Who
|
Comment
|
PRA
Response
|
Background
|
Port
Authority of New York/New Jersey
|
FAA’s
estimate of the annual public burden could be improved.
|
|
|
|
FAA
estimates the annual public burden per Competition plan to be 150
hours or roughly 19 business days. The Port Authority finds this
estimate to be inaccurate, particularly for large hub airports
when added due diligence seems to be necessary to ensure
comprehensive reporting.
|
The
FAA will take this comment into consideration.
|
The
FAA estimates the FAA’s burden hours to review each
Competition Plan or Plan Update to be 30 hours. The competition
plan and plan update require coordination with multiple offices.
The burden hours do not include the time allowed for coordination
with the offices reviewing the plans. Some Competition Plans or
Plan Updates are more complex and/or require further clarification
and coordination. Each clarification event requires additional
time to allow for review and response of any concerns. Only
actual time in review is used to calculate the burden hours.
|
|
The
Port Authority assumes the FAA’s burden was more than 19
hours, as the FAA reviewed this plan and submitted approval over
the course of 293 calendar days, or 197 business days.
Notwithstanding any changes to the reporting requirements for
covered airports, the Port Authority recommends that FAA modify
its estimated administrative burden to provide greater
transparency to covered airports regarding how long they would be
anticipated to await review and approval of a Competition Plan.
|
The
FAA estimates the FAA’s burden hours to review each
Competition Plan or Plan Update to be 30 hours. The competition
plan and plan update require coordination with multiple offices.
The burden hours do not include the time allowed for coordination
with the offices reviewing the plans. Some Competition Plans or
Plan Updates are more complex and/or require further clarification
and coordination. Each clarification event requires additional
time to allow for review and response of any concerns. Only
actual time in review is used to calculate the burden hours.
|
PANYNJ
submitted the competition plan on the last day of the fiscal year.
An initial review was performed. The FAA reached out to the
internal stakeholders to discuss the approach for review and
decision considering the slots element. A comprehensive list of
questions was drafted in collaboration with internal stakeholders.
A meeting was held with PANYNJ around the same time. A follow-up
meeting was supposed to be scheduled, but it is uncertain if it
occurred. The PANYNJ was supposed to provide a written response
by a certain date, but the PANYNJ kept pushing it out further and
further. The FAA received the response sometime in April or May.
The information was circulated to the internal stakeholders for
review and coordination. A letter was drafted and sent to the
internal stakeholders for concurrence before a letter was issued
July 19, 2023. The entire process may have been 7 – 9
months instead of the normal 2-month process due to the additional
coordination required to address the complex nature of the
competition plan.
|
|
FAA
may consider improvements that could shorten its review and
approval process of submitted competition plans.
|
The
FAA will take this comment into consideration.
|
Due
to the amount of information to cover and number of internal
stakeholders involved in coordination, the process timeline is
estimated as 60 days. The FAA will look for possible ways to
reduce the time without compromising the ability to adequately
review the information.
|
Port
Authority of New York/New Jersey
|
Certain
capacity-constrained airports do not have sufficient information
regarding air carrier access to airports to prepare meaningful
competition plans.
|
49
U.S.C. 47106(f) defines the type of airport to file a competition
plan. The FAA does not have authority to change the type of
airport required to file this plan.
|
Much
of the competition plan is reviewing of the airport’s lease
with air carriers. The review identifies pro-competitive
practices, transparency and potential deficiencies meeting the
requirements of the statutes, regulation, and assurances.
|
|
FAA’s
exclusive control over Slot Coordination and Schedule Facilitation
severely impacts the ability of those airports to encourage new
entrants and incumbents to commence or expand service.
|
The
FAA takes into consideration unique circumstances of each airport
when reviewing the competition plans.
|
The
competition plan looks at:
The
availability of airport gates and related facilities,
reviews
the lease and subleasing arrangements to ensure the airport has a
process to accommodate new or expanding carriers,
gate
use requirements to review the airport’s process to
recapture gates,
gate-assignment
policy so existing and new entrant air carriers know the method
of announcing gate availability.
Airport
controls over air and ground-side capacity. The FAA pays
particular attention to MII conditions and the effect they may
have on capital construction projects.
The
competition plan reviews the sponsor’s lease and other
documents for the airport’s process to convey information to
new and expanding air carriers. The completion plan
|
Port
Authority of New York/New Jersey
|
The
proposed collection of information may be unnecessary for the
FAA’s performance when triggered by extraordinary
circumstances.
|
49
U.S.C. 47106(f) does contain any exceptions during COVID.
|
Congress
did not provide an exception during COVID for 49 USC 47106(f)
|
|
The
composition of passenger enplanement during the period based on
2020 passenger boardings was highly altered by (1) the effect of
the COVID-19 pandemic on global air travel and (certain air
carriers’ response to FAA’s waiver of the slot usage
requirement.
|
|
JFK
became a covered airport based CY2020 enplanements. The
enplanements continue to recover in CY2022. JFK continues to be a
covered airport.
|