Federal Register / Vol. 85, No. 68 / Wednesday, April 8, 2020 / Notices
an application under section 7(c) of the
Natural Gas Act to amend the existing
Order Issuing Certificates and
Approving Abandonment issued on
January 19, 2017 (Order) for the Leach
XPress Project (LXP) in Docket No.
CP15–514–000. In the LXP Amendment,
Columbia Gas proposes to modify its
operation of the Ceredo Compressor
Station authorized in the Order and
requests modifying the Order noise level
requirement for the Ceredo and
Crawford Compressor Stations. The
proposed LXP Amendment would allow
Columbia Gas to operate the Ceredo and
Crawford Compressor Stations under
the modified full load scenario, and
ensure that the noise level requirement
associated with the compressor stations
would be consistent with the
Commission’s policy.
On November 19, 2019, the Federal
Energy Regulatory Commission (FERC
or Commission) issued its Notice of
Application for the LXP Amendment.
Among other things, that notice alerted
agencies issuing federal authorization of
the requirement to complete all
necessary reviews and to reach a final
decision on a request for a federal
authorization within 90 days of the date
of issuance of the Commission’s staff’s
Environmental Assessment (EA) for the
LXP Amendment. This instant notice
identifies the FERC staff’s planned
schedule for completion of an EA for the
LXP Amendment.

lotter on DSKBCFDHB2PROD with NOTICES

Schedule for Environmental Review
Issuance of EA—May 7, 2020
90-day Federal Authorization Decision
Deadline—August 5, 2020
If a schedule change becomes
necessary, additional notice will be
provided so that the relevant agencies
are kept informed of the LXP
Amendment’s progress.
Project Description
Columbia Gas is proposing to modify
its operation of the Ceredo Compressor
Station authorized in the Order to
reduce operational noise levels on noise
sensitive areas by: (1) Modifying the
full-load operation of the Ceredo
Compressor Station to limit the use of
the seven existing legacy reciprocating
units operating prior to the LXP Order
to four units at a given time; and (2)
allowing for the use of additional
horsepower (hp) at the Ceredo
Compressor Station that is available
from existing electric-driven compressor
units installed since issuance of the LXP
Order. Columbia Gas also requests
amending the Order noise level
requirement for the Ceredo and
Crawford Compressor Stations to
conform to the Commission staff

VerDate Sep<11>2014

18:37 Apr 07, 2020

Jkt 250001

recommended environmental condition
31 in the September 2016 final
Environmental Impact Statement for the
LXP rather than environmental
condition 31 of the Order.

19753

Dated: April 1, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–07375 Filed 4–7–20; 8:45 am]
BILLING CODE 6717–01–P

Background
On February 26, 2020, the
Commission issued a Notice of Intent to
Prepare an Environmental Assessment
for the Proposed Leach XPress Project
Amendment and Request for Comments
on Environmental Issues (NOI). The NOI
was sent to affected landowners; federal,
state, and local government agencies;
elected officials; other interested parties;
and local libraries and newspapers. In
response to the NOI, the Commission
received one comment letter from the
U.S. Environmental Protection Agency
raising issues including: Expected noise
impacts and existing and potential
alternative noise mitigation applicable
to noise sensitive receivers in the
vicinity of the compressor stations; and
clarification of what facility
modifications Columbia Gas carried out
at the compressor stations under the
LXP Order. All substantive comments
received from the U.S. Environmental
Protection Agency will be addressed in
the EA.

DEPARTMENT OF ENERGY

Additional Information

DATES:

Frm 00029

Fmt 4703

Sfmt 4703

[Docket No. IC20–14–000]

Commission Information Collection
Activities (FERC–725T); Comment
Request; Extension
Federal Energy Regulatory
Commission, Department of Energy.

AGENCY:

Notice of information collection
and request for comments.

ACTION:

In compliance with the
requirements of the Paperwork
Reduction Act of 1995, the Federal
Energy Regulatory Commission
(Commission or FERC) is soliciting
public comment on the currently
approved information collection, FERC–
725T, Mandatory Reliability Standards
for the Bulk-Power System: TRE
Reliability Standards.

SUMMARY:

Comments on the collection of
information are due June 8, 2020.

In order to receive notification of the
issuance of the EA and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
can reduce the amount of time you
spend researching proceedings by
automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Additional information about the LXP
Amendment is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC
website (www.ferc.gov). Using the
‘‘eLibrary’’ link, select ‘‘General Search’’
from the eLibrary menu, enter the
selected date range and ‘‘Docket
Number’’ excluding the last three digits
(i.e., CP20–12), and follow the
instructions. For assistance with access
to eLibrary, the helpline can be reached
at (866) 208–3676, TTY (202) 502–8659,
or at [email protected]. The
eLibrary link on the FERC website also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and rule
makings.

PO 00000

Federal Energy Regulatory
Commission

You may submit comments
(identified by Docket No. IC20–14–000)
by either of the following methods:
• eFiling at Commission’s Website:
http://www.ferc.gov/docs-filing/
efiling.asp.
• Mail/Hand Delivery/Courier:
Federal Energy Regulatory Commission,
Secretary of the Commission, at Health
and Human Services, 12225 Wilkins
Avenue, Rockville, Maryland 20852.
Instructions: All submissions must be
formatted and filed in accordance with
submission guidelines at: http://
www.ferc.gov/help/submissionguide.asp. For user assistance contact
FERC Online Support by email at
[email protected], or by phone
at: (866) 208–3676 (toll-free).
Docket: Users interested in receiving
automatic notification of activity in this
docket or in viewing/downloading
comments and issuances in this docket
may do so at http://www.ferc.gov/docsfiling/docs-filing.asp.

ADDRESSES:

FOR FURTHER INFORMATION CONTACT:

Ellen Brown may be reached by email
at [email protected], telephone
at (202) 502–8663.
SUPPLEMENTARY INFORMATION:

E:\FR\FM\08APN1.SGM

08APN1

19754

Federal Register / Vol. 85, No. 68 / Wednesday, April 8, 2020 / Notices

Title: FERC–725T, Mandatory
Reliability Standards for the Bulk-Power
System: TRE 1 Reliability Standards.
OMB Control No.: 1902–0273.
Type of Request: Three-year extension
of the FERC–725T information
collection requirements with no changes
to the current reporting requirements.
Abstract: TRE Reliability Standards
apply to entities registered as Generator
Owners (GOs), Generator Operators
(GOPs), and Balancing Authorities (BAs)
within the Texas Reliability Entity
region.
The information collection
requirements entail the setting or
configuration of the Control System
software, identification and recording of
events, data retention, and submitting
frequency measurable events to the
compliance enforcement authority
(Regional Entity or NERC).
Submitting frequency measurable
events. The BA has to identify and post

information regarding Frequency
Measurable Events (FME). Further, the
BA has to calculate and report to the
Compliance Enforcement Authority data
related to Primary Frequency Response
(PFR) performance of each generating
unit/generating facility.
Data retention. The BA, GO, and GOP
shall keep data or evidence to show
compliance, as identified below, unless
directed by its Compliance Enforcement
Authority to retain specific evidence for
a longer period of time as part of an
investigation. Compliance audits are
generally about three years apart.
• The BA shall retain a list of
identified Frequency Measurable Events
and shall retain FME information since
its last compliance audit.
• The BA shall retain all monthly
PFR performance reports since its last
compliance audit.

• The BA shall retain all annual
Interconnection minimum Frequency
Response calculations, and related
methodology and criteria documents,
relating to time periods since its last
compliance audit.
• The BA shall retain all data and
calculations relating to the
Interconnection’s Frequency Response,
and all evidence of actions taken to
increase the Interconnection’s
Frequency Response, since its last
compliance audit.
• Each GOP and GO shall retain
evidence since its last compliance audit.
Type of Respondents: NERC
Registered entities: Balancing
Authorities, Generator Owners,
Generator Operators.
Estimate of Annual Burden : 2 The
Commission estimates the annual public
reporting burden for the information
collection as:

FERC–725T (MANDATORY RELIABILITY STANDARDS FOR THE BULK-POWER SYSTEM: TRE RELIABILITY STANDARDS)
Number of
respondents

Annual
number of
responses per
respondent

Total
number of
responses

Average
burden & cost per
response 3

Total annual burden
hours & total annual
cost

Cost per
respondent
($)

(1)

(2)

(1) * (2) = (3)

(4)

(3) * (4) = (5)

(5) ÷ (1)

Maintenance and Submission of Event Log
Data.
Evidence Retention ......

41

1

1

16 hrs.; $821.44 ..........

16 hrs.; $821.44 ..........

821.44

5 130

1

130

2 hrs.; 102.68 ..............

260 hrs.; 13,348.4 .......

102.68

Total ......................

........................

........................

131

.....................................

276 hrs.; 14,169.84 .....

........................

lotter on DSKBCFDHB2PROD with NOTICES

Comments: Comments are invited on:
(1) Whether the collection of
information is necessary for the proper
performance of the functions of the
Commission, including whether the
information will have practical utility;
(2) the accuracy of the agency’s estimate
of the burden and cost of the collection
of information, including the validity of
the methodology and assumptions used;
(3) ways to enhance the quality, utility
and clarity of the information collection;
and (4) ways to minimize the burden of
the collection of information on those
who are to respond, including the use
of automated collection techniques or
other forms of information technology.

1 Texas

Reliability Entity.
is defined as the total time, effort, or
financial resources expended by persons to
generate, maintain, retain, or disclose or provide
information to or for a Federal agency. For further
explanation of what is included in the information
collection burden, reference 5 Code of Federal
Regulations 1320.3.
2 Burden

VerDate Sep<11>2014

18:37 Apr 07, 2020

Jkt 250001

Dated: April 1, 2020.
Kimberly D. Bose,
Secretary.

In accordance with the National
Environmental Policy Act of 1969 and
the Federal Energy Regulatory
Commission’s regulations, 18 CFR part

380 (Order No. 486, 52 FR 47879), the
Office of Energy Projects has reviewed
the application for non-capacity license
amendment for the North Platte/
Keystone Diversion Dam Hydroelectric
Project, located on the North/South
Platte Rivers in Lincoln and Keith
counties, Nebraska, and has prepared an
Environmental Assessment (EA). In the
EA, Commission staff analyzes the
potential environmental effects of the
proposed license amendment and
concludes that issuing an order
approving the proposal, with
appropriate environmental measures,
would not constitute a major federal
action significantly affecting the quality
of the human environment.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all

3 The figures for May 2018 posted by the Bureau
of Labor Statistics for the Utilities sector (available
at http://www.bls.gov/oes/current/naics2_22.htm)
and updated March 2019 for benefits information
(at http://www.bls.gov/news.release/ecec.nr0.htm).
The hourly estimates for salary plus benefits are:
—File Clerks (code 43–4071), $34.50.

—Electrical Engineer (code 17–2071), $68.17.
The average hourly burden cost for this collection
is $51.34 [$34.50 + $68.17 = 51.335] and is rounded
to $51.34.
4 BA (balancing authority).
5 BA (balancing authority), GO (generator owner),
and GOP (generator operator).

[FR Doc. 2020–07374 Filed 4–7–20; 8:45 am]
BILLING CODE 6717–01–P

DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 1835–290]

Nebraska Public Power District; Notice
of Availability of Environmental
Assessment

PO 00000

Frm 00030

Fmt 4703

Sfmt 4703

E:\FR\FM\08APN1.SGM

08APN1


File Typeapplication/pdf
File Modified2020-04-08
File Created2020-04-08

© 2024 OMB.report | Privacy Policy