Table 1 Index: Total Annual Respondent Burden and Cost | ||||||
Table | NSPS Standard(s) | Labor Hours | Annual Cost | |||
Table 1a | NSPS for Secondary Brass and Bronze Production (40 CFR Part 60, Subpart M) | 14 | $1,660 | |||
Table 1b | NSPS for Primary Copper Smelters (40 CFR Part 60, Subpart P); Primary Zinc Smelters (40 CFR Part 60, Subpart Q); and Primary Lead Smelters (40 CFR Part 60, Subpart R) | 1,554 | $180,000 | |||
Table 1c | NSPS for Primary Aluminum Reduction Plants (40 CFR Part 60, Subpart S) | 1,869 | $216,000 | |||
Table 1d | NSPS for Ferroalloy Production Facilities (40 CFR Part 60, Subpart Z) | 444 | $51,400 | |||
Total Cost | 3,880 | $449,000 | 47 | Hrs/response | ||
Total O&M Costs | $127,000 | |||||
Grand Total (Labor + O&M Costs) | $576,000 | |||||
Table 2 Index: Total Annual Burden and Cost for the Federal Government | ||||||
Table | NSPS Standard(s) | Labor Hours | Annual Cost | |||
Table 2a | NSPS for Secondary Brass and Bronze Production (40 CFR part 60, subpart M) | 0 | $0 | |||
Table 2b | NSPS for Primary Copper Smelters (40 CFR part 60, subpart P); Primary Zinc Smelters (40 CFR part 60, subpart Q); and Primary Lead Smelters (40 CFR part 60, subpart R) | 64 | $3,100 | |||
Table 2c | NSPS for Primary Aluminum Reduction Plants (40 CFR part 60, subpart S) | 156 | $8,090 | |||
Table 2d | NSPS for Ferroalloy Production Facilities (40 CFR part 60, subpart Z) | 18 | $887 | |||
Total Cost | 238 | $12,100 |
Table 1a: | Annual Respondent Burden and Cost for NSPS for Secondary Brass and Bronze Production | ||||||||||
(40 CFR part 60, Subpart M) (Renewal) | |||||||||||
0.869565 | $120.27 | $141.06 | $58.67 | ||||||||
REPORTING/RECORDKEEPING REQUIREMENT | (A) Respondent Hours per Occurence (Technical hours) |
(B) Number of Occurences per Respondent per Year |
(C) Hours per Respondent per Year (C=A x B) |
(D) Number of Respondents per Year a |
(E) Technical Hours per Year @ $120.27 (E=C x D) |
(F) Management Hours per Year @ $141.06 (F= E x 0.05) |
(G) Clerical Hours per Year @ $58.67 (G= E x 0.1) |
Total Labor Costs per Year b | |||
1. APPLICATIONS | N/A | ||||||||||
2. SURVEY AND STUDIES | N/A | ||||||||||
3. ACQUISITION, INSTALLATION, AND UTILIZATION OF TECHNOLOGY AND SYSTEMS | N/A | ||||||||||
4. REPORTING REQUIREMENTS | |||||||||||
A. Familiarize with rule requirements | 1 | 1 | 1 | 5 | 5 | 0.25 | 1 | $665.95 | |||
B. Required Activities | |||||||||||
Initial performance testc | 24 | 1 | 24 | 0 | 0 | 0 | 0 | $0 | |||
Repeat of Performance Test d | 24 | 0.2 | 4.8 | 0 | 0 | 0 | 0 | $0 | |||
Reference Method 5 or 9 e | 4 | 1.2 | 4.8 | 0 | 0 | 0 | 0 | $0 | |||
Monitoring of emissions and systems performance f | 0.5 | 365 | 182.5 | 0 | 0 | 0 | 0 | $0 | |||
C. Create Information | See 4B and 5E | ||||||||||
D. Gather Existing Information | See 4B and 5E | ||||||||||
E. Write Report | |||||||||||
Notification of actual startupc | 2 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | |||
Notification of initial performance test c | 2 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | |||
Notification of CMS e,f | 2 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | |||
Notification of anticipated date for conducting the opacity of observationse,f | 2 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | |||
Notification of modification/reconstruction | 2 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | |||
Semiannual reports of excess emissions and monitoring systems performanceg | 4 | 2 | 8 | 0 | 0 | 0 | 0 | $0 | |||
Subtotal for Reporting Requirements | 5.8 | Hours | $666 | ||||||||
5. RECORDKEEPING REQUIREMENTS | |||||||||||
A. Read and understand rule requirements | See 4A | ||||||||||
B. Plan Activities | See 4B | ||||||||||
C. Implement Activities | See 4B | ||||||||||
D. Develop Record System | N/A | ||||||||||
E. Time to Enter and Transmit Informationh | |||||||||||
Records of startups, shutdowns, malfunctions, etc. | 1.5 | 1 | 1.5 | 5 | 7.5 | 0.38 | 0.75 | $998.93 | |||
Records of emissions and systems performance | See 4B | ||||||||||
F. Time to Train Personnel | N/A | ||||||||||
G. Time for Audits | N/A | ||||||||||
Subtotal for Recordkeeping Requirements | 8.6 | Hours | $999 | ||||||||
TOTAL LABOR BURDEN AND COSTS j | 14 | Hours | $1,660 | ||||||||
TOTAL CAPITAL AND O&M COSTS (rounded) j | $0 | ||||||||||
GRAND TOTAL(rounded) j | $1,660 | ||||||||||
Assumptions: | |||||||||||
a We have assumed that are approximately 5 out of 11 secondary brass and bronze ingots production plants subject to NSPS Subpart M. We have further assumed that no new sources will become subject to the rule over the three year period of this ICR. | |||||||||||
b The labor rates are from the United States Department of Labor, Bureau of Labor Statistics, June 2019, “Table 2. Civilian Workers, by occupational and industry group.” The rates are from column 1, “Total compensation.” The rate has been increased by 110% to account for the benefit packages available to those employed by private industry. | |||||||||||
c Initial rule requirements would apply only to new sources. We have assumed that no new sources will become subject to the rule over the three year period of this ICR. | |||||||||||
d We have assumed that 20 percent of initial performance tests must be repeated due to failure. | |||||||||||
e Sources are required to use the following Reference Methods (RM) in conducting performance tests, if applicable: 1) RM 5 for particulate matter concentrations and volumetric flow rate of the effluent gas (all subparts); 2) RM 9 for visible emissions observations of opacity. | |||||||||||
f Section 60.11 of the General Provisions allows sources to use a continuous opacity monitor (COM) in lieu of Method 9 to determine compliance with the opacity standard. However, we have assumed that all sources are complying with the standard using RM 9. | |||||||||||
g Only existing sources using a continuous monitoring system (i.e., a COM or a continuous parameter monitoring system) are required to submit semiannual reports. Therefore, sources subject to NSPS subpart M are not required to submit semiannual reports. | |||||||||||
h Sources are required to maintain records of startups, shutdowns and malfunctions including periods where the continuous monitoring system is inoperative, and of emission test results, continuous monitoring system data including, performance test results and other data needed to determine compliance with mass and visible emission limits. | |||||||||||
i Totals have been rounded to 3 significant figures. Figures may not add exactly due to rounding. |
Table 1b: | Annual Respondent Burden and Cost for Primary Copper Smelters (40 CFR Part 60, Subpart P), Primary Zinc Smelters (40 CFR Part 60, Subpart Q), and Primary Lead Smelters (40 CFR Part 60, Subpart R) (Renewal) |
||||||||||
0.869565 | $120.27 | $141.06 | $58.67 | ||||||||
REPORTING/RECORDKEEPING REQUIREMENT | (A) Respondent Hours per Occurence (Technical hours) |
(B) Number of Occurences per Respondent per Year |
(C) Hours per Respondent per Year (C=A x B) |
(D) Number of Respondents per Year a |
(E) Technical Hours per Year @ $120.27 (E=C x D) |
(F) Management Hours per Year @ $141.06 (F= E x 0.05) |
(G) Clerical Hours per Year @ $58.67 (G= E x 0.1) |
Total Labor Costs per Year b | |||
1. APPLICATIONS | N/A | ||||||||||
2. SURVEY AND STUDIES | N/A | ||||||||||
3. ACQUISITION, INSTALLATION AND UTILIZATION OF TECHNOLOGY AND SYSTEMS |
N/A | ||||||||||
4. RECORDING REQUIREMENTS | |||||||||||
A. Familiarize with rule requirements | 1 | 1 | 1 | 7 | 7.0 | 0.35 | 0.70 | $932.33 | |||
B. Required Activities | |||||||||||
Initial performance test c | 24 | 1 | 24 | 0 | 0 | 0 | 0 | $0 | |||
Repeat of performance test d | 24 | 0.2 | 4.8 | 0 | 0 | 0 | 0 | $0 | |||
Reference Method 5 or 9 e | 4 | 1.2 | 4.8 | 0 | 0 | 0 | 0 | $0 | |||
Monitoring of emissions and operations f | 0.5 | 365 | 182.5 | 7 | 1277.5 | 63.88 | 127.75 | $170,150.23 | |||
C. Create Information | See 4B and 5E | ||||||||||
D. Gather Existing Information | See 4B and 5E | ||||||||||
E. Write Report | |||||||||||
Notification of actual startupc | 2 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | |||
Notification of initial performance test c | 2 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | |||
Performance test results c, f | 2 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | |||
Notification of CMS c,e,f | 2 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | |||
Notification of anticipated date for conduction the opacity of observations c,e,f | 2 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | |||
Notification of modification/reconstruction | 2 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | |||
Semiannual reports of excess emissions and monitoring systems performance g | 4 | 2 | 8 | 7 | 56 | 2.8 | 5.6 | $7,458.64 | |||
Process Change | 2 | 2 | 4 | 0 | 0 | 0 | 0 | $0 | |||
Subtotal for Reporting Requirements | 1,542 | Hours | $178,541 | ||||||||
5. RECORDKEEPING REQUIREMENTS | |||||||||||
A. Read and understand rule requirements | See 4A | ||||||||||
B. Plan Activities | See 4B | ||||||||||
C. Implement Activities | See 4B | ||||||||||
D. Develop Record System | N/A | ||||||||||
E. Time to Enter and Transmit Information: h | |||||||||||
Records of startups, shutdowns, malfunctions, etc. | 1.5 | 1 | 1.5 | 7 | 10.5 | 0.53 | 1.05 | $1,398.50 | |||
Records of monitoring of emissions and operations | See 4B | ||||||||||
F. Train Personnel | N/A | ||||||||||
G. Audits | N/A | ||||||||||
Subtotal for Recordkeeping Requirements | 12 | Hours | $1,398 | ||||||||
TOTAL LABOR BURDEN AND COSTS j | 1,554 | Hours | $180,000 | ||||||||
TOTAL CAPITAL AND O&M COSTS (rounded) j | $90,300 | ||||||||||
GRAND TOTAL(rounded) j | $270,000 | ||||||||||
Assumptions: | |||||||||||
a It is estimated that six primary pyrometallic copper smelters (Subpart P), one primary pryrometallurgical zinc smelter (Subpart Q), and zero primary pryrometallurgical lead smelter (Subpart R) are currently subject to the NSPS standards, which totals 7 respondents. However, the affected units at the primary lead smelter will be shutdown, and only 7 respondents will have burden associated with this rule. We have further assumed that no additional sources will become subject to the standard in the next three years. | |||||||||||
b The labor rates are from the United States Department of Labor, Bureau of Labor Statistics, June 2019, “Table 2. Civilian Workers, by occupational and industry group.” The rates are from column 1, “Total compensation.” The rate has been increased by 110% to account for the benefit packages available to those employed by private industry. | |||||||||||
c Initial rule requirements would apply only to new sources. We have assumed that no new sources will become subject to the rule over the three year period of this ICR. | |||||||||||
d We have assumed that 20 percent of initial performance tests must be repeated due to failure. | |||||||||||
e Sources are required to use the following Reference Methods (RM) in conducting performance tests, if applicable: 1) RM 5 for particulate matter concentrations and volumetric flow rate of the effluent gas (all subparts); 2) RM 9 for visible emissions observations of opacity. Sources are expected to conduct the visible emissions observation of opacity during the initial performance test. | |||||||||||
f Section 60.11 of the General Provisions allows sources to use a continuous opacity monitor (COM) in lieu of Method 9 to determine compliance with the opacity standard. We have assumed that all sources are complying with the standard using COMs. In addition, we assume the sources are using continuous monitoring systems (CMS) to monitor other parameters. | |||||||||||
g Only existing sources using a continuous monitoring system (i.e., a COM or a continuous parameter monitoring system) are required to submit semiannual reports. Therefore, sources subject to NSPS subparts P, Q, R and are required to submit semiannual reports. | |||||||||||
h Sources are required to maintain records of monitoring of operations including startups, shutdowns and malfunctions including periods where the continuous monitoring system is inoperative, emission test results, continuous monitoring system data including, performance test results and other data needed to determine compliance with mass and visible emission limits. | |||||||||||
i Totals have been rounded to 3 significant figures. Figures may not add exactly due to rounding. |
Table 2a: | Average Annual Agency Burden for NSPS for Secondary Brass and Bronze Production (40 CFR Part 60, Subpart M) (Renewal) | |||||||||
0.869565 | $49.44 | $66.62 | $26.75 | |||||||
REPORTING/RECORDKEEPING REQUIREMENT | (A) EPA Hours per Occurence (Technical hours) |
(B) Number of Occurences per Plant per Year |
(C) EPA Hours per Year (C=A x B) |
(D) Plants per Year a |
(E) Technical Hours per Year @ $49.44 (E=C x D) | (F) Management Hours per Year @ $66.62 (F= E x 0.05) |
(G) Clerical Hours per Year @ $26.75 (G= E x 0.1) |
Costs per Year b |
||
Notification of actual startup c | 2.00 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | ||
Notification of initial performance test | 2.00 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | ||
Report of performance test results | 2.00 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | ||
Notification of CMS | 2.00 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | ||
Notification of anticipated date for conducting the opacity of observations | 2.00 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | ||
Notification of modification/reconstruction | 2.00 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | ||
Semiannual reports of excess emissions and monitoring systems performance d | 4.00 | 2 | 8 | 0 | 0 | 0 | 0 | $0 | ||
SALARY BURDEN (per year) | $0 | |||||||||
ANNUAL TRAVEL EXPENSES e | ||||||||||
(1 person x 0 plants/year x 1 d/plant x $50 per diem) + ($400 round trip/plant x 1 plant/yr) = | $0 | |||||||||
TOTAL (rounded) f | 0 | Hours | $0 | |||||||
Assumptions: | ||||||||||
a We have assumed that there are approximately five secondary brass and bronze producers subject to the NSPS subpart M standard and that no new sources will become subject to the NSPS standard in the next three years. | ||||||||||
b This cost is based on the following hourly labor rates times a 1.6 benefits multiplication factor to account for government overhead expenses: $66.62 for Managerial (GS-13, Step 5, $41.64 x 1.6), $49.44 for Technical (GS-12, Step 1, $30.90 x 1.6) and $26.75 Clerical (GS-6, Step 3, $16.72 x 1.6). These rates are from the Office of Personnel Management (OPM) "2019 General Schedule" which excludes locality rates of pay. | ||||||||||
c We have assumed that all existing sources are in compliance with the initial rule requirements. | ||||||||||
d Only existing sources using a continuous monitoring system (i.e., a COM or a continuous parameter monitoring system) are required to submit semiannual reports. Therefore, sources subject to NSPS Subpart M are not required to submit semiannual reports. | ||||||||||
e The time required to attend a performance test per plant is estimated to be approximately 24 hours (1 day). | ||||||||||
f Totals have been rounded to 3 significant figures. Figures may not add exactly due to rounding. |
Table 2b: | Average Annual Agency Burden for NSPS for Primary Copper Smelters (40 CFR part 60, subpart P), Primary Zinc Smelters (40 CFR part 60, subpart Q), and Primary Lead Smelters (40 CFR part 60, subpart R) (Renewal) | |||||||||
0.869565 | $49.44 | $66.62 | $26.75 | |||||||
REPORTING/RECORDKEEPING REQUIREMENT | (A) EPA Hours per Occurence (Technical hours) |
(B) Number of Occurences per Plant per Year |
(C) EPA Hours per Year (C=A x B) |
(D) Plants per Year a |
(E) Technical Hours per Year @ $49.44 (E=C x D) | (F) Management Hours per Year @ $66.62 (F= E x 0.05) |
(G) Clerical Hours per Year @ $26.75 (G= E x 0.1) |
Costs per Year b |
||
Notification of actual startup c | 2 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | ||
Notification of initial performance test | 2 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | ||
Report of performance test results | 2 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | ||
Notification of CMS | 2 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | ||
Notification of anticipated date for conducting the opacity of observations | 2 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | ||
Notification of modification/reconstruction | 2 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | ||
Semiannual reports of excess emissions and monitoring systems performance d | 4 | 2 | 8 | 7 | 56 | 2.8 | 5.6 | $3,104.98 | ||
SALARY BURDEN (per year) | $3,104.98 | |||||||||
ANNUAL TRAVEL EXPENSES e | ||||||||||
(1 person x 0 plants/year x 1 d/plant x $50 per diem) + ($400 round trip/plant x 1 plant/yr) = | $0 | |||||||||
TOTAL (rounded) f | 64 | Hours | $3,100 | |||||||
Assumptions: | ||||||||||
a We have assumed that are approximately six primary copper smelters (subpart P), one primary zinc smelter (subpart Q), and one primary lead smelter (subpart R) subject to the NSPS standard for a total of eight respondents. However, we assume that the affected units at the one primary lead smelter facility has be shutdown, so only 7 facilities in total will have burden associated with this rule. We have further assumed that there will be no new sources in the next three years. |
||||||||||
b This cost is based on the following hourly labor rates times a 1.6 benefits multiplication factor to account for government overhead expenses: $66.62 for Managerial (GS-13, Step 5, $41.64 x 1.6), $49.44 for Technical (GS-12, Step 1, $30.90 x 1.6) and $26.75 Clerical (GS-6, Step 3, $16.72 x 1.6). These rates are from the Office of Personnel Management (OPM) "2019 General Schedule" which excludes locality rates of pay. | ||||||||||
c We have assumed that all existing sources are in compliance with the initial rule requirements. | ||||||||||
d Only existing sources using a continuous monitoring system (i.e., a COM or a continuous parameter monitoring system) are required to submit semiannual reports. Therefore, sources subject to NSPS subparts P, Q and R are required to submit semiannual reports. | ||||||||||
e The time required to attend a performance test per plant is estimated to be approximately 24 hours (1 day). | ||||||||||
f Totals have been rounded to 3 significant figures. Figures may not add exactly due to rounding. |
Table 2c. | Average Annual Agency Burden for NSPS for Primary Aluminum Reduction Plants (40 CFR part 60, subpart S) (Renewal) | ||||||||
0.869565 | $49.44 | $66.62 | $26.75 | ||||||
(A) EPA Hours per Occurence (Technical hours) |
(B) Number of Occurences per Plant per Year |
(C) EPA Hours per Year (C=A x B) |
(D) Plants per Year a |
(E) Technical Hours per Year @ $49.44 (E=C x D) | (F) Management Hours per Year @ $66.62 (F= E x 0.05) |
(G) Clerical Hours per Year @ $26.75 (G= E x 0.1) |
Costs per Year b |
||
Notification of actual startup c | 2 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | |
Notification of annual or monthly performance tests d | 2 | 1 | 2 | 2 | 4 | 0.2 | 0.4 | $221.78 | |
2 | 12 | 24 | 2 | 48 | 2.4 | 4.8 | $2,661.41 | ||
Report of annual or monthly performance test results d | 2 | 1 | 2 | 2 | 4 | 0.2 | 0.4 | $221.78 | |
2 | 12 | 24 | 2 | 48 | 2.4 | 4.8 | $2,661.41 | ||
Notification of CMS | 2 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | |
Notification of anticipated date for conducting the opacity of observations | 2 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | |
Notification of modification/reconstruction | 2 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | |
Semiannual reports of excess emissions and monitoring systems performance e | 4 | 2 | 8 | 4 | 32 | 1.6 | 3.2 | $1,774.27 | |
SALARY BURDEN (per year) | $7,541 | ||||||||
ANNUAL TRAVEL EXPENSES e | |||||||||
(1 person x 1 plants/year x 3 d/plant x $50 per diem) + ($400 round trip/plant x 1 plant/yr) = | $550.00 | ||||||||
TOTAL (rounded) f | 156 | Hours | $8,090 | ||||||
Assumptions: | |||||||||
e The time required to attend a performance test per plant is estimated to be approximately 24 hours (1 day). | |||||||||
f Totals have been rounded to 3 significant figures. Figures may not add exactly due to rounding. |
Table 2d: | Average Annual Agency Burden for NSPS for Ferroalloy Production Facilities (40 CFR part 60, subpart Z) (Renewal) | |||||||||
0.869565 | $49.44 | $66.62 | $26.75 | |||||||
REPORTING/RECORDKEEPING REQUIREMENT | (A) EPA Hours per Occurence (Technical hours) |
(B) Number of Occurences per Plant per Year |
(C) EPA Hours per Year (C=A x B) |
(D) Plants per Year a |
(E) Technical Hours per Year @ $49.44 (E=C x D) | (F) Management Hours per Year @ $66.62 (F= E x 0.05) |
(G) Clerical Hours per Year @ $26.75 (G= E x 0.1) |
Costs per Year b |
||
Notification of actual startup c | 2 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | ||
Notification of initial performance test | 2 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | ||
Report of performance test results | 2 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | ||
Notification of CMS | 2 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | ||
Notification of anticipated date for conducting the opacity of observations | 2 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | ||
Notification of modification/reconstruction | 2 | 1 | 2 | 0 | 0 | 0 | 0 | $0 | ||
Notification of product change | 4 | 1 | 4 | 0 | 0 | 0 | 0 | $0 | ||
Semiannual reports of excess emissions and monitoring systems performance e | 4 | 2 | 8 | 2 | 16 | 0.8 | 1.6 | $887.14 | ||
SALARY BURDEN (per year) | $887.14 | |||||||||
ANNUAL TRAVEL EXPENSES e | (1 person x 0 plants/year x 1 d/plant x $50 per diem) + ($400 round trip/plant x 1 plant/yr) = | $0 | ||||||||
TOTAL (rounded) f | 18 | Hours | $887 | |||||||
Assumptions: | ||||||||||
a We have assumed that there are 2 ferroalloy production facilities subject to NSPS subpart Z and that no new sources will become subject to the NSPS standard in the next three years. | ||||||||||
b This cost is based on the following hourly labor rates times a 1.6 benefits multiplication factor to account for government overhead expenses: $66.62 for Managerial (GS-13, Step 5, $41.64 x 1.6), $49.44 for Technical (GS-12, Step 1, $30.90 x 1.6) and $26.75 Clerical (GS-6, Step 3, $16.72 x 1.6). These rates are from the Office of Personnel Management (OPM) "2019 General Schedule" which excludes locality rates of pay. | ||||||||||
c We have assumed that all existing sources are in compliance with the initial rule requirements. | ||||||||||
d Only existing sources using a continuous monitoring system (i.e., a COM or a continuous parameter monitoring system) are required to submit semiannual reports. Therefore, sources subject to NSPS subpart Z are required to submit semiannual reports. | ||||||||||
e The time required to attend a performance test per plant is estimated to be approximately 24 hours (1 day). | ||||||||||
f Totals have been rounded to 3 significant figures. Figures may not add exactly due to rounding. |
Capital/Startup vs. Operation and Maintenance (O&M) Costs | ||||||
(A) | (B) | (C) | (D) | (E) | (F) | (G) |
Continuous Monitoring Device | Capital/Startup Cost for One Respondent | Number of New Respondents | Total Capital/Startup Cost, (B X C) | Annual O&M Costs for One Respondent | Number of Respondents with O&M | Total O&M, |
(E X F) | ||||||
Subpart M | ||||||
None | N/A | 0 | $0 | N/A | 0 | $0 |
Subparts P, Q, R a | ||||||
Opacity monitor | $36,000 | 0 | $0 | $7,500 | 7 | $52,500 |
CMS that measures SO2 emissions | $25,100 | 0 | $0 | $5,400 | 7 | $37,800 |
Subpart S | ||||||
CMS that weighs Al and anode produced daily | Unknown | 0 | $0 | $5,000 | 4 | $20,000 |
Subpart Z | ||||||
Opacity monitor | $36,000 | 0 | $0 | $7,500 | 2 | $15,000 |
CMS that measures furnace power input and flow rate or fan motor power consumption and pressure drop across fan | Gas flow - $13,500 | 0 | $0 | $900 | 2 | $1,800 |
Pressure drop - $1,300 | ||||||
TOTAL | $0 | $127,000 |
File Type | application/vnd.openxmlformats-officedocument.spreadsheetml.sheet |
File Modified | 0000-00-00 |
File Created | 0000-00-00 |