10 CFR 52 establishes requirements for
the granting of early site permits, certifications of standard
nuclear power plant designs, and licenses which combine in a single
license a construction permit, and an operating license with
conditions (combined licenses), manufacturing licenses, standard
design approvals, and pre-application reviews of site suitability
issues. Part 52 also establishes requirements for renewal of those
approvals, permits, certifications, and licenses; amendments to
them; exemptions from certifications; and variances from early site
permits.
On behalf of this Federal agency, I certify that
the collection of information encompassed by this request complies
with 5 CFR 1320.9 and the related provisions of 5 CFR
1320.8(b)(3).
The following is a summary of the topics, regarding
the proposed collection of information, that the certification
covers:
(i) Why the information is being collected;
(ii) Use of information;
(iii) Burden estimate;
(iv) Nature of response (voluntary, required for a
benefit, or mandatory);
(v) Nature and extent of confidentiality; and
(vi) Need to display currently valid OMB control
number;
If you are unable to certify compliance with any of
these provisions, identify the item by leaving the box unchecked
and explain the reason in the Supporting Statement.