Emission Guidelines for Municipal Solid Waste Landfills (40 CFR part 60, subpart Cf) (Renewal)
Extension without change of a currently approved collection
No
Regular
Improperly submitted and continue
05/07/2024
01/31/2023
This ICR is returned as improperly submitted, due to non-compliance with prior terms of clearance.
Prior terms of clearance:
Due to lack of response to OMB during the review, this OMB control number is approved for a one-year. Upon resubmission, the program must use the standard 18 question Supporting Statement format. Per 5 CFR 1320(a)(1)(iii)(G) the agency is reminded to provide OMB with a copy of the statutory or regulatory authority to collect information. In addition, the agency must provide OMB with all of the ICs including instructions.
table that charts list comparision
Inventory as of this Action
Requested
Previously Approved
01/31/2023
36 Months From Approved
05/31/2024
1,372
0
1,372
635,900
0
635,900
2,760,000
0
2,760,000
Previously, the EPA issued New Source Performance Standards (NSPS) and Emission Guidelines (EG) and Compliance Times for Existing Municipal Solid Waste Landfills under the regulations published at 40 CFR Part 60, Subpart WWW and 40 CFR Part 60, Subpart Cc as promulgated on March 12, 1996; and revised on both June 16, 1998, and February 24, 1999. The Federal plan requirements implementing the regulations were published at 40 CFR Part 62, Subpart GGG and promulgated on November 8, 1999. On August 29, 2016 (81 FR 59332), EPA finalized a new NSPS subpart (40 CFR Part 60, Subpart XXX), based on its review of 40 CFR Part 60, Subpart WWW. Subpart XXX applies to MSW landfills that are either new, or reconstructed, or modified after July 17, 2014, and is effective as of October 28, 2016. Concurrently, EPA finalized revised Emissions Guidelines under a new subpart (40 CFR Part 60, Subpart Cf). The new Emission Guidelines apply to existing landfills accepting waste after November 8, 1987, for which construction was commenced either on or before July 17, 2014. The revised guidelines are implemented under state or federal plans. The EPA subsequently finalized a federal plan implementing 40 CFR Part 60, Subpart Cf under a new subpart (40 CFR Part 62, Subpart OOO) on May 21, 2021. This ICR includes burden for MSW landfills that are subject to the requirements of Subpart Cf, which are implemented under State plans and a Federal plan (40 CFR part 62, subpart OOO). All MSW landfills that are subject to the original NSPS (40 CFR part 60, subpart WWW), the federal plan (40 CFR part 62, subpart GGG), or a state plan implementing the original emission guidelines (40 CFR part 60, subpart Cc) were required to comply with their current requirements unless and until they are covered by a more stringent State or Federal plan implementing the emission guidelines in subpart Cf. Since EPA has finalized the Federal plan at 40 CFR Part 62, Subpart OOO, all respondents previously subject to Subpart WWW, a state plan implementing subpart Cc, or GGG, are now either subject to either a State plan under implementing 40 CFR Part 60, Subpart Cf, or must comply with the Federal plan under 40 CFR Part 62, Subpart OOO, or if they have modified since July 17, 2014, they must now comply with the NSPS at 40 CFR Part 60, Subpart XXX.
Subpart Cf reduces the NMOC emission rate threshold from the previous level of 50 megagrams per year (Mg/yr) to 34 Mg/yr for landfills that are not closed as of August 29, 2016. The final rule retained the design capacity cutoff of 2.5 million Mg and 2.5 million cubic meters in the current emission guidelines. Closed landfills retain the same NMOC threshold of 50 Mg/yr, as was the case under Subpart WWW. Closed landfills are also exempted from the one-time reporting requirements, provided the landfill fulfilled these requirements under the NSPS (40 CFR Part 60, Subpart WWW), the Federal plan (40 CFR Part 62, Subpart GGG), or a state plan implementing 40 CFR Part 60 Subpart Cc. This information is being collected to assure compliance with 40 CFR Part 60, Subpart Cf and 40 CFR Part 62, Subpart OOO.
The decrease in burden from the most-recently approved ICR is due to an adjustment. The adjustment decrease in burden from the most-recently approved ICR is due to a decrease in the number of respondents. The number of respondents has been adjusted in this ICR based on the regulatory database used for the 2016 rule. The number of respondents reflects the lower expected number of landfills controlling between years 2023 through 2025 based on projected emissions, as well as the number of landfills subject between years 2023 and 2025, based on waste disposal quantities which increase over time at active landfills. The number of respondents also assumes that, in these years, landfills will be controlled under the more stringent 34 Mg/yr requirements. The estimates also subtract out landfills expected to modify during this time period and become subject to the MSW landfill 2016 NSPS Subpart XXX instead (ICR No. 2498, OMB Control Number 2060-0697). This ICR therefore reflects a decrease in the total number of respondents subject to the rule, but a similar number of controlling landfills subject to monitoring and testing requirements. There is a slight increase in burden for states/local agencies implementing state/local agency plans due to an adjustment increase in the number of states/local agencies that are enforcing State Plans.
There is a decrease in the capital costs from the most-recently approved ICR due to a decrease in the number of respondents expected to install controls and therefore conduct initial performance tests and install monitoring equipment during the three-year period of this ICR. There is no change in the O&M costs because the number of respondents expected to maintain controls and monitoring equipment is unchanged.
$503,000
No
No
No
No
No
No
No
Muntasir Ali 919 541-0833
Reginfo record details
No
On behalf of this Federal agency, I certify that the collection of information encompassed by this request complies with 5 CFR 1320.9 and the related provisions of 5 CFR 1320.8(b)(3).
The following is a summary of the topics, regarding the proposed collection of information, that the certification covers:
(i) Why the information is being collected;
(ii) Use of information;
(iii) Burden estimate;
(iv) Nature of response (voluntary, required for a benefit, or mandatory);
(v) Nature and extent of confidentiality; and
(vi) Need to display currently valid OMB control number;
If you are unable to certify compliance with any of these provisions, identify the item by leaving the box unchecked and explain the reason in the Supporting Statement.