18 Cfr 5.16

18 CFR 5.16.docx

FERC-505, (Proposed Rule in Docket RM20-21-000) Small Hydropower Projects and Conduit Facilities including License/Relicense, Exemption, and Qualifying Conduit Facility Determination

18 CFR 5.16

OMB: 1902-0115

Document [docx]
Download: docx | pdf

Electronic Code of Federal Regulations (eCFR) Page 1 of 2

ELECTRONIC CODE OF FEDERAL REGULATIONS

e-CFR data is current as of May 19, 2021

Title 18Chapter ISubchapter BPart 5 → §5.16

Title 18: Conservation of Power and Water Resources PART 5—INTEGRATED LICENSE APPLICATION PROCESS

Shape1

§5.16 Preliminary licensing proposal.

  1. No later than 150 days prior to the deadline for filing a new or subsequent license application, if applicable, the potential applicant must file for comment a preliminary licensing proposal.

  2. The preliminary licensing proposal must:

  1. Clearly describe, as applicable, the existing and proposed project facilities, including project lands and waters;

  2. Clearly describe, as applicable, the existing and proposed project operation and maintenance plan, to include measures for protection, mitigation, and enhancement measures with respect to each resource affected by the project proposal; and

  3. Include the potential applicant's draft environmental analysis by resource area of the continuing and incremental impacts, if any, of its preliminary licensing proposal, including the results of its studies conducted under the approved study plan.

  1. A potential applicant may elect to file a draft license application which includes the contents of a license application required by §5.18 instead of the Preliminary Licensing Proposal. A potential applicant that elects to file a draft license application must include notice of its intent to do so in the updated study report required by §5.15(f).

  2. A potential applicant that has been designated as the Commission's nonFederal representative may include a draft Biological Assessment, draft Essential Fish Habitat Assessment, and draft Historic Properties Management Plan with its Preliminary Licensing Proposal or draft license application.

  3. Within 90 days of the date the potential applicant files the Preliminary

Licensing Proposal or draft license application, participants and the Commission

https://www.ecfr.gov/cgi-bin/text-idx?SID=234c8133442ad847ec19497e03e08c18&mc=tr... 5/21/2021 Electronic Code of Federal Regulations (eCFR) Page 2 of 2

staff may file comments on the Preliminary Licensing Proposal or draft application, which may include recommendations on whether the Commission should prepare an Environmental Assessment (with or without a draft Environmental Assessment) or an Environmental Impact Statement. Any participant whose comments request new information, studies, or other amendments to the approved study plan must include a demonstration of extraordinary circumstances, pursuant to the requirements of §5.15(f).

  1. A waiver of the requirement to file the Preliminary Licensing Proposal or draft license application may be requested, based on a consensus of the participants in favor of such waiver.

Need assistance?

https://www.ecfr.gov/cgi-bin/text-idx?SID=234c8133442ad847ec19497e03e08c18&mc=tr... 5/21/2021

File Typeapplication/vnd.openxmlformats-officedocument.wordprocessingml.document
File Titlehttps://www.ecfr.gov/cgi-bin/text-idx?SID=234c8133442ad847ec194
Authorjnsed34
File Modified0000-00-00
File Created2021-06-07

© 2024 OMB.report | Privacy Policy