Implementation Plan

2023-03 Implementation Plan FB clean.pdf

FERC-725B, NOPR in RM24-7, Adding Voluntary Requests for Cybersecurity Incentives to Mandatory Reliability Standards for Critical Infrastructure Protection

Implementation Plan

OMB: 1902-0248

Document [pdf]
Download: pdf | pdf
Implementation Plan

Project 2023-03 Internal Network Security Monitoring (INSM)
Reliability Standard CIP-015-1
Applicable Standard(s)
•

CIP-015-1 – Cyber Security – Internal Network Security Monitoring

Requested Retirement(s)
•

None

Applicable Entities
•

Balancing Authority

•

Distribution Provider 1

•

Generator Operator

•

Generator Owner

•

Reliability Coordinator

•

Transmission Operator

•

Transmission Owner

Background

On January 19, 2023, the Federal Energy Regulatory Commission (FERC) issued Order No. 887
directing NERC to develop requirements within the Critical Infrastructure Protection (CIP) Reliability
Standards for INSM of all high-impact Bulk Electric System (BES) Cyber Systems and medium impact
BES Cyber Systems with External Routable Connectivity (ERC) 2. INSM permits entities to monitor
traffic within a trusted zone, such as the Electronic Security Perimeter, to detect intrusions or
malicious activity. Specifically, Order No. 887 directs NERC to develop Reliability Standard(s)
requirement(s) for any new or modified CIP Reliability Standards that address three security issues.

1 See Applicability Section of Revised CIP Standards and Definitions for additional information on Distribution Providers subject to

the standards.
2 Internal Network Security Monitoring for High and Medium Impact Bulk Electric System Cyber Systems, Order No. 887, 182 FERC ¶
61,021 (2023).
2 Id. P 5. (Order No. 887 provides that any new or modified CIP Reliability Standards should: (1) address the need for responsible
entities to develop baselines of their network traffic inside their CIP-networked environment; (2) address the need for responsible
entities to monitor for and detect unauthorized activity, connections, devices, and software inside the CIP-networked environment)
and (3) require responsible entities to identify anomalous activity to a high level of confidence by logging network traffic,
maintaining logs and other data collected regarding network traffic, and implementing measures to minimize the likelihood of an
attacker removing evidence of their tactics, techniques, and procedures from compromised devices).

RELIABILITY | RESILIENCE | SECURITY

In Order No. 887, FERC directs NERC to submit these revisions for approval within 15 months of the
final rule’s effective date, i.e., July 9, 2024.
Order No. 887 also directed NERC to conduct a study on the risks of lack of INSM for medium impact
BES Cyber Systems without ERC, and all low-impact BES Cyber Systems, and on the challenges and
solutions for implementing INSM for those BES Cyber Systems. NERC has completed this study, and
it was filed with FERC on January 18, 2024.

General Considerations

This implementation plan reflects consideration that entities will need time to develop and
implement Requirements R1, R2, and R3. In order to achieve the objectives of the requirements, all
affected Responsible Entities may need to: (1) procure sensors to facilitate the gathering of network
data for applicable networks, taking into consideration the availability of products and services by a
relatively small vendor marketplace and supply chain challenges; (2) make modifications to
networks to better align with the standard; (3) deploy technical solutions to gather network
information, which could require outages of operational facilities, which can be challenging to
schedule; and (4) implement capabilities to ingest large amounts of network information and
perform the necessary analysis. This phased implementation plan is intended to provide additional
time to fully comply with Reliability Standard CIP-015-1, prioritizing that the most critical networks,
such as Control Centers, are addressed first.

Effective Date and Phased-In Compliance Dates

The effective dates for the proposed Reliability Standard are provided below. Where the standard
drafting team identified the need for a longer implementation period for compliance with a
particular section of a proposed Reliability Standard (i.e., an entire Requirement or a portion
thereof), the additional time for compliance with that section is specified below.
Reliability Standard – CIP-015-1 Internal Network Security Monitoring

Where approval by an applicable governmental authority is required, the standard shall become
effective on the first day of the first calendar quarter that is thirty-six (36) months after the effective
date of the applicable governmental authority’s order approving the standard, or as otherwise
provided for by the applicable governmental authority.
Where approval by an applicable governmental authority is not required, the standard shall become
effective on the first day of the first calendar quarter that is thirty-six (36) months after the date the
standard is adopted by the NERC Board of Trustees, or as otherwise provided for in that jurisdiction.
Compliance Date for – CIP-015-1 Internal Network Security Monitoring

All Responsible Entities with applicable systems located at Control Centers and backup Control
Centers identified pursuant to CIP-002-5.1(a) Requirement R1 Parts 1.1. and 1.2. shall initially
comply with the requirements in CIP-015-1 for those Control Centers upon the effective date of
Reliability Standard CIP-015-1. This implementation timeframe recognizes the increased reliability
risk posed by high impact BES Cyber Systems, Control Centers, and backup Control Centers. It
Implementation Plan
Project 2023-03 Internal Network Security Monitoring | April 2024

2

further accommodates for the challenges posed by the limited pool of vendors, time required to
identify and implement data feeds, the analysis of results and necessary testing, and adjustments
for the implementation of INSM.
All Responsible Entities with applicable systems located at medium impact BES Cyber Systems with
External Routable Connectivity, with the exception of Control Centers and backup Control Centers
discussed above, shall be required to apply CIP-015-1 within 24 calendar months after the effective
date of Reliability Standard CIP-015-1. This phased-in implementation allows for the prioritization of
high impact BES Cyber Systems, Control Centers, and backup Control Centers, discussed above,
which pose the greatest risk to reliability. It further balances the limited resources, such as available
vendors and the added complexity posed by bringing medium impact BES Cyber Systems with
External Routable Connectivity into compliance, e.g., increased number of widely separated systems
with varying capabilities and connectivity, some power plants may require scheduled outages or
upgrades prior to implementing, as well as longer design and testing periods to alleviate risks to
generating assets.

Implementation Plan
Project 2023-03 Internal Network Security Monitoring | April 2024

3

