Appendix A-1: Microloan Program Deliverables Schedule


Tasks

Deliverables

Due/Delivered Date

Task 2

Evaluation Design and Planning

 


Evaluation Methodology FINAL

7/17/2020

Task 3

Data Collection and Analysis



Instrument Design


Pilot Instruments Completed

8/31/2020

Instrument FINAL

9/14/2020

OMB ICR Package and submission

12/28/2020

Obtain OMB Clearance

4/12/2021


Microloan administrative data analysis and sampling

3/22/2021

Web surveys and qualitative interviews initiated

4/13/2021

Web surveys and qualitative interviews completed

7/12/2021

Data linking and Management

7/27/2021

Initial descriptive statistics

8/11/2021

Task 4

Reports

 


Report FINAL

10/8/2021

COMPLETION DATE

11/1/2021