Subcontracting Policies and Procedures -- DoD FAR Supplement Part 244

ICR 201703-0704-005

OMB: 0704-0253

Federal Form Document

Forms and Documents
Document
Name
Status
Supporting Statement A
2017-03-29
IC Document Collections
ICR Details
0704-0253 201703-0704-005
Historical Active 201401-0704-008
DOD/DODDEP
Subcontracting Policies and Procedures -- DoD FAR Supplement Part 244
Revision of a currently approved collection   No
Regular
Approved without change 05/30/2017
Retrieve Notice of Action (NOA) 03/31/2017
  Inventory as of this Action Requested Previously Approved
05/31/2020 36 Months From Approved 05/31/2017
72 0 90
576 0 1,440
26,496 0 53,280

DFARS clause 252.244-7001 requires the contractor to respond within 30 days to the administrative contracting officer’s initial determination of a contractor purchasing system deficiency. The administrative contracting officer, in turn, evaluates the contractor’s response and issues a final determination either approving or disapproving the contractor’s system. If the administrative contracting officer disapproves the contractor’s system, the contractor has 45 days to either correct the significant deficiencies or submit an acceptable corrective action plan.

US Code: 41 USC 421 Name of Law: null
  
None

Not associated with rulemaking

  81 FR 93907 12/22/2016
82 FR 15192 03/27/2017
No

1
IC Title Form No. Form Name
Subcontracting Policies and Procedures -- DoD FAR Supplement Part 244

  Total Approved Previously Approved Change Due to New Statute Change Due to Agency Discretion Change Due to Adjustment in Estimate Change Due to Potential Violation of the PRA
Annual Number of Responses 72 90 0 0 -18 0
Annual Time Burden (Hours) 576 1,440 0 0 -864 0
Annual Cost Burden (Dollars) 26,496 53,280 0 0 -26,784 0
No
No
The revisions to the change in burden are based on data obtained from subject matter experts at Defense Contract Management Agency (DCMA) responsible for conducting purchasing system reviews and an analysis of the impact of corrective action plans implemented by the contractors. Specifically, contracting officer determinations are required only to the extent that the contractor’s purchasing system is found to contain significant deficiencies. Accordingly, the need for information collection decreases as contractor purchasing systems improve and gain contracting officer approval. The cost per hour is based on the Office of Personnel Management (OPM) General Schedule (GS) 12 employee hourly rate versus the previous burden estimates based on a GS-11 employee. DCMA subject matter experts state that workload is primarily administered by individuals at the GS-12 level.

$3,312
No
No
No
No
No
Uncollected
Jennifer Hawes 571 372-6115 [email protected]

  No

On behalf of this Federal agency, I certify that the collection of information encompassed by this request complies with 5 CFR 1320.9 and the related provisions of 5 CFR 1320.8(b)(3).
The following is a summary of the topics, regarding the proposed collection of information, that the certification covers:
 
 
 
 
 
 
 
    (i) Why the information is being collected;
    (ii) Use of information;
    (iii) Burden estimate;
    (iv) Nature of response (voluntary, required for a benefit, or mandatory);
    (v) Nature and extent of confidentiality; and
    (vi) Need to display currently valid OMB control number;
 
 
 
If you are unable to certify compliance with any of these provisions, identify the item by leaving the box unchecked and explain the reason in the Supporting Statement.
03/31/2017


© 2024 OMB.report | Privacy Policy