This ICR is
approved for three years. Before resubmission of this ICR for
extension, the agency should revisit the estimate of the number of
respondents and demonstrate to OMB that the estimates are
consistent with agency experience. In addition, the agency should
revise wage estimates to reflect guidance provided by EPA and/or
OMB, especially with respect to appropriate calculation of wage
overhead. The agency should respond to public comment received,
specifically addressing the suggestion that burden reduction may be
achieved by allowing visual inspection of fabric filters instead of
performance tests.
Inventory as of this Action
Requested
Previously Approved
04/30/2003
04/30/2003
01/31/2000
121
0
72
250
0
107
0
0
0
Owners or operators of subject
facilities must notify EPA of construction, reconstruction,
modification, anticipated and actual startup, dates, and must
provide both notification of and the results of performance tests.
Records must be maintained of the performance test results,
startups, shutdowns, and malfunctions to ensure compliance with the
standards.
On behalf of this Federal agency, I certify that
the collection of information encompassed by this request complies
with 5 CFR 1320.9 and the related provisions of 5 CFR
1320.8(b)(3).
The following is a summary of the topics, regarding
the proposed collection of information, that the certification
covers:
(i) Why the information is being collected;
(ii) Use of information;
(iii) Burden estimate;
(iv) Nature of response (voluntary, required for a
benefit, or mandatory);
(v) Nature and extent of confidentiality; and
(vi) Need to display currently valid OMB control
number;
If you are unable to certify compliance with any of
these provisions, identify the item by leaving the box unchecked