Subcontracting Policies and Procedures -- DoD FAR Supplement Part 244

ICR 202005-0704-006

OMB: 0704-0253

Federal Form Document

Forms and Documents
Document
Name
Status
Supporting Statement A
2020-05-28
IC Document Collections
ICR Details
0704-0253 202005-0704-006
Active 201703-0704-005
DOD/DODDEP
Subcontracting Policies and Procedures -- DoD FAR Supplement Part 244
Revision of a currently approved collection   No
Regular
Approved without change 07/27/2020
Retrieve Notice of Action (NOA) 05/29/2020
  Inventory as of this Action Requested Previously Approved
07/31/2023 36 Months From Approved 07/31/2020
44 0 72
352 0 576
19,980 0 26,496

DFARS clause 252.244-7001 requires the contractor to respond within 30 days to the administrative contracting officer’s initial determination of a contractor purchasing system deficiency. The administrative contracting officer, in turn, evaluates the contractor’s response and issues a final determination either approving or disapproving the contractor’s system. If the administrative contracting officer disapproves the contractor’s system, the contractor has 45 days to either correct the significant deficiencies or submit an acceptable corrective action plan.

US Code: 41 USC 1303 Name of Law: OFPP Statute
  
None

Not associated with rulemaking

  85 FR 16330 03/23/2020
85 FR 23023 05/28/2020
No

1
IC Title Form No. Form Name
Subcontracting Policies and Procedures -- DoD FAR Supplement Part 244

  Total Approved Previously Approved Change Due to New Statute Change Due to Agency Discretion Change Due to Adjustment in Estimate Change Due to Potential Violation of the PRA
Annual Number of Responses 44 72 0 0 -28 0
Annual Time Burden (Hours) 352 576 0 0 -224 0
Annual Cost Burden (Dollars) 19,980 26,496 0 0 -6,516 0
No
No
Revisions to the estimated burden are based on a program change, which increased the contractor purchasing system review (CPSR) threshold. This change was published an December 31, 2019, at 84 FR 72247, and raised the CPSR threshold from $25 to $50 million. In addition, updated actual data was obtained from subject matter experts at DCMA responsible for conducting purchasing system reviews and an analysis of the impact of corrective action plans implemented by the contractors. Contracting officer determinations are required only to the extent that the contractor’s purchasing system is found to contain significant deficiencies. The need for contractor purchasing system reviews will decrease as a result of the increased threshold, reducing the number of contracting officer determinations. The need for information collection decreases as contractors fall below the new threshold and no longer need to maintain an approved system. The hourly rate is based on GS-12 step 5 for 2020 vice 2016 for the previous burden estimate. DCMA subject matter experts state that workload is primarily administered by individuals at the GS-12 level.

$2,497
No
    No
    No
No
No
No
No
Jennifer Hawes 571 372-6115 [email protected]

  No

On behalf of this Federal agency, I certify that the collection of information encompassed by this request complies with 5 CFR 1320.9 and the related provisions of 5 CFR 1320.8(b)(3).
The following is a summary of the topics, regarding the proposed collection of information, that the certification covers:
 
 
 
 
 
 
 
    (i) Why the information is being collected;
    (ii) Use of information;
    (iii) Burden estimate;
    (iv) Nature of response (voluntary, required for a benefit, or mandatory);
    (v) Nature and extent of confidentiality; and
    (vi) Need to display currently valid OMB control number;
 
 
 
If you are unable to certify compliance with any of these provisions, identify the item by leaving the box unchecked and explain the reason in the Supporting Statement.
05/29/2020


© 2024 OMB.report | Privacy Policy