SUPPORTING STATEMENT – PART A


Defense Federal Acquisition Regulation Supplement (DFARS)

Information Collection in Support of the DoD Acquisition Process (Various Miscellaneous Requirements); OMB Control Number 0704-0187


Summary of Changes from Previously Approved Collection


  • Decrease in burden due to the removal from this information collection of the solicitation provision at DFARS 252.209-7002, Disclosure of Ownership or Control by a Foreign Government, and the contract clause at DFARS 252.209-7004, Subcontracting with Firms That Are Owned or Controlled by the Government of Country that is a State Sponsor of Terrorism.


  • Reduction in respondents for the clause at DFARS 252.235-7003.


1. Need for the Information Collection

This is a request for revision and renewal of the information collection requirements currently approved under OMB Control Number 0704-0187. These Defense Federal Acquisition Regulation Supplement (DFARS) solicitation provisions and contract clauses implement 10 U.S.C. 2354. The information collection requirements are as follows:

a. DFARS 252.208-7000, Intent to Furnish Precious Metals as Government-Furnished Material, paragraphs (b) and (c). This contract clause is prescribed at DFARS 208.7305(a) for use in solicitations and contracts exceeding the simplified acquisition threshold except when the contracting officer has determined that the required precious metals are not available from the Defense Supply Center, Philadelphia (DSCP), or when the contracting officer knows that the items being acquired do not require precious metals in their manufacture. The clause requires contractors to use the clause in subcontracts and purchase orders, unless the contractor knows that the item being purchased does not contain precious metals. Paragraph (b) requires offerors to cite the type and quantity of precious metals required in performance of the contracts, and the national stock number and nomenclature, if known, of the deliverable item requiring precious metals. Paragraph (c) requires offerors to submit two prices for each deliverable item which contains precious metals — one based on the Government furnishing the precious metals, the other based on the contractor furnishing the precious metals.


b. DFARS 252.235-7000, Indemnification Under 10 U.S.C. 2354–Fixed Price, paragraph (f) and DFARS 252.235-7001, Indemnification Under 10 U.S.C. 2354–Cost-Reimbursement, paragraph (e). These clauses are prescribed at DFARS 235.070-3 for use in solicitations and contracts when the contractor is to be indemnified against unusually hazardous risks in accordance with DFARS 235.070-1. Paragraphs (f) and (e), respectively, require contractors to notify the contracting officer of any claim and provide (i) proof or evidence of a claim, and (ii) copies of all pertinent papers when the contractor is to be indemnified.

c. DFARS 252.235-7003, Frequency Authorization, paragraph (b). This clause is prescribed at DFARS 235.072(b) for use in solicitations and contracts for developing, producing, constructing, testing, or operating a device requiring frequency authorization. Paragraph (b) requires that the contractor or subcontractor provide to the contracting officer the technical operating characteristics for any experimental, developmental, or operational equipment for which the appropriate frequency allocation has not been made.

d. DFARS 252.209-7002, Disclosure of Ownership or Control by a Foreign Government, paragraph (c). This provision is prescribed at DFARS 209.104-70 for use in solicitations when access to proscribed information is necessary for contract performance. Paragraph (c) requires an offeror to disclose and provide additional information to the Government if a foreign government has a controlling interest in the offeror, or in a parent company of which the offeror is a subsidiary. The DFARS solicitation provision at 252.204-7007 Alternate A, Annual Representations and Certifications, includes the provision at 252.209-7002, Disclosure of Ownership or Control by a Foreign Government. The annual representations and certifications are in the System for Award Management (SAM) and the associated burdens are covered by OMB Control Number 9000-0189. Therefore, the provision at DFARS 252.209-7002 is being removed from OMB Control Number 0704-0187.


e. DFARS 252.209-7004, Subcontracting with Firms That Are Owned or Controlled by the Government of Country that is a State Sponsor of Terrorism, paragraph (b). This clause is prescribed at DFARS 209.409 for use in solicitations and contracts with a value of $150,000 or more. Paragraph (b) requires the contractor to notify the contracting officer in writing before entering into a subcontract in excess of $35,000 with a party that is identified in the SAM Exclusions as being ineligible for award of Defense contracts or subcontracts because it is owned or controlled by the government of a country that is a state sponsor of terrorism. The contractor must provide the name of the proposed subcontractor and the compelling reasons for doing business with the subcontractor. .Such a disclosure is expected to be made very rarely, i.e., by fewer than 10 respondents per year. Therefore, the contract clause at DFARS 252.209-7004 is being removed from this information collection.


2. Use of the Information


This information is used by Government contracting officers as follows:


a. DFARS 252.208-7000(b) and (c). The information is used to determine whether to provide precious metals as Government-furnished material.


b. DFARS 252.235-7000(f) and DFARS 252.235-7001(e). This information is used to evaluate claims of indemnification for losses or damages occurring under a research and development contract.


c. DFARS 252.235-7003(b). This information is used to keep track of radio frequencies on electronic equipment under research and development contracts so that the user does not override or interfere with the use of that frequency by another user.


3. Use of Information Technology


Information technology is used approximately 100% of the time to reduce burden.


4. Non-duplication


The information obtained through this collection is unique and is not already available for use or adaptation from another cleared source.


5. Burden on Small Business


The collections associated with small businesses are the minimum consistent with applicable laws, regulations, and prudent business practices.


6. Less Frequent Collection


The frequency for collecting this information was reviewed by the DoD specialists who are most knowledgeable of the requirements and the need for the information. This information is collected in response to individual solicitations or contracts. Collecting this information less frequently would impede contracting officers from making informed contract-award and contract administration decisions.


7. Paperwork Reduction Act Guidelines


This collection of information does not require collection to be conducted in a manner inconsistent with the guidelines delineated in 5 CFR 1320.5(d)(2).


8. Consultation and Public Comments


a. Public Notice


i. A 60-day notice for the collection was published in the Federal Register on June 27, 2024, at 89 FR 53591. No public comments were received during the 60-day comment period.


ii. A 30-day notice for the collection was published in the Federal Register on September 27 2024, at 89 FR 79261.


b. Consultation


Subject matter experts within DoD were consulted regarding the renewal and revision of this information collection.


9. Gifts or Payment


No payments or gifts are being offered to respondents as an incentive to participate in the collection, other than remuneration to contractors under their contracts.



10. Confidentiality


This information is disclosed only to the extent consistent with prudent business practices and current regulatory, statutory, and Freedom of Information Act requirements. No assurance of confidentiality is provided to respondents. A Privacy Act Statement is not required for this collection because DoD is not requesting individuals to furnish personal information for a system of records. A System of Record Notice (SORN) is not required for this collection because records are not retrievable by personally identifiable information (PII). A Privacy Impact Assessment (PIA) is not required for this collection because PII is not being collected electronically.


11. Sensitive Questions


No questions considered sensitive are being asked in this collection.


12. Respondent Burden and its Labor Costs


The estimated respondent burdens and labor costs associated with the information collections covered under OMB Control Number 0704-0187 are shown in the tables below. These estimates are based on recent data available in the Federal Procurement Data System (FPDS) for DoD contract actions, DoD’s Electronic Data Access (EDA) application, and consultations with DoD subject matter experts.


a. DFARS 252.208-7000(b) and (c). The following is a summary of the estimated annual burden for offerors to cite the type and quantity of precious metals required in performance of the contracts and to submit two prices for each deliverable item which contains precious metals — one based on the Government furnishing the precious metals, the other based on the contractor furnishing the precious metals.


1. Estimation of Respondent Burden


Based on fiscal year (FY) 2019 and FY 2020 data from the Defense Logistics Agency, DoD estimates that 10 contractors will receive precious metals under this clause in approximately 38 different shipments in a year. DoD estimates there will be twice as many respondents as contractors receiving shipments (10 x 2 = 20), because responses are required from all offerors, not only those who are awarded contracts and ultimately receive a shipment. DoD also estimates that the number of solicitations equals the number of shipments (38); i.e., each solicitation results in a contract under which precious metals are shipped to the contractor. DoD further estimates there are four responses per solicitation (38 x 4 = 152) and that each response takes one hour to prepare and submit.


Estimation of Respondent Burden: DFARS 252.208-7000(b) and (c)

Number of respondents

20

Number of responses per respondent

7.60

Number of total annual responses

152

Hours per response

1

Annual Respondent burden hours

152


2. Labor Cost of Respondent Burden


The fully burdened rate per hour is $48, based on the OPM GS-11, step 5, base hourly rate for 2024 ($39.40) plus the 36.25% civilian personnel full fringe benefit rate from OMB Memo M-08-13, rounded to the nearest dollar ($54). The OPM rate used includes locality pay area for the rest of the U.S.


Labor Cost of Respondent Burden: 252.208-7000(b) and (c)

Number of total annual responses

152

Hours per response

1

Cost per hour (hourly wage)

$54

Labor burden per response

$54

Annual Labor Burden

$8,208


b. DFARS 252.235-7000(f) and 252.235-7001(e). The following is a summary of the estimated annual burden for contractors to notify the contracting officer of any claim and provide (i) proof or evidence of a claim, and (ii) copies of all pertinent documents when the contractor is to be indemnified.


1. Estimation of Respondent Burden


Based on information from EDA for FY 2023 and specialists responsible for reviewing and processing claims under the requirements of these clauses, DoD estimates approximately 50 contractors may file an applicable claim, however, there has not been more than one claim per year. In order to keep the information collection in an active state, DoD has used 10 respondents and 1 response for each clause, for a total of 20 respondents and 20 responses. The contractor should already have the information available, as the same information is necessary to answer suits filed against them by a third party. DoD has estimated 1 hour per response to prepare and submit the information.


Estimation of Respondent Burden: DFARS 252.235-7000(f)/-7001(e)

Number of respondents

20

Number of responses per respondent

1

Number of total annual responses

20

Hours per response

1

Annual respondent burden hours

20


2. Labor Cost of Respondent Burden


The fully burdened rate per hour is $54, based on the OPM GS-11, step 5, base hourly rate for 2024 ($39.40) plus the 36.25% civilian personnel full fringe benefit rate from OMB Memo M-08-13, rounded to the nearest dollar ($54). The OPM rate used includes locality pay area for the rest of the U.S.


Labor Cost of Respondent Burden: 252.235-7000(f)/-7001(e)

Number of total annual responses

20

Hours per response

1

Cost per hour (hourly wage)

$54

Labor burden per response

$54

Annual Labor Burden

$1,080


c. DFARS 252.235-7003(b). The following is a summary of the estimated annual burden for contractors or subcontractors provide to the contracting officer the technical operating characteristics for any experimental, developmental, or operational equipment for which the appropriate frequency allocation has not been made.


1. Estimation of Respondent Burden


According to EDA, in FY 2023 there were 35 contracts that would require approval to use a radio frequency. DoD estimates that it will take the contractor approximately 2 hours to prepare and submit the required information.


Estimation of Respondent Burden Hours: DFARS 252.235-7003(b)

Number of respondents

35

Number of responses per respondent

1

Number of total annual responses

35

Hours per response

2

Annual respondent burden hours

70


2. Labor Cost of Respondent Burden


The fully burdened rate per hour is $54, based on the OPM GS-11, step 5, base hourly rate for 2021 ($39.40) plus the 36.25% civilian personnel full fringe benefit rate from OMB Memo M-08-13, rounded to the nearest dollar ($54). The OPM rate used includes locality pay area for the rest of the U.S.


Labor Cost of Respondent Burden: 252.235-7003

Number of total annual responses

35

Hours per response

2

Cost per hour (hourly wage)

$54

Labor burden per response

$108

Annual Labor Burden

$3,780


d. Total Respondent Burden for OMB Control Number 0704-0187


1. Total Submission Burden

The total estimated burden hours for OMB Control Number 0704-0187 is provided in the following table:

Estimation of Respondent Burden Hours: OMB Control Number 0704-0187

Total number of respondents

75

Total number of annual responses

207

Total burden hours

242


2. Overall Labor Burden


The total estimated labor cost of the respondent burden for OMB Control Number 0704-0187 is provided in the following table:


Labor Cost of Respondent Burden: OMB Control Number 0704-0187

Total number of annual responses

207

Annual Labor Burden

$13,068


13. Respondent Costs Other Than Burden Hour Costs


There are no annualized costs to respondents other than the labor burden costs addressed in Section 12 of this document to complete this collection.


14. Cost to the Federal Government


a. Labor Cost to the Federal Government


The estimated Government burden hours and labor costs associated with the information collections covered under OMB Control Number 0704-0187 are summarized in the table below. These estimates are based on consultations with DoD subject matter experts.


1. DFARS 252.208-7000(b) and (c)


Labor Cost to the Federal Government: 252.208-7000(b) and (c)

Number of total annual responses

152

Hours per response

0.5

Cost per hour (hourly wage)

$54

Cost per response

$27

Total cost

$4,104


2. DFARS 252.235-7000(f) and 252.235-7001(e)


Labor Cost to the Federal Government: 252.235-7000(f)/-7001(e)

Number of total annual responses

20

Hours per response

1

Cost per hour (hourly wage)

$54

Cost per response

$54

Total Cost

$1,080


3. DFARS 252.235-7003(b).


Labor Cost to the Federal Government: 252.235-7003

Number of total annual responses

35

Hours per response

2

Cost per hour (hourly wage)

$54

Cost per response

$108

Total Cost

$3,780


4. Total Government Burden for OMB Control Number 0704-0187


Overall Labor Burden to the Federal Government: OMB Control Number 0704-0187

Total number of annual responses

207

Total Labor Burden

$8,964



b. Operational and Maintenance Costs


There are no operational and maintenance costs to the Government associated with this information collection.


c. Total Cost to the Federal Government


Total labor burden

$8,964

Total operational and maintenance costs

$0

Total cost to the Federal Government

$8,964


15. Reasons for Change in Burden


The burden has decreased since the previous approval as a result of the removal of the burden associated with a solicitation provision that is already covered by OMB Control Number 9000-0189 and a contract clause for which there are fewer than 10 respondents per year. In addition, more recent and accurate data has been obtained and current labor rates have been used.


0704-0187

Change in Burden

2021

2024

Difference

Number of respondents

469

75

-394

Total annual responses

601

207

-394

Total Hours

1,010

242

-768

Cost per hour

$48

$54

$6

Total Cost

$48,480

$13,068

-$35,412


16. Publication of Results


Results of this information collection will not be published.


17. Non-Display of OMB Expiration Date


DoD is not seeking approval to omit the display of the expiration date of the OMB approval on the collection instrument.


18. Exceptions to “Certification for Paperwork Reduction Submissions”


DoD is not requesting any exemptions to the provisions stated in 5 CFR 1320.9.


Page 13 of 13

File Typeapplication/vnd.openxmlformats-officedocument.wordprocessingml.document
AuthorJohnson, Jennifer D CIV OSD OUSD A-S (USA)
File Modified0000-00-00
File Created2024-09-28

© 2024 OMB.report | Privacy Policy