Download:
pdf |
pdfFederal Aviation
Administration
Memorandum
Date:
January 22, 2020
To:
Regional Airports Directors, 610 Managers, and ADO Managers
From:
Robert J. Craven, Director, Office of Airport Planning and Programming,
APP-1
Subject:
INFORMATION: PFC Update, PFC 73-20
PFC 73-20. Streamlined Procedures for Passenger Facility Charge (PFC)
Authorizations at Small-, Medium-, and Large-Hub Airports.
This PFC update letter provides Federal Aviation Administration (FAA) Airport District
Offices/Regional Offices (ADOs/ROs) with interim, internal guidance on processing
applications to impose and/or use PFCs received from small-, medium-, and large-hub
airports. The draft guidance in this letter applies to all PFC applications received after
January 22, 2020.
Section 121 of the Federal Aviation Administration (FAA) Reauthorization Act of 2018
(Pub. L. 115-254, October 5, 2018), as codified at 49 U.S.C. § 40117(l), authorizes FAA
to implement a pilot program to streamline processing of PFC authorizations to include
small-, medium-, and large-hub airports. FAA, through a public process, intends to
develop procedures for public agencies to follow in implementing this provision.
However, FAA recognizes the immediate need for expeditious processing of PFC
applications. Therefore, FAA is using this update guidance to implement Section 121
internally. This interim, internal implementation will streamline the review of PFC
applications for small-, medium-, and large-hub airports meeting eligible criteria.
This interim, internal guidance does not change the current PFC application procedures
that public agencies must follow. All applications must meet the requirements of 49
U.S.C. § 40117 and 14 CFR Part 158.
2
Applications and Projects Ineligible for Streamlining
All PFC applications received by FAA ADOs/ROs from small-, medium-, or largehub airports are to be processed using the streamlined procedures identified below
unless such applications are excluded in accordance with applicable PFC guidance.
Consistent with PFC Order 5500.1, Paragraph 1-16, applications involving the
following are ineligible for streamlined processing:
(a) Significant policy precedent;
(b) Significant legal issues, as determined by the FAA's Chief Counsel;
(c) Significant controversy, as evidenced by significant opposition to the FAA's
proposed action by the applicant or other airport authorities, airport users, Federal,
State or local agencies, elected officials, or communities;
(d) Multimodal projects; or
(e) Significant airport noise, access, or revenue diversion issues, including
compliance with 49 U.S.C. 47521 et seq. (the Airport Noise and Capacity Act of
1990 (ANCA) and 49 U.S.C. 47111(e) (Action on Grant Assurances Concerning
Airport Revenues)).
Additionally, the following types of projects tend to be unique and complex, and they
require more time for review, thus such projects are ineligible for streamlined processing:
(a) Debt Service on otherwise ineligible projects;
(b) Blending of two or more PFC decisions to obtain a uniform collection level;
(c) Terminal building projects in excess of $25 million, except stand-alone passenger
boarding bridges.1
FAA Procedures
General
The information below specifies the procedures the FAA ADO/RO must follow when
processing an application from a small-, medium-, or large-hub airport to impose a PFC
and/or to use PFC revenue on projects that do not meet one of the above exclusions.
Definitions
Small-, medium-, or large-hub airport means a commercial service airport (as
defined in 49 U.S.C. § 47102) that has 0.05 percent or greater of the passenger
boardings in the United States, in the prior calendar year, on aircraft in service in air
commerce.
1
The $25 million threshold of requested PFC funding is calculated as the sum of all terminal buildingrelated projects (except stand-alone passenger boarding bridges) contained in an application.
3
Procedures
(a) Review of Applications. FAA review of PFC applications submitted by small-,
medium-, and large-hub airports.
(1) The FAA ADO/RO will review the public agency’s application to determine that:
(A) There are no projects that meet one of the exclusions above.
(B) The amount and duration of the PFC will not result in revenue that
exceeds the amount necessary to finance the project(s).
(C) Each proposed project meets the project eligibility requirements of
14 CFR § 158.15. The project does not have to be reviewed for eligibility
and justification (§ 158.15(b) and (c)) if:
(1) a project is in an existing Airport Improvement Program (AIP) grant;
(2) there is no scope change to the project; and
(3) the requested PFC amount is only for the local match of the AIP
grant.
(D) Each project proposed at a PFC level above $3 meets the eligibility
requirement of 14 CFR § 158.17(a)(3).
(1) The ADO/RO should make the airside needs test determination after a
review of any available planning documents, airport inspection and
certification reports, and the Airport’s Capital Improvement Plan
(ACIP) (See PFC Order 5500.1, Par.10-8).
(E) Project costs are reasonable.
(F) All applicable airport layout plan, airspace, and environmental
requirements have been met for each project. No review is required if:
(1) a project is in an existing AIP grant;
(2) there is no scope change to the project; and
(3) the requested PFC amount is only for the local match of the AIP
grant.
(G) Any request by the public agency to exclude any class of carriers from
the requirement to collect the PFC is reasonable, not arbitrary,
nondiscriminatory, and otherwise complies with the law.
(H) The consultation and public comment processes complied with 14 CFR
§ 158.23 and § 158.24.
(I) The public agency is in compliance with:
(1) 49 USC § 47524 and § 47526 governing airport noise and access
restrictions;
4
(2) 49 USC § 47107(b) governing the use of airport revenue; and
(3) 49 USC § 47106(f) requirements for competition plans.
(2) Because of the short processing time of the streamlined procedures, the FAA
ADO/RO cannot request additional public comment through a Federal Register
notice for a streamlined PFC application.
(3) The FAA ADO/RO will indicate its findings on either the Attachment B or
Attachment H, as submitted by the public agency.
(4) Unlike the traditional PFC application process, the FAA ADO/RO is not required
to make a separate determination that an application reviewed under this
streamlined process is or is not substantially complete. The decision on the
application will fulfill this statutory function.
(5) The FAA ADO/RO may request supplemental information that has been
previously subject to the consultations required by 49 U.S.C. 40117(l)(2).
(6) Finally, the FAA ADO/RO will review all comments filed during the air carrier
consultation and public notice processes and consider them in issuing its
acknowledgement of the application as required by 49 U.S.C. 40117(l)(2).
(b) Acknowledgements. Within 30 days of receipt of the public agency's application, the
FAA ADO/RO will issue a written acknowledgment of the public agency's intent to
impose and/or use PFC revenue for the various projects.
(1) The FAA's acknowledgment may concur with all proposed projects, may object
(or partially object) to some of the proposed projects, or may object to the
application in its entirety.
(2) The FAA's acknowledgment will include the reason(s) for any objection(s).
(3) The FAA ADO/RO will respond to any disagreements resulting from the air
carrier or public notice processes in its acknowledgement letter.
(4) The FAA ADO/RO will issue an acknowledgement letter to the public agency
consistent with the latest approved template.
(5) An electronic copy of each acknowledgement letter must be uploaded into SOAR
as soon as possible after issuing the letter.
(6) As prescribed in 49 USC § 40117(l)(7), an FAA acknowledgment issued under
these procedures is not considered an order issued by the Secretary for purposes
of 49 USC § 46110 (Judicial Review).
5
(c) In accordance with 49 USC § 40117(l)(5), if the FAA ADO/RO does not issue its
acknowledgement letter within 30 days of receipt of the public agency’s application,
the public agency is authorized to impose the PFC as proposed in its application.
Data Collection
The FAA intends to collect data on the streamlined PFC process for a period of one year
after issuing this guidance. FAA will use this data to measure program efficiency and
effectiveness, and to inform future changes to the PFC program. This data will include,
but is not limited to, the following:
•
•
•
•
•
•
•
Number of small, medium, and large hubs streamlined applications
Streamlined application average processing time
Streamlined application average dollar amount
Number of traditional applications
Traditional application average processing time
Traditional application average dollar amount
Number of terminal projects processed through the traditional application process
If you have any questions on any of the above information, please contact APP-510 at
(202) 267-8375 for further information.
File Type | application/pdf |
File Title | P F C Update 73-20. Streamlined Procedures for Passenger Facility Charge (PFC) Authorizations at Small-, Medium , and Large-Hub |
Author | Federal Aviation Administration Airports Financial Assistance (2 |
File Modified | 2020-01-22 |
File Created | 2020-01-22 |