18 Cfr 4.50

18 CFR 4.50.docx

FERC-505, (Proposed Rule in Docket RM20-21-000) Small Hydropower Projects and Conduit Facilities including License/Relicense, Exemption, and Qualifying Conduit Facility Determination

18 CFR 4.50

OMB: 1902-0115

Document [docx]
Download: docx | pdf

Electronic Code of Federal Regulations (eCFR) Page 1 of 2

ELECTRONIC CODE OF FEDERAL REGULATIONS

e-CFR data is current as of May 14, 2021

Title 18Chapter ISubchapter BPart 4Subpart F → §4.50

Title 18: Conservation of Power and Water Resources

PART 4—LICENSES, PERMITS, EXEMPTIONS, AND DETERMINATION OF

PROJECT COSTS

Subpart F—Application for License for Major Project—Existing Dam

Shape1

§4.50 Applicability.

(a) Applicability. (1) Except as provided in paragraph (a)(2) of this section, the provisions of this subpart apply to any application for either an initial license or new license for a major project—existing dam that is proposed to have a total installed capacity of more than 5 megawatts.

(2) This subpart does not apply to any major project—existing dam (see §4.40) that is proposed to entail or include:

  1. Any repair, modification or reconstruction of an existing dam that would result in a significant change in the normal maximum surface area or normal maximum surface elevation of an existing impoundment; or

  2. Any new development or change in project operation that would result in a significant environmental impact.

(3) An applicant for license for any major project—existing dam that would have a total installed capacity of 5 megawatts or less must submit application under subpart G (§§4.60 and 4.61).

(b) Guidance from Commission staff. A prospective applicant for a major license—existing dam may seek advice from the Commission staff regarding the applicability of these sections to its project (see §4.32(h)), including the determinations whether any proposed repair or reconstruction of an existing dam would result in a significant change in the normal maximum surface area or the normal maximum surface elevation of an existing impoundment, or whether any proposed new development or change in project operation would result in a

significant environmental impact.

[Order 59, 44 FR 67651, Nov. 27, 1979, as amended by Order 184, 46 FR 55942, Nov. 13, 1981; Order 413, 50 FR 11684, Mar. 25, 1985; Order 499, 53 FR 27002, July 18, 1988]

https://www.ecfr.gov/cgi-bin/text-idx?SID=f2ed52f1b650b93387741ee78d17c2bd&mc=tr... 5/18/2021 Electronic Code of Federal Regulations (eCFR) Page 2 of 2

Need assistance?

https://www.ecfr.gov/cgi-bin/text-idx?SID=f2ed52f1b650b93387741ee78d17c2bd&mc=tr... 5/18/2021

File Typeapplication/vnd.openxmlformats-officedocument.wordprocessingml.document