FERC-537, Gas Pipeline Certificates: Construction, Acquisition and Abandonment
Revision of a currently approved collection
No
Regular
10/21/2026
table that charts list comparision
Requested
Previously Approved
11/30/2027
11/30/2027
443
444
48,395
49,091
0
0
The FERC 537 collection includes the requirements to obtain FERC approval for construction, aquisition, or abandonment of natural gas pipelines. Under the Natural Gas Act (NGA) a natural gas company must obtain FERC authorization to engage in the transportation of natural gas in interstate commerce, to undertake the construction or extension of any facilities, or to acquire or operate any such facilities or extensions in accordance with sSection 7(c) of the NGA. A natural gas company must also obtain FERC approval under sSection 7(b) of the NGA prior to abandoning any jurisdictional facility or service. Under the Natural Gas Policy Act (NGPA) (Public Law 96-621) interstate pipelines must also obtain FERC authorization for certain transportation arrangements. If a certificate is granted, the natural gas company can engage in the interstate transportation of natural gas and construct, acquire, or operate facilities. Conversely, approval of an abandonment application permits the pipeline to cease service and discontinue the operation of such facilities. Authorization under NGPA Section 311(a) allows the interstate or intrastate pipeline applicants to render certain transportation services.
In this Notice of Proposed Rulemaking (NOPR), the Commission proposes to amend its regulations to establish procedures for authorizing activities at liquefied natural gas (LNG) plants without the need for operators to file case-specific applications or for the Commission to issue case-specific orders under sections 3 or 7 of the Natural Gas Act (NGA).1 This NOPR includes proposed revisions to Parts 2, 153, and 375 of the Commissionâs regulations. The proposal includes the creation of an LNG blanket program allowing the automatic or prior notice authorization for certain activities.
In this Notice of Proposed Rulemaking (NOPR), the Commission proposes to amend its regulations to establish procedures for authorizing activities at liquefied natural gas (LNG) plants without the need for operators to file case-specific applications or for the Commission to issue case-specific orders under sections 3 or 7 of the Natural Gas Act (NGA).1 This NOPR includes proposed revisions to Parts 2, 153, and 375 of the Commissionâs regulations. The proposal includes the creation of an LNG blanket program allowing the automatic or prior notice authorization for certain activities. This proposed rule would reduce the reporting burden because it expands exemptions to submitting a full application, as a result, there would be more entities that would not need to submit full applications and they would either submit abbreviated fillings or only report activities on an annual report (already required). The other changes to the ICs are due to FERC revising our approach to documenting the reporting burden so that it more clearly matches to regulatory requirements.
$860,416
No
No
No
No
No
No
No
Chrystal Martin 202 502-6043
Reginfo record details
No
On behalf of this Federal agency, I certify that the collection of information encompassed by this request complies with 5 CFR 1320.9 and the related provisions of 5 CFR 1320.8(b)(3).
The following is a summary of the topics, regarding the proposed collection of information, that the certification covers:
(i) Why the information is being collected;
(ii) Use of information;
(iii) Burden estimate;
(iv) Nature of response (voluntary, required for a benefit, or mandatory);
(v) Nature and extent of confidentiality; and
(vi) Need to display currently valid OMB control number;
If you are unable to certify compliance with any of these provisions, identify the item by leaving the box unchecked and explain the reason in the Supporting Statement.