical
information and development activity necessary to achieve project success. That risk analysis is
then updated during each of the life cycle phases of the project. Performing risk analysis is
particularly necessary in preparing for key project decisions. Periodic reviews of the risks at
appropriate intervals should be performed to identify new risks, to evaluate progress in risk
handling strategies, as well as to evaluate changes during the project development and
implementation cycles. Risk Management Planning, and the RMP, may also need to be
re-addressed at times of significant change, such as transitions from one project life cycle to
another or during a re-baselining with significant modifications to the project baseline.

Section Revision:
May 2, 2016

6.2.4-2

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.5 Risk Management Planning
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Risk Management Planning
Planning begins by developing and documenting a Risk Management strategy. Early efforts
establish the purpose and objectives, assign responsibilities for specific areas, identify
additional technical expertise needed, describe the assessment process and areas to consider,
delineate considerations for mitigation planning, define a rating scheme, dictate the reporting
and documentation needs, and establish report requirements. The strategy to manage root
causes provides the program team with direction and a basis for planning. The output of risk
management planning is a written document – the Risk Management Plan (RMP) – containing
the details of how risk will be managed through application of tools and processes defined in
the plan. See the next subsection for a description of requirements for the RMP.
One key strategic decision that should be made early in the Risk Management planning is the
selection and assignment of personnel with appropriate capability in Risk Management to lead
and/or guide the planning and analyses. As will be seen from the topics presented in the
analysis portion of the section, the art and science of risk management can be extremely
complicated for complex, high risk projects. While project managers, scientists and engineers
may have expert knowledge and judgment for identifying, estimating impacts from, and
defining mitigation for individual risks, they are usually not expert in estimating the overall or
aggregate risk exposure to the project from the combined impact of many individual risks.
Finding qualified resources to meet the risk management requirements of the project,
particularly for establishing the amount of contingency, should be a high priority for early
planning in order to ensure that methodologies and programming tools can be selected and
implemented in a timely manner. Options include sending existing staff for specialized training
in risk management and tool usage, directly hiring risk management experts, contracting with
industry, or some combination of the above.
A second early key decision is the determination of what risk assessment methodologies and
tools will be used, from first estimates through construction. The sophistication of the
appropriate risk assessment tools typically increases with advancing planning detail and
maturity, as well as with increasing project complexity. A project that includes a high number of
procurements and in-house tasks typically requires software applications and methods that use
a fully resource loaded schedule for risk assessment and contingency estimation, while a
project entailing management of a single large contract may be adequately served by tools and
methods that use cost spreadsheets and summary level schedules. Choosing the appropriate
tools and methods at the outset can avoid the need and the burden of changing to different
systems as the project planning matures.
Risk Management planning is iterative. Normally, the risk management methodology and
procedures are defined as part of the risk management process planning early in the design
stage, but they may be extended or modified during design and execution as long as the efforts
remain within approved scope.

Section Revision:
May 2, 2016

6.2.5-1

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.5 Risk Management Planning
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

6.2.5.1 Risk Management Plan (RMP)
The Risk Management Plan (RMP) describes how risks are documented and risk management
will be applied on the project. It is an integral part of the PEP, as outlined in Section 3.4 of this
Guide. The level of detail in the plan and the scope, timing, and level of risk analysis should be
commensurate with the complexity and maturity of the project as it advances through design
and construction stages. The plan is a living document used throughout design and
implementation and should therefore be under configuration management. The Risk
Management Plan should include the following elements:
•
•
•
•
•
•

Risk Management Strategy and Approach
Roles and Responsibilities
Processes used to apply the Risk Management process
Baseline definition for Calculating Risk Exposure and Contingency needs
Contingency Estimating and Management
Resources assigned to and schedule, cost, and timing of risk management activities

The Recipient should periodically review the RMP and revise it, if necessary. Some events may
drive the need to update an existing RMP, such as: (1) the baselining of a project,
(2) preparation for a major decision point, (3) technical audits and reviews, (4) an update of
other project plans, and (5) a change in major project assumptions. A sample format with the
expected content for a Risk Management Plan (RMP) is outlined in Table 6.2.5-1.
Table 6.2.5-1
Section

Sample Format for a Risk Management Plan

Description

1.

Introduction

This section should address the purpose and objective of the plan, and provide a
brief summary of the project, to include the approach being used to manage the
project, and the acquisition strategy.

2.

Definitions

Definitions used by the Recipient should be consistent with NSF definitions for ease
of understanding and consistency. However, the NSF definitions allow program
officers flexibility in constructing their risk management programs. Therefore, each
Recipient’s RMP may include definitions that expand the NSF definitions to fit its
particular needs. For example, each plan should include, among other things,
definitions for the ratings used for technical, schedule, and cost risk in qualitative
risk analysis.

3.

Risk
Management
Strategy and
Approach

Provide an overview of the risk management approach, to include the status of the
risk management effort to date, and a description of the project risk management
strategy.

4.

Organization

Describe the risk management organization of the Recipient and list the roles and
responsibilities of each of the risk management participants.

5.

Resources
Implications of
the Plan

The resources to be used in managing risk on the project should include the time of
management and project team members as well as risk specialists and contractors if
appropriate, to manage effectively the risks on the project. These risk management
costs should appear specifically in the project budget.

Section Revision:
May 2, 2016

6.2.5-2

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.5 Risk Management Planning
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)
Section

Description

6.

Schedule
Implications of
the Plan

The time periods in the project schedule when risk management activities are
planned to occur. Activities providing sufficient time to perform the tasks and
milestones to record their completion should be inserted in the project schedule
and statused along with the schedule statusing plan.

7.

Risk
Management
Process and
Procedures

Describe the project risk management process to be employed, i.e., risk planning,
qualitative and quantitative risk assessment, handling, monitoring and
documentation, and a basic explanation of these components. Also provide
application guidance for each of the risk management functions in the process. If
possible, the guidance should be as general as possible to allow the project’s risk
management organization flexibility in managing the project risk, yet specific
enough to ensure a common and coordinated approach to risk management. It
should address how the information associated with each element of the risk
management process will be documented and communicated to all participants in
the process, and how risks will be tracked to include the identification of specific
metrics if possible.

8.

Risk Planning

This section describes the relationship between continuous risk planning and this
RMP. Guidance on updates of the RMP and the approval process to be followed
should be included.

9.

Risk
Identification

This section of the plan describes the identification process. It includes procedures
to be used for examining the critical risk areas and processes to identify and
document the associated risks.

10. Risk Register
Analysis and
Ranking

This section summarizes the analyses process for developing a qualitative or
quantitative risk rating and populating the Risk Register. This rating is a reflection of
the potential probability of each risk and the impact of each risk on the project
schedule, cost, scope and quality. It also describes how the risk analysis data will be
collected and maintained throughout the project’s life cycle.

11. Probabilistic Risk
Analysis and
Contingency

This section describes the way the project will analyze the implications of identified
and quantified risks on the total project schedule and cost objectives or major
milestones. Typically, a Monte Carlo simulation is used based on the project
resource-loaded schedule or on the cost estimate if a schedule is not available. This
section also describes the use of the risk analysis results for setting contingency
amounts and prioritizing risks for risk mitigation.

12. Risk Handling

This section describes the risk handling options, and identifies tools that can assist
in implementing the risk handling process. It also provides guidance on the use of
the various handling options for specific risks.

13. Risk Monitoring

This section describes the process and procedures that will be followed to monitor
the status of the various risk events identified including the frequency and
organizational level of risk review. It provides for identification and calibration of
new risks should they arise. It should provide criteria for the selection of risks and
risk mitigations to be reported on, and the frequency of reporting. Guidance on the
selection of metrics should also be included.

14. Risk
Management
Information
System,
Documentation
and Reports

This section describes the management information system structure, rules, and
procedures that will be used to document the results of the risk management
process. It also identifies the risk management documentation and reports that will
be prepared; specifies the format and frequency of the reports; and assigns
responsibility for their preparation and dissemination.

Section Revision:
May 2, 2016

6.2.5-3

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.5 Risk Management Planning
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)
Section

Description

15. Risk Exposure
and Contingency
Management

This section describes the specific process and procedures used to determine
construction project risk exposures and the concomitant contingencies for scope,
cost, and schedule. It describes contingency management plans and processes and
ensures that contingency use is linked to both an identified risk and an appropriate
Work Breakdown Structure (WBS) element within project scope.

6.2.5.2 Roles and Responsibilities
Typically, the Project Manager or a designated Risk Manager (RM) is responsible for leading the
identification and analysis of project risks. All stakeholders (e.g., users, designers, and sponsors)
involved in the project are asked to provide input on what they deem to be the risks for the
project, possible risk mitigations, and ways to capture potential opportunities. The RM
consolidates the information collected and creates the list of risks with accompanying
attributes, and manages the response to the risks. An example of a Roles and Responsibilities
table for key stakeholders and project staff that meets requirements is shown below in Table
6.2.5-2.
Table 6.2.5-2
Roles

Example of a Risk Management Roles and Responsibilities Table

Responsibilities

Organization
Management

• Support the risk management process. Encourage all levels of the project organization to
participate fully and openly in the process.
• Make project decisions based in part on the results of risk analysis.
• Provide the culture that supports risk management and welcomes honest and realistic
results.

Risk Manager

• Oversee the Identification and documentation of new risks (threats and opportunities)
in the risk register
• Oversee the analysis of risks by the project team and work with them to develop risk
response plans (mitigate, avoid, accept, and transfer).
• Oversee reporting and tracking of risk activities during project status meetings
• Document and communicate risk activities frequently with stakeholders
• Review risks as they are concluded, and identify lessons learned
• Recommend and champion mitigation strategies to the Change Control Board (CCB) on
behalf of the risk management team.

Project Team
Members

• Assist the RM with the risk identification, qualitative and quantitative risk analysis and
development of risk response plans (mitigate, avoid, accept, and transfer). Participate in
risk workshops and interviews to provide risk data.
• Submit new threats, opportunities, and mitigations into the risk system as they arise.
• Assist the RM with the development and execution of risk response plans
• Attend project risk status meetings, as needed, and assist RM with the reporting and
tracking of risk activities
• Assist the RM with documenting and communicating the risk (threats and opportunities)
activities frequently with stakeholders
• Review risks as they are concluded, and identify lessons learned

Section Revision:
May 2, 2016

6.2.5-4

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.5 Risk Management Planning
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)
Roles
Risk Owner

Section Revision:
May 2, 2016

Responsibilities
• Assist the risk originator (PM, RM, project team member, etc.) with development of the
risk descriptions
• Assist the RM and project team with the analysis development of risk response plans
(mitigate, avoid, accept, and transfer) contingency plans
• Update the risk register with modifications to risks
• Monitor the risk triggers and update the risk register
• Attend project status meetings, as needed, and assist the PM with reporting and
tracking risk activities
• Assist the RM and project team with documenting and communicating risk activities
with stakeholders
• Capture risk closure notes in the risk register and lessons learned

6.2.5-5

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.6 Risk Identification
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Risk Identification
6.2.6.1 Risk Identification Process
Risk identification is an organized approach for determining, listing, and describing events that
might impact a project’s objectives (for example, time, cost, scope, and performance). It is an
iterative process that is conducted throughout the entire project life cycle. The risks are
described with a basis as to why this event is considered a risk. Identification relies on the skill,
experience, and insight of project personnel and subject matter experts (SMEs), as well as the
Recipient’s project manager, the NSF Program Officer, and the NSF Grants and Agreements
Officer. The objective of risk identification is to describe all the relevant risks so that the group
can focus on uncovering the probability and impact of the risks on project objectives (used in
qualitative risk analysis) or activities / costs affected (used in quantitative risk analysis). The
process for performing Risk Identification, along with inputs and outputs, is given in Figure
6.2.6-1.
Figure 6.2.6-1

Risk Identification Process

Process
• Project schedule,
scope, budget
• System and project
artifacts
• Meeting Minutes
• Environmental
factors, PEP

Inputs

• Review key project/ phase deliverables
• Meet with the Risk Manager and project team
on a regular basis to discuss and identify
potential risks
• Interview key stakeholders
• Review existing risks to validate
• Update risk or add new risk to Risk Register
• Brainstorm for risk at status meetings
• WHEN: at the beginning of projects, project
milestones, and at weekly/ monthly status
meetings

• New and updated
risks
• Updated Risk
Register with
description
• Potential risk
responses

Outputs

Techniques used in identifying risks include leveraging existing project artifacts and guidance
documents, as well as proactively searching and gathering information to assist in that identification. The quality and completeness of risk identification is primarily dependent upon the
knowledge and experience of the project team and its commitment to risk management
processes. For example, the following basic methods can be used to assist in the identification
of risks:
•

Brainstorming

Section Revision:
May 2, 2016

6.2.6-1

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.6 Risk Identification
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

•
•
•
•

Diagramming
Interviewing
Analysis of existing project artifacts
Comparison to historical information

Formal risk identification is performed in the early part of the project life cycle and as part of a
continuous effort during the project life cycle. Any person associated with the project should be
encouraged to continually identify potential project risks. Risk Identification, whether in
workshops or in interviews, should include at least the following participants:
•
•
•
•
•
•
•

Project managers
Project team leaders
Project team members
Business stakeholders
SMEs Contractors
SMEs outside the project team, for unbiased perspective
Project partners (e.g., foreign agencies, organizations with diverse objectives)

One immediate outcome of risk identification is the populating of the Risk Register, or tracking
tool, with the identified risks. The priorities based on impacts to project objectives and plans for
handling and reducing impacts will be added after analysis and risk handling planning, as
described in later sections. The Risk Register provides a means of tracking and reporting status
as risks occur and mitigation strategies are implemented, and is an important tool for Risk
Management implementation.
6.2.6.2 Risk Identification and the Risk Register
The Risk Register includes a description of all risks that are deemed to be important to
achieving project success (from the Risk Identification process) along with an assessment of
those risks (using Qualitative Risk Analysis) that allows risks to be prioritized for effective risk
management. The results of identification, qualitative analysis, and risk handling – the major
components in the Risk Register – can lead to further analysis (Quantitative Risk Analysis, for
example).
Each risk should be assigned a unique identification number or code. Once a risk is entered in to
the Register, it is never deleted. Its state may be changed to inactive (for example, retired,
closed, or merged with another risk), but it should never be deleted from the register. Risk IDs
are never reused.
The Register should be accessible (read-access) to all project members – the primary objective
of the Register is to keep the project team thinking pro-actively about how to avoid or mitigate
threats and take advantage of opportunities. It can be a spreadsheet, data base, or a specialized
risk management software tool. Changes to the Register should be managed through the risk

Section Revision:
May 2, 2016

6.2.6-2

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.6 Risk Identification
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

process, which often may restrict ability to make changes (write-access) to a small team or to
the Risk Manager. The mechanism for all project members to read, comment on, and submit
new risks and mitigations should be established in the RMP.
The examples shown here and in Section 6.2.7, Qualitative Risk Analysis – Risk Register Ranking,
lead to a Risk Register containing a ranked subset or summarized set of risks based on
individual, qualitative impact analysis. Note that numeric impacts determined by the qualitative
method for individual risks may not be summed or combined to give a value for overall project
risk exposure.
Further discussion of Risk Register content is given in Section 6.2.7, Qualitative Risk Analysis –
Risk Register Ranking, with a sample Risk Register shown in Figure 6.2.7-6.
6.2.6.3 Risk Description
The risk description serves as a key point in the Risk Register and will be generated and updated
as needed. If there is a trigger event that causes the risk or foretells the risk’s occurring, it
should be described since it will specify what condition(s) would launch the risk and maybe
activate a contingency plan.
Risks (both threats and opportunities) are typically identified and tracked using the following
sentence structure for the Risk Description:
“Because of (some cause) a (risk) may occur, and (consequences) will happen.”
Example:
“Because foreign exchange rates may change, the cost of components in WBS 3.1 and
2.6 may increase or decrease, causing cost variances which affect contingency use.”
Using this format helps to distinguish the uncertainty or risk from its cause and its
consequence, a distinction which is important for mitigation planning. For instance, a statement
that “we have 5 schedule risks” is focused on an objective (schedule) that is impacted, not the
root cause of the risk or uncertainty. Alternatively, a statement that “the risk is that the
technology is really hard” does not lend itself to mitigation efforts. Difficulty of technology is a
fact or a “cause” in this format, which cannot be changed. The risk may be that “we do not have
the right skills on the project to handle the complexity” or “we may have to rely on third parties
to gain control of this technology.” That is a risk that can perhaps be mitigated. A possible risk
description for this scenario may be:
Because the technology for the major components in WBS 2.7 is very advanced, we may
have to rely on third parties for design, with the consequence that we have less control
over cost and schedule and an added burden of increased communication efforts.
Section Revision:
May 2, 2016

6.2.6-3

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.6 Risk Identification
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Risks should be identified that are both internal, perhaps under project control, and external,
likely to be beyond project control. Risks for which there are no plans for mitigation should also
be included in the register. 1 However, note that NSF does not allow the use of contingency for
risks that are commonly referred to as “unknown unknowns” 2 such as exceptional events or
major changes in scope. These exceptional events may not be included in quantitative risk
analyses used in determining contingency amounts.
6.2.6.4 Risk Identification Concerns
Efforts should be made to identify all risks to the project as early as possible, employing all
stakeholders identified in and using the techniques listed in Section 6.2.6.1, Risk Identification
Process. At the time of the risk analysis there are likely to be risks that are currently unknown
but may be revealed at a later date. When they become apparent, they can be then analyzed
and a “corrective action” can be specified and implemented. The objective of the Risk
Management program is to minimize the number of unanticipated issues and to address them
when possible and prudent.
Some people believe that project risk is often underestimated in both cost and schedule,
leading to well-known, sometimes notorious, overruns.3, 4 Historical experience suggests that
mega-projects suffer from such problems systematically. 5 Strategic or overarching risks are
often missed in the risk identification process since the participants do not think globally, only
locally. Systemic or overarching risks are often not discussed or even considered during risk
identification. There may be cultural bias that leads to optimistic thinking in which threats are
systematically underestimated, outcomes are assumed to be achievable with less than realistic
effort and the potential for set-backs and rework is ignored. Any tool or technique that will
encourage people to “think outside of the box” when identifying project risk will help identify
the possibility of large overruns – when caught early, these risks may be manageable.
One common issue in identifying and collecting project risks is that people’s response and
participation in the identification process may be “stove-piped.” That means that people will
ordinarily discuss threats and opportunities that have to do with their own area of
concentration. In practice the project teams and other SMEs have experience and knowledge
The fact that “we cannot do anything about it” or “we choose to accept the risk” does not disqualify it as a risk to the project.
One can argue that these risks should be in the Risk Register and certainly in the Quantitative Risk Analysis.

1

In many risk management guides, a portion of contingency is designated as management reserve for “unknown unknowns.”
NSF does not allow this.

2

See Bent Flyvbjerg, Nils Bruzelius, and Werner Rothengatter, Megaprojects and Risk: An Anatomy of Ambition, 2003
Cambridge University Press, and Glenn Butts and Kent Linton, “NASA the Joint Confidence Level Paradox – a History of Denial,”
NASA Cost Symposium, April 28, 2009.
3

4

Challenges to Meeting cost, Schedule, and Performance Goals, NASA IG-12-21

5

Edward W. Merrow, Industrial Megaprojects, 2011, Wiley.

Section Revision:
May 2, 2016

6.2.6-4

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.6 Risk Identification
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

outside these narrow areas, so the data collection method used should encourage them to
think broadly and strategically when identifying risks. Reminding risk identification participants
of external, organizational and project management source-areas of risks can help elucidate
strategic risks that they know about but that are outside their narrow area of technical
expertise or their work assignment. Often the use of a standard Risk Breakdown Structure
shown in Figure 6.2.6-2 will encourage risk identification participants to think more broadly
about risks to the project.
Figure 6.2.6-2

Typical Risk Breakdown Structure (RBS) 1

Project

Technical

External

Organizational

Project Management

Requirements

Subcontractors
and Suppliers

Project
Dependencies

Estimating

Technology

Regulatory

Resources

Planning

Complexity and
Interfaces

Market

Funding

Controlling

Performance and
Reliability

Customer

Prioritization

Communication

Quality

Weather

Different approaches to Risk Management may subdivide risks into various categories for
analysis. For illustrative purposes, this guide will use cost, schedule, and technical or
performance risk as the categories used in examples. Other risk categories commonly in use are
programmatic, business or economic, design requirements, software, and technology risks.
Alternatively, the OMB Risk Categories shown in Figure 6.2.6-3 could be used as guidelines for
identifying the various types of risk that apply to the project (refer to “OMB Risk Categories”
document in Critical Infrastructure Protection (CIP) for detailed descriptions and examples of
these categories). See the Government Accountability Office (GAO) Cost Estimating and
Assessment Guide, GAO-09-3SP, Chapter 14, for more examples. Some projects may also decide
to differentiate between internal and external risks. In many cases, it may be advisable to use
different categories for various parts of a project. For instance, categories of risk may be
1

This RBS was the initial model for the RBS in the PMBOK® Guide, Chapter 11 of the Project Management Institute

Section Revision:
May 2, 2016

6.2.6-5

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.6 Risk Identification
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

different for software development than for hardware procurement. Each project should
decide which categories are most appropriate for its use while establishing the Risk
Management Plan and processes.
Figure 6.2.6-3

1)
2)
3)
4)
5)
6)
7)
8)
9)
10)

OMB Risk Categories: to be used as a starting point for projects to select their own categories

Schedule
Initial Costs
Life Cycle Costs
Technical Obsolescence
Feasibility
Reliability of Systems
Dependencies and Interoperability
Surety (Asset Protection)
Risk of Creating a Monopoly
Capability of Agency to Manage the
Investment

11) Overall Risk of Project Failure
12) Organizational and Change
Management
13) Business
14) Data/Info
15) Technology
16) Strategic
17) Security
18) Privacy
19) Project Resources

Another related social or cultural issue in identifying project risks is that people are often
uneasy about (or even afraid to be) discussing risks that can be embarrassing or harmful to the
project. This unease is often experienced during risk workshops or in other group settings.
Social pressures to conform (“groupthink”) – to suppress dissenting opinions clearly unpopular
to the group, including management, to agree with others against personal opinion just to
move the workshop along, and to defer to people perceived to have greater expertise even
when in disagreement – often make it difficult for some people to speak out. 1 A possible
solution to the impacts of social pressure is to conduct one-on-one, in-depth interviews with
SMEs in which the interviewee is promised confidentiality. Such interviews often yield honest
opinions about what might affect the project’s success. Usually some or most of the risks
revealed and discussed in these sessions are not on the organization’s risk register and would
not be analyzed in qualitative or quantitative risk analysis in the absence of the interviews. For
these reasons it is important to provide a safe environment for project team members and
others to identify and discuss project risks.
Risk identifiers may have concerns about including risks that are 100% likely to happen
(sometimes these are called “uncertainties or issues”) in the Risk Register. If the risks are 100%
likely to happen and their impacts are known, they should be included in the PMB. Often,
however, a risk that is certain to occur will have an impact that is not already included in the
project execution plan and that needs to be handled somewhere else, such as in the risk
analysis. Or the risk may have an uncertain impact on project objectives. These situations call
for the risk to be identified, even if it is already happening or certainly will happen, so the risk
These phenomena are discussed in Understanding and Managing Risk Attitude, David Hillson and Ruth Murray-Webster,
Gower, 2005.
1

Section Revision:
May 2, 2016

6.2.6-6

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.6 Risk Identification
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

can be included in the Risk Register and the subsequent quantitative risk analysis. The objective
of risk identification is to describe all the relevant risks so that the group can focus on
uncovering the probability and impact of the risks on project objectives (used in qualitative risk
analysis) or activities / costs affected (used in quantitative risk analysis). Once a risk that is
certain to occur has been included in the PMB it can be removed from the Risk Register.
Care should be taken to provide the same thoroughness of identification for events far in the
future as well as for the near term for projects that have an execution period of several years.
Project team members usually find that it is easier to identify and discuss the risks that are
current or on the near horizon than those that may occur much later in the project. Adding to
the difficulty is the fact that future events may not be well defined at the time of risk analysis.
The risk identification exercise should take special care to encourage the participants to look
into the future, maybe with the help of lessons learned documents or their own experiences on
prior projects, to see what risks are far down the project life cycle. Another useful technique is
to “walk through” the activities planned for later execution. Examples of unidentified risks may
include unexpected legal changes, technical performance issues, resource losses, etc. Other
sources of future risks might include the reliance on unproven or even just conceptualized
technology or on doing business with an organization or in a country unknown to the sponsors.
The risk identification should include thinking about risks that have happened on other similar
projects or might occur in later phases of this project. If the team spends some time discussing
these down-stream risks, they can perhaps remember other projects or conceptualize the
existence of risks that would otherwise go unreported.

Section Revision:
May 2, 2016

6.2.6-7

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.7 Qualitative Risk Analysis – Risk Register Ranking
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Qualitative Risk Analysis – Risk Register Ranking
6.2.7.1 Purpose of Qualitative Risk Analysis
Qualitative risk analysis involves determining the probability of the occurrence of a risk,
assessing the consequences of this risk on specific project objectives (time, cost, scope and
quality) if it occurs, and using the two dimensions of a risk (probability and consequence) to
identify a rank or “risk level.” This risk level represents a judgment as to the relative risk to the
project objectives and the project as a whole and is categorized as Low, Moderate, or High.
Based on the risk level, risks can be prioritized for mitigation to responses. The results of Risk
Identification, Qualitative Risk Analysis, and Risk Response Planning comprise the main
elements of the Risk Register. The process for performing Qualitative Risk Analysis, along with
inputs and outputs, is given in Figure 6.2.7-1 below.
Figure 6.2.7-1
• Risk and uncertainty
descriptions and
calibration
• Project artifacts such
as schedule, estimate
• Client and team
interviews for risk
data
• Other data gathering,
lessons learned

Inputs

Qualitative Risk Analysis Process

Process
• Assess the schedule and cost against good
practices
• Conduct in-depth confidential risk interviews for
probability, impact and activities / costs affected
• Calibrate and assign inherent uncertainty and
estimating error, providing for more uncertainty
for work performed in the future
• Run Monte Carlo simulation on the risk-assigned
project schedule or estimate
• Prioritize the risks to the project
• Mitigate the high-priority risks and create a
post-mitigated result

• Likelihood of
finishing on time
and budget
• Needed cost and
time contingency
amounts
• Identification of high
priority risks and
needed risk
mitigations

Outputs

Achieving risk reduction is an integral part of setting priorities, sequencing project work, and
responding to the most serious risks first. Thus, the identified risks should be prioritized.
Note that Qualitative Risk Analysis is applied only to individual risks and is not used in
estimating overall project risk exposure or in determining contingency amounts. The analysis of
impact or consequence, however, may serve as input to Quantitative Analysis used to estimate
overall risk exposure.
6.2.7.2 Considerations When Performing Qualitative Risk Analysis
A number of factors complicate qualitative risk analysis, including:
•

Risk data, like data about the future contained in cost estimates or project schedules,
have a significant content based on subjective, expert judgment. The evaluation of risks

Section Revision:
November 25, 2016

6.2.7-1

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.7 Qualitative Risk Analysis – Risk Register Ranking
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

to cost and schedule therefore generate approximate rather than precise results. “There
are no facts about the future.” 1
•

The term “risk” includes both “threats” and “opportunities” for NSF purposes. Project
risk team members should look for uncertainties that could help improve the project’s
results or offset threats. Both threats and opportunities should be examined for total
project impact, since opportunities for one project participant may be considered
threats by another, and vice versa.

•

The probability that a risk may occur and the impact if the risk were to occur should be
evaluated separately before combining the two parameters in a risk matrix. The idea
that “the risk is unlikely so its impact must be low” confuses the two parameters of
probability and impact. SMEs should be asked to estimate the impacts as if the risk has
occurred. Probability and impact will be considered together in the combined risk matrix
approach.

•

It is good practice to assess risks’ impact on separate objectives such as time, cost,
scope or quality/performance Impact ranges rather than creating a single, overall risk
level for the risk. Thus, ranking levels are defined for each of these objectives. For
instance, a risk can be judged to have a high impact on time but a moderate impact on
cost and a low impact on scope.

•

The definitions of impact on each project objective (very low, low, moderate, high and
very high) are set by the Risk Manager and documented in the RMP.

•

The definitions of combined risk level for probability and impact taken together (low,
moderate or high; or green, yellow or red) in the Risk Matrix are set by the Risk Manager
and documented in the RMP.

•

The impact of an individual risk may be modest and still be considered a high or very
high priority for mitigation. This is because the combined or aggregate risk of many
moderate risks may be high. The project may want to mitigate some low or moderate
risk in order to reduce the combined threat from many risks.

•

The risk register should include only root cause risks. Risks as defined in the plan may
not be mutually exclusive, that is, they may have the same root cause risk. Put another
way, if two or more risks are not mutually exclusive as written, their common root cause
risk should be identified and used instead.

Lincoln E. Moses, Administrator of the Energy Information Administration, Administrator’s Message to the Annual Report To
Congress, 1977, Volume Three.
1

Section Revision:
November 25, 2016

6.2.7-2

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.7 Qualitative Risk Analysis – Risk Register Ranking
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

6.2.7.3 Limitations of Qualitative Analysis
There are some limitations to the practice of qualitative risk analysis. Recognizing these will
help the organization appreciate and use the results correctly:
•

Qualitative Risk Analysis addresses the impact of individual risks on project objectives
one at a time. As such it is dedicated to prioritizing individual risks based on subjective
estimates of probability and subjective estimates of the impact to the project objectives.
It is not equipped to forecast or estimate overall project results such as the finish date
or total cost.

•

Qualitative Risk Analysis is unlikely to yield valid quantitative results since it usually does
not include all possible correlations and outcomes for impacted activities from a single
risk. SMEs should consider the risk with its probability of occurring and all the activities
in the schedule it would affect if it occurred, whether or not those activities are on the
risk critical path (the risk equivalent to the critical path in CPM scheduling). They should
also evaluate whether other risks might prevent mitigation of a particular risk from
resulting in much improvement. All of this analysis is being done in the individual SME’s
head. Such complex calculations are best handled by the Quantitative Risk Analysis
simulation method described in Section 6.2.7.

•

The estimation of the impact of a risk on cost should consider the impact of that risk
directly on cost plus the impact indirectly on the cost of time-dependent resources if the
risk also affects time. This is another calculation that individuals are not well-equipped
to make without a computer but is handled well by Quantitative Risk Analysis.

•

Judging whether a risk has a high-priority for the project would involve reviewing the
conclusions on each objective and asking the risk manager to prioritize the objectives.
Some projects are time sensitive and some are budget driven, others have a fixed scope
or could be de-scoped. These factors would need to be considered to determine
whether the risk is low, moderate or high priority for the project as a whole. Some
software packages that perform qualitative risk analysis assume that if a risk is “high”
for any objective it should be judged to be “high” for the entire project. There is no real
basis for doing so, since the risk may be judged to be high for an objective that is not the
most important for the specific project under consideration.

6.2.7.4 Qualitative Risk Analysis – Probability and Impact Assessment
Risk level determination can be done using a variety of techniques. The method given here
begins by assigning qualitative values for event probability and impact/consequence(s) to each
objective separately. These will then be used to determine a qualitative risk level. A key feature
of this method is that it requires independent assessment of the probability and consequence
of a risk.

Section Revision:
November 25, 2016

6.2.7-3

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.7 Qualitative Risk Analysis – Risk Register Ranking
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

The probability of a risk occurring is usually given to a range of possible probabilities of
occurring. Similarly, consequences are usually expressed in levels that represent ranges of
impacts judged by the risk manager to be of very low, low, moderate, high or very high impact
as the result of one risk among many. The ranking of a risk as it is applied to a particular
objective (e.g., time) is determined by the combination of probability and impact ranges, where
the project manager or some other stakeholder (e.g., the customer) determines which
combinations would indicate that the risk is high, moderate of low priority for further study,
quantitative risk analysis or handling.
The following steps provide the details of this Qualitative Analysis method:
1. Address each risk statement from the Risk Identification process individually.
2. Determine the qualitative probability of occurrence value (P) range that best describes
the probability for each risk with appropriate basis and justification. Discuss the
probability that the risk might occur on the project with some noticeable effect on the
objective being discussed. Estimate the probability for the risk without regard to which
objective(s) the risk affects if it occurs. The probability of occurrence is for the duration
of all project phases. Table 6.2.7-1 provides an example of typical criteria for
establishing probability values.
3. Determine the qualitative consequence or impact of occurrence value I range that best
describes the impact for the objective such as time, cost, scope or performance for each
risk with appropriate basis and justification. In the evaluation, assume that the risk has
occurred and determine the recovery time, the cost of recovery, and the impact on
scope or quality. The consequence of occurrence is for the duration of all project phases
and for the objective being assessed. Table 6.2.7-2 provides typical criteria for
establishing consequence values. This table illustrates the different definitions that are
applied to the implications for time, cost, scope and quality. Of course these definitions
should be tailored to the project by the project manager or some other stakeholder
(e.g., the owner or customer).

Section Revision:
November 25, 2016

6.2.7-4

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.7 Qualitative Risk Analysis – Risk Register Ranking
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)
Table 6.2.7-1

Sample Risk Probabilities Table

Each project should determine the appropriate number of levels and their definitions that match that project’s
circumstances.
Probability of
Occurrence Descriptor

Probability of Occurrence
Numerical Ranges
equivalent levels 1

Very Low

<0.1

Low

>0.1 but <0.4

Will not very likely occur in the life cycle of the project
or its facilities; or the probability of occurrence is
greater than 10% but less than or equal to 40%.

Moderate

>0.4 but <0.6

Will likely with middling probability (e.g., a coin flip) to
occur sometime during the life cycle of the project or its
facilities; or the probability of occurrence is greater than
40% but less than 60%.

High

>.6 but <.8

Likely to occur with more than 60 percent chance during
the project, or the probability of occurrence is between
60% and 80%

Very High

>0.8

Will likely occur sometime during the life cycle of the
project; or the probability of occurrence is greater than
or equal to 80%.

Table 6.2.7-2

Criteria in Words
Will not likely occur anytime in life cycle of the facilities;
or the probability of occurrence is less than equal to
10%.

Sample Risk Consequences 2 Table

The descriptors for the objectives of cost and time are explicitly given as numbers while those for scope and quality
are expressed in narrative descriptions.
Defined Conditions for Impact Scales of a Risk on Major Project Objectives, e.g., Time
Definition for Threats Only
Project Objective

1

Very Low

Low

Moderate

High

Very High

Cost

Insignificant Cost
Increase

<5% Cost Increase

<5 - 10% Cost
Increase

<0 - 20% Cost
Increase

>20% Cost
Increase

Time

Insignificant Time
Increase

<5% Time
Increase

<5 - 10 % Time
Increase

<0 - 20 % Time
Increase

>20% Time
Increase

Scope

Scope Decreases are
Barely Noticeable

Minor Areas of
Scope Affected

Major Areas of
Scope Affected

Scope Reduction
Unacceptable to
Sponsor

Project End Item
is Effectively
Useless

Quality

Quality Degradation
Barely Noticeable

Only Very
Demanding
Applications are
Affected

Quality
Reduction
Requires
Sponsor
Approval

Quality
Reduction
Unacceptable to
Sponsor

Project End Item
is Effectively
Useless

The scales still should be calibrated per the discussion and reference in Section 6.2.9.

An earlier version of this table was used in the PMBOK® Guide. The percentage ranges should be adjusted by the project
manager for the project and translated into days and dollars for ease of use.

2

Section Revision:
November 25, 2016

6.2.7-5

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.7 Qualitative Risk Analysis – Risk Register Ranking
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Notice that the definitions for time and cost can be quantitative but that those for scope and
quality are generally descriptive. Sometimes a project’s scopes can be quantified, though it may
have several dimensions. Quality or performance might be measurable in terms of failure rates
or number of “fixes” that would be needed. The more the impact levels can be quantified the
more the responses by different people will be comparable. The project manager can calibrate
the numerical ranges for the specific project. The consequence definitions of very low, low,
moderate, high or very high (or Negligible, Marginal, Significant, Critical, and Crisis) may vary
considerably from a small to a large project. These tables should be provided as part of the
RMP.
It is preferable to refer to the numerical levels when gathering qualitative risk data since
definitions in words are often misleading. For instance, two people may use the term “Likely”
but mean different values. Or, one may say the risk is “likely” to occur and another may say
“unlikely” but mean the same numerical value, or at least in the same “bucket” or range of
values. Research has shown that the lack of overlap in assigning probability values with
common word definitions is severe.1 (See Figure 6.2.7-2.)
Figure 6.2.7-2

Overlap in Risk Probability of Occurring When Descriptors Are Used

Expert judgment is required in risk analysis, just as it is for project scheduling and project cost
estimating. That is why several or many people need to be involved in providing their opinions
and experiences when assessing project risks. With multiple people assessing the probability
and impact of each risk against each objective, such as in the recommended in-depth
1

Private research conducted by Dr. David Hillson in 2004 and presented at a PMI EMEA conference.

Section Revision:
November 25, 2016

6.2.7-6

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.7 Qualitative Risk Analysis – Risk Register Ranking
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

confidential interviews, there will be differences of opinion between them. The risk analyst has
to consolidate the data from different sources into one set of parameters for each risk and
objective from the dissimilar responses. This process uses expert judgment.
6.2.7.5 Alternative Approach to Qualitative Risk Impact Analysis ‒ Maxwell
An alternative approach is that proposed by F. D. Maxwell for projects such as those supported
by the Aerospace Corporation or the Space & Missile Systems Center of the US Air Force in Los
Angeles. See Table 6.2.7-3. The “risk driver category” is not the same as the project objectives,
but rather describes where the risks might be originating. This was not used by Maxwell in
conjunction with the probability before 1990, but it does illustrate definitions of impact that
were used on many aerospace and scientific projects. Maxwell stated that:
Special attention should be given to first-of-a-kind risks because they are often
associated with project failure. First-of-a-kind risks should receive a critical or
crisis consequence estimate unless there is a compelling argument for a lesser
consequence value determination.
Table 6.2.7-3
Risk Driver Category

Maxwell Risk Driver Assessment Framework 1

Very Low
Risk Level

Low Risk Level

Medium
Risk Level

High Risk
Level

Very High
Risk Level

1

Required Technical
Advancement

Nothing New

Minor
Modifications
Only

Major
Modifications

State of the
Art

Beyond State
of the Air

2

Technology Status

Currently in
Use

Prototype
Exists

Under
Development

In Design

Concept State

3

Complexity

Simple

Somewhat
Complex

Moderately
Complex

Highly
Complex

Highly
Complex with
Uncertainties

4

Interaction/
Dependencies

Independent
of Other Risk
Drivers

Dependent on
One Additional
Risk Driver

Dependent on
Two
Additional
Risk Drivers

Dependent on
Three
Additional
Risk Drivers

Dependent
on more than
Three
Additional
Risk Drivers

5

Producibility

Established

Demonstrated

Feasible

Known
Difficulties

Infeasible

6

Process Controls

Statistical
Process
Controls (SPC)

Documented
Controls
(No SPC)

Limited
Controls

Adequate
Controls

No Known
Controls

7

Manufacturing
Precision

High

Adequate

Limited
Margins

Known but
Inadequate

Unknown

Developed by F. D. Maxwell at the Aerospace Corporation. Included in “Estimating Cost Uncertainty when only Baseline Cost is
Available,” quoting R.L. Abramson and S. A. Book, “A Quantification Structure for Assessing Risk-Impact Drivers,” Laserlight
Networks, briefing presented to the 24th Annual DOD Cost Symposium (Leesburg, VA, September 5-7, 1990).

1

Section Revision:
November 25, 2016

6.2.7-7

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.7 Qualitative Risk Analysis – Risk Register Ranking
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Risk Driver Category

Very Low
Risk Level

Low Risk Level

Medium
Risk Level

High Risk
Level

Very High
Risk Level

8

Reliability

Historically
High

Average

Known
Limited
Problems

Serious
Problems of
Unknown
Scope

Infeasible

9

Criticality to Mission

Nonessential

Minimum
Impact

Known
Alternatives
Available

Possible
Alternatives
Exist

“Show
Stopper”

10

Cost

Established

Known History
or Close
Analogies

Predicted by
Calibrated
Model

Out of Range
of Experience

Unknown or
Unsupported
Estimate

11

Schedule

Demonstrated

Historical
Similarity

Validated
Analysis

Inadequate
Analysis

Unknown or
Unsupported
Estimate

6.2.7.6 Qualitative Risk Analysis – Risk Level Matrix
Once the probability and impact level of each identified risk is agreed to, the risk’s position is
determined on the probability and impact matrix shown in the following figures. The vertical
matrix axis labels in the figures correspond to the definitions for probability levels given in Table
6.2.7-1, and the horizontal axis labels correspond to the values for impact defined in Table
6.2.7-2. Combinations of probability and impact for a risk are shaded as red, yellow and green
for high, medium, and low risk level. The risk manager, project manager, or other stakeholder
should set these regions for each risk level, based on an understanding of the definitions of the
axes, which would cause the risk to rise to the appropriate level of attention.
Figure 6.2.7-3 shows a risk probability and impact matrix for one objective that is symmetrical.
Figure 6.2.7-4 shows a risk probability and impact matrix for an objective that emphasizes the
impact of the risk on its red-yellow-green status. This asymmetrical risk matrix indicates that
any risk that has a very high impact will achieve “high risk” or “red risk” status without regard to
the probability that the risk will occur on the project. Of course, the definitions of risk impact
and probability buckets defined in the RMP will determine the relative score that the risk
achieves.

Section Revision:
November 25, 2016

6.2.7-8

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.7 Qualitative Risk Analysis – Risk Register Ranking
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Figure 6.2.7-3

Symmetrical Risk Level Matrix

Probability and Impact Matrix for a Specific Objective (Time, Cost, Scope or Quality)
Probability
Symmetrical
Very High
Mod
Mod
High
High
High
High
Low
Mod
High
High
High
Mod
Low
Mod
Mod
High
High
Low
Low
Low
Mod
Mod
Mod
Very Low
Low
Low
Low
Low
Mod
Very Low
Low
Moderate
High
Very High
Impact
Figure 6.2.7-4

Asymmetrical Risk Level Matrix

Probability and Impact Matrix for an Objective (Time, Cost, Scope)
Probability
Impact Averse
Very High
Low
Mod
High
High
High
High
Low
Mod
Mod
High
High
Mod
Low
Low
Mod
High
High
Low
Low
Low
Mod
Mod
High
Very Low
Low
Low
Low
Mod
High
Very Low
Low
Moderate
High
Very High
Impact
The Risk Level for each objective for a defined risk depends upon where it falls in the Risk Level
Matrix according to the axes definitions. For example, a cost risk with an estimated probability
of 70% of occurrence and an estimated impact of $280K, or cost increase of 9% for the item at
risk, would fall into the High probability range and the Moderate cost impact range, according
to Table 6.2.7-1 and Table 6.2.7-2. Thus, the Risk Level for cost for this particular risk occurring
falls into the High, or “red” range in Figure 6.2.7-3.
It is important to scale probability and impact so that the risks can be distinguished. On the one
hand, if the lower bound for an impact score of very high is easy to reach there will be many
risks with the same “red” assessment and the method will not distinguish risks for priority Risk
Handling. On the other hand, definitions of high or very high impacts that are very difficult to
reach will lead to very few or no “red” risks. While that may be true for some projects it would
be unusual for an NSF project with a high scientific impact.

Section Revision:
November 25, 2016

6.2.7-9

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.7 Qualitative Risk Analysis – Risk Register Ranking
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

The objective of the matrix is to communicate the choice of priorities for monitoring and
response, which may best be done with the 2-D diagrams (5x5) shown herein. Depending upon
the activity and the ability to differentiate the risk levels, other matrices may be chosen by the
risk analysis team. For example, a 5x5x4 risk level (the fourth level represents the 4 objectives)
matrix would then have five values for probability, five for consequence and four for objectives.
Recall that Risk Management entails the identification and ranking of opportunities as well as
threats. 1 Opportunities that are assessed to be in the “High” category are viewed as “lowhanging fruit” that can be easily claimed for the project if sought. For instance, if people are
coming off another similar project where they have had a good result, our project will benefit if
we can encourage or otherwise get them to join our project team. However, if such an
opportunity is not recognized in a timely manner, those productive people will go to other
projects. Another example is a potential cost saving if older but acceptable technologies can be
used in place of cutting edge solutions without impacting performance or quality. This type of
cost savings is common in data acquisition and storage systems, for instance.
The butterfly or mirror risk probability and impact matrix below shows scoring threats and
opportunities in similar ways. The red-yellow-green ranges for threats have been discussed. The
red risks for opportunities are those that have a high likelihood of occurring and if they occur
they help the project achieve its objectives, if only by offsetting threats. Risk Response of
opportunities needs to be proactive in order to secure these opportunities for the project.
Figure 6.2.7-5

Prob.
VH
H
M
L
VL

Probability and Impact Matrix including Threats and Opportunities

Mirror or Butterfly Probability and Impact Matrix for Threats and Opportunities
Project Objective (e.g., time, cost, scope, quality)
Threats
Opportunities
L
M
M
H
H
H
H
M
M
L
L
L
M
H
H
H
H
M
L
L
L
L
M
H
H
H
H
M
L
L
L
L
L
M
H
H
M
L
L
L
L
L
L
L
M
M
L
L
L
L
VL
L
M
H
VH
VH
H
M
L
VL
Impact (threats)
Impact (opportunities)

Prob.
V
H
M
L
VL

An early discussion of the use of opportunities in project management can be found in: Effective Opportunity Management for
Projects: Exploiting Positive Risk, David Hillson, Marcel Dekker, 2004.
1

Section Revision:
November 25, 2016

6.2.7-10

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.7 Qualitative Risk Analysis – Risk Register Ranking
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

6.2.7.7 Risk Level Input to the Risk Register
The Risk Levels per each objective for all identified risks are entered into the Risk Register. See
the sample Risk Register in Figure 6.2.7-6. It is common practice to also include a column in the
matrix for the probability descriptor for ease of reference. As mentioned before, it is good
practice to list the Risk Level for each project objective separately and not combine them into a
single risk level for the stated risk. Projects may choose, however, to designate a flag to identify
some risks as “Major” or “Top” risks. These Top Risks are judged by the project management to
call for more aggressive management and more frequent monitoring than other risks.
Communicating and tracking the status of the top project risks is a key element of project
management. The Risk Management Plan should address the frequency with which these
significant risks are tracked. Top risks should be reviewed and evaluated during standard subsystem team meetings and reviews as well as at project status meetings.
Projects should also include a status report for the top risks in the various required reports to
NSF, including the monthly report, as well as for reviews. One simple method for
communicating the summary status of top risks to various stakeholders is shown in the sample
Top Risk Matrix shown in Figure 6.2.7-6, which shows risk level and trend data for selected
risks.

Section Revision:
November 25, 2016

6.2.7-11

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.7 Qualitative Risk Analysis – Risk Register Ranking
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)
Figure 6.2.7-6

Sample Risk Register with Risk ID Number, Associated WBS Identification, Qualitative Probability and Impact for Initial and Post-mitigation States, and
Mitigation Actions
Pre-Mitigated Scores
Probability and Impacts

Post-Mitigated Scores

Resulting Risk Score

Risk
ID

Risk
Description

Associated
WBS

Prob.
Risk
Occurs

On
Sched.

On
Cost

On
Scope/
Quality/
Performance

Risk
on
Sched.

Risk
on
Cost

Risk on
Scope/
Quality/
Performance

PM1

If …., then …

2.2

H

VH

H

M

H

H

TECH1

If …., then …

3.2.5

H

VH

H

H

H

EXT8

If …., then …

3.1.3

M

VH

H

M

H

ORG4

If …., then …

1.2

M

H

M

M

PM4

If …., then …

2.4.1

M

H

H

M

TECH5

If …., then …

3.3.1

Risk Action
Risk
Owner

Risk
Mitigation
Actions

Probability and Impacts
Trigger
or
Watch
date

Major
Risk
Flag

Resulting Risk Score

Prob.
Risk
Occurs

On
Schedule

On
Cost

On
Scope/
Quality/
Performance

Risk
on
Sched.

Risk
on
Cost

Risk on
Scope/
Quality/
Performance

M

M

M

M

L

M

M

M

H

H

M

H

M

L

H

M

M

H

M

L

H

M

L

M

M

L

H

M

M

L

M

M

M

M

M

M

H

H

M

L

L

L

L

L

L

L

M

VH

H

M

H

M

M

VL

M

M

M

L

M

L

TECH6

L

H

M

M

M

M

M

VL

L

L

M

L

L

M

EXT6

L

H

H

L

M

M

L

VL

M

L

L

M

L

L

PM2

M

L

H

L

M

H

M

L

L

H

VL

L

M

L

TECH9

VL

VH

VH

L

M

H

L

VL

H

VH

L

M

H

L

TECH10

VL

VH

M

VL

M

L

L

VL

M

L

VL

L

L

L

Section Revision:
November 25, 2016

6.2.7-12

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.7 Qualitative Risk Analysis – Risk Register Ranking
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)
Figure 6.2.7-7 Sample Top Risk Matrix and Status Report, showing list of project risks selected as most significant to monitor on a frequent basis, with ranking and trend data
Note that top risks include some with Low and Medium criticality (or ranking), as well as those evaluated as High criticality.

Project Top Risk Matrix
Trend Rank

L
LI
KI
K
E
E
L
HI
O
H
O
O
D
O
D

5
RSK-025
RSK-025
RSK-105

4

SOF-RSK-005 SOF-RSK-001
RSK-098

RSK-065
RSK-101
RSK-076
RSK-103

3

SOF-RSK-007

RSK-066

2

RSK-053

SOF-RSK-003,
RSK-102
SOF-RSK-010

RSK-106

RSK-100
SOF-RSK-009

SOF-RSK-002,
RSK-059
SOF-RSK-006

RSK-051

1
1

2

3

4

High
Med
Low

Section Revision:
November 25, 2016

Risk ID

Approach

L x C Trend

Approach



Decreasing (Improving)

M – Mitigate



Increasing (Worsening)

W – Watch



Unchanged

A – Accept



New since last period

R – Research

Title
Inadequate Observatory
Performance for initial
operations



1

(4X4) RSK-025

M



1

(4x4) RSK-098

M

Operations Staff Fatigue



2

(3X4) RSK-102

M

Lack of Adequate
Planning for data analysis
pipeline



4

(3x3) RSK-103

M

Lack of Data Extraction
and Analysis Tools



5

(4x2) RSK-105

M

Scientist support staff
resources



6

(2x5) RSK-059

M

Loss of single-point-failure
component



7

(3x3) RSK-076

M

Maintaining Science
Instruments



8

(2X4) RSK-100

M

Instrument support
structural Integrity



9

(3x3) RSK-101

M

Undocumented Hardware
Requirements



3

(3X4) RSK-106

M

Science Instrument
Hardware Change
Control



10

(2x3) RSK-066

W

Operations Staff
Retention

11

(2x3) RSK-053

W

Changes in Safety and
Reliability Requirements

5

CONSEQUENCE
CONSEQUENCE
Criticality

LxC



6.2.7-13

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.7 Qualitative Risk Analysis – Risk Register Ranking
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

6.2.7.8 Other Qualitative Risk Analysis Methods
Expected monetary value, simulation, Bayesian probability theory, reliability, and the use of
decision trees or its inverse, failure mode effects and criticality analysis (FMECA) are other risk
analysis methods that are used in project management. They are not described in detail here
but may be researched using the given references.
Expected monetary value is the product of the risk event probability multiplied by the value of
the gain or loss that will be incurred. Schedule impacts and intangibles (i.e., a loss may put the
organization out of business) should be considered when using this approach. This method for
scaling contingency amounts does not take advantage of information about the range of
possible impacts or probabilities. It can only provide a mean value of the contingency, not some
other target level of confidence. It is not good for time risks or cost risks that have time risk
components.1
Any schedule of a real project can easily be handled using Monte Carlo simulation techniques, 2
discussed in the next section on Quantitative Risk Analysis. Simulation uses a model of a system
such as the project schedule to simulate a project using Monte Carlo analysis. Monte Carlo
“performs” the project many times so as to provide a statistical distribution of calculated
results under many different scenarios, since in each scenario different risks may occur with
different combinations of impact. The use of Monte Carlo analysis to estimate the risk schedule
or cost distribution by statistically combining risk costs is illustrated in the next section.
A decision tree is a diagram depicting key interactions between decisions and associated events
and uncertainties as understood by the decision-maker. 3 A FMECA is a bottoms-up version of a
decision tree, building up from the elements to the decisions. Either approach helps the analyst
to divide a problem into a series of smaller, simpler, and more manageable events that more
accurately represent reality to simplify decision-making.
Bayesian probability theory treats probability as a degree of belief or uncertainty in a given
statement. More information may be found in Foundations of Risk Analysis. 4

1

Integrated cost-schedule risk analysis is presented in Section 6.2.8, Quantitative Risk Analysis.

For schedule impact the organization should not use the Program Evaluation and Review Technique (PERT or the Method of
Moments) to represent project risk in schedules. This method underestimates risk for the type of projects addressed herein.
Refer to “Project Schedule Risk Analysis: Monte Carlo Simulation or PERT?” David T. Hulett, PM Network published by the
Project Management Institute, February 2000, pp. 43 ff
2

See Recommended Practice 85R-14, Use of Decision Trees in Decision Making, Association for the Advancement of Cost
Engineering International (AACEI), 2014, David T. Hulett principal author. Also, “Use Decision Trees to Make Important Project
Decisions,” David T. Hulett, Cost Engineering (published by AACEI, July / August 2014.

3

4

Pages 62 and 64 of Foundations of Risk Analysis by Aven.

Section Revision:
November 25, 2016

6.2.7-14

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.8 Quantitative Risk Analysis – Estimating Contingency
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Quantitative Risk Analysis – Estimating Contingency
6.2.8.1 The Purpose of Quantitative Risk Analysis
Quantitative risk analysis can analyze the impact of all of the risks and uncertainties on the
project objectives of overall time and cost. Hence quantitative risk analysis can derive results
that qualitative risk analysis cannot provide, i.e. the likely finish date and project cost when all
risks are considered within a model of the entire project.
Quantitative risk analysis allows the risk analyst to estimate:
•
•
•

How likely is the project to meet its schedule and cost goals?
How much schedule and cost contingency is needed to achieve the project’s desired
level of certainty?
Which risks are causing any potential overrun and are thus high priority for risk
mitigation?

Quantitative risk analysis allows the analyst to estimate the finish date and cost of the project
based on a probability distribution created by applying Monte Carlo simulation to a project plan
such as the schedule, cost estimate or cost-loaded schedule. The inputs are uncertainty and
discrete risk events, although there may also be probabilistic branches, weather / calendar
effects and even conditional branches. The process for performing Quantitative Risk Analysis is
shown in Figure 6.2.8-1 below. Outputs are the estimated total cost and finish date and
associated contingency amounts above the baseline input cost and finish date.
Figure 6.2.8-1
• Risk and uncertainty
descriptions and
calibration
• Project artifacts such
as schedule,
estimate
• Client and team
interviews for risk
data
• Other data
gathering, lessons
learned

Inputs

Quantitative Risk Analysis Process

Process
• Assess the schedule and cost against good
practices
• Conduct in-depth confidential risk interviews for
probability, impact and activities / costs affected
• Calibrate and assign inherent uncertainty and
estimating error, providing for more uncertainty
for work performed in the future
• Run Monte Carlo simulation on the risk-assigned
project schedule or estimate
• Prioritize the risks to the project
• Mitigate the high-priority risks and create a
post-mitigated result

• Likelihood of
finishing on time
and budget
• Needed cost and
time contingency
amounts
• Identification of
high priority risks
and needed risk
mitigations

Outputs

A quantitative risk analysis requires an accurate, up-to-date schedule as well as up-to-date risk
data to be useful. The schedule used for analysis is often not the detailed Integrated Master
Schedule (IMS), but is a summary schedule that can be resource loaded.

Section Revision:
May 2, 2016

6.2.8-1

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.8 Quantitative Risk Analysis – Estimating Contingency
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

While software tools have made it relatively simple to run a Quantitative Analysis, the
preparation work for a simulation run can take significant time and effort. Often, projects use
Qualitative Analysis for month-to-month risk management and use Quantitative Analysis for
establishing a new baseline or calculating an updated Estimate at Completion (EAC).
There are several commercial packages available that provide tools and programs for
performing Quantitative Analysis using cost estimates and/or resource loaded schedules.
While NSF strongly recommends probabilistic analysis methods for estimating total project risks
and contingency amounts, it does not endorse or recommend any particular program or
product.
A typical result of a quantitative schedule risk analysis using one such commercial tool, in this
case a schedule risk analysis histogram of possible end dates, is shown in Figure 6.2.8-2. The
estimated ranges of impact of risks and uncertainties on the duration of scheduled activities
were fed into a Monte Carlo simulation program that generated a distribution of possible end
dates based on a resource loaded schedule. For the histogram below, the horizontal axis shows
the possible end dates. The right vertical axis shows the end dates for the confidence level
curve. 1 The dotted lines on the plot represent the end dates for which the confidence level for
completion by that date is 50% and 80% respectively. For this example, the PMB end date is
11/20/2015. If the project elects to use the 80% confidence level, then the chosen project finish
date is 7/28/2016, indicating that the project needs to mitigate or provide contingency for an
additional 8.3 months beyond the baseline date.

NSF sets a required range for the confidence level unless an exception is requested and approved by NSF. See Section 4.2.5 for
details.

1

Section Revision:
May 2, 2016

6.2.8-2

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.8 Quantitative Risk Analysis – Estimating Contingency
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)
Figure 6.2.8-2

Typical Result of a Quantitative Schedule Risk Analysis

Another typical output, from quantitative analysis of a resource-loaded schedule, is a time-cost
scatter diagram. Figure 6.2.8-3 plots cost on the y-axis against end date on the x-axis. A line is
drawn through the slope of the distribution. The plot illustrates the important fact that time
and cost are related. In this case, longer schedule activities with labor-type resources generate
higher cost.

Section Revision:
May 2, 2016

6.2.8-3

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.8 Quantitative Risk Analysis – Estimating Contingency
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)
Figure 6.2.8-3

Time-Cost Scatter Diagram: Each data point represents one realization of the simulation

6.2.8.2 Key Elements in Quantitative Risk Analysis
The platform for quantitative risk analysis is the project cost estimate or project schedule. Since
most cost estimates are developed in a spreadsheet, a risk analysis of the project’s cost
estimate alone is often conducted using a software package that simulates a spreadsheet
model.1 Schedule risk analyses simulate a project schedule, so software that is able to simulate
schedules developed in the organization’s preferred scheduling package should be used.2
Integrated cost-schedule risk analyses involve a good-quality PMB schedule (i.e., without cost
or schedule contingency) with loaded resources representing the cost estimate attached to the
activities they support.
Two commonly-used packages are @RISK from Palisade Corporation and Crystal Ball from Oracle. (NSF does not endorse or
recommend any particular package.)

1

There are several schedule simulation packages available. Two of the schedule simulation packages with the most capabilities
are Polaris from Booz Allen Hamilton and Primavera Risk Analysis from Oracle. Others include Acumen RISK from Deltek, Risky
Project from Intaver Institute, @RISK for Project from Palisades, JACS from Tecolote and Full Monte from Barbecana. (NSF does
not endorse or recommend any particular package.)

2

Section Revision:
May 2, 2016

6.2.8-4

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.8 Quantitative Risk Analysis – Estimating Contingency
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

The elements of risk that may affect the cost, duration, or both cost and duration of a project
include uncertainty, identified discrete risk events, and possible discontinuous events.
• Uncertainty represents inherent variability in predicting the outcome of future events.
The uncertainty may be from people and organizations’ inability to do the same thing
the same way reliably or from the fact that future events cannot be predicted with
complete accuracy. Uncertainty has a probability of 100% (since it is always present) and
an estimated range for duration or cost. The range often has a positive tail (opportunity)
and a negative tail (threat) such as -5% and +10%. These ranges represent the
confidence in the estimates of activity duration or cost element actually occurring as
estimated. The uncertainty ranges are often specified as a 3-point estimate with low,
most likely and high values for a specified distribution shape, often a triangular
distribution. For every iteration in a simulation, the software pulls a random impact
multiplier for each duration and/or each cost item from within the chosen distributions.
That value, say 1.07, is then multiplied by the activity duration or element cost in the
model to get the value to be used for that iteration.
o There may be asymmetry in the range of uncertainty since it is often easier to
overrun than underrun an estimated value. Hence the optimistic tail of the
distribution may not have as much probability as the pessimistic tail has. Also,
the most likely value may not be the assigned value in the schedule or estimate.
Hence a fairly typical uncertainty range could be .95, 1.05, and 1.15 – the middle
value implies that the duration or cost is most likely 5% higher than in the
baseline model.
o The range of uncertainty can also be used to cover potential, but as yet
unidentified, discrete risks that may surface later in the project than at the time
of analysis. The inability to identify discrete risks is common for events that occur
significantly later in the project or for activities that cannot yet be well defined.
Most often these uncertain risks can be addressed by allocating a wider range of
uncertainty to these durations or costs than to those assigned to better
understood activities occurring in the early years of the project. In this way the
generally higher level of uncertainty for durations and costs in the later years of
the project can be included in the risk analysis leading to the size of the
contingency reserve.
o Some types of activities have more inherent uncertainty than others. It may be
more difficult to make estimates of duration and cost for testing than for design,
whereas fabrication may be somewhere in between. Therefore, some categories
of activities may have wider uncertainty ranges than others. These activity-type
specific uncertainty bands are sometimes termed reference ranges.
•

Discrete Risk Events include those already identified and quantified in the Risk Register
as well as any that may be discovered when interviewing for risk data to use in the
quantitative risk analysis. Discrete risks are specified by their probability and range of
impact if they happen to activity durations or cost elements.

Section Revision:
May 2, 2016

6.2.8-5

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.8 Quantitative Risk Analysis – Estimating Contingency
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

•

o The probability determines the fraction of the Monte Carlo iterations that they
appear in.
o The impact range is related to the duration of the individual activities or size of
cost line items that they are assigned to. Hence the concept of impact range for
quantitative analysis is not the same as that used for qualitative risk analysis,
which is impact on the final date or total cost for the entire project.
o A risk can affect many activities or cost elements. Activities or cost elements can
be affected by more than one, sometimes many, discrete risks.
o Discrete risks can be represented by adding a risk to a cost element or schedule
activity or by specifying a multiplicative factor to apply to the estimated cost (risk
register method) or activity duration (risk driver method).
Discontinuous Risk Events are discrete events that can have consequences beyond
adding duration to existing activities or cost to an existing budget element. Technically
challenging projects such as NSF facilities typically have numerous discontinuous risks.
Capturing a complete list of these risks is critical to effective RM and project success. For
example, failing a qualifying test (or other discontinuous event) may require adding new
activities and cost to the schedule in order to recover from the event. These activities
and cost elements are almost certain not to be in the baseline schedule or cost estimate
since those artifacts are usually based upon success of the baseline plan.

6.2.8.3 Platforms for a Project Quantitative Risk Analysis
A project schedule risk analysis starts with a good-quality Critical Path Method (CPM) schedule:
•

The schedule can be a summary or roll-up of the detailed schedule of the project and
should not have any padding or contingency for risk. Estimated project end date and
schedule contingency duration are outputs of the risk analysis. The detailed project
schedule is not always a good candidate for risk analysis input since it usually has several
thousand activities and may be difficult to debug. That is, the detailed project schedule,
perhaps a contractor’s schedule, may not conform to scheduling best practices. 1 Hence,
and in recognition that a schedule risk analysis is a strategic analysis of the project,
summary or “analytical” schedules may be used instead of the detailed schedule. This
analytical schedule needs to represent all the work of the project (including contractor
and other participants such as the customer) and be validated against CPM good
practices. It is recommended that the summary or analytical schedule format adheres to
the project WBS to facilitate reporting of contingency usage.

Characteristics of a schedule used for Quantitative Risk Analysis are:
1) It represents all the work of the project,
2) All logic links are established,
One source of complete scheduling best practices is the Government Accountability Office (GAO) Schedule Assessment Guide,
2015.

1

Section Revision:
May 2, 2016

6.2.8-6

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.8 Quantitative Risk Analysis – Estimating Contingency
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

3) All constraints are appropriate, and
4) It is resource loaded.
Since the schedule validation process can require significant effort by project leaders, some
references1 recommend creating a 300-1000 line summary schedule from the project IMS and
resource loading it with a minimal number of summary resources. (Some multi-billion-dollar
projects have been known to use as few as eight summary resources.) That methodology is
followed in the exercise demonstrated in the following case study.
A cost risk analysis starts with a complete, PMB cost estimate:
•

The PMB cost estimate is complete for all in-scope work but does not include any builtin “padding” or contingency for risk. The estimated cost contingency amount is an
output of the risk analysis. The cost estimate is usually specified in spreadsheet format
and may be simple or detailed. It is recommended that the summary or analytical
schedule format adheres to the project WBS to facilitate reporting of contingency usage.

An integrated cost-schedule risk analysis starts with a resource loaded schedule for a PMB with
cost and schedule estimates:
•

A schedule, either analysis or detailed level, that is loaded with resources. For the
purpose of a risk analysis the resources do not have to be detailed at the same level as
the Cost Book, but they do have to distinguish between time-dependent (e.g., labor,
rented equipment) resources that will cost more if their activities are longer and timeindependent (e.g., materials, purchased equipment) resources that may have variable
cost but not because of uncertainty in duration. Again, it is recommended that the
summary or analytical schedule format adheres to the project WBS to facilitate
reporting of contingency usage.

All quantitative risk analyses require:
•

Good quality risk data collected in the Risk Register but usually enhanced using good
interview techniques. Note that SMEs are often more willing to talk freely about
extreme good and bad possible risk results in confidential interviews.

•

A professional schedule risk simulation package 2 that can perform a Monte Carlo risk
analysis simulation on a risk-loaded schedule.

David T. Hulett, principal author, Recommended Practice 57R-09, Integrated Cost and Schedule Risk Analysis Using Monte
Carlo Simulation of a CPM Model, AACEI, 2011.

1

There are several different software packages that can do this analysis. The package used for these charts and tables is
Polaris® from Booz Allen Hamilton.

2

Section Revision:
May 2, 2016

6.2.8-7

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.8 Quantitative Risk Analysis – Estimating Contingency
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

•

An organizational culture that is committed to conducting an unbiased and realistic risk
analysis and to use its output, such as total risk to objectives or prioritized risk events to
be mitigated in order to improve the prospects of the project.

6.2.8.4 Case Study: Quantitative Risk Analysis 1 Exercise
These steps will be illustrated with a simple case study of an integrated cost-schedule risk
analysis of design and fabrication of a space vehicle, as shown in the resource-loaded Gantt
chart schedule shown in Figure 6.2.8-4.
Figure 6.2.8-4

Resource Loaded Schedule Used for a Simple Case Study of an Integrated Cost-Schedule Risk
Analysis for Design, Fabrication, Testing, and Delivery of a Space Vehicle

This is a project starting June 1, 2008, with a ship to launch site end date of November 20, 2015.
The project cost is estimated at $651.6 million.2 Resources are shown on the bar chart and
include mostly labor, with some equipment in the First Stage and Upper Stage Fabrication
activities.
In this case study the resources, as shown in Table 6.2.8-1, are few and summary.
1 David T. Hulett, principal author, Recommended Practice 57R-09, Integrated Cost and Schedule Risk Analysis Using Monte
Carlo Simulation of a CPM Model, AACEI, 2011.
This schedule has been developed in Microsoft Project. Another popular scheduling package is Primavera P6 from Oracle.
Most schedule simulation packages can import projects from these two scheduling packages.

2

Section Revision:
May 2, 2016

6.2.8-8

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.8 Quantitative Risk Analysis – Estimating Contingency
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Table 6.2.8-1 Resources for Quantitative Risk Analysis Example
Resource Name

Type

Preliminary Designers

Work

Detail Engineers

Work

Fabrication

Material

Integrators

Work

Integration Testers

Work

Specification Writers

Work

Unit Testers

Work

Fabricators

Work

6.2.8.5 Schedule Risk Analysis ‒ Uncertainty
The schedule risk analysis starts with uncertainty reference ranges, estimated by the project
SMEs. Recall that the probability for uncertainty occurring is 100%, and thus occurs for all
simulation iterations for all assigned durations. The ranges shown in Table 6.2.8-2 are the SMEs’
estimates of uncertainty in the task durations. Note that three of these imply that the SME
interviewees assess the “Most Likely” value to be greater than the durations in the schedule.
This may be because they view the schedule as being built with optimistic durations or that
more has been learned about activity durations, leading to a higher estimate of the “most
likely” durations. Although not shown here, their evaluation could also have resulted in lower,
mostly durations. The use of Risk Drivers allows these distributions to have both threat and
opportunity tails.
Table 6.2.8-2

Schedule Duration Risk Reference Ranges

Activity Category

Low

Most
Likely

High

Designers

0.90

1.00

1.20

Fabricators

0.95

1.05

1.20

Integrators

0.95

1.05

1.20

Requirement Writers

0.90

1.00

1.15

Testers

0.85

1.10

1.25

Notice that these are fairly narrow ranges that represent inherent variability, for instance, but
do not represent the impact of discrete risks on the activity durations. These ranges are applied
to the activities in the named categories by a triangular distribution, in this case, from which
the computer pulls at random a multiplicative factor that is applied to the schedule duration.
The example exercise demonstrated here uses 5,000 iterations because the software is fast, but
3,000 iterations would generally be enough.

Section Revision:
May 2, 2016

6.2.8-9

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.8 Quantitative Risk Analysis – Estimating Contingency
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Uncertainty ranges should be wider the further out into the future the work is being planned
and estimated. This is because it is harder to estimate durations or costs several years into the
future, since the work has not been contracted yet and may not actually be detailed with any
specificity. Also, there will be risks in the future that cannot be identified today as discrete risks
but should be provided for with wider uncertainty ranges.
The analysis is performed using the reference ranges. If the analysis stopped at this point with
just uncertainties, the schedule results would look like the histogram shown in Figure 6.2.8-5
below. The 80th percentile has been chosen as the target level of confidence for this example.
The target confidence level for actual projects is chosen by the project or the customer. 1 The
related cost risk histogram shown in Figure 6.2.8-6 represents the effect of duration uncertainty
alone on the costs for time-dependent resource.
Figure 6.2.8-5

End Date Results for Schedule Duration Uncertainties

To show these results one software package, Polaris, was chosen. However, these results can be achieved using Primavera
Risk Analysis, JACS, Risky Project and others.

1

Section Revision:
May 2, 2016

6.2.8-10

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.8 Quantitative Risk Analysis – Estimating Contingency
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)
Figure 6.2.8-6

Cost Result for Schedule Duration Uncertainties

The results can also be shown in tabular form, with the 5% and 95% values included to
determine if the total range is believable. For uncertainties alone, the results in Table 6.2.8-3
are believable.
Table 6.2.8-3

Results with Schedule Uncertainties Assigned

Schedule

Baseline

5%

50%

80%

95%

Dates

20-Nov-15

8-Feb-16

19-May-16

14-Jul-16

7-Sep-16

2.6

6.0

7.8

9.6

Months from Base
Cost

Baseline

5%

50%

80%

95%

Dollars (millions)

651.6

660.6

684.4

697.1

709.5

1%

5%

7%

9%

% above Base

Because this is an integrated cost-schedule risk analysis there is interest in the relationship
between time and cost. This is shown in a finish date – total cost scatter diagram shown in
Figure 6.2.8-7. The scatter plot has a dot for each of all 5,000 iterations. The scatter slope
indicates the positive relationship between time on the horizontal axis and cost on the vertical
axis. The curved line toward the top right of the scatter represents those combinations of cost
and schedule results that exhibit a 70% probability of meeting both objectives, given the
uncertainties applied to the cost-loaded schedule. The target of 70% confidence level for

Section Revision:
May 2, 2016

6.2.8-11

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.8 Quantitative Risk Analysis – Estimating Contingency
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

budgeting and scheduling was chosen in this case since it is often used by several government
funded agencies, such as NASA.1
Figure 6.2.8-7

Total Cost and End Date Scatterplot for Schedule Uncertainties

Note that the schedule uncertainty data in this example are assumed to be not correlated. If
they were correlated (i.e. if one is high in its range then the others would also be high in their
ranges), the extremes in cost and time would be greater and the correlation between time and
cost would be tighter than shown above. The analyst should explore whether the uncertainty
distributions should exhibit correlation or not. If so, then the analyst will want to exploit the
capabilities of the chosen analysis package to handle correlations.
6.2.8.6 Schedule Risk Analysis ‒ Discrete Risks Added as Drivers
The second step is to identify, calibrate and assign discrete risks to the project schedule. The
risks used in this example are applied to the categories of activities, including design,
fabrication, integration, testing and requirements. For this exercise the risks are given generic
names, but in an actual analysis the risks would be taken from the Risk Register and augmented
by risks discussed in the confidential risk interviews. The generic risks for this exercise, with
their probabilities are shown in the top section in Figure 6.2.8-8. One risk, “Organizational risk
1

See: “Understanding the Joint Confidence Level (JCL) at NASA,” NASA Office of Evaluation at 9/4/14.

Section Revision:
May 2, 2016

6.2.8-12

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.8 Quantitative Risk Analysis – Estimating Contingency
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

affecting all,” has been selected to show its assigned impact range next to the triangle symbol
on the right: Min 0.85, mode 1.05, Max 1.3. The Organizational risk has a probability of 70% and
is assigned to all tasks since its impact is felt on everything. Although the description has not
been filled in for this exercise, the organizational risk could stem from “lack of ready access to
key decision makers that can increase durations” or to “organizational red tape that could slow
decision making,” for example.
Figure 6.2.8-8

Schedule Risk Drivers – Organizational Risk

When these risk drivers are assigned to multiple tasks or activities, those activities’ durations
become correlated since (1) if the risk occurs it occurs for all activities to which it is assigned,
and (2) the multiplicative factor chosen for that iteration is applied to all of those activities. If
only one risk is involved the activities become 100% correlated. If other risks are also assigned
the correlation between activity durations is reduced. In this way the risk driver method models
how correlation occurs so SMEs do not have to guess at the correlation matrix. With the
addition of discrete risks to the analysis, the schedule impacts are more pronounced, and the
results show a later start (by 15.4 months) and higher cost (by $100 million) than with just the
uncertainties for the 80% confidence level. See Table 6.2.8-4 below. Note that the cost increase
is due to schedule duration risk drivers alone, and not to any cost uncertainty or risk.
The scatterplot in Figure 6.2.8-9 shows greater correlation of time and cost risk than the
previous plot showing uncertainties only, since the Organizational risk driver was assigned to all
activities.

Section Revision:
May 2, 2016

6.2.8-13

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.8 Quantitative Risk Analysis – Estimating Contingency
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)
Table 6.2.8-4

Results with Schedule Uncertainties and Discrete Risks Assigned

Schedule

Baseline

5%

50%

80%

95%

Dates

20-Nov-15

5-Jan-16

28-Dec-16

26-Oct-17

16-Aug-18

1.5

13.3

23.2

32.9

Months from Base
Cost

Baseline

5%

50%

80%

95%

Dollars (millions)

651.6

650.7

730.6

797.6

865

0%

12%

22%

33%

% above Base

Figure 6.2.8-9

Total Cost and End Date Scatterplot Showing Greater Correlation of Time and Cost Risk

6.2.8.7 Cost Risk Analysis ‒ Uncertainty and Discrete Risk Drivers
The last consideration in this simple example is whether there are uncertainties and discrete
risks for cost which would cause cost variations that are independent of schedule.
Examples of uncertainty could be errors in the time independent cost of fabrication, variances
in the time-dependent activities’ daily “burn rate” due to uncertainty in the number of
hours/workers needed per day, and/or uncertainty in the estimated salaries. These risks, if they
Section Revision:
May 2, 2016

6.2.8-14

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.8 Quantitative Risk Analysis – Estimating Contingency
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

occur, are in addition to the cost impact from schedule duration risks already discussed in the
previous material. The cost estimating error on the burn rate of labor or total cost of
equipment can be entered by resource as uncertainties, with probability of 100% and a range of
impact. Example uncertainty reference ranges for cost uncertainty as applied to different
resources for this exercise are shown in Figure 6.2.8-10.
Figure 6.2.8-10

Uncertainty in the Burn Rate and Total Cost

Resources and Their Utilization Uncertainty
UID

Planned Units per
Unit or Day

Rate Per Unit or Day
Min - Most Likely - Max

Resource

Type

1

Preliminary Engineers

Time Dependent

640

600 - 650 - 700

2

Detail Engineers

Time Dependent

960

900 - 960 - 1,020

3

Fabrication

Time Independent

1

0.9 - 1.05 - 1.15

4

Integrators

Time Dependent

1,200

1,100 - 1,250 - 1,500

5

Integration Testers

Time Dependent

1,200

1,150 - 1,250 - 1,550

6

Specification Writers

Time Dependent

800

750 - 800 - 850

7

Unit Testers

Time Dependent

800

700 - 825 - 950

8

Fabricators

Time Dependent

720

680 - 720 - 760

Discrete Risk drivers affecting cost can also be included to the analysis, in addition to the
uncertainty factors. These cost factors can be entered as the implication of identified risk
drivers, just as in the previous exercise for schedule drivers. If both cost and schedule risks
occur, the burn rate, cost estimate, and duration will vary, and each driver will cost to vary.
While new risks may be entered that just affect the burn rate or total cost of equipment, the
existing risks with schedule drivers already included can have those impacts as well. For
example, a cost factor has been added to the Risk Driver Editor for the previously identified
Organizational risk affecting all tasks, as shown in the Figure 6.2.8-11.

Section Revision:
May 2, 2016

6.2.8-15

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.8 Quantitative Risk Analysis – Estimating Contingency
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)
Figure 6.2.8-11

Screenshot of Risk Driver Editor

After running the program with the addition of cost uncertainties to resources and allowing risk
drivers to affect costs directly rather than only through schedule risk, there is a direct impact on
cost, as can be seen in Table 6.2.8-5 below. The schedule table is not shown, since the cost
drivers included in the exercise do not by themselves impact duration. Note that some risks will
have just schedule duration uncertainties and risk drivers, some will have just cost uncertainties
and drivers, and some will have both. Cost will be affected in all cases, but schedule is affected
only for those risks with duration uncertainties and drivers.
Table 6.2.8-5

Results with Uncertainties and Cost Risks Assigned

Cost

Baseline

5%

50%

80%

95%

Dollars (millions)

651.6

679

838.6

975

1100

4%

29%

50%

69%

% above Base

Adding the uncertainty and risks affecting the costs independently of time to the simulations
results in a time-cost scatterplot shows less connection between time and cost, as shown in
Figure 6.2.8-12.

Section Revision:
May 2, 2016

6.2.8-16

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.8 Quantitative Risk Analysis – Estimating Contingency
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)
Figure 6.2.8-12

Scatterplot Showing Less Connection between Time and Cost

6.2.8.8 Handling Inflation
Inflation is a part of the NSF budgeting and project planning. The program should select an
acceptable source for the future inflation rate and use it in the baseline and the risk analysis of
that baseline. For the case study in this exercise, the baseline cost is projected at $651.6 million
in base year dollars, that is, without inflation. With risks but no inflation the risk analysis
simulation shows a cost in base year dollars of $975 million at the 80th percentile of certainty.
The analysis program can be used to factor in inflation if the cost estimating has been
performed in base year dollars. Adding the factor of cost inflation and setting it at the rate of
3% causes the risked cost at the P-80 level to increase to $993 million in then-year dollars as
shown below in Figure 6.2.8-13:

Section Revision:
May 2, 2016

6.2.8-17

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.8 Quantitative Risk Analysis – Estimating Contingency
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)
Figure 6.2.8-13

Scatterplot with Addition of Cost Inflation Factor

The value of 3% inflation may be a most likely number, but the software used in this exercise
does not support an uncertain inflation level in simulation. A suggestion is to perform two
scenarios where the inflation rate is either lower or higher than 3%.
• At 2% inflation the cost is estimated at $987 million
• At 4% inflation the cost is estimated at $1 billion.
These scenarios can help understand the total “then dollar” cost of the project that is risk
adjusted, and the impact of the inflation assumption on that number.
6.2.8.9 Prioritizing the Discrete Risks ‒ Risk Mitigation Workshop
The organization is encouraged to use these results to help improve the prospects of the
project by mitigating the important risks. To do this the risks are prioritized. See Table 2.1.6-1
for sample prioritization from this exercise. This prioritization method uses the Monte Carlo
simulation, a 60-year old method, and the schedule which the project team is using to manage
or at least summarize the project. It is thought that this prioritization of risks is more realistic
than that using qualitative methods resulting in the risk register, in part because it recognizes
the structure of the schedule and handles correlations.

Section Revision:
May 2, 2016

6.2.8-18

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.8 Quantitative Risk Analysis – Estimating Contingency
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)
Table 6.2.8-6

Savings and Days Saved

ID

Name

Cost Savings

Days Saved

7

Organizational risk affecting all

$196.15M

207

7

Uncertainty

$48.03M

152

6

External risk affecting all

$34.97M

41

2

Risk affecting fabrication

$23.8M

31

4

Risk affecting testing

$4.28M

34

3

Risk affecting Integration

$10.86M

32

1

Risk affecting design

$5.35M

10

5

Risk affecting requirements

$0

0

The risk mitigation exercise should be done in a workshop setting since many people have to
contribute and commit to the mitigations.
•

This workshop includes the PM, DPM, team leads and others involved in mitigation of
risk.

•

Given the prioritized list of risks for a project that may overrun cost and schedule
targets, the project team can develop risk mitigation actions. The mitigation workshop
estimates the improvement in the probability and impact parameters is expected to
result from the various mitigations planned for each identified risk (uncertainty cannot
be mitigated in concept).

•

For the mitigation actions to “count” against the project risk management should
commit to them as evidenced by their post-mitigation budget, schedule and assignment
of people to monitor the risks and their mitigations. These risks should be added to the
risk register as well so they are reviewed frequently.

•

Each risk mitigation action accepted is modeled and the post-mitigation amount of risk
to time and cost is recorded, along with the cost of the risk mitigation. A post-mitigation
simulation will determine how much benefit is expected from the mitigations.

•

The final report includes post-risk mitigation results and the overall project cost and
schedule risk if those risk mitigation actions are taken and mitigate the risks. Note that
the original cost and schedule target will generally not be met since that would require
complete mitigation of the risks that caused the estimate of overrun in the risk analysis
itself.

Section Revision:
May 2, 2016

6.2.8-19

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.9 Risk Response Planning
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Risk Response Planning
Figure 6.2.9-1

• Risk Register
• Meeting and
stakeholder
interviews
with
dependent
organizations

Inputs

Risk Response Planning Process

Process
• Confirm whether mitigation is required for risks
based on the Probability/Impact Ranking Chart
• Confirm root causes
• Develop a plan to mitigate the risk and provide a
Description and an Owner in the Risk Register
• Chart the risk mitigation events in time
throughout execution and map the improvement
in risk status to mitigation events
• WHEN: at the time risks are identified, at weekly/
monthly status meetings, and when changes to
the risks occur

• Updated Risk
Register
• A separate action
item or schedule for
implementing risk
mitigation

Outputs

A known risk (often referred to as a “known unknown”) is a risk that has been identified and
can be calibrated (probability and impact) and analyzed. Examples of known risks may include
strategic or overriding aspects of the project environment such as poor project management
practices, lack of resources, multiple projects, external dependencies, relationships between
project participants, technical complexity etc. Identified risks need to be proactively managed
throughout the project life cycle by identifying who owns the management of that risk and by
outlining risk symptoms, triggers, and contingency plans that would prevent the risk from
occurring or that would lessen the project impact should it occur.
The Risk Response Planning step includes considerations related to risk mitigation and response
planning. This includes the assignment of one or more persons to take responsibility for each
identified risk and the development of measures and action plans to respond to the risk should
it become an issue. PMI PMBOK® Guide defines Risk Response Planning as the process of
developing options and actions to enhance opportunities and to reduce threats to project
objectives.
Risk response actions for threats are generally categorized as: 1

1

•

Avoid – This strategy involves changing the project to eliminate the threat from
identified risk

•

Mitigate – This strategy involves taking early action to reduce the likelihood and/or
impact of risk

•

Transfer – This strategy involves shifting the responsibility and ownership of the risk to
another party. Although this strategy is seldom used for NSF projects, it typically

This listing and these descriptions are described in the PBMOK® Guide, 5th Edition, 2013 PMI

Section Revision:
May 2, 2016

6.2.9-1

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.9 Risk Response Planning
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

involves purchasing insurance against the type of risk or requiring vendors to assume
more risk.
•

Accept – This strategy involves acknowledging the threat as part of the project and
accepting the consequences of its occurrence. An example of this is political or
legislative risk that is out of the control of the project team. The consequence of
acceptance may mean that contingency resources may need to be applied if the risk is
realized.

Risk response actions for opportunities are generally categorized as:
•

Exploit – This strategy seeks to eliminate the uncertainty associated with this
opportunity to ensure it happens. This is similar to Avoid threats.

•

Enhance – This strategy seeks to increase the probability and / or the positive impacts of
the opportunity. This is similar to Mitigate threats.

•

Share – This strategy seeks to share the benefits of the opportunity with another
organization that is in the best position to secure the opportunity for the project. This is
similar to Transfer for threats.

•

Accept – This strategy accepts an opportunity if it arises but does not envision pursuing
it, similar to Accept for threats.

For the most part, project risk response planning will consist of defining risk thresholds for
action, confirming risk triggers, and then planning a mitigation strategy and/or developing
backup plans if risks occur. A risk trigger is an event or events that activate the execution of a
backup plan, should the risk become an issue. Triggers should be specified in the Risk Definition
in the Risk Register, as well as the date that risk resolution is required for each risk. Mitigation
strategies identify actions that may minimize or eliminate project risks before the risk occurs or
document decisions to accept the consequences of risks without action. A risk may have several
mitigation activities that attempt to balance the reduction in the probability and/or the severity
of the risk occurrence with the cost-effectiveness of the mitigation strategy. Mitigation planning
requires that the root cause(s) of the risk be identified and that the mitigation strategy and
plans be aligned accordingly. Backup plans define actions to be taken in response to identified
risk triggers in hopes of reducing potential project impact as a result of a realized risk (often
defined in the literature as an “issue”).
A tabulated example of the impact of Risk Response evaluation is given below in Table 6.2.9-1.

Section Revision:
May 2, 2016

6.2.9-2

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.9 Risk Response Planning
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)
Table 6.2.9-1

Impact of Risk Handling on Project Cost

Before Handling

Risk Item or Basis
Redesign to solve problems identified during reviews
Do analyses or design per external comments
Rework design documents during concept evolution
Redesign for add’l equipment for ops or pretreat interface
Design for sintering equipment
Redo design for SNF re-sizing
Redesign; contamination control in process room
Change design basis, due to scale-up impact
Redesign, for SC furnace
Redesign to add gas-trapping system
Rework to add waste streams to design
Rework robotic features design
Redesign for characterization
Redesign to meet canister requirements
Design for new cables
Redesign for additional MC&A equipment
Redesign, to apply new structural criteria to 105L
Redesign, per SGS inputs
Redesign for changes, per NRC interface
Additional utility design features
Delays initiating design, awaiting R&D completion
Delays redesigning for classified process control system
Add features to meet IAEA
Uncertainty in obtaining contingency funds
Disposal of bundling tubes
Decontamination of final-product canister
Storage location for depleted uranium
Availability of emergency generator and fuel tank
Redesign for necessary structural supports
Arithmetic Sums:
Section Revision:
May 2, 2016

Risk Level
Moderate
Moderate
Moderate
Moderate
High
Moderate
Moderate
Low
Low
Low
High
High
High
Moderate
Moderate
Moderate
Moderate
Low
Moderate
Moderate
High
Low
Moderate
Moderate
Moderate
Moderate
Moderate
Moderate
Moderate

Worst Case
Cost ($K)
3,360
390
5,720
160
500
200
5,000
50
800
1,550
3,000
7,440
5,000
3,000
400
400
1,500
500
200
500
5,360
60
500
2,000
100
500
100
40
300
48,630

After Handling
Residual Risk Cost Estimates ($K)
Handling
Strategy
Mitigate
Avoid
Mitigate
Mitigate
Mitigate
Accept
Mitigate
Accept
Mitigate
Accept
Mitigate
Mitigate
Mitigate
Accept
Mitigate
Mitigate
Mitigate
Accept
Mitigate
Accept
Mitigate
Avoid
Mitigate
Avoid
Avoid
Avoid
Avoid
Avoid
Avoid

Cost Implement
Handling
75
0
0
0
308
0
361
0
0
0
0
53
176
0
0
0
300
0
0
0
0
0
0
0
75
341
75
0
225
1,989

Risk
Level
Low
-Moderate
Low
Moderate
Moderate
Moderate
Low
Low
Low
Moderate
Moderate
Moderate
Moderate
Low
Low
Low
Low
Low
Moderate
Moderate
-Low
-------

Best
Case
0
N/A
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
N/A
0
N/A
N/A
N/A
N/A
N/A
N/A
0

Most
Likely
150
N/A
750
40
0
50
300
15
0
0
250
500
600
100
0
0
0
0
0
300
240
N/A
0
N/A
N/A
N/A
N/A
N/A
N/A
3,295

Worst
Case
500
N/A
2,500
100
200
200
3,000
50
50
1,550
2,300
2,000
3,000
3,000
50
50
700
500
150
500
720
N/A
50
N/A
N/A
N/A
N/A
N/A
N/A
21,170

6.2.9-3

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.9 Risk Response Planning
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

The risks with mitigation plans and risk triggers are all listed in the Risk Register with their
Qualitative Risk Assessment status. After Risk Response Planning has been performed the entire
entry for the risk includes:
•
•
•
•

•
•

Its statement or definition
Analysis and ranking of initial risk
Assignment to a risk owner
Risk mitigation actions and backup plans
o Costs
o Timing and risk triggers
o Expected results
Status of mitigation efforts
Analysis and ranking of residual risk after mitigation

The last item listed above is the expected residual risk and ranking after mitigation has been
applied. This is accomplished by repeating the analysis of probability and ranked impact on
project objectives with successful mitigation assumed. Thus, the Risk Register shows “before”
and “after” views of the analysis, with risks migrating down from red to yellow to green with
the mitigation steps that cause the improvement in risk status and timing of those steps. The
sample risk register shown in Figure 6.2.7-6 shows columns with headings for “Pre-Mitigated”
and Post-Mitigated” analysis results.

Section Revision:
May 2, 2016

6.2.9-4

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.10 Risk Monitoring and Control
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Risk Monitoring and Control
Risk Management requires continuous monitoring of project risk and iterative application of the
risk identification, analysis, and response processes. Existing risks need to be monitored,
controlled, and ultimately retired, while new risks should be identified and added to the Risk
Management process. Risk Monitoring and Control is the process of identifying, analyzing, and
planning for new risk, keeping track of and re-analyzing identified risks, monitoring risk
symptoms and triggers, reviewing the execution of risk responses strategies while evaluating
their effectiveness, and reporting status to stakeholders. The Risk Register, as the tool that
supports Risk Management and provides a means of communication, should be kept up to date
with status and changes. The frequency and process for reviewing project risk is set out in the
project Risk Management Plan.
Risk Control includes the process of regularly updating the Risk Register and communicating to
stakeholders the latest risk status, with resulting impacts on the project and mitigation plans.
Reporting of project and program level risks should be included as part of regularly scheduled
status meetings with, and in formal status reports to, internal project members as well as
eternal stakeholders and the NSF. The NSF has emphasized the need to communicate the risks
at regularly scheduled status meetings to ensure that continued focus and awareness is placed
on risk management.
Figure 6.2.10-1

• Risk Register
• Meeting and
stakeholder
interviews with
dependent
organizations
• Supporting
documentation
from project
artifacts

Inputs

Risk Monitoring and Control Process

Process
• Repeat risk identification to determine if new risks
should be put on the Risk Register and handled
• Regularly review the project for the risks reported on
the Risk Register to see if they have changed
probability or impact or should be retired
• Review the mitigation plans and validate that they still
represent an acceptable approach
• Disseminate mitigation strategies to stakeholders and
responsible resources. Follow on action items for
mitigation plans and report on status
• Use Risk Register to create and communicate the risk
disposition
• Ensure a continuous review of the risks and
monitoring for the mitigation and contingency efforts

• Updated Risk
Register
• Corrective actions
(not originally
identified as
mitigations)
• Report and
communicate on
new risks and
updated items

Outputs

When risks are resolved, they should be retired from the list of active risks. When the project
ends, the risk register may be closed. If some risks pose other future threats to the program or
future projects, consideration should be given to re-opening a risk with the appropriate
operations management, or at the program level as an “ongoing risk.”

Section Revision:
May 2, 2016

6.2.10-1

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.11 Contingency Management for Risk Mitigation
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Contingency Management for Risk Mitigation
6.2.11.1 Contingency Budget Timeline
NSF expects the project to refine its WBS budget estimates following the Preliminary Design
Review (PDR), adding additional definition to the tasks associated with accomplishing the
project’s deliverable activities. At Final Design Review (FDR) the PEP budget estimate should be
substantially based on externally obtained cost estimates (vendor quotes, bids, historical data,
etc.). This added definition is expected to result in an increase to the project’s estimated
Budget at Completion (BAC) and project schedule, and a concomitant reduction in its budget
and schedule contingencies, while TPC and the risk-adjusted, committed schedule finish date
remain constant. The quantitative risk analysis should have a component to anticipate this
increase in cost and time so that the original contingency amounts are sufficient to provide for
this increase.
As a project progresses, the baseline cost estimate and schedule will typically be exceeded and
contingency amounts of dollars and time will be used. Periodically the project cost estimate
must be revised to reflect all new information, including actual costs and use of contingency
funds, adjustments to the risk profile, learning curves for manufactured items, etc. This new
estimate of the cost of the remaining work is called the Estimate to Complete (ETC), and the
Actual Cost of Work Performed + ETC is equal to the latest revision of the Estimate at
Completion (EAC). The EAC should be compared to the sum of BAC plus remaining contingency
to ensure that it is less than the TPC. If the sum of BAC plus remaining contingency is greater
than the TPC, de-scoping may be necessary. See Section 4.2.5 for details on requirements for
budget contingency use.
The project should create and maintain an expected contingency allocation profile. Contingency
allocation profiles usually do not track the commitment or spending profiles. For many projects,
the highest use of both schedule and budget contingency occurs during procurement and
during final commissioning/integration phases. A contingency allocation curve for such a
project would be bi-modal, with one peak for procurements activities and another for
significant contingency amounts held back until the end of the project, even though the
spending curve may be low near the end of the project. Although risk does burn down over
time, there may be significant reworking of hardware, for example, needed as a result of
knowledge gained during integration and commissioning activities.
6.2.11.2 Change Control for Contingency Adjustments
Adjustments to cost, schedule, and scope are documented and approved under the project
Change/Configuration Control Process (CCP, PEP-8.2). The Risk Management Plan describes how
the project uses the Change/Configuration Control Process (CCP) to assign contingency to
specific WBS elements when risks materialize, and how budget contingency is de-allocated from
WBS elements and returned to the contingency category when budget underruns occur. The
Change Control Process should be initiated when the Total Project Cost target is established at
Section Revision:
March 10, 2017

6.2.11-1

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.11 Contingency Management for Risk Mitigation
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

the Preliminary Design Review, and followed for the duration of the project. All change control
actions that affect the use of contingency – cost, schedule, or technical performance and scope –
should include a link to an identified and documented risk and indicate the affected WBS
elements at the first meaningful level of technical differentiation within the project. The CCP
must make provision for seeking prior approval from the NSF Program Officer for all actions
exceeding thresholds as defined in the CA. All change requests are to be archived by the project,
and made available for review by NSF. The Project must keep a log of all change actions such
that contingency actions, including puts and takes, can be reported and summarized. See
Section 4.2.5 for further details and a sample Change Request form.
Note that use of contingency does not automatically require a change to the baseline. For
instance, a change control action can authorize contingency to cover a cost overrun which is
tracked as a variance on the baseline Budget at Completion (BAC). In such a case the
contingency can be incorporated into either the BAC or the EAC. In the first instance, the BAC is
changed. In the second, the variance from the BAC remains and can be used for trending and
other information. See Section 4.2.5 for further details on approval levels for use of
contingency.
Adjustments to contingency should include taking advantage of opportunities to assign savings
and underruns to contingency. Savings should not be left in associated WBS elements if they
are above thresholds set out in the Risk Management Plan, nor should they be shifted to other
tasks without going through the Change Control Process for return to contingency and
subsequent allocation to a different WBS element. Budget and cost underruns should be moved
to contingency as risks are retired and WBS elements are closed out and reconciled. Savings
realized through the implementation of planned de-scoping options should also be placed into
contingency. Returning the savings allows the best use of contingency for overall project
priorities.
6.2.11.3 Liens List: Forecasting and Opportunity Management
The Project should maintain a Liens List of planned future adjustments to contingency as a
forecasting tool that tracks actions that have not yet been incorporated into the BAC or EAC.
The list may document items such as very high probability risks with trigger points for action,
deferred scope held as contingency until a decision date, realized risks needing draws on
contingency that require more definition for a change control action to be implemented, and
anticipated opportunities for returns to contingency. It can also be used to record the need for
contingency to cover variances that will not/cannot be mitigated. It does not serve the same
purpose as a watch list or major threats list from the Risk Register. It acts as an escrow or
staging account for planned or near certain contingency allocations.
The List should include a description of the identified risk and the anticipated action, with
estimates of budget and schedule impacts, and anticipated decision date for any CCB action.

Section Revision:
March 10, 2017

6.2.11-2

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.11 Contingency Management for Risk Mitigation
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

The affected WBS elements should be identified, at the second level (or the first meaningfully
specific level of scope description), where known.
Projected amounts of possible future adjustments to contingency in the Liens List are to be
periodically reported to NSF. NSF recommends including this information within the monthly
status report as well.
6.2.11.4 Updates of the Estimate at Complete and Risk Exposure
The project should maintain an estimate of total costs and risk exposure by periodically
updating the schedule, the Estimate at Completion (EAC), and the analysis of overall project
risk. Estimated contingency amounts should be appropriate for the risk exposure throughout
the project life cycle. During concept and early development stages, a qualitative risk analysis
and risk register may provide an adequate estimate of risk exposure for both the design and
construction planning estimates. As project planning reaches the preliminary design phase, the
drawbacks of qualitative analysis – limited subset of risks, ignored correlations, and arithmetic
sums of averages – do not allow that method to adequately portray total project risk. 1 Project
planners should transition to quantitative risk analysis in order to establish a substantiated total
project cost at the time of the PDR.
For the construction stage, initial contingency is a part of project total budget as defined by the
award instrument; or in other words the Budgeted Cost of Work Scheduled (BCWS) under EVM.
As time goes by, risk exposure changes with risk mitigation, new knowledge, and new
circumstances. The amount of remaining budget contingency fluctuates over time with
assignments to risk mitigation and return of any savings; either from a risk being retired or work
packages coming in below the estimated budget. The total remaining available budget
contingency should be compared to the remaining risk exposure to determine whether the
project has adequate funds to cover anticipated risks. Remaining available contingency should
always equate to the difference between the project total budget (Budget at Completion, BAC)
minus the Estimate at Completion (EAC) and any liens.
The sum of the (EAC + liens) should include variances (backward looking actuals) and updated
estimates (forward looking forecasting) in the current plan, not the target baseline BAC. The
EAC should equal the BAC only at project start and after major changes to the baseline from replanning or re-baselining.
It is good practice to re-estimate EAC and Risk Exposure yearly, unless stated otherwise in the
CA. Specific dates may also be appropriate times for re-evaluation, such as at major milestones
dates. The Project Manager periodically re-assesses the current risk assessment to identify and
address any new risks that arise as the project progresses. This assessment should result in a
determination of whether cost and schedule contingency remain sufficient for project risks.
1

Projects usually adopt a more conservative certainty target such as the 80th percentile.

Section Revision:
March 10, 2017

6.2.11-3

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.11 Contingency Management for Risk Mitigation
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

6.2.11.5 Contingency Use and NSF Oversight during Construction
The NSF Program Officer must concur on all CCB actions exceeding CA- or contract-defined
thresholds for allocation of budget, schedule, or scope contingency. NSF will negotiate a CA
with the Recipient institution to fund project construction activity which will specify thresholds
above which prior NSF approval 1 is required before allocation of contingency (following formal
CCB review) to specific WBS elements. Contingency may only be used to support in-scope work
for the approved project baseline. See Section 4.2.5.7 for additional details.
6.2.11.6 Documentation and Reporting of Contingency Use
Risk management actions involving Change Control actions fall under the following
documentation and reporting requirements, as stated in more detail in Section 4.2.5:
•

All Change Control Requests, irrespective of amount or whether they increase or
decrease the BAC, are to be reported directly to NSF Program Officer

•

The Recipient will keep an archive of all Change Control Requests

•

The Recipient will keep a summary log of all Change Control Requests

•

Projected amounts of possible future adjustments to contingency (“liens”) are to be
periodically reported to NSF.

NSF recommends including this information within the monthly status report. Note that
National Science Board (NSB) approvals 2 are required when Change Control actions exceed the
even higher thresholds defined by NSB policy.
The required summary log of all Change Control actions should include the following:
•

Change control action title,

•

Change control document reference number,

•

Change control approval date,

•

Amounts of change in budget, scope, and/or schedule, for each affected and identified
WBS element,

•

Any adjustments to contingency amounts,

•

WBS elements affected by the changes (at WBS Level II or at the first meaningful level
of technical differentiation within the project)

•

Risk Register ID number and description for the risk being addressed, and

•

NSF approval date if required.

Thresholds are necessary to allow the project to respond in a timely way to small, immediate needs for use of contingency,
such as field changes during construction. This avoids potential cost escalation that could result from delay.

1

2

See Section 2.4, Construction Stage, for details on NSF policy on how and when NSB authorization is required.

Section Revision:
March 10, 2017

6.2.11-4

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.11 Contingency Management for Risk Mitigation
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Monthly reports must also include the status of contingency as part of the Earned Value
Management (EVM) reports. See Sections 4.2.5.8 and 4.6.2 for details on reporting.

Section Revision:
March 10, 2017

6.2.11-5

Major Facilities Guide: NSF 19-68 (May 2019)
6.2.12 Partnership Considerations for Contingency Management
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Partnership Considerations for Contingency Management
NSF may partner with other entities to plan and construct a major facility. The guidelines within
Section 4.2.5.9 of this document are applicable when NSF funds a particular scope of work
within a larger overall project. Risk assessment, contingency development processes and
contingency status reporting are to be applied to those WBS elements to be funded by NSF.
NSF encourages the development of unified management for project planning and execution of
the entire project scope wherever practical.

Section Revision:
May 2, 2016

6.2.12-1

Major Facilities Guide: NSF 19-68 (May 2019)
6.3.1 Introduction
Prepared by the Directorate for Computer & Information Science & Engineering (CISE)

6.3

GUIDELINES FOR CYBER-SECURITY OF NSF’S MAJOR FACILITIES
Introduction

Data creation, sharing, and analysis are central to the progress of science. As information has
becoming increasing digital and increasingly accessible from anywhere, the confidentiality,
availability, and integrity of information and information systems has raised the importance of
cybersecurity considerations. Cybersecurity protects the availability of instruments and
systems; promotes trust in, and availability of, data; and provides confidence in the integrity of
the research resulting from use of facility information and information resources. At the same
time, inappropriate, inefficient, and ineffective cybersecurity compliance regimes can be costly
in time, human capital, and funding. Cybersecurity programs for a facility must appropriately
balance risk with cost and research innovation. Thus, a cybersecurity program is based on a
structured approach to planning, developing, and maintaining levels of information security and
risk appropriate to a facility’s mission and phase. A cybersecurity program should be scoped to
the key assets, resources, and the full lifespan of the facility. It is necessarily a living program
that adapts, adjusts, and advances. As such, cybersecurity programs require reporting,
evaluation, and updating as appropriate.

Section Revision:
May 30, 2019

6.3.1-1

Major Facilities Guide: NSF 19-68 (May 2019)
6.3.2 Major Facility Cybersecurity Program
Prepared by the Directorate for Computer & Information Science & Engineering (CISE)

Major Facility Cybersecurity Program
Uniform Guidance §200.303 states that the Recipient’s internal controls, including technology
infrastructure and security management, should be compliant with guidance published by the
Comptroller General or Committee of Sponsoring Organizations of the Treadway Commission
(COSO) 1. Further, the Cooperative Agreement Supplemental Financial & Administrative Terms
and Conditions (CA-FATC) for Recipients of major facilities or Federally Funded Research and
Development Centers (FFRDC) 2 requires an information security program 3 and identifies a
modest set of required components for the program. Additionally, an information security plan
is a required element of the construction stage Project Execution Plan (PEP) per Section 3.4 of
this Guide.
The foundation for developing and maintaining a project’s cybersecurity program lies in the
research mission and goals of the facility itself. Related foundational considerations are project
phase, size, complexity, project budget, and the project’s required data management plan
which identifies key information assets. In addition, geographic and institutional distribution
can be an important overall factor. The three pillars of a cybersecurity program which rest on
this foundation are governance; resources; and controls. Like other facility project components,
the cybersecurity program should be appropriately represented in standard project documents
and NSF oversight activities such as the project execution plan, project risk management plan,
project budget, project reports, and project reviews.
The following sections define and describe a suggested framework for the facility cybersecurity
plan. This framework is based on the previously mentioned three pillars of information security
programs: Governance, Resources, and Controls. 4 Major facilities may use these pillars as a
framework for founding, operating, evaluating, and improving their information security
programs, and meeting the award terms and conditions. Since there are interdependencies
among the pillars, an integrative approach is required. The exact content and emphasis of the
information security program should be tailored to the mission, phase, size and scope of an
individual facility.
The three pillars of a cybersecurity program rely on a project-specific inventory of “information
assets” to be protected. Risk-based approaches to protection of information assets are further
determined by a project-tailored “information classification” 5 which recognizes varying degrees

1

Standards for Internal Control in the Federal Government and Internal Control – Integrated Framework,

These documents are updated every 6 to 12 months. Check at https://www.nsf.gov for the most recent version that applies to
major facilities or FFRDCs.
2

3For

the purposes of this section, there is no distinction among the terms “information security,” “cybersecurity,” and “IT
security” as referenced in the award terms and conditions. However, this section specifically addresses digital information.

4

See, NSF Cybersecurity Center of Excellence program guidance, e.g., https://trustedci.org/guide

5

https://www.scribd.com/document/203236714/CISO-Perspectives-Data-Classification

Section Revision:
May 30, 2019

6.3.2-1

Major Facilities Guide: NSF 19-68 (May 2019)
6.3.2 Major Facility Cybersecurity Program
Prepared by the Directorate for Computer & Information Science & Engineering (CISE)

of value, priority, and/or sensitivity of the information assets. The information asset inventory
and information classification are described in the Controls section.

Section Revision:
May 30, 2019

6.3.2-2

Major Facilities Guide: NSF 19-68 (May 2019)
6.3.3 Governance
Prepared by the Directorate for Computer & Information Science & Engineering (CISE)

Governance
Recommended governance elements for cybersecurity programs include: roles and
responsibilities; policies and practices, risk acceptance and management.
6.3.3.1 Roles and Responsibilities
Successful cybersecurity programs require an active role for facility leadership in policy
development and implementation, assigning information asset ownership, and accepting
residual risk.
A second essential role is that of information asset owner. This is a person, position, or entity
given formal responsibility for an information asset (or set of assets) within an organization.
There are typically multiple information asset owners. The asset owner understands the risks to
the asset and ensure adequate controls are in place over the life of the project.
In addition, cybersecurity programs should have an identified senior security role, such as a
Chief Information Security Officers (CISO) or Information Security Officer (ISO) as owner of the
cybersecurity program and lead decisionmaker for operational aspects of the cybersecurity
program. This individual also facilitates the formation of informed cybersecurity policies,
practices and risk management decisions by facility leadership and information asset owners.
6.3.3.2 Policies
Every facility project with information assets will require the development, approval and
implementation of some information security policies within its cybersecurity program. Policies
are driven not only by the facility’s information assets and classifications, but also by relevant
regulations. Regulations may be international, national or local. Regulations may be specific to
an information asset (e.g. HIPAA, FERPA, etc.) or to specific needs of a facility collaborator or
user (e.g. ITAR, FISMA). Examples of common policies include: Acceptable Use Policy; Access
Control Policy; Incident Response Policy. Sample templates may be found at the Trusted CI
website 1. Trusted CI’s guidance recommends developing a “Master Information Security Policy
& Procedures” (MISPP) document as an initial policy-making step. A master policy provides an
overview of the project’s information security program including a summary of roles and
responsibilities, as well as an organized list of specific information security policy documents.
Additional sources of policy templates and forms include the Higher Education Information
Security Council (HEISC) Resources Center,2 and SANS Institute’s Information Security
Templates page. 3 Using example and template policies can streamline the policy production
process, even if substantial customization is warranted. The policies themselves only reduce
1

See, NSF Cybersecurity Center of Excellence program guidance, e.g., https://trustedci.org/guide

2

https://www.educause.edu/focus-areas-and-initiatives/policy-and-security/cybersecurity-initiative/resources

3

https://www.sans.org/security-resources/policies

Section Revision:
May 30, 2019

6.3.3-1

Major Facilities Guide: NSF 19-68 (May 2019)
6.3.3 Governance
Prepared by the Directorate for Computer & Information Science & Engineering (CISE)

risk if attached to other elements of the cybersecurity program (e.g. roles and responsibilities,
controls) and integrated into overall project governance and management.
6.3.3.3 Risk Management and Acceptance
Cybersecurity programs employ a risk-based approach to information security and as such,
there is inherent acknowledgement by NSF that any valuable activity requires acceptance of
residual risk. Residual risk is that risk that remains in the presence of controls. An important
output of a risk-based information security program is a documented set of well-informed risk
management and project leadership acceptance decisions. Due to the rapidly changing
technology landscape, a flexible, informal risk assessment process is often more valuable than a
formal, detailed risk assessment that is out of date long before it is completed. In addition to
the Trusted CI guide which is tailored to the scientific community, the Open Science Risk Profile
Working Group (OSCRP), has developed and released a “best practices” document 1 to assist
NSF, NIH and DOE projects in assessing cybersecurity risks related to Open Science projects.
Finally, the Armed Forces Communications and Electronics Association International (AFCEA)’s I
Cyber Committee has produced a useful and relevant publication: The Economics of
Cybersecurity, A Practical Framework for Cybersecurity Investment 2.
6.3.3.4 Evaluation
Given the dynamic technology and cybersecurity landscape, organizations should plan for
periodic evaluations of the cybersecurity program, including policies, practices, and controls.
While project management and NSF oversight will involve regular reporting and review of
program milestones, outcome metrics, and incidents, the project is encouraged to consider
periodic self-assessments, external or stakeholder reviews, and evaluation of incident response.
Tools are available from variety of sources to aid in assessment.3 4

1

http://trustedci.github.io/OSCRP/

2

https://www.afcea.org/committees/cyber/documents/cybereconfinal.pdf

3

https://library.educause.edu/resources/2015/11/information-security-program-assessment-tool

4

https://cset.inl.gov/SitePages/Home.aspx

Section Revision:
May 30, 2019

6.3.3-2

Major Facilities Guide: NSF 19-68 (May 2019)
6.3.4 Resources
Prepared by the Directorate for Computer & Information Science & Engineering (CISE)

Resources
6.3.4.1 Budget
Overall, worldwide cybersecurity spending is on the rise 12 driven in part by response to
increased cyber crime and new data protection regulations. There is wide variability in the cost
of cybersecurity as a percent of overall IT budgets (3-12%) depending on the mission of the
institution (e.g. Defense and Aerospace industries have more stringent requirements and
proportionally higher costs.)) and size of the institution (Small institutions may not achieve
economies of scale.). A secondary contribution to variability is the considerable discrepancy in
what is within the cybersecurity budget as well as what is in the IT budget. A 2016 NSF
Cybersecurity Summit examination of public data on DOE open science laboratory cybersecurity
spending3 indicated that approximately 0.5% of the overall lab budget and 8-12% of the IT
budget (excluding scientific IT) were spend on cybersecurity.
6.3.4.2 Personnel
In addition to the CISO/ISO, ongoing access to skilled cybersecurity professionals is key to a
successful cybersecurity program. The CISO may manage a team of dedicated information
security professionals or oversee staff/activities in various departments within the facility.
Considering the demand for experienced cybersecurity professionals, 4 5 organizations may
need to consider outsourcing security services. In any scenario, information security resources
outside the facility such as a parent institution/campus, peer organizations, commercial security
consultants, intrusion detection and log monitoring services, and incident response services can
be an important source of security expertise, training, evaluation, and recommendations.
While technical skills are important, teaching skills, communication skills and negotiating skills
are endemic to cybersecurity programs and are, therefore, necessary personnel considerations.

1

https://www.gartner.com/newsroom/id/3836563

2

https://securityintelligence.com/news/cybersecurity-spending-poised-to-rise-in-2018-gartner-reports/

3https://static1.squarespace.com/static/5047a5a6e4b0dcecada15549/t/57b4b32dd2b857a1b6827a7f/1471460142220/Cybers

ecurity+Budgets+NSF+Summit+2016.pdf
4

https://www.monster.com/career-advice/article/future-of-cybersecurity-jobs

5

https://www.csoonline.com/article/3201974/it-careers/cybersecurity-job-market-statistics.html

Section Revision:
May 30, 2019

6.3.4-1

Major Facilities Guide: NSF 19-68 (May 2019)
6.3.5 Controls
Prepared by the Directorate for Computer & Information Science & Engineering (CISE)

Controls
Controls are tailored to the facility’s portfolio of information assets and aligned to protect
confidentiality, integrity, and availability based on the corresponding information classification
for those information assets.
6.3.5.1 Information Asset Inventory
Organizational identification and location of information assets is a prerequisite to competently
securing those assets. See, CIS Critical Security Controls 1 and 2, 1 and NIST 800-53 control CM8. 2 The inventory might include many details, but at a minimum it should identify the asset and
indicate the value or sensitivity of the system and/or classification of the information. The
facility data management plan which is a required document for proposal submission is a key
source for both asset identification and classification.
The asset inventory can be built by manually using publicly or commercially available templates
or worksheets or by constructing a custom database. The Open Science Cyber Risk Profile
(OSCRP) provides guidance on assets to consider for science projects. 3 Trusted CI 4 has
developed substantial guidance 5 for information security programs in NSF projects, including a
template for recording data about information assets. To reduce the manual effort, security
products or scanners6 can aid with asset discovery and inventory.
Information is any communication or representation of knowledge such as facts, data, or
opinions in any medium or form, including textual, numerical, graphic, cartographic, narrative,
or audiovisual.7 Organizational information may be stored and used within the organization’s
information systems, as well as flow out to third party systems.
An information system is a discrete set of information and related resources (such as people,
equipment, and information technology) organized for the collection, processing, maintenance,
use, sharing, dissemination, and/or disposition of information.8

1

https://www.cisecurity.org/controls/

2

http://nvlpubs.nist.gov/nistpubs/SpecialPublications/NIST.SP.800-53r4.pdf

3

https://trustedci.github.io/OSCRP/OSCRP.html

Trusted CI, the NSF Cybersecurity Center of Excellence, is an NSF-funded center dedicated to assisting the NSF community,
including Major Facilities, with information security needs. More information is available at https://trustedci.org

4

5

https://trustedci.org/guide

6

https://www.cisecurity.org/white-papers/cis-controls-sme-guide/

7

See, National Information Assurance (IA) Glossary, CNSS Instruction No. 4009, Apr. 2010.

8

See, 44 U.S.C. 3502

Section Revision:
May 30, 2019

6.3.5-1

Major Facilities Guide: NSF 19-68 (May 2019)
6.3.5 Controls
Prepared by the Directorate for Computer & Information Science & Engineering (CISE)

6.3.5.2 Information Classification
Information has varying degrees of organizational value, sensitivity, and protection
requirements. 1 These qualities are key factors to consider in analyzing the anticipated impact of
security incidents. In addition, some information assets may be subject to additional external
control (e.g. federal or state privacy laws, international regulations, contractual obligations). In
most cases, information can be classified into two to four categories (e.g., public, internal, and
controlled).
6.3.5.3 Control Set
Controls or mitigations are the administrative, technical, and physical safeguards and
countermeasures implemented to support the facility’s mission and ensure the appropriate
protection of information assets. Control selection, implementation and evaluation are ongoing
processes in any information security program.
While efficiency and effectiveness will require customization of controls, there are several
authoritative sources to assist in selecting baseline controls. 2,3,4 Scientific facilities may merit
special security considerations (e.g. diverse research data flows; identity management for
distributed science communities 5; non-facility device connectivity to facility networks and data;
unique Industry Control (ICS) and/or Supervisory Control and Data Acquisition (SCADA)
systems 6; application software development 7, 8, 9).

1

https://www.scribd.com/document/203236714/CISO-Perspectives-Data-Classification

2

https://www.cisecurity.org/controls/ ; for more detail including history, see https://www.sans.org/critical-security-controls

3

https://www.asd.gov.au/publications/protect/essential-eight-explained.htm

4

https://www.nist.gov/cybersecurity-framework

5

https://refeds.org/sirtfi

6

https://ics-cert.us-cert.gov/ See, also, NIST SP 800-82r2. Available at http://csrc.nist.gov/publications/PubsSPs.html

7

https://social.technet.microsoft.com/wiki/contents/articles/7100.the-security-development-lifecycle.aspx

8

https://www.owasp.org/index.php/Category:OWASP_Top_Ten_Project

9

https://software-security.sans.org/resources/swat

Section Revision:
May 30, 2019

6.3.5-2

Major Facilities Guide: NSF 19-68 (May 2019)
6.4 Guidelines for Planning and Executing External Reviews of NSF's Major Facilities
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

6.4

GUIDELINES FOR PLANNING AND EXECUTING EXTERNAL REVIEWS OF NSF'S MAJOR
FACILITIES

This document, which is in preparation, will describe the process for evaluation and review of
all NSF major facility projects proposed for construction, under construction or currently in
operation. It will provide assistance to the Program Officer (PO) in preparing and planning a
review of the non-research related aspect of the project’s management, budgets, schedule and
related activities. The information contained will offer guidance for three situations: reviews of
facilities in planning; reviews of construction activity; and operational reviews of ongoing
facilities. A description of the overall process of planning and carrying out an external review of
a major facility project will be provided as an aid to the PO or associated staff who may be
unfamiliar with these processes or need a reference source on good practices.
The evaluation and reviews covered in the document include assessment of management,
schedules and budgets, as well as other matters relevant to a major facility project, such as
changes to technical aspects or scope. It does not address the intellectual merit or the broader
impact criteria used to select the project for support, but rather focuses on evaluation of the
Recipient’s planning and implementation activities.
The reports and recommendations from these external reviews are made directly to NSF. NSF
evaluates the review panel input, determines the appropriate response, and issues written
guidance to award Recipients for any subsequent response and action.

Section Revision:
November 25, 2016

6.4-1

Major Facilities Guide: NSF 19-68 (May 2019)
6.5 Environmental Considerations in Major Facility Planning
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

6.5

ENVIRONMENTAL CONSIDERATIONS IN MAJOR FACILITY PLANNING

NSF’s funding for the construction or modification of facilities constitutes a Federal Action that
triggers compliance with several statutes designed to protect the Nation’s environmental,
cultural and historic resources. Awareness of, and strict adherence to, all relevant
environmental regulations are extremely important considerations in the planning,
construction and operation of facilities.
These statutes include, but are not limited to, the National Environmental Policy Act (NEPA),
the National Historic Preservation Act (NHPA) and the Endangered Species Act. While NEPA and
its implementing regulations focus on activities that take place within the United States,
proposed activities that take place outside of United States may also be subject to NEPA.
Furthermore, there are international agreements and treaties that deal with environmental
impacts. For further information, see the Proposal and Award Policies Procedures Guide
Chapter II.C.2.j and consult with the PO.
NSF regulations governing compliance with the National Environmental Policy Act (NEPA) are
found at 45 CFR §640. NSF regulations supplement the Council on Environmental Quality’s
(CEQ) regulations, published at 40 CFR §§1500-1508. Program Officers, as required by NSF
regulations, are responsible for evaluating the environmental impacts that may result from the
implementation of a Foundation award and determining into which category incoming
proposals fall (i.e., CATEX, EA, or EIS). Compliance with NEPA also includes providing
opportunities for public input on issues such as potential environmental impacts and ways to
avoid, minimize, and/or mitigate adverse impacts. Determining the required level of
compliance activities – including what documentation, consultation and/or permits may be
required – is a complex task. The Program Officer (PO) should not attempt to determine the
extent of compliance requirements without consulting the Environmental Compliance Team
within NSF's Office of the General Counsel. NEPA compliance may require the preparation of an
Environmental Assessment (EA) in cases where no significant environmental impacts are
expected or the more extensive documentation of an Environmental Impact Statement (EIS)
where adverse effects are anticipated. Failure to take necessary steps can cause undue delays
in a project’s schedule, significant cost escalation and potential federal litigation.
Additionally, in conjunction with or independent of its NEPA compliance, NSF may be required
to initiate consultations with Native Americans and other interested parties pursuant to the
NHPA and/or initiate informal or formal consultation with the U.S. Fish and Wildlife Service
under the Endangered Species Act. These compliance requirements can introduce significant
schedule and cost risk into the project which should be considered and addressed.
Furthermore, there is no special source of funding within NSF to pay for the environmental
compliance process; the cost is normally borne by the program using Research and Related
Activities (R&RA) funds.

Section Revision:
November 25, 2016

6.5-1

Major Facilities Guide: NSF 19-68 (May 2019)
6.5 Environmental Considerations in Major Facility Planning
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Given the above considerations, the following guidance is offered:
1. It is imperative that the PO contact the Environmental Compliance Team within NSF's
Office of the General Counsel early in the conceptual design stage to seek guidance on
specific requirements for compliance. The time required to complete environmental
compliance can take a year or more depending upon the level of impacts associated
with a proposed project.
2. It is extremely important that the PO and the project get cost estimates for the
compliance process and factor these into the project’s scope, schedule and budget early
in the design process.
The cost drivers associated with these activities (their impact on the project construction cost)
need to be well understood by PDR since the PDR budget and risk assessment provide the basis
for the construction funding request.

Section Revision:
November 25, 2016

6.5-2

Major Facilities Guide: NSF 19-68 (May 2019)
6.6 Guidelines for Property Management
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

6.6

GUIDELINES FOR PROPERTY MANAGEMENT

NSF retains ownership to major research equipment and facilities it funds only if specified in the
terms and conditions of the award, otherwise title resides with the Recipient. At the end of the
award, NSF may choose to invoke its contingent interest in NSF-funded property and
equipment to take title or transfer to another organization. This stewardship responsibility is
necessary to protect the U.S. Government’s and the public’s investment in these unique
research facilities.
The requirements for management of property procured using NSF funds are detailed in key
NSF documents: Cooperative Agreement and Cooperative Support Agreement specific to the
award; Chapter IX Grantee Standards, Section D; Property Management Standards of the NSF
Proposal and Award Policies and Procedures Guide (PAPPG); the NSF Cooperative Agreement
FATC, Article 6, Equipment; Article 61, 62, 63, 64, 65 of the Cooperative Agreement
Modifications and Supplemental Financial & Administrative Terms and Conditions for Major
Multi-User Research Facility Projects and Federally Funded Research and Development Centers;
or other supplements. In addition, 2 CFR § 200.310-316 prescribes standards for managing and
disposing of property furnished by the Federal government or whose cost was charged to a
project supported by a Federal award. It is incumbent on the Recipient to understand these
policies and maintain a property management system.
Each NSF major research facility is unique in its mission and its circumstances and thus the
approach to property management will likely be unique but must comply with federal
regulations and NSF policy. The policies and procedures governing the management of
Federally funded property and equipment should cover the following general topic areas:
•

The process for acquisition and procurement;

•

The process for retention of financial records (physical and electronic) necessary for
property audits or closeout;

•

The process for inventory management including custody, location, use, and disposition
(note that awardees should seek instruction from NSF in most disposition cases);

•

The process for marking or identification of equipment, as appropriate;

•

The process to establish and perform routine and preventative maintenance, and

•

The process to secure property while in operation, storage, or transit.

Section Revision:
May 30, 2019

6.6-1

Major Facilities Guide: NSF 19-68 (May 2019)
6.7 Guidelines for Financial Management
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

6.7

GUIDELINES FOR FINANCIAL MANAGEMENT

[Reserved for future content]

Section Revision:
May 2, 2016

6.7-1

Major Facilities Guide: NSF 19-68 (May 2019)
6.8.1 EVMS Requirements
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

6.8

GUIDELINES FOR EARNED VALUE MANAGEMENT SYSTEMS

Earned Value Management (EVM) is a recognized project management methodology that
provides insight into a project’s technical, cost, and schedule progress. NSF recognizes that a
properly implemented Earned Value Management System (EVMS) can provide accurate and
reliable performance measurement metrics, forecast cost and schedule information, and
uncover potential problems to support sound and timely management decisions. A properly
implemented EVMS is also essential to inform NSF’s oversight of the project.
EVMS Requirements
NSF requires major facility project Recipients to use EVMS as the management tool for project
planning and execution. The project should adhere to the seven basic principles outlined in the
EIA-748 Standard for EVMS:
•

Plan all the project’s work scope to completion using discrete work packages and
planning packages.

•

Break down the project work scope into finite pieces that are assigned to a responsible
person or organization for control of technical, schedule and cost objectives.

•

Integrate project work scope, schedule, and cost objectives into a performance
measurement baseline plan against which accomplishments are measured. Control
changes to the baseline.

•

Use actual costs incurred and recorded in accomplishing the work performed.

•

Objectively assess accomplishments at the work performance level.

•

Analyze significant variances from the plan, forecast impacts, develop corrective actions,
and prepare an estimate at completion based on performance to date and the
remaining work to be performed.

•

Use the EVMS information in the project’s management processes.

The 32 guidelines of EIA-748 Standard should be used in establishing the project’s EVMS
process. These guidelines are high-level and goal-oriented. They state the qualities and
operational considerations of an integrated management system using EVM methods without
mandating detailed system characteristics. They give a project sufficient flexibility within the 32
guidelines to develop an integrated management process that is tailored to the project’s
specific needs. Therefore, the project’s management team should implement an EVMS in a
manner that employs the most effective and efficient performance management methods and
techniques. The project’s EVMS process should be documented in the Project Execution Plan
(PEP-10.2). The document address how the 32 guidelines of the EIA-748 are implemented and
describe how the processes are integrated into an effective approach for project management.

Section Revision:
May 30, 2019

6.8-1

Major Facilities Guide: NSF 19-68 (May 2019)
6.8.2 Scaled Application of EVMS Guidelines
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Scaled Application of EVMS Guidelines
To realize the full benefit of EVM for effective project management, the 32 EVMS guidelines
should be applied in a way that suits the size, complexity, risk, and type of work. For large
science projects, the unique challenges of being on the fore-front of enabling scientific research
and the need of scientific collaborations should be taken into account. EVM data should not be
viewed simply as static metrics or as a compliance report. Instead, the project’s EVMS should
be implemented in a manner that can provide the Recipient management team with a reliable
basis for objectively assessing performance against plan, identifying potential issues,
forecasting future trends, and initiating corrective actions.
When implementing the EVMS guidelines, the Recipient management team should evaluate the
project’s inherent complexity, external dependencies, unique challenges and constraints, and
scale the EVMS accordingly. The Earned Value Management System Guideline Scalability Guide
published by NDIA Integrated Program Management Division (IPMD) provides a reference in
scaled application of EVMS. A properly implemented EVMS should be no more complex than is
necessary to inform sound project management decisions while reflecting the business
practices and other related documents (such as the WBS) as outlined in the PEP.

Section Revision:
May 30, 2019

6.8-2

Major Facilities Guide: NSF 19-68 (May 2019)
6.8.3 Guidelines for Establishing an EVMS
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Guidelines for Establishing an EVMS
Earned Value Management (EVM) is an integrated management methodology and an Earned
Value Management System (EVMS) is an integrated set of processes, people and tools for
managing projects using earned value management. The primary purpose for establishing an
EVMS is to support successful management of the project by the Recipient. As stated above,
each project should consider the nature of the project’s work, unique challenges and
constraints in establishing the process to ensure the process supports the project’s
management needs. There is no single correct process for establishing an EVMS. Below is an
outline of what is typically involved:
•
•
•
•
•
•

Obtaining institutional support for the project’s implementation of EVMS
Selecting and implementing the project management tools for EVMS
Assessing the project’s needs and existing processes to establish the project’s EVMS
process following EIA-748 EVMS guidelines
Documenting the EVMS processes and procedures in the PEP
Training the project management team to facilitate implementation of the project’s
EVMS and instill a culture that accepts the use of EVM as a credible management tool
Developing structured surveillance and training programs

•
•

Conducting an NSF EVMS verification review
Receiving NSF’s acceptance that the EVMS meets the intent of 32 guidelines (see
Section 4.6.3.6)

•

Conducting NSF surveillance reviews throughout the Construction Stage

Section Revision:
December 14, 2018

6.8-3

Major Facilities Guide: NSF 19-68 (May 2019)
7 References
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

7

REFERENCES

NSF Reference Documents
NSF Business Systems Review (BSR) Guide
https://www.nsf.gov/publications/pub_summ.jsp?ods_key=nsf13100
NSF Proposal and Award Policies and Procedures Guide (PAPPG)
https://www.nsf.gov/pubs/policydocs/pappg18_1/index.jsp
Suite of NSF Terms and Conditions: The NSF website on How to Manage Your Award
http://www.nsf.gov/awards/managing/
Joint National Science Board —National Science Foundation Management Report: Setting
Priorities for Large Facility Projects Supported by the National Science Foundation (NSB05-77); September 2005
Setting Priorities for Large Research Facility Projects Supported by the National Science
Foundation, a 2004 National Academies report
US Government Acts and Laws References
42 U.S. Code 1873(b), which states “The Foundation shall not, itself, operate any laboratories or
pilot plants.”
Endangered Species Act
Government Performance and Results Modernization Act (GPRAMA) of 2010 (Public Law 111352)
National Environmental Policy Act (NEPA)
National Historic Preservation Act (NHPA)
NSF’s Authorization Act of 2002, 42 U.S.C.1862n-4(c), signed into law on December 19, 2002,
Public Law 107-368, Section 14(c)
“Uniform Guidance”, 2 CFR § 200, Uniform Administrative Requirements, Cost Principles, and
Audit Requirements for Federal Awards, Office of Management and Budget (OMB),
December 2014
General Facility & Project Management Guides
“Best Practices for Federal Research and Development Facility Partnerships,” IDA Science &
Technology Policy Institute, IDA Paper P-5148 Log: H 14-000676
Guide to the Project Management Body of Knowledge, (PMBOK® Guide), Project Management
Institute, 5th Edition, 2013
National Defense Industrial Association (NDIA) Integrated Program Management Division
(IPMD) Earned Value Management Systems EIA-748-C Intent Guide, April 29, 2014*

Section Revision:
December 14, 2018

7-1

Major Facilities Guide: NSF 19-68 (May 2019)
7 References
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

National Defense Industrial Association (NDIA) Integrated Program Management Division
(IPMD) Earned Value Management System Acceptance Guide, March 24, 2013, Revision
1*
National Defense Industrial Association (NDIA) Integrated Program Management Division
(IPMD) Surveillance Guide, Revision 2, July 15, 2015
Cost and Schedule Estimating and Risk Analysis References
Aven, Foundations of Risk Analysis
Butts, Glenn and Kent Linton, “NASA the Joint Confidence Level Paradox – a History of Denial,”
NASA Cost Symposium, April 28, 2009
“Estimating Cost Uncertainty when only Baseline Cost is Available,” quoting R.L. Abramson and
S. A. Book, “A Quantification Structure for Assessing Risk-Impact Drivers,” Laserlight
Networks, briefing presented to the 24th Annual DOD Cost Symposium (Leesburg, VA,
September 5-7, 1990)
Federal Acquisition Regulations (FAR Part 35.017-4, Reviewing FFRDCs)
Flyvbjerg, Bent, Nils Bruzelius, and Werner Rothengatter, Megaprojects and Risk: An Anatomy
of Ambition, 2003 Cambridge University Press
Government Accountability Office (GAO) Cost Estimating and Assessment Guide, (GAO-09-3SP
2009)
Government Accountability Office (GAO) Schedule Assessment Guide (GAO-16-89G 2015)
Hillson, David, Effective Opportunity Management for Projects: Exploiting Positive Risk, Marcel
Dekker, 2004
Hillson, David and Ruth Murray-Webster, Understanding and Managing Risk Attitude, Gower,
2005
Hillson, David Private research conducted in 2004 and presented at a PMI EMEA conference
Hulett, David T., “Project Schedule Risk Analysis: Monte Carlo Simulation or PERT?” PM
Network published by the Project Management Institute, February 2000, pp. 43 ff
Hulett, David T., “Use Decision Trees to Make Important Project Decisions", Cost Engineering
(published by AACEI, July / August 2014)
Hulett, David T., Integrated Cost-Schedule Risk Analysis, Cost Engineering (AACE International),
November/December 2012, pp. 5-15, with Michael Nosbisch
Hulett, David T., principal author, Recommended Practice 57R-09, Integrated Cost and Schedule
Risk Analysis using Monte Carlo Simulation of a CPM Model, AACEI, 2011
Hulett, David T., principal author, Recommended Practice 85R-14, "Use of Decision Trees in
Decision Making", AACEI, 2014

Section Revision:
December 14, 2018

7-2

Major Facilities Guide: NSF 19-68 (May 2019)
7 References
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Hulett, David T., “Use Decision Trees to Make Important Project Decisions,” Cost Engineering
(published by AACEI, July / August 2014
Hulett, David T., Integrated Cost-Schedule Risk Analysis, Gower Publishers, 2011
Hulett, David T., Practical Schedule Risk Analysis, Gower Publishers, 2009
Merrow, Edward W., Industrial Megaprojects, 2011, Wiley
NASA's Challenges to Meeting cost, Schedule, and Performance Goals, NASA IG-12-21
Pariseau and Oswalt, Using Data Types and Scales for Analysis and Decision Making
Planning, Budgeting, Acquisition, and Management of Capital Assets, OMB Circular No. A–11
(2014).
“Understanding the Joint Confidence Level (JCL) at NASA,” NASA Office of Evaluation at 9/4/14.

Section Revision:
December 14, 2018

7-3

Major Facilities Guide: NSF 19-68 (May 2019)
8 List of Acronyms
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

8

LIST OF ACRONYMS

AC
AD
ADR
AICA
AMBAP
AWP
BAC
BFA
BLS
BOE
BSR
CA
CAP
CATEX
CCB
CCP
CDR
CEP
CER
CFR
CISO
CO
CORF
CPI
CPM
CSB
CV
DACS
DD
DGA
DIAS
DRB
EA
EAC
EHR
EIS
ES&H
ETC
EV
EVM
EVMS
Section Revision:
May 30, 2019

Actual Cost
Assistant Director
Accountable Directorate Representative
American Innovation and Competitiveness Act
Award Monitoring and Business Assistance Program
Annual Work Plan
Budget at Completion
Office of Budget, Finance, and Award Management
Bureau of Labor Statistics
Basis of Estimate
Business Systems Review
Cooperative Agreement
Cost Analysis and Pre-Award
Categorical Exclusion (NEPA)
Change Control Board
Change/Configuration Control Process
Conceptual Design Review
Cost Estimating Plan
Compliance Evaluation Review
Code of Federal Regulations
Chief Information Security Officer
Contracting Officer
Chief Officer for Research Facilities
Cost Performance Index
Critical Path Method
Cooperative Support Branch
Cost Variance
Division of Acquisition and Cooperative Support
Division Director
Division of Grants and Agreements
Division of Institution and Award Support
Director’s Review Board
Environmental Assessment
Estimate at Completion
Education and Human Resources
Environmental Impact Statement
Environmental Safety and Health
Estimate to Complete (for Cost)
Earned Value
Earned Value Management
Earned Value Management System
8-1

Major Facilities Guide: NSF 19-68 (May 2019)
8 List of Acronyms
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

FAR
FDR
FFRDC
FGB
FRP
FY
GAO
G/AO
GPRA
GR&As
HLFO
ICE
IMP
IMS
IPT
ISO
IT
LFO
MFG
MFWG
MOU
MP
MREFC
NCE
NEPA
NHPA
NICRA
NRC
NSB
NSF
O&M
OD
OGC
OMB
PAM
PAPPG
PDR
PEP
PI
PMB
PMBOK
PMCS
PMI
Section Revision:
May 30, 2019

Federal Acquisition Regulations
Final Design Review
Federally Funded Research and Development Center
Facilities Governance Board
Facilities Readiness Panel
Fiscal Year
Government Accountability Office
Grants and Agreements Officer
Government Performance and Results Act
Ground Rules and Assumptions
Head, Large Facilities Office
Independent Cost Estimate
Internal Management Plan
Integrated Master Schedule
Integrated Project Team
Information Security Officer
Information Technology
Large Facilities Office
Major Facilities Guide
Major Facilities Working Group
Memorandum of Understanding
Management Plan (for mid-scale projects)
Major Research Equipment and Facilities Construction
No-Cost Extension
National Environmental Policy Act
National Historic Preservation Act
Negotiated Indirect Cost Rate Agreement
National Research Council
National Science Board
National Science Foundation
Operations and Maintenance
Office of the Director
Office of the General Counsel
Office of Management and Budget
Proposal and Award Manual
Proposal and Award Policies and Procedures Guide
Preliminary Design Review
Project Execution Plan
Principal Investigator
Performance Measurement Baseline
Project Management Body of Knowledge
Project Management Control System
Project Management Institute
8-2

Major Facilities Guide: NSF 19-68 (May 2019)
8 List of Acronyms
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

PO
PTO
PV
R&D
R&RA
RBS
RI
RM
RMP
S&E
SOG
SME
SPC
SPI
SV
TPC
WBS

Section Revision:
May 30, 2019

Program Officer
Paid Time Off
Planned Value
Research and Development
Research and Related Activities
Risk Breakdown Structure
Research Infrastructure
Risk Manager
Risk Management Plan
Science and Engineering
Standard Operating Guidance
Subject Matter Expert
Statistical Process Control
Schedule Performance Index
Schedule Variance
Total Project Cost
Work Breakdown Structure

8-3

Major Facilities Guide: NSF 19-68 (May 2019)
9.1 Lexicon Preface
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

9
9.1

LEXICON
LEXICON PREFACE

This Lexicon contains definitions of project and program management terms used in this Guide,
as applied to NSF major facilities. It is a combination of specialized terms defined by NSF and
used in the management of its major facilities, and terms and definitions commonly used in
professional project and program management. A subset of common project management
terms compatible with NSF usage were selected from a standard source, the PMI Lexicon, 1 for
inclusion in this lexicon.
The Lexicon provides a common set of standard terms and definitions that should facilitate
communication and understanding between stakeholders when used in documents and
correspondence related to major facility management.
The terms and definitions included in this lexicon are in development and are subject to
modifications in future versions.

Entries in italics in this lexicon have been reproduced with permission from Project Management Institute, Inc., [PMI Lexicon],
(2012) Copyright and all rights reserved.

1

Section Revision:
December 14, 2018

9-1

Major Facilities Guide: NSF 19-68 (May 2019)
9.2 Terms and Definitions
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

9.2

TERMS AND DEFINITIONS

Acceptance Criteria. A set of conditions that is required to be met before deliverables are
accepted.
Activity. A distinct, scheduled portion of work performed during the course of a project.
Actual Cost. The realized cost incurred for the work performed on an activity during a specific
time period.
Allowance. Resources included in the basis of estimate for baseline cost estimates to cover the
cost of known but as-of-yet undefined details or requirements for an individual WBS element.
May be used when the level of project definition may not enable certain costs to be estimated
definitively or times when it is simply not cost effective to quantify and cost every small item
included with the WBS element, but reliable correlations are available.
Analogous Estimating. A technique for estimating the duration or cost of an activity or a
project, using historical data from a similar activity or project.
Apportioned Effort. An activity where effort is allotted proportionately across certain discrete
efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned
value management [EVM] types of activities used to measure work performance.)
Approval. The act of officially accepting an idea, action, or plan.
Assistance. The act of giving support or help; making it easier for someone to do something or
for something to happen.
Assumption. A factor in the planning process that is considered to be true, real, or certain,
without proof or demonstration.
Assurance. To give a strong and/or definite statement that something will happen or that
something is true; to give confidence to.
Award Instrument. An agreement between NSF and a Recipient with the terms and conditions
set forth in (cooperative agreements, contracts, etc.).
Backward Pass. A critical path method technique for calculating the late start and late finish
dates by working backward through the schedule model from the project end date.
Baseline. The cost and schedule plan for a scope of work, used during planning. For NSF,
contingency is not included in the baseline but is held and managed separately. A planning
baseline may or may not be under change control. Once a baseline has been approved, is under
change control, and is used as the basis for Earned Value Measurement comparison, it is
referred to as the Performance Measurement Baseline.

Entries in italics are from Project Management Institute, Inc., [PMI Lexicon], (2012) Copyright and all rights reserved. Material
from this publication has been reproduced with the permission of PMI. Italicized entries with leading asterisks have been
modified slightly from the original PMI version for NSF purposes.
Section Revision:
May 30, 2019

9-2

Major Facilities Guide: NSF 19-68 (May 2019)
9.2 Terms and Definitions
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Baseline Definition. The description of the approved scope of work and resources for a
construction project, including a hierarchical, product-oriented Work Breakdown Structure
(WBS) and associated WBS dictionary; the cost and schedule Performance Measurement
Baselines (PMB). Any contingency amounts, cost and time, are added to the baseline to
establish the Recipient managed TPC.
Basis of Estimate. Supporting documentation outlining the details used in establishing project
estimates such as assumptions, constraints, level of detail, ranges, and confidence levels.
Bottom-up Estimating. A method of estimating project duration or cost by aggregating the
estimates of the lower-level components of the work breakdown structure (WBS).
*Budget at Completion. The sum of all budgets established for the work to be performed. (For
NSF projects, contingency amounts are not included in the ETC, EAC, BAC, or PMB due to the
NSF requirement that contingency is held and managed separately from the baseline.)
Change Control. A process whereby modifications to documents, deliverables, or baselines
associated with the project are identified, documented, approved, or rejected.
Change Control Board. A formally chartered group responsible for reviewing, evaluating,
approving, delaying, or rejecting changes to the project, and for recording and communicating
such decisions.
Change Control System. A set of procedures that describes how modifications to the project
deliverables and documentation are managed and controlled.
Change Request. A formal proposal to modify any document, deliverable, or baseline.
Closeout. The process by which the Federal awarding agency or pass-through entity determines
that all applicable administrative actions and all required work of the Federal award have been
completed.
Code of Accounts. A numbering system used to uniquely identify each component of the work
breakdown structure.
Conceptual Design Phase. The first phase of the Design Stage, after passing the gate from the
Development Stage, that advances the definition of the scope and requirements, determines
feasibility, and produces updated drafts of most elements of the Project Execution Plan,
including parametric cost and schedule range estimates and a preliminary risk analysis.

Entries in italics are from Project Management Institute, Inc., [PMI Lexicon], (2012) Copyright and all rights reserved. Material
from this publication has been reproduced with the permission of PMI. Italicized entries with leading asterisks have been
modified slightly from the original PMI version for NSF purposes.
Section Revision:
May 30, 2019

9-3

Major Facilities Guide: NSF 19-68 (May 2019)
9.2 Terms and Definitions
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Contingency. A planned amount of budget and time added to the baseline estimate to allow for
items, conditions, or events for which the state, occurrence, or effect is uncertain and that
experience shows will likely result, in aggregate, in additional costs. These events are often
referred to as “known-unknowns” and are considered manageable by the Recipient. Budget
and schedule contingency are typically estimated using statistical analysis and professional
judgment based on experience. Budget contingency is called out separately as part of the Total
Project Cost estimate and obligated to the project for the Recipient to manage based on need
per NSF policy.
Contingency Report Table. A table containing a list of change control actions and allocations,
with ties to associated WBS elements and identified risk events, for all Performance
Measurement Baseline (PMB) changes that impact the use of contingency.
Constraint. A limiting factor that affects the execution of a project, program, portfolio, or
process.
Construction Stage. The period of time in which funds are obligated for acquisition and/or
construction of a facility that fulfills the terms and conditions set forth in an award instrument
between NSF and the Recipient(s). This stage ends with the start of the Operations Stage.
Contract. A contract is for the purpose of obtaining goods and services for the non-Federal
entity’s own use and creates a procurement relationship with the contractor. All contracts over
$250,000 require written prior NSF authorization.
Control Account. A management control point where scope, budget, actual cost, and schedule
are integrated and compared to earned value for performance measurement.
Corrective Action. An intentional activity that realigns the performance of the project work
with the project management plan.
Cost Book. A compilation of Cost Book Sheets, typically used to present baseline or total project
cost, but may be used to present rolled-up costs for smaller elements or sub-elements.
Cost Book Sheet. A compilation of related information from the Cost Model Data Set, used to
define and present the cost estimate for a particular element or sub-element of a deliverablebased work breakdown structure for construction or a functional, activity, and/or deliverable
based work breakdown structure for operations.
Cost Estimating Plan. A plan to establish and communicate how the preparation, development,
review and approval of the estimate will be completed.
Cost Model Data Set. The cost data used as input to software tools and/or project reports to
organize, correlate, and calculate different project management information.
Cost Performance Index. A measure of the cost efficiency of budgeted resources expressed as
the ratio of earned value to actual cost.
Entries in italics are from Project Management Institute, Inc., [PMI Lexicon], (2012) Copyright and all rights reserved. Material
from this publication has been reproduced with the permission of PMI. Italicized entries with leading asterisks have been
modified slightly from the original PMI version for NSF purposes.
Section Revision:
May 30, 2019

9-4

Major Facilities Guide: NSF 19-68 (May 2019)
9.2 Terms and Definitions
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Cost Variance. The amount of budget deficit or surplus at a given point in time, expressed as the
difference between the earned value and the actual cost.
Crashing. A technique used to shorten the schedule duration for the least incremental cost by
adding resources.
Critical Chain Method. A schedule method that allows the project team to place buffers on any
project schedule path to account for limited resources and project uncertainties.
Critical Path. The sequence of activities that represents the longest path through a project,
which determines the shortest possible duration.
Critical Path Activity. Any activity on the critical path in a project schedule.
Critical Path Method. A method used to estimate the minimum project duration and determine
the amount of scheduling flexibility on the logical network paths within the schedule model.
Current Plan. The project cost and schedule plan reflecting the status of progress to date and
updated estimates for completing remaining work that is compared to the approved
Performance Measurement Baseline (PMB), as part of Earned Value Management.
Data Date. A point in time when the status of the project is recorded.
Decision Tree Analysis. A diagramming and calculation technique for evaluating the
implications of a chain of multiple options in the presence of uncertainty.
Decomposition. A technique used for dividing and subdividing the project scope and project
deliverables into smaller, more manageable parts.
Defect Repair. An intentional activity to modify a nonconforming product or product
component.
Deliverable. Any unique and verifiable product, result, or capability to perform a service that is
required to be produced to complete a process, phase, or project.
De-Scoping Options (Plan). See Scope Management Plan.
Design Stage. The life cycle stage for detailed planning for projects approved by the NSF
Director at the end of the Development Stage and funded under the formal major facility
planning process. It is divided into the Conceptual, Preliminary, and Final Design Phases; with a
formal and rigorous review gate at the end of each phase to show readiness for advancement
to a higher level of refinement with regard to scope, cost, and schedule.
Development Stage. The Facility Life Cycle stage in which initial high-level ideas are developed
and a consensus built for the potential long-term need, priorities, and general requirements for
a large research facility of interest to NSF and the broader research community.

Entries in italics are from Project Management Institute, Inc., [PMI Lexicon], (2012) Copyright and all rights reserved. Material
from this publication has been reproduced with the permission of PMI. Italicized entries with leading asterisks have been
modified slightly from the original PMI version for NSF purposes.
Section Revision:
May 30, 2019

9-5

Major Facilities Guide: NSF 19-68 (May 2019)
9.2 Terms and Definitions
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Discrete Effort. An activity that can be planned and measured and that yields a specific output.
(Note. Discrete effort is one of three earned value management [EVM] types of activities used to
measure work performance.)
Divestment Stage. The stage in the facility life cycle encompasses divestment of the facility
starting after of the NSF Operations Stage ends and funding for divestment begins. Divestment
options may include partial or complete transfer of a facility to another entity’s operational and
financial control (with or without reduction in project scope), “moth-balling” the facility so that
operations can be restarted at a later date, or decommissioning. Decommissioning may include
complete removal of the infrastructure and site restoration.
Early Finish Date. In the critical path method, the earliest possible point in time when the
uncompleted portions of a schedule activity can finish based on the schedule network logic, the
data date, and any schedule constraints.
Early Start Date. In the critical path method, the earliest possible point in time when the
uncompleted portions of a schedule activity can start based on the schedule network logic, the
data date, and any schedule constraints.
Earned Value. The measure of work performed expressed in terms of the budget authorized for
that work.
Earned Value Management. A methodology that combines scope, schedule, and resource
measurements to assess project performance and progress.
Effort. The number of labor units required to complete a schedule activity or work breakdown
structure component, often expressed in hours, days, or weeks.
eJacket. An electronic Web portal for NSF staff to perform essential business functions related
to proposal and award processing and to access associated documents.
Enterprise Environmental Factors. Conditions, not under the immediate control of the team,
that influence, constrain, or direct the project, program, or portfolio.
*Estimate at Completion. The expected total cost of completing all work expressed as the sum
of the actual cost to date and the estimate to complete. (For NSF projects, contingency amounts
are not included in the ETC, EAC, BAC, or PMB due to the NSF requirement that contingency is
held and managed separately from the baseline.)
*Estimate to Complete. The expected cost to finish all the remaining project work. (For NSF
projects, contingency amounts are not included in the ETC, EAC, BAC, or PMB due to the NSF
requirement that contingency is held and managed separately from the baseline.)

Entries in italics are from Project Management Institute, Inc., [PMI Lexicon], (2012) Copyright and all rights reserved. Material
from this publication has been reproduced with the permission of PMI. Italicized entries with leading asterisks have been
modified slightly from the original PMI version for NSF purposes.
Section Revision:
May 30, 2019

9-6

Major Facilities Guide: NSF 19-68 (May 2019)
9.2 Terms and Definitions
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Facility. Shared-use infrastructure, equipment, or instrument - or an integrated network and/or
collection of the same – that is either acquired or constructed to collect, analyze, and provide
necessary data and information in support of research having a major impact on a broad
segment of a scientific or engineering discipline.
Facility Life Cycle. The sequence of steps or stages that characterize the lifetime of a facility
from beginning to end. For NSF, the stages are Development, Design, Construction, Operations,
and Divestment.
FastLane. NSF online website through which we conduct our relationship to researchers and
potential researchers, reviewers, and research administrators and their organizations. Other
web portals used by Recipients to submit proposal and reporting actions include Grants.gov and
Research.gov.
Fast Tracking. A schedule compression technique in which activities or phases normally done in
sequence are performed in parallel for at least a portion of their duration.
Final Design Phase. The third and last phase of the Design Stage, after a successful Preliminary
Design Phase, that further refines the project Baseline Definition and the Project Execution Plan
and demonstrates that project planning and management meet requirements for readiness to
receive funding. The Final Design phase ends in a potential NSF approval to obligate
construction funds.
Finish-to-Finish. A logical relationship in which a successor activity cannot finish until a
predecessor activity has finished.
Finish-to-Start. A logical relationship in which a successor activity cannot start until a
predecessor activity has finished.
Forward Pass. A critical path method technique for calculating the early start and early finish
dates by working forward through the schedule model from the project start date or a given
point in time.
Free Float. The amount of time that a schedule activity can be delayed without delaying the
early start date of any successor or violating a schedule constraint.
Gantt Chart. A bar chart of schedule information where activities are listed on the vertical axis,
dates are shown on the horizontal axis, and activity durations are shown as horizontal bars
placed according to start and finish dates.
Independent Cost Estimate Review. As defined by Government Accountability Office (GAO),
there are eight different types of reviews that may be used by NSF to help validate the
Recipient’s estimate. An Independent Cost Estimate (ICE) is one of the eight types.
Internal Management Plan. The internal document that defines NSF strategy for conducting
project oversight and assurance, managing NSF risk, and providing project funding.
Entries in italics are from Project Management Institute, Inc., [PMI Lexicon], (2012) Copyright and all rights reserved. Material
from this publication has been reproduced with the permission of PMI. Italicized entries with leading asterisks have been
modified slightly from the original PMI version for NSF purposes.
Section Revision:
May 30, 2019

9-7

Major Facilities Guide: NSF 19-68 (May 2019)
9.2 Terms and Definitions
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Lag. The amount of time whereby a successor activity is required to be delayed with respect to a
predecessor activity.
Late Finish Date. In the critical path method, the latest possible point in time when the
uncompleted portions of a schedule activity can finish based on the schedule network logic, the
project completion date, and any schedule constraints.
Late Start Date. In the critical path method, the latest possible point in time when the
uncompleted portions of a schedule activity can start based on the schedule network logic, the
project completion date, and any schedule constraints.
Lead. The amount of time whereby a successor activity can be advanced with respect to a
predecessor activity.
Lessons Learned. The knowledge gained during a project which shows how project events were
addressed or should be addressed in the future for the purpose of improving future
performance.
Level of Effort. An activity that does not produce definitive end products and is measured by the
passage of time. (Note. Level of effort is one of three earned value management [EVM] types of
activities used to measure work performance.)
Liens List. A list of expected adjustments to project scope, budget, and schedule contingency
amounts that are waiting for implementation, including formal change control actions for
planned baseline modifications, scope contingency options held for decision, and coverage of
variances.
Logical Relationship. A dependency between two activities or between an activity and a
milestone.
Major Facility. A facility for which the construction cost is more than a specified percentage of
the sponsoring NSF organization’s budget plan, or paid for out of MREFC funds. Construction
costs for major facilities typically range between $70M and $800M.
Management. The act of controlling and making decisions about an operation, organization or
project; the act or process of deciding how to use something; the judicious use of means to
accomplish an end.
Management Reserve. An amount of money or time included as part of the Total Project Cost
estimate to address unforeseen events or uncertainties that are beyond the control of the
Recipient or the agency. These events are often referred to as “unknown unknowns”. The
amount of management reserve (if any) is determined based on agency risk tolerance and
managed exclusively by the agency. Similar “reserves” are not allowable in Recipient estimates
per the Uniform Guidance.
Milestone. A significant point or event in a project, program, or portfolio.
Entries in italics are from Project Management Institute, Inc., [PMI Lexicon], (2012) Copyright and all rights reserved. Material
from this publication has been reproduced with the permission of PMI. Italicized entries with leading asterisks have been
modified slightly from the original PMI version for NSF purposes.
Section Revision:
May 30, 2019

9-8

Major Facilities Guide: NSF 19-68 (May 2019)
9.2 Terms and Definitions
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Most Likely Duration. An estimate of the most probable activity duration that takes into
account all of the known variables that could affect performance.
“No Cost Overrun” Policy. NSF policy requiring that a Total Project Cost estimate established at
the Preliminary Design Stage have adequate contingency to cover all foreseeable risks.
However, NSF conducts its oversight of projects against the Total Project Cost authorized by the
NSB following Final Design Review (FDR).
Operations Stage. The Life Cycle Stage that succeeds Construction and includes the day-to-day
work to operate and maintain the facility and to perform research. Operations may also include
activities to transition from construction to operations, replacement or upgrade activities,
technology research and development, and activities that support planning and staging for the
Divestment Stage.
Opportunity. A risk that would have a positive effect on one or more project objectives.
Optimistic Duration. An estimate of the shortest activity duration that takes into account all of
the known variables that could affect performance.
Organizational Breakdown Structure. A hierarchical representation of the project organization,
which illustrates the relationship between project activities and the organizational units that will
perform those activities.
Organizational Project Management Maturity. The level of an organization's ability to deliver
the desired strategic outcomes in a predictable, controllable, and reliable manner.
Oversight. Watchful and responsible care of something or some activity; regulatory supervision.
Parametric Estimating. An estimating technique in which an algorithm is used to calculate cost
or duration based on historical data and project parameters.
Path Convergence. A relationship in which a schedule activity has more than one predecessor.
Path Divergence. A relationship in which a schedule activity has more than one successor.
Percent Complete. An estimate expressed as a percent of the amount of work that has been
completed on an activity or a work breakdown structure component.
Performance Measurement Baseline. (PMB) The approved cost and schedule baseline for
accomplishing project work scope used as a basis of comparison for Earned Value Management.
The PMB is typically approved and established at the time of award, in the terms and conditions
of the award instrument, and is under formal change control for the life of the project. (For NSF
projects, contingency amounts are not included in the PMB due to the NSF requirement that
contingency is held and managed separately from the baseline.)
Pessimistic Duration. An estimate of the longest activity duration, which takes into account all
of the known variables that could affect performance.
Entries in italics are from Project Management Institute, Inc., [PMI Lexicon], (2012) Copyright and all rights reserved. Material
from this publication has been reproduced with the permission of PMI. Italicized entries with leading asterisks have been
modified slightly from the original PMI version for NSF purposes.
Section Revision:
May 30, 2019

9-9

Major Facilities Guide: NSF 19-68 (May 2019)
9.2 Terms and Definitions
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Phase Gate. A review at the end of a phase in which a decision is made to continue to the next
phase, to continue with modification, or to end a project or program.
Planned Value. The authorized budget assigned to scheduled work.
Portfolio. Projects, programs, subportfolios, and operations managed as a group to achieve
strategic objectives.
Portfolio Management. The centralized management of one or more portfolios to achieve
strategic objectives.
Precedence Diagramming Method. A technique used for constructing a schedule model in
which activities are represented by nodes and are graphically linked by one or more logical
relationships to show the sequence in which the activities are to be performed.
Predecessor Activity. An activity that logically comes before a dependent activity in a schedule.
Preliminary Design Phase. The second phase of the Design Stage, after the Conceptual Design
Phase, that further advances the project definition and the Project Execution Plan. It produces a
bottom-up scope, cost, schedule, and risk analysis of sufficient maturity to allow determination
of the Project Total Cost and Duration for a stated future start date and to establish the
construction budget request.
Preventive Action. An intentional activity that ensures the future performance of the project
work is aligned with the project management plan.
Probabilistic Risk Assessment. A quantitative risk analysis that uses probability distributions to
represent the uncertainty usually present in the cost of a deliverable or the duration of a
scheduled activity, in order to obtain a range of outcomes for overall project cost and finish
dates that support selection of contingency amounts as part of risk management. Many
commercial probabilistic risk analysis applications employ Monte Carlo simulations of project
cost and schedule.
Probability and Impact Matrix. A grid for mapping the probability of each risk occurrence and
its impact on project objectives if that risk occurs.
Procurement Management Plan. A component of the project or program management plan
that describes how a team will acquire goods and services from outside of the performing
organization.
Program. A group of related projects, subprograms, and program activities that are managed in
a coordinated way to obtain benefits not available from managing them individually.
Program Management. The application of knowledge, skills, tools, and techniques to a program
to meet the program requirements and to obtain benefits and control not available by
managing projects individually.
Entries in italics are from Project Management Institute, Inc., [PMI Lexicon], (2012) Copyright and all rights reserved. Material
from this publication has been reproduced with the permission of PMI. Italicized entries with leading asterisks have been
modified slightly from the original PMI version for NSF purposes.
Section Revision:
May 30, 2019

9-10

Major Facilities Guide: NSF 19-68 (May 2019)
9.2 Terms and Definitions
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Progressive Elaboration. The iterative process of increasing the level of detail in a project
management plan as greater amounts of information and more accurate estimates become
available.
Project Calendar. A calendar that identifies working days and shifts that are available for
scheduled activities.
Project End Date. The projected date for the completion of all the project baseline schedule
activities plus use of all schedule contingency. (Note that this date may be earlier than, but no
later than, the end date of the award instrument.)
*Project Execution Plan. The document that describes how the project will be executed,
monitored, and controlled.
Project Life Cycle. The series of phases that a project passes through from its initiation to its
closure.
Project Management. The application of knowledge, skills, tools, and techniques to project
activities to meet the project requirements.
Project Management Office. A management structure that standardizes the project-related
governance processes and facilitates the sharing of resources, methodologies, tools, and
techniques.
Project Manager. The person assigned by the performing organization to lead the team that is
responsible for achieving the project objectives.
Project Phase. A collection of logically related project activities that culminates in the
completion of one or more deliverables.
Project Schedule. An output of a schedule model that presents linked activities with planned
dates, durations, milestones, and resources.
Project Scope. The work performed to deliver a product, service, or result with the specified
features and functions.
Project Scope Statement. The description of the project scope, major deliverables, assumptions,
and constraints.
Quality Management Plan. A component of the project or program management plan that
describes how an organization's quality policies will be implemented.
Re-Baselining. Project re-planning that results in a change that is outside the terms set forth in
the award instrument for any of the following: 1) Total Project Cost (TPC); 2) total project
duration; or 3) project scope, except for approved options in the scope management plan. Rebaselining actions require special review and approval by NSF beyond those of the typical
change control approval process for re-planning actions.
Entries in italics are from Project Management Institute, Inc., [PMI Lexicon], (2012) Copyright and all rights reserved. Material
from this publication has been reproduced with the permission of PMI. Italicized entries with leading asterisks have been
modified slightly from the original PMI version for NSF purposes.
Section Revision:
May 30, 2019

9-11

Major Facilities Guide: NSF 19-68 (May 2019)
9.2 Terms and Definitions
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Re-Planning. A normal project management process to modify or re-organize the Performance
Measurement Baseline cost and/or schedule plans for future work without impacting total
project cost, total project duration, or overall scope objectives; or the implementation of
approved de-scoping options. Formal change control processes are followed for all baseline
changes. Retroactive changes to past performance should not be included in re-planning.
Requirement. A condition or capability that is required to be present in a product, service, or
result to satisfy a contract or other formally imposed specification.
Research Infrastructure. Any combination of facilities, equipment, instrumentation,
computational hardware and software, and the necessary supporting human capital.
Resource Breakdown Structure. A hierarchical representation of resources by category and
type.
Resource Calendar. A calendar that identifies the working days and shifts upon which each
specific resource is available.
Resource Leveling. A technique in which start and finish dates are adjusted based on resource
constraints with the goal of balancing demand for resources with the available supply.
Responsibility Assignment Matrix. A grid that shows the project resources assigned to each
work package.
Review and Recommend. The act of carefully looking at or examining the quality or condition
of something AND then suggesting that someone taken action or do something.
Risk. An uncertain event or condition that, if it occurs, has a positive or negative effect on one or
more project objectives.
Risk Acceptance. A risk response strategy whereby the project team decides to acknowledge the
risk and not take any action unless the risk occurs.
Risk Avoidance. A risk response strategy whereby the project team acts to eliminate the threat
or protect the project from its impact.
Risk Breakdown Structure. A hierarchical representation of risks that is organized according to
risk categories.
Risk Category. A group of potential causes of risk.
Risk Exposure. Quantitative impact of risk for a single event, quoted in currency or time, and
typically estimated from probability of occurrence and a likely impact or consequence. Overall
project risk exposure results from an accumulation of individual risk impacts for the work to be
completed, typically determined by applying probabilistic analysis to the set of individual risks.
Risk Management Plan. A component of the project, program, or portfolio management plan
that describes how risk management activities will be structured and performed.
Entries in italics are from Project Management Institute, Inc., [PMI Lexicon], (2012) Copyright and all rights reserved. Material
from this publication has been reproduced with the permission of PMI. Italicized entries with leading asterisks have been
modified slightly from the original PMI version for NSF purposes.
Section Revision:
May 30, 2019

9-12

Major Facilities Guide: NSF 19-68 (May 2019)
9.2 Terms and Definitions
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Risk Mitigation. A risk response strategy whereby the project team acts to reduce the
probability of occurrence or impact of a risk.
Risk Register. A document in which the results of risk analysis and risk response planning are
recorded.
Risk Transference. A risk response strategy whereby the project team shifts the impact of a
threat to a third party, together with ownership of the response.
Rolling Wave Planning. An iterative planning technique in which the work to be accomplished in
the near term is planned in detail, while the work in the future is planned at a higher level.
Schedule Compression. A technique used to shorten the schedule duration without reducing the
project scope.
Schedule Management Plan. A component of the project or program management plan that
establishes the criteria and the activities for developing, monitoring, and controlling the
schedule.
Schedule Model. A representation of the plan for executing the project’s activities, including
durations, dependencies, and other planning information, used to produce a project schedule
along with other scheduling artifacts.
Schedule Performance Index. A measure of schedule efficiency expressed as the ratio of earned
value to planned value.
Schedule Variance. A measure of schedule performance expressed as the difference between
the earned value and the planned value.
Scope Baseline. The approved version of a scope statement, work breakdown structure (WBS)
and its associated WBS dictionary, which can be changed only through formal change control
procedures and is used as a basis for comparison.
Scope Contingency. Scope included in the project baseline definition that can be removed
without affecting the overall project’s objectives, but that may still have undesirable effects on
facility performance. Identified scope contingency should have a value equal to at least 10% of
the baseline budget.
Scope Management Plan. A component document of the Project Execution Plan that describes
how scope contingency is determined, monitored, and controlled over the project lifetime.
Scope Creep. The uncontrolled expansion to product or project scope without adjustments to
time, cost, and resources.
Scope Management Plan. A component of the project or program management plan that
describes how the scope will be defined, developed, monitored, controlled, and validated.

Entries in italics are from Project Management Institute, Inc., [PMI Lexicon], (2012) Copyright and all rights reserved. Material
from this publication has been reproduced with the permission of PMI. Italicized entries with leading asterisks have been
modified slightly from the original PMI version for NSF purposes.
Section Revision:
May 30, 2019

9-13

Major Facilities Guide: NSF 19-68 (May 2019)
9.2 Terms and Definitions
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

S-Curve Analysis. An earned value management technique used to indicate performance trends
by using a graph that displays cumulative costs over a specific time period.
Secondary Risk. A risk that arises as a direct result of implementing a risk response.
Sponsor. A person or group that provides resources and support for the project, program, or
portfolio, and is accountable for enabling success.
Staffing Management Plan. A component of the human resource plan that describes when and
how team members will be acquired and how long they will be needed.
Stakeholder. An individual, group, or organization that may affect, be affected by, or perceive
itself to be affected by a decision, activity, or outcome of a project, program, or portfolio.
Start-to-Finish. A logical relationship in which a successor activity cannot finish until a
predecessor activity has started.
Start-to-Start. A logical relationship in which a successor activity cannot start until a
predecessor activity has started.
Subaward: Award made by the prime Recipient of an NSF for the purpose of carrying out a
portion of a Federal award and creates a Federal assistance relationship with the Subrecipient.
It does not include payments to a contractor or payments to an individual that is a beneficiary
of a Federal program. A subaward may be provided through any form of legal agreement,
including an agreement that the prime Recipient considers a contract. All subawards require
written prior NSF authorization.
Successor Activity. A dependent activity that logically comes after another activity in a schedule.
Summary Activity. A group of related schedule activities aggregated and displayed as a single
activity.
Termination. The ending of a Federal award, in whole or in part at any time prior to the
planned end of period of performance.
Threat. A risk that would have a negative effect on one or more project objectives.
Three-Point Estimate. A technique used to estimate cost or duration by applying an average or
weighted average of optimistic, pessimistic, and most likely estimates when there is uncertainty
with the individual activity estimates.
To-Complete Performance Index. A measure of the cost performance that is required to be
achieved with the remaining resources in order to meet a specified management goal,
expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
Total Float. The amount of time that a schedule activity can be delayed or extended from its
early start date without delaying the project finish date or violating a schedule constraint.

Entries in italics are from Project Management Institute, Inc., [PMI Lexicon], (2012) Copyright and all rights reserved. Material
from this publication has been reproduced with the permission of PMI. Italicized entries with leading asterisks have been
modified slightly from the original PMI version for NSF purposes.
Section Revision:
May 30, 2019

9-14

Major Facilities Guide: NSF 19-68 (May 2019)
9.2 Terms and Definitions
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

Total Project Cost. The sum of the baseline budget (including indirect costs), the budget
contingency, fee/profit (as applicable), and management reserve (if authorized) for the
Construction Stage.
The TPC authorized by the NSB following FDR is a “not-to-exceed” figure against which NSF
manages the No Cost Overrun Policy. The initial award may be at or below this figure.
Throughout the Design and Construction Stages, the TPC is an estimate and only at the end of
the project will the final TPC be known.
Total Project Duration. The sum of the amount of time (in months) for the Performance
Measurement Baseline schedule duration and the schedule contingency. The NSB authorized
duration is the estimated project duration plus approximately 6 months.
Trigger Condition. An event or situation that indicates that a risk is about to occur.
Variance Analysis. A technique for determining the cause and degree of difference between the
Performance Measurement Baseline and actual performance.
Variance at Completion. A projection of the amount of budget deficit or surplus, expressed as
the difference between the budget at completion and the estimate at completion.
WBS Dictionary. A document that provides detailed deliverable, activity, and scheduling
information about each component in the work breakdown structure.
What-If Scenario Analysis. The process of evaluating scenarios in order to predict their effect on
project objectives.
Work Breakdown Structure. A hierarchical decomposition of the total scope of work to be
carried out by the project team to accomplish the project objectives and create the required
deliverables.
Work Package. The work defined at the lowest level of the work breakdown structure for which
cost and duration can be estimated and managed.
Workaround. A response to a threat that has occurred, for which a prior response had not been
planned or was not effective.

Entries in italics are from Project Management Institute, Inc., [PMI Lexicon], (2012) Copyright and all rights reserved. Material
from this publication has been reproduced with the permission of PMI. Italicized entries with leading asterisks have been
modified slightly from the original PMI version for NSF purposes.
Section Revision:
May 30, 2019

9-15

Major Facilities Guide: NSF 19-68 (May 2019)
Appendix A. Ranking Criteria for Prioritizing Major Facility Projects
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

10 APPENDICES
Appendix A. Ranking Criteria for Prioritizing Major Facility Projects
Excerpted from the National Academies’ Report: Setting Priorities for Large Facility Projects
Supported by the National Science Foundation
(http://www.nap.edu/books/0309090849/html/R1.html)1.
First Ranking: Scientific and Technical Criteria Assessed by Researchers in a Field or
Interdisciplinary Area
•
•
•
•

Which projects have the most scientific merit, potential and opportunities within a field
or interdisciplinary area?
Which projects are the most technologically ready?
Are the scientific credentials of the proposers of the highest rank?
Are the project-management capabilities of the proposal team of the highest quality?

Second Ranking: Agency Strategic Criteria Assessed across Related Fields
•
•
•
•
•

Which projects will have the greatest impact on scientific advances in this set of related
fields taking into account the importance of balance among fields for NSF's portfolio
management in the nation's interest?
Which projects include opportunities to serve the needs of researchers from multiple
disciplines or the ability to facilitate interdisciplinary research?
Which projects have major commitments from other agencies or countries that should
be considered?
Which projects have the greatest potential for education and workforce development?
Which projects have the most readiness for further development and construction?

Third Ranking: National Criteria Assessed across All Fields
•
•
•
•

Which projects are in new and emerging fields that have the most potential to be
transformative? Which projects have the most potential to change how research is
conducted or to expand fundamental science and engineering frontiers?
Which projects have the greatest potential for maintaining US leadership in key science
and engineering fields?
Which projects produce the greatest benefits in numbers of researchers, educators and
students enabled?
Which projects most need to be undertaken in the near term? Which ones have the
most current windows of opportunity, pressing needs and international or interagency
commitments that should be met?

As referenced in Joint National Science Board —National Science Foundation Management Report: Setting Priorities for Large
Facility Projects Supported by the National Science Foundation (NSB-05-77); September 2005

1

Section Revision:
December 14, 2018

A-1

Major Facilities Guide: NSF 19-68 (May 2019)
Appendix A. Ranking Criteria for Prioritizing Major Facility Projects
Prepared by the Large Facilities Office in the Budget, Finance, and Award Management Office
(BFA-LFO)

•
•

Which projects have the greatest degree of community support?
Which projects will have the greatest impact on scientific advances across fields taking
into account the importance of balance among fields for NSF's portfolio management in
the nation's interest?

Section Revision:
December 14, 2018

A-2


File Typeapplication/pdf
File TitleMajor Facilities Guide: NSF 19-68 (May 2019)
AuthorYasky, Rebecca Kay
File Modified2019-05-30
File Created2019-05-15

© 2024 OMB.report | Privacy Policy