Staff Presentation | Building for the Future
Through Electric Regional Transmission
Planning and Cost Allocation
May 13, 2024

Item E-1 | News Release | Fact Sheet
Good morning, Chairman Phillips and Commissioners,
Item E-1 is a draft final rule, issued pursuant to section 206 of the Federal Power Act, to reform
the Commission’s regional transmission planning and cost allocation requirements.  The
reforms remedy deficiencies in the existing requirements to ensure that Commissionjurisdictional rates remain just and reasonable and not unduly discriminatory or preferential. 
Today’s draft final rule builds on Order Nos. 888, 890, and 1000.  In those orders, the
Commission incrementally developed the requirements that govern regional transmission
planning and cost allocation processes. 
The Commission initially considered these reforms in its July 2021 Advanced Notice of
Proposed Rulemaking (or “ANOPR”), and later issued an April 2022 Notice of Proposed
Rulemaking (or “NOPR”) that proposed specific reforms.  The ANOPR and the NOPR received
approximately 26,850 pages of initial comments and appendices by August 2022, and 3,825
pages of reply comments and appendices by September 2022.  In addition, after September
2022, the NOPR received approximately 1,480 pages of supplemental comments and
appendices.  To our knowledge, this is the largest record ever considered by the Commission.  
Today’s draft final rule, based on the extensive record in this proceeding, finds that sufficiently
long-term, forward-looking, and comprehensive regional transmission planning and cost
allocation to meet long-term transmission needs is not occurring on a consistent and sufficient
basis, and that the absence of this type of regional transmission planning is resulting in
piecemeal transmission expansion that addresses relatively near-term transmission needs.  In
addition, the draft final rule finds that the status quo approach results in transmission
providers investing in relatively inefficient or less cost-effective transmission infrastructure,
with the costs ultimately recovered through Commission-jurisdictional rates.  This dynamic
results in, among other things, transmission customers paying more than is necessary or
appropriate to meet their transmission needs, and customers missing out on benefits that
outweigh their costs, which results in less efficient or cost-effective transmission investments.

 This in turn renders Commission-jurisdictional regional transmission planning and cost
allocation processes unjust and unreasonable.
The reforms in this draft final rule remedy this problem by requiring transmission providers to
conduct regional transmission planning on a sufficiently long-term, forward-looking, and
comprehensive basis to identify long-term transmission needs.  Transmission providers must,
among other things, plan ahead at least 20 years, using best available data to develop wellinformed projections of long-term transmission needs and long-term regional transmission
facilities to meet those needs.  In addition, transmission providers must conduct this planning
at least every five years and incorporate specific categories of factors that affect long-term
transmission needs, including certain laws and regulations, integrated resource plans, trends
in fuel costs, retirements, interconnection requests and withdrawals, and policy goals and
corporate commitments.
 The draft final rule also requires transmission providers to measure and use at least seven
enumerated economic and reliability benefits for the evaluation and selection of long-term
regional transmission facilities.  These seven benefits are: (1) avoided or deferred reliability
transmission facilities and aging infrastructure replacement; (2) either reduced loss of load
probability or reduced planning reserve margin; (3) production cost savings; (4) reduced
transmission energy losses; (5) reduced congestion due to transmission outages; (6) mitigation
of extreme weather events and unexpected system conditions; and (7) capacity cost benefits
from reduced peak energy losses. 
Additionally, the draft final rule requires transmission providers to include in their tariffs an
evaluation process, including selection criteria, that they will use to identify and evaluate longterm regional transmission facilities for potential selection.  Transmission providers must
establish an evaluation process that identifies long-term regional transmission facilities that
address long-term transmission needs, measures the benefits of the identified transmission
facilities consistent with the final rule requirements, and designates a point in the evaluation
process at which transmission providers will determine whether to select or not select
identified transmission facilities.  Transmission providers must also establish selection criteria
that are transparent and not unduly discriminatory or preferential, aim to ensure that more
efficient or cost-effective long-term regional transmission facilities are selected, and seek to
maximize benefits accounting for costs over time without over-building transmission facilities. 
 With respect to cost allocation, the draft final rule requires transmission providers to file one
or more ex ante methods to allocate the costs of long-term regional transmission facilities (or a
portfolio of such facilities) that are selected.  Transmission providers are also required to hold a
six-month engagement period with relevant state entities regarding cost allocation methods
and/or a state agreement process prior to compliance.  The draft final rule provides additional
flexibility on cost allocation by permitting transmission providers to adopt a state agreement
process, agreed to by relevant state entities, which could occur before, as well as up to six

months after selection, for its participants to determine, and transmission providers to file, a
cost allocation method for specific long-term regional transmission facilities.
The draft final rule also requires transmission providers to include in their tariffs provisions to
reevaluate previously selected long-term regional transmission facilities in certain
circumstances.
In addition, the draft final rule contains provisions to ensure the evaluation of regional
transmission facilities that will address certain transmission needs identified through the
generator interconnection process and have not yet been built.
In order to make the use of existing transmission infrastructure more efficient and optimize the
performance of such infrastructure, and to promote cost savings by improving operational
efficiency of new transmission facilities, the draft final rule requires transmission providers to
consider several alternative transmission technologies—dynamic line ratings, advanced power
flow control devices, advanced conductors, and transmission switching—in regional
transmission planning processes.
Recognizing that local transmission planning may affect the more efficient or cost-effective
regional transmission needs identified in long-term regional transmission planning, the draft
final rule requires transmission providers to adopt enhanced transparency for local
transmission planning information and identify potential opportunities to “right-size”
replacement transmission facilities to more efficiently or cost-effectively address long-term
transmission needs.  Transmission providers must also adopt tariff provisions that provide a
federal right of first refusal for a transmission provider to develop any “right-sized” facility.  
In addition, the draft final rule declines to adopt the NOPR proposal to establish a conditional
federal right of first refusal based on joint ownership.  The draft final rule explains that the
Commission will continue to consider the NOPR proposal and potential federal right of first
refusal issues in other proceedings. 
Another NOPR proposal that the draft final rule does not adopt is the proposal to limit the
availability of the construction work in progress (or “CWIP”) incentive.  The draft final rule
explains that any action on the CWIP incentive is more appropriately considered in a separate
proceeding to allow for a holistic approach to transmission incentives.
Finally, the draft final rule requires transmission providers to revise their interregional
transmission coordination processes to reflect the long-term regional transmission planning
reforms adopted in the draft final rule. 
The draft final rule will be effective 60 days from publishing in the Federal Register.  It requires
that each transmission provider submit a compliance filing within ten months of the effective
date of the draft final rule for most draft final rule requirements, but provides for a compliance

filing within twelve months of the effective date of the draft final rule for the interregional
transmission coordination requirements.
Thank you, this concludes our presentation.  We are happy to address any questions.

Contact Information
News Media
Email: [email protected]

This page was last updated on May 14, 2024


File Typeapplication/pdf
File TitleStaff Presentation | Building for the Future Through Electric Regional Transmission Planning and Cost Allocation | Federal Energ
File Modified2024-06-14
File Created2024-06-14

© 2024 OMB.report | Privacy Policy