Information Collection Request

FERC-917/918: Electric Transmission Facilities (extension)

ICR 202409-1902-005 · OMB 1902-0233 · Received in OIRA

Forms and Documents

Forms and supporting documents for this ICR
DocumentTypeStatusAvailability
18 CFR 35.28.docx Supplementary Document Uploaded 2024-09-19 Repair queued
20240809-3021_Final_FERC-917 and 918 30 Day Notice.docx Supplementary Document Uploaded 2024-09-17 Repair queued
20240603-3044_Final_FERC-917 and 918 60-day Notice_6_3_2024.docx Supplementary Document Uploaded 2024-09-17 Repair queued
FERC 917_918 Fed Reg. June 7_24.pdf Supplementary Document Uploaded 2024-09-17 Repair queued
FERC 917_918 Fed Reg. Aug 15 24.pdf Supplementary Document Uploaded 2024-09-17 Missing upstream
Final_FERC-917_918_Supporting Statement_2024.docx Supporting Statement A Uploaded 2024-09-17 Repair queued
Pro Forma OATT-Att.pdf Supplementary Document Uploaded 2024-06-12 Repair queued
16 U.S.C. 824e.pdf Supplementary Document Uploaded 2022-05-06 Missing upstream

IC Document Collections

Information collection document groups
IC IDCollectionTypeStatusForm
268435 RM21-17: Sharing Information between planning regions Unchanged
268434 RM21-17: Evaluating Alternative Transmission Technologies (without OATT) Unchanged
268433 RM21-17: Evaluating Alternative Transmission Technologies (with OATT) Unchanged
268432 RM21-17: Revise the regional transmission planning process - Right-sizing transmission (with OATT) (One-time) Unchanged
268431 RM21-17: Revise the regional transmission planning process - Right-sizing transmission (without OATT) (One-Time)) Unchanged
268430 RM21-17: Revise the regional transmission planning process - Right-sizing transmission (without OATT) (Ongoing) Unchanged
253277 RM21-17: Consider in the regional transmission planning processes regional transmission facilities that address certain interconnection-related needs Unchanged
253275 RM21-17: Seek agreement from the states to establish a Long-Term Regional Transmission Cost Allocation Method and/or a State Agreement Process (Year 1) Unchanged
253274 RM21-17: Revise the regional transmission planning process - Right-sizing transmission (with OATT) (Ongoing)) Unchanged
253272 RM21-17: Revise OATT to comply with regional transmission planning process (One-Time)) Unchanged
253271 RM21-17: Participate in Long-Term Regional Transmission Planning (With OATT)) Unchanged
253270 RM21-17: Participate in Long-Term Regional Transmission Planning (Without OATT)) Unchanged
179057 FERC-918, Information to be Posted on the OASIS and Auditing Transmission Service Information (Standards) Modified
179056 FERC-917, Non-discriminatory Open Access Transmission Tariff Modified

ICR Details

Reginfo record details
table that charts list comparision
  Requested Previously Approved
36 Months From Approved 11/30/2024
1,016 1,016
470,354 460,969
0 0





table that charts list of burden
  Total Request Previously Approved Change Due to New Statute Change Due to Agency Discretion Change Due to Adjustment in Estimate Change Due to Potential Violation of the PRA
Annual Number of Responses 1,016 1,016 0 0 0 0
Annual Time Burden (Hours) 470,354 460,969 0 0 9,385 0
Annual Cost Burden (Dollars) 0 0 0 0 0 0